CN205475300U - Utilize foundation pit retaining structure's tower crane foundation cushion cap - Google Patents

Utilize foundation pit retaining structure's tower crane foundation cushion cap Download PDF

Info

Publication number
CN205475300U
CN205475300U CN201620286493.4U CN201620286493U CN205475300U CN 205475300 U CN205475300 U CN 205475300U CN 201620286493 U CN201620286493 U CN 201620286493U CN 205475300 U CN205475300 U CN 205475300U
Authority
CN
China
Prior art keywords
tower crane
cushion cap
trestle
foundation pit
pit enclosure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620286493.4U
Other languages
Chinese (zh)
Inventor
黄沛林
余林峰
王俊佚
陈华
万展君
李满
杨成林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201620286493.4U priority Critical patent/CN205475300U/en
Application granted granted Critical
Publication of CN205475300U publication Critical patent/CN205475300U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to an utilize foundation pit retaining structure's tower crane foundation cushion cap, include: locate the landing stage board in the foundation pit retaining structure, connect in the landing stage roof beam on landing stage flange edge, the tower crane foundation cushion cap, the part coincidence is connected in the landing stage board and is encorbelmented in the landing stage roof beam, locate the landing stage board lattice column of landing stage board below, and locate the tower crane foundation cushion cap lattice column of tower crane foundation cushion cap below. The utility model discloses link together tower crane foundation cushion cap and landing stage board under the less condition of construction region and to save space. Envelope has the displacement constraint effect to the tower crane foundation cushion cap, has increased tower crane foundation 's stability.

Description

Utilize the tower crane cushion cap of foundation pit enclosure structure
Technical field
This utility model relates to the realm of building construction, a kind of tower crane base utilizing foundation pit enclosure structure Plinth cushion cap.
Background technology
At the realm of building construction, for needs of constructing, it is contemplated that when using tower crane, engineering ground is narrow and small In the range of situation, i.e. land red-line, available construction site is limited, and surrounding enviroment are complicated, Er Qiegong Journey structure construction stage vertical transportation machinery tower crane needs to be arranged in range of floors, tower in conventional art The setting hanging foundation platform can not meet requirement.
Utility model content
The purpose of this utility model is to overcome the defect of prior art, it is provided that one utilizes foundation pit enclosure The tower crane cushion cap of structure, solves the problems of the prior art.
The technical scheme realizing above-mentioned purpose is: provides and utilizes the tower crane of foundation pit enclosure structure to hold Platform, including:
The trestle plate being located in foundation pit enclosure structure;
It is connected to the trestle beam on described trestle edges of boards edge;
Tower crane cushion cap, partially overlaps and is connected to described trestle plate and encorbelments in described trestle beam;
It is located at the trestle plate lattice column below described trestle plate;And
It is located at the tower crane cushion cap lattice column below described tower crane cushion cap.
This utility model utilizes the beneficial effect of the tower crane cushion cap of foundation pit enclosure structure:
This utility model utilizes the tower crane cushion cap of foundation pit enclosure structure to be connected by tower crane cushion cap In the trestle plate of foundation pit enclosure structure, the bottom shelf of tower crane is located at the upper surface of tower crane concrete cushion cap, Thus in the case of construction area is less, tower crane cushion cap and trestle plate are linked together permissible Save space.Building enclosure has displacement constraint effect to tower crane cushion cap, adds tower crane Stability.This utility model had both met the needs going along with sb. to guard him design, efficiently solved again down town The narrow and small engineering ground vertical transportation machinery horizontal layout problem in area.Construction for similar engineering provides relatively Abundant construction experience.Tower crane cushion cap has solely prior to the construction of trestle plate, tower crane cushion cap Vertical property, the installation that this is crane machine provides advantage.
This utility model utilizes further improvement is that of the tower crane cushion cap of foundation pit enclosure structure, institute State trestle plate to include:
Trestle slab muscle;And
Pouring in the xoncrete structure of described trestle slab muscle, described trestle plate is provided with cross-coupled First construction joint and the second construction joint.
This utility model utilizes further improvement is that of the tower crane cushion cap of foundation pit enclosure structure, institute State the first construction and be sewed with two, be respectively arranged on two relative outsides of described foundation pit enclosure structure, described Second construction joint lateral cross is in described first construction joint, described first construction joint and described second construction Seam is equipped with dabbing layer, and described first construction joint is additionally provided with reinforcement planting concrete structure.
This utility model utilizes further improvement is that of the tower crane cushion cap of foundation pit enclosure structure, institute Stating tower crane cushion cap is rectangle steel tendon concrete structure.
This utility model utilizes further improvement is that of the tower crane cushion cap of foundation pit enclosure structure, institute State under four angles that tower crane cushion cap lattice column stays on described rectangle steel tendon concrete structure.
This utility model utilizes further improvement is that of the tower crane cushion cap of foundation pit enclosure structure, institute State trestle beam to include:
Trestle beam steel, the density of described trestle beam steel arrangement is more than described trestle plate arrangement of bar Density;And
Pour in the xoncrete structure of described trestle beam steel.
Accompanying drawing explanation
Fig. 1 is the floor map that this utility model utilizes the tower crane cushion cap of foundation pit enclosure structure.
Fig. 2 is the floor map of the first construction joint in Fig. 1.
Fig. 3 is the floor map of the second construction joint in Fig. 1.
Detailed description of the invention
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
This utility model provides a kind of tower crane cushion cap utilizing foundation pit enclosure structure, below in conjunction with attached This utility model is illustrated by figure.
Refering to Fig. 1, it is shown that this utility model utilizes the tower crane cushion cap of foundation pit enclosure structure.As Shown in Fig. 1, this utility model utilizes the tower crane cushion cap of foundation pit enclosure structure, including foundation pit enclosure Structure 1, trestle plate 2, tower crane cushion cap 3, trestle beam 5, trestle plate lattice column and tower crane base Plinth cushion cap lattice column 4, in wherein foundation pit enclosure structure 1 is located at by trestle plate 2, trestle beam 5 is connected to The edge of trestle plate 2, tower crane cushion cap 3 partially overlaps and is connected to trestle plate 2 and encorbelments in stack Bridge 5, tower crane is located on tower crane cushion cap 3, and trestle plate lattice column is located at the lower section of trestle plate 2, Tower crane cushion cap lattice column 4 is located at the lower section of tower crane cushion cap 3.This utility model utilizes foundation ditch Tower crane cushion cap is connected to the trestle plate of foundation pit enclosure structure by the tower crane cushion cap of building enclosure, The bottom shelf of tower crane is located at the upper surface of tower crane concrete cushion cap.The lower section of tower crane cushion cap and stack The lower section of bridge plate is provided with lattice column.Thus by tower crane cushion cap in the case of construction area is less Link together with trestle plate and can save space.
As it is shown in figure 1, be provided with trestle plate 2 in foundation pit enclosure structure 1, trestle plate 2 is provided with intersection The first construction joint 21 and the second construction joint 22 connected.In the present embodiment, foundation pit enclosure structure 1 It is primarily subjected to water pressure produced by Unloading and soil pressure, and by this pressure transmission to propping up Support, is the one interim barrier wall structure of construction of stable foundation ditch.Trestle plate 2 includes: trestle slab muscle 20; And xoncrete structure, during wherein trestle slab muscle 20 is erected on foundation pit enclosure structure 1, is formed and prop up Support bone shelf structure, sets up casting concrete on the support framework structure of formation at trestle slab muscle 20, Form this reinforced concrete structure of trestle plate 2.Divide in two relative outsides of foundation pit enclosure structure 1 Not staying and set the first construction joint 21, the second construction joint 22 lateral cross is arranged at the first construction joint 21, and Second construction joint 22 is located at outside another of foundation pit enclosure structure 1.
Trestle beam 5 is connected to the edge of trestle plate 2, and trestle beam 5 includes: trestle beam steel and coagulation Soil structure, wherein the density of trestle beam steel arrangement is more than the density of trestle slab muscle 20 arrangement, adopts With concrete structure pouring in trestle beam steel, thus form the trestle beam 5 of reinforced concrete structure. Trestle beam 5 has bigger bearing capacity, it is ensured that tower crane cushion cap is encorbelmented stablizing when trestle beam 5 Property.
Refering to Fig. 2, it is shown that the floor map of the first construction joint in Fig. 1.Refering to Fig. 3, aobvious Show the floor map of the second construction joint in Fig. 1.Shown in Fig. 1, Fig. 2 and Fig. 3, the Being provided with dabbing layer 210 in one construction joint 21, in the present embodiment, shadow region uses concrete surface exactly Dabbing, the way of cleaning, dabbing is that the instrument with a kind of " cutting axe " is the xoncrete structure being complete A rule indenture is dug out in face, and effect is that the construction surface making two construction stages is firmly bonded.When construction The region surrounded can be separated by first pouring construction seam, conveniently first complete tower crane cushion cap, it is possible to install Tower crane.Generally in cast-in-place structural, after Bars In Poured Concrete Slab is poured, dabbing, carry out next layer of post The cast of wall, makes concrete binding firm.First construction joint is additionally provided with reinforcement planting concrete structure 211. Reinforcement planting concrete structure is connected with the end of dabbing layer 210.Second construction joint 22 also is provided with chisel equally Batt 220.
Tower crane cushion cap 3 is arranged in foundation pit enclosure structure 1, and partially overlaps and be connected to trestle plate 2.In the present embodiment, tower crane cushion cap 3 is rectangle steel tendon concrete structure.Tower crane holds Platform lattice column 3 stays under four angles of rectangle steel tendon concrete structure.Trestle plate 2 also mixes for reinforcing bar Xtah Crude Clay structure, links together tower crane cushion cap 3 and partially overlapping of trestle plate 2, decreases Both floor spaces, thus both met the needs going along with sb. to guard him design, efficiently solve again narrow and small engineering Place vertical transportation machinery horizontal layout problem.
On tower crane cushion cap 3, tower crane is set, for the hoisting construction of engineering.Tower crane cushion cap 3 Prior to the construction of trestle plate 2, tower crane cushion cap 3 has independence, and this is the installation of crane machine Advantage is provided.
The construction method that this utility model utilizes the tower crane cushion cap of foundation pit enclosure structure below is made Illustrate:
Construction foundation pit building enclosure, ready for construction in later period.
Reinforcing bar casting concrete are set in foundation pit enclosure structure, tower crane cushion cap lattice of constructing Post, and tower crane cushion cap of constructing on tower crane cushion cap lattice column.
Construction bridge slab muscle in foundation pit enclosure structure, and casting concrete, form trestle panel structure Post and trestle plate.Together with the partly overlapping of tower crane cushion cap and trestle plate.
Tower crane cushion cap is installed crane machine.
This utility model utilizes having the beneficial effect that of the tower crane cushion cap of foundation pit enclosure structure
This utility model utilizes the tower crane cushion cap of foundation pit enclosure structure to be connected by tower crane cushion cap In the trestle plate of foundation pit enclosure structure, the bottom shelf of tower crane is located at the upper surface of tower crane concrete cushion cap, Thus in the case of construction area is less, tower crane cushion cap and trestle plate are linked together permissible Save space.Building enclosure has displacement constraint effect to tower crane cushion cap, adds tower crane Stability.This utility model had both met the needs going along with sb. to guard him design, efficiently solved again down town The narrow and small engineering ground vertical transportation machinery horizontal layout problem in area.Construction for similar engineering provides relatively Abundant construction experience.Tower crane cushion cap has solely prior to the construction of trestle plate, tower crane cushion cap Vertical property, the installation that this is crane machine provides advantage.
Above in association with accompanying drawing embodiment, this utility model is described in detail, common skill in this area This utility model can be made many variations example by art personnel according to the above description.Thus, in embodiment Some details should not constitute restriction of the present utility model, and this utility model will be with appended claims The scope defined is as protection domain of the present utility model.

Claims (6)

1. the tower crane cushion cap utilizing foundation pit enclosure structure, it is characterised in that including:
The trestle plate being located in foundation pit enclosure structure;
It is connected to the trestle beam on described trestle edges of boards edge;
Tower crane cushion cap, partially overlaps and is connected to described trestle plate and encorbelments in described trestle beam;
It is located at the trestle plate lattice column below described trestle plate;And
It is located at the tower crane cushion cap lattice column below described tower crane cushion cap.
Utilize the tower crane cushion cap of foundation pit enclosure structure, its feature the most as claimed in claim 1 Being, described trestle plate includes:
Trestle slab muscle;And
Pouring in the xoncrete structure of described trestle slab muscle, described trestle plate is provided with cross-coupled First construction joint and the second construction joint.
Utilize the tower crane cushion cap of foundation pit enclosure structure, its feature the most as claimed in claim 2 Be, described first construction is sewed with two, be respectively arranged on described foundation pit enclosure structure two relative outside Side, described second construction joint lateral cross in described first construction joint, described first construction joint and described Second construction joint is equipped with dabbing layer, and described first construction joint is additionally provided with reinforcement planting concrete structure.
Utilize the tower crane cushion cap of foundation pit enclosure structure, its feature the most as claimed in claim 1 Being, described tower crane cushion cap is rectangle steel tendon concrete structure.
Utilize the tower crane cushion cap of foundation pit enclosure structure, its feature the most as claimed in claim 4 Being, described tower crane cushion cap lattice column stays on four angles of described rectangle steel tendon concrete structure Under.
Utilize the tower crane cushion cap of foundation pit enclosure structure, its feature the most as claimed in claim 1 Being, described trestle beam includes:
Trestle beam steel, the density of described trestle beam steel arrangement is more than described trestle plate arrangement of bar Density;And
Pour in the xoncrete structure of described trestle beam steel.
CN201620286493.4U 2016-04-08 2016-04-08 Utilize foundation pit retaining structure's tower crane foundation cushion cap Active CN205475300U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620286493.4U CN205475300U (en) 2016-04-08 2016-04-08 Utilize foundation pit retaining structure's tower crane foundation cushion cap

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620286493.4U CN205475300U (en) 2016-04-08 2016-04-08 Utilize foundation pit retaining structure's tower crane foundation cushion cap

Publications (1)

Publication Number Publication Date
CN205475300U true CN205475300U (en) 2016-08-17

Family

ID=56643465

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620286493.4U Active CN205475300U (en) 2016-04-08 2016-04-08 Utilize foundation pit retaining structure's tower crane foundation cushion cap

Country Status (1)

Country Link
CN (1) CN205475300U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235482A (en) * 2018-10-30 2019-01-18 中建交通建设集团有限公司 Tower crane and its construction method based on bonded prestressed concrete

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235482A (en) * 2018-10-30 2019-01-18 中建交通建设集团有限公司 Tower crane and its construction method based on bonded prestressed concrete
CN109235482B (en) * 2018-10-30 2023-06-02 中建交通建设集团有限公司 Tower crane foundation based on bonded prestressed concrete and construction method thereof

Similar Documents

Publication Publication Date Title
CN103195085B (en) Downward story-adding basement and construction method thereof
CN108487252A (en) A kind of deep foundation pit open cutting is suitable to make construction method
CN103334439A (en) Long-span reinforced concrete inner support structure of rectangular deep foundation pit and construction method of structure
CN101614019A (en) The multilayer underground structure next to existing building self-supporting construction method
CN101914925A (en) Basement by using optimized composite prefabricated arch wall as external wall
CN206545215U (en) A kind of precast spliced sinking type garage parking
CN203296038U (en) High embankment chair-type sheet-pile retaining wall structure
CN205242436U (en) Supplementary soleplate traded interim bearing structure who props during system was gone along with sb. to guard him to underground complex
CN101418569B (en) Optimization complex arch wall combining prefabricated arch leaf, support and major structure
CN208072415U (en) Deep foundation pit reinforced concrete support part changes structure
CN109403654A (en) A kind of underpinning method of existing building structure
CN103967018B (en) Deep big foundation pit angle support level shear structure
CN106088120A (en) Construction method is transferred in a kind of cofferdam
CN106164380A (en) Wind-driven generator fabricated base
KR101187170B1 (en) Application of under pinning method in remodeling
CN207714348U (en) A kind of deep basal pit fast rainfall device
CN205475300U (en) Utilize foundation pit retaining structure's tower crane foundation cushion cap
CN105421477A (en) Construction method for tower crane foundation
CN105888281A (en) Method for utilizing jacking storey-adding technique to promote integrated function of community
CN106193101B (en) Tower crane steel platform pile foundation and its construction method
CN110904992B (en) Elevator foundation member for integrally assembling elevator and construction method thereof
CN207728018U (en) The building structure of skyscraper is built suitable for tier building set
CN105421488A (en) Constriction method for changing support of foundation slab in underground composite enclosure system
CN107916798A (en) The building structure of skyscraper is built suitable for tier building set
CN210117724U (en) Garage foundation structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant