CN205576860U - Dam crest is as floodgate dam structure of traffic bridge - Google Patents

Dam crest is as floodgate dam structure of traffic bridge Download PDF

Info

Publication number
CN205576860U
CN205576860U CN201620359049.0U CN201620359049U CN205576860U CN 205576860 U CN205576860 U CN 205576860U CN 201620359049 U CN201620359049 U CN 201620359049U CN 205576860 U CN205576860 U CN 205576860U
Authority
CN
China
Prior art keywords
gate
dam
dam structure
door slot
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620359049.0U
Other languages
Chinese (zh)
Inventor
张金明
何贞俊
王建平
苏波
吕文斌
张艳艳
杨聿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pearl River Hydraulic Research Institute of PRWRC
Original Assignee
Pearl River Hydraulic Research Institute of PRWRC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pearl River Hydraulic Research Institute of PRWRC filed Critical Pearl River Hydraulic Research Institute of PRWRC
Priority to CN201620359049.0U priority Critical patent/CN205576860U/en
Application granted granted Critical
Publication of CN205576860U publication Critical patent/CN205576860U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Barrages (AREA)

Abstract

本实用新型公开了一种坝顶用作交通桥的闸坝结构,包括坝顶用作交通桥的闸墩、以及用于消能的消力池;所述消力池连接在所述闸墩下游,并且,所述消力池的上游端位于所述闸墩内。本实用新型的坝顶用作交通桥的闸坝结构,消力池的上游端位于闸墩内,在水闸泄流时,泄流能够很快进入消力池,形成稳定的底流消能,达到消力池设计的消能目的,同时降低水闸泄流时的闸下回流引起的闸门激流振动问题。

The utility model discloses a gate dam structure with a dam crest used as a traffic bridge, comprising a gate pier used as a traffic bridge at the dam crest and a stilling pool for energy dissipation; the stilling pool is connected to the gate pier downstream, and the upstream end of the stilling basin is located in the pier. The dam crest of the utility model is used as the gate and dam structure of the traffic bridge. The upstream end of the stilling pool is located in the gate pier. The energy dissipation purpose of the design of the stilling basin is to reduce the torrent vibration of the sluice caused by the backflow under the sluice when the sluice discharges.

Description

坝顶用作交通桥的闸坝结构The dam crest is used as a gate and dam structure for traffic bridges

技术领域technical field

本实用新型涉及水力学大坝消能技术领域,尤其涉及一种坝顶用作交通桥的闸坝结构。The utility model relates to the technical field of hydraulic dam energy dissipation, in particular to a gate dam structure with a dam crest used as a traffic bridge.

背景技术Background technique

对于坝顶用于交通桥的闸坝结构来说,闸墩段的设计长度通常较常规闸坝有所增加。在闸门位置布置时,为保证正常运行条件下,充分利用闸墩混凝土的抗压性能,一般将闸门设置在闸墩段的上游端。For the gate and dam structures whose dam crest is used for traffic bridges, the design length of the gate pier section is usually increased compared with conventional gate dams. When arranging the gate position, in order to ensure the normal operating conditions and make full use of the compressive performance of the gate pier concrete, the gate is generally set at the upstream end of the gate pier section.

常规的闸门设置在闸墩中部或中下部的闸坝结构,出闸水流能够很快进入消力池,形成稳定的底流消能,达到消力池设计的消能目的。而对于闸门12设置在闸墩11上游端的闸坝结构来讲,如图1所示,出闸水流在经过一定长度的闸墩段后再进入消力池13,若下游水位相对较低,则在消力池13内形成底流消能;若设计下游水位相对较高,则在闸门12出流较大推力作用下,泄流顶部形成较大回流区,回流间歇性的拍打闸门12,形成闸门12泄流激流振动,易造成闸门12损坏。Conventional gates are set in the middle or lower part of the dam structure of the gate pier, and the water flow out of the gate can quickly enter the stilling basin, forming a stable bottom flow energy dissipation, and achieving the energy dissipation purpose of the stilling basin design. For the gate dam structure in which the gate 12 is arranged at the upstream end of the gate pier 11, as shown in Figure 1, the water flowing out of the gate enters the stilling pool 13 after passing through a certain length of the gate pier section. If the downstream water level is relatively low, then Underflow energy dissipation is formed in the stilling pool 13; if the design downstream water level is relatively high, then under the action of the large thrust of the gate 12, the top of the discharge flow forms a large backflow area, and the backflow intermittently beats the gate 12 to form a gate The torrent vibration of the 12 discharges can easily cause the gate 12 to be damaged.

实用新型内容Utility model content

本实用新型要解决的技术问题在于,提供一种改进的坝顶用作交通桥的闸坝结构。The technical problem to be solved by the utility model is to provide an improved dam crest used as a gate and dam structure for traffic bridges.

本实用新型解决其技术问题所采用的技术方案是:提供一种坝顶用作交通桥的闸坝结构,包括坝顶用作交通桥的闸墩、以及用于消能的消力池;所述消力池连接在所述闸墩下游,并且,所述消力池的上游端位于所述闸墩内。The technical solution adopted by the utility model to solve the technical problems is: to provide a gate dam structure with the top of the dam as a traffic bridge, including a pier used as a traffic bridge at the top of the dam, and a stilling pool for energy dissipation; The stilling basin is connected downstream of the gate pier, and the upstream end of the stilling basin is located inside the gate pier.

优选地,该闸坝结构还包括设置在所述闸墩上游端的检修门槽和工作门槽;Preferably, the dam structure also includes an inspection door slot and a working door slot arranged at the upstream end of the gate pier;

所述检修门槽和工作门槽相平行间隔,并且,所述检修门槽位于所述工作门槽的上游。The access door slot and the working door slot are parallel and spaced apart, and the access door slot is located upstream of the working door slot.

优选地,该闸坝结构还包括设置在所述检修门槽底部的第一闸门、以及设置在所述工作门槽底部的第二闸门。Preferably, the dam structure further includes a first gate arranged at the bottom of the maintenance door slot, and a second gate arranged at the bottom of the working door slot.

优选地,所述第一闸门和第二闸门位于所述闸墩的上游端。Preferably, the first gate and the second gate are located at the upstream end of the pier.

优选地,所述检修门槽和所述工作门槽位于所述交通桥的外侧。Preferably, the inspection door slot and the working door slot are located on the outer side of the traffic bridge.

优选地,所述消力池上游端的底面为斜面。Preferably, the bottom surface of the upstream end of the stilling basin is a slope.

优选地,优选地,该闸坝结构还包括海漫,所述海漫铺设连接所述消力池的下游端。Preferably, preferably, the dam structure further includes a sea diffuser, and the sea diffuser is laid to connect the downstream end of the stilling basin.

优选地,所述海漫为混凝土海漫或浆砌石海漫。Preferably, the seam is a concrete seam or a masonry stone seam.

本实用新型的坝顶用作交通桥的闸坝结构,消力池的上游端位于闸墩内,在水闸泄流时,泄流能够很快进入消力池,形成稳定的底流消能,达到消力池设计的消能目的,同时降低水闸泄流时的闸下回流引起的闸门激流振动问题。The dam crest of the utility model is used as the gate and dam structure of the traffic bridge. The upstream end of the stilling pool is located in the gate pier. The energy dissipation purpose of the design of the stilling basin is to reduce the torrent vibration of the sluice caused by the backflow under the sluice when the sluice discharges.

附图说明Description of drawings

下面将结合附图及实施例对本实用新型作进一步说明,附图中:The utility model will be further described below in conjunction with accompanying drawing and embodiment, in the accompanying drawing:

图1是现有技术中闸坝结构的剖面结构示意图;Fig. 1 is the sectional structure schematic diagram of gate dam structure in the prior art;

图2是本实用新型一实施例的闸坝结构的剖面结构示意图。Fig. 2 is a schematic cross-sectional structure diagram of a gate and dam structure according to an embodiment of the present invention.

具体实施方式detailed description

为了对本实用新型的技术特征、目的和效果有更加清楚的理解,现对照附图详细说明本实用新型的具体实施方式。In order to have a clearer understanding of the technical features, purposes and effects of the utility model, the specific implementation of the utility model is described in detail with reference to the accompanying drawings.

如图2所示,本实用新型一实施例的坝顶用作交通桥的闸坝结构,包括坝顶用作交通桥21的闸墩2、以及用于消能的消力池3。As shown in Figure 2, the dam crest of an embodiment of the utility model is used as a traffic bridge gate dam structure, including the gate pier 2 used as a traffic bridge 21 at the dam crest, and a stilling pool 3 for energy dissipation.

其中,消力池3连接在闸墩2下游,并且,消力池3的上游端位于闸墩2内,使得出闸水流经过闸墩段后很快进入消力池3。对于闸门设置在闸墩2上游的情况,在水闸泄流时,泄流能够很快进入消力池3,形成稳定的底流消能,达到消力池3设计的消能目的,同时降低水闸泄流时的闸下回流引起的闸门激流振动问题。Wherein, the stilling pool 3 is connected downstream of the gate pier 2, and the upstream end of the stilling pool 3 is located in the gate pier 2, so that the water flowing out of the gate enters the stilling pool 3 soon after passing through the gate pier section. For the case where the gate is arranged upstream of the gate pier 2, when the sluice discharges, the discharge can quickly enter the stilling basin 3, forming a stable bottom flow energy dissipation, achieving the energy dissipation purpose of the design of the stilling basin 3, and at the same time reducing the discharge rate of the sluice. The gate torrent vibration problem caused by the backflow under the gate during flow.

本实施例中,消力池3上游端的底面31为斜面,该斜面与闸墩2的下游底面连接。消力池3的底板通常为混凝土结构,底板上的底面31结构强度高。In this embodiment, the bottom surface 31 of the upstream end of the stilling pool 3 is an inclined surface, and the inclined surface is connected with the downstream bottom surface of the gate pier 2 . The bottom plate of the stilling basin 3 is usually a concrete structure, and the bottom surface 31 on the bottom plate has a high structural strength.

该闸坝结构还包括设置在闸墩2上游端的检修门槽4和工作门槽5。检修门槽4和工作门槽5相平行间隔,并且,检修门槽4位于工作门槽5的上游,即:检修门槽4位于工作门槽5远离消力池3的一侧。The dam structure also includes an inspection door slot 4 and a working door slot 5 arranged at the upstream end of the gate pier 2 . The inspection door slot 4 and the working door slot 5 are parallel and spaced apart, and the inspection door slot 4 is located upstream of the working door slot 5 , that is, the inspection door slot 4 is located on the side of the working door slot 5 away from the stilling pool 3 .

在闸墩2上,检修门槽4和工作门槽5位于作为交通桥21的外侧。如图2中所示,交通桥21对应在消力池3的上游端的上方。On the gate pier 2 , the inspection door slot 4 and the working door slot 5 are located on the outside as the traffic bridge 21 . As shown in FIG. 2 , the traffic bridge 21 is correspondingly above the upstream end of the stilling basin 3 .

此外,该闸坝结构还包括设置在检修门槽4底部的第一闸门6、以及设置在工作门槽5底部的第二闸门7。第一闸门6和第二闸门7均位于闸墩2上游端。第二闸门7打开泄流时,泄流能够很快进入消力池3。In addition, the dam structure also includes a first gate 6 arranged at the bottom of the maintenance door slot 4 and a second gate 7 arranged at the bottom of the working door slot 5 . Both the first gate 6 and the second gate 7 are located at the upstream end of the pier 2 . When the second gate 7 is opened to discharge the flow, the discharge flow can quickly enter the stilling basin 3 .

进一步地,该闸坝结构还可包括海漫8,海漫8铺设连接消力池3的下游端。海漫8主要用作消能防冲措施,其作用是进一步消能,保护河床。作为选择,海漫8可为混凝土海漫或浆砌石海漫。Further, the gate and dam structure may also include a seaman 8 , and the seaman 8 is laid to connect the downstream end of the stilling basin 3 . Haiman 8 is mainly used as energy dissipation and anti-scour measures, and its function is to further dissipate energy and protect the riverbed. As an option, Seaman 8 can be a concrete seam or a masonry stone seam.

可以理解地,上述的各门槽、闸门及海漫8等均可通过现有技术实现。It can be understood that the above-mentioned door slots, gates, and seaman 8 can all be realized by existing technologies.

以上所述仅为本实用新型的实施例,并非因此限制本实用新型的专利范围,凡是利用本实用新型说明书及附图内容所作的等效结构或等效流程变换,或直接或间接运用在其他相关的技术领域,均同理包括在本实用新型的专利保护范围内。The above is only an embodiment of the utility model, and does not limit the patent scope of the utility model. Any equivalent structure or equivalent process conversion made by using the utility model specification and accompanying drawings, or directly or indirectly used in other Related technical fields are all included in the patent protection scope of the present utility model in the same way.

Claims (8)

1.一种坝顶用作交通桥的闸坝结构,其特征在于,包括坝顶用作交通桥(21)的闸墩(2)、以及用于消能的消力池(3);所述消力池(3)连接在所述闸墩(2)下游,并且,所述消力池(3)的上游端位于所述闸墩(2)内。 1. a dam crest is used as the gate dam structure of traffic bridge, it is characterized in that, comprises dam crest as the gate pier (2) of traffic bridge (21) and the stilling pool (3) that is used for energy dissipation; The stilling basin (3) is connected downstream of the gate pier (2), and the upstream end of the stilling basin (3) is located inside the gate pier (2). 2.根据权利要求1所述的闸坝结构,其特征在于,该闸坝结构还包括设置在所述闸墩(2)上游端的检修门槽(4)和工作门槽(5); 2. The gate and dam structure according to claim 1, characterized in that, the gate and dam structure also includes an inspection door slot (4) and a working door slot (5) arranged at the upstream end of the gate pier (2); 所述检修门槽(4)和工作门槽(5)相平行间隔,并且,所述检修门槽(4)位于所述工作门槽(5)的上游。 The inspection door slot (4) and the working door slot (5) are parallel and spaced apart, and the inspection door slot (4) is located upstream of the working door slot (5). 3.根据权利要求2所述的闸坝结构,其特征在于,该闸坝结构还包括设置在所述检修门槽(4)底部的第一闸门(6)、以及设置在所述工作门槽(5)底部的第二闸门(7)。 3. The dam structure according to claim 2, characterized in that the dam structure further comprises a first gate (6) arranged at the bottom of the maintenance door slot (4), and a first gate (6) arranged at the bottom of the working door slot (5) Second gate (7) at the bottom. 4.根据权利要求3所述的闸坝结构,其特征在于,所述第一闸门(6)和第二闸门(7)位于所述闸墩(2)的上游端。 4. The dam structure according to claim 3, characterized in that, the first gate (6) and the second gate (7) are located at the upstream end of the gate pier (2). 5.根据权利要求2所述的闸坝结构,其特征在于,所述检修门槽(4)和所述工作门槽(5)位于所述交通桥(21)的外侧。 5. The dam structure according to claim 2, characterized in that, the inspection door slot (4) and the working door slot (5) are located outside the traffic bridge (21). 6.根据权利要求1所述的闸坝结构,其特征在于,所述消力池(3)上游端的底面(31)为斜面。 6. The gate and dam structure according to claim 1, characterized in that, the bottom surface (31) of the upstream end of the stilling basin (3) is an inclined surface. 7.根据权利要求1-6任一项所述的闸坝结构,其特征在于,该闸坝结构还包括海漫(8),所述海漫(8)铺设连接所述消力池(3)的下游端。 7. The gate and dam structure according to any one of claims 1-6, characterized in that the gate and dam structure also includes a sea diffuser (8), and the sea diffuser (8) is laid and connected to the stilling pool (3 ) downstream end. 8.根据权利要求7所述的闸坝结构,其特征在于,所述海漫(8)为混凝土海漫或浆砌石海漫。 8. The gate and dam structure according to claim 7, characterized in that, the diffuser (8) is a concrete diffuser or a mortared stone diffuser.
CN201620359049.0U 2016-04-25 2016-04-25 Dam crest is as floodgate dam structure of traffic bridge Expired - Fee Related CN205576860U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620359049.0U CN205576860U (en) 2016-04-25 2016-04-25 Dam crest is as floodgate dam structure of traffic bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620359049.0U CN205576860U (en) 2016-04-25 2016-04-25 Dam crest is as floodgate dam structure of traffic bridge

Publications (1)

Publication Number Publication Date
CN205576860U true CN205576860U (en) 2016-09-14

Family

ID=56860157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620359049.0U Expired - Fee Related CN205576860U (en) 2016-04-25 2016-04-25 Dam crest is as floodgate dam structure of traffic bridge

Country Status (1)

Country Link
CN (1) CN205576860U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447736A (en) * 2017-09-08 2017-12-08 中国电建集团中南勘测设计研究院有限公司 A kind of power station inlet/outlet arrangement
CN109750591A (en) * 2019-01-15 2019-05-14 中国电建集团北京勘测设计研究院有限公司 A kind of portal crane traffic bridge arranged on the sluice and dam of the hydropower station
CN109881643A (en) * 2019-04-09 2019-06-14 吉林省水利水电勘测设计研究院 Down-the-hole gates of segmental shape Anti-freezing arranges figure and its determines method
CN113832924A (en) * 2021-10-11 2021-12-24 中国海洋大学 A sluice for maintaining the stability of upstream waters and method of using the same

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447736A (en) * 2017-09-08 2017-12-08 中国电建集团中南勘测设计研究院有限公司 A kind of power station inlet/outlet arrangement
CN107447736B (en) * 2017-09-08 2020-02-07 中国电建集团中南勘测设计研究院有限公司 Water inlet/outlet arrangement structure of hydropower station
CN109750591A (en) * 2019-01-15 2019-05-14 中国电建集团北京勘测设计研究院有限公司 A kind of portal crane traffic bridge arranged on the sluice and dam of the hydropower station
CN109881643A (en) * 2019-04-09 2019-06-14 吉林省水利水电勘测设计研究院 Down-the-hole gates of segmental shape Anti-freezing arranges figure and its determines method
CN109881643B (en) * 2019-04-09 2023-12-22 吉林省水利水电勘测设计研究院 Anti-freezing arrangement shape of down-the-hole arc gate and its determination method
CN113832924A (en) * 2021-10-11 2021-12-24 中国海洋大学 A sluice for maintaining the stability of upstream waters and method of using the same
CN113832924B (en) * 2021-10-11 2022-05-27 中国海洋大学 Water storage gate for maintaining stability of upstream water area and use method thereof

Similar Documents

Publication Publication Date Title
CN205576860U (en) Dam crest is as floodgate dam structure of traffic bridge
CN103410130B (en) Multi-purpose tunnel arrangement structure
CN207003391U (en) A kind of water gate energy-dissipating installation
CN202039329U (en) Dividing pier structure capable of eliminating the water ring at tail part of sluice pier
CN103195016A (en) Flow guiding ridge technology for controlling water flow of canal bend from being overhigh
CN204825802U (en) Compound line type overflow weir
CN107975015A (en) It is provided with the checkdam of surface spillways
CN110528475A (en) A water intake system for water conservancy projects
CN210002360U (en) A damming and flood discharge structure in alpine canyons
CN202214710U (en) Overflow and water discharge integrated sluice weir
CN103821112B (en) Side goes out to flow spillway on bank along journey
CN103541330A (en) Tailings pond flood drainage system for draining in advance efficiently and prolonging clarification distance
CN106869090B (en) Dreg-blocking board sub-assembly and diversion tunnel debris retaining Slagoff method
CN209025056U (en) A kind of Floater removing gate and scouring sluice integrated structure
CN106702968A (en) Arc type overflow dam capable of automatically washing away sand and reducing siltation and running method of arc type overflow dam
CN204644992U (en) A kind of absorption basin energy-dissipating structure
CN104963379B (en) For the water intaking structure on mountain channel
CN103614986B (en) It a kind of is applicable to the pressure free current inlet method that Tailings Dam drains off floodwaters
CN209066370U (en) A kind of multi-layer noise reduction bulwark
CN102691280B (en) For multi-stage slide ladder and the absorption basin combined energy dissipater of soft base section
CN217078619U (en) A slope protection structure for hydraulic engineering
CN206529746U (en) A kind of Concrete Dam Construction arrangement of excessively stream arch dam free removal
CN105239540B (en) A kind of inclined floor formula stiling basin
CN204982820U (en) A lock chamber arrangement structure that is used for high arch dam water conservancy diversion bottom outlet
CN103981842A (en) X-shaped flaring pier of trapezoid shrinkage outlet

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914

Termination date: 20170425

CF01 Termination of patent right due to non-payment of annual fee