CN205369513U - Non - infiltration detention pond structure of concatenation formula - Google Patents

Non - infiltration detention pond structure of concatenation formula Download PDF

Info

Publication number
CN205369513U
CN205369513U CN201620059234.8U CN201620059234U CN205369513U CN 205369513 U CN205369513 U CN 205369513U CN 201620059234 U CN201620059234 U CN 201620059234U CN 205369513 U CN205369513 U CN 205369513U
Authority
CN
China
Prior art keywords
main splice
gripper shoe
vertical gripper
delaying basin
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620059234.8U
Other languages
Chinese (zh)
Inventor
李习洪
马佳
姜景升
刘肯林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Meihua Yushui Environment Co Ltd
Original Assignee
Wuhan Meihua Yushui Environment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Meihua Yushui Environment Co Ltd filed Critical Wuhan Meihua Yushui Environment Co Ltd
Priority to CN201620059234.8U priority Critical patent/CN205369513U/en
Application granted granted Critical
Publication of CN205369513U publication Critical patent/CN205369513U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a non - infiltration detention pond structure of concatenation formula, be the main member of rivers passageway, the lower part component that the cooperation was fixed bottom the main member including the middle part to and with the main member around the laminating of both sides surface fixed, and the fixed headwall component of both sides cooperation around bottom and the lower part component, main member, lower part component and headwall component enclose into a confined detention pond body, and the main member internal fixation has the overflow weir, and open the overflow weir bottom has the apopore, overflow weir left and right sides surface is fixed with the fit with the inner surface of main member, and the bottom surface is fixed with the laminating of lower part component, and inlet tube and outlet pipe are connected respectively to the headwall component of both sides around the detention pond body, the top of main member is equipped with the inspection well casing. The prefabricated component of modular design and seriation can satisfy not co -content detention pond 's demand, assemble the flexibility, but different whole shapes is assembled by the environment under the base area.

Description

A kind of spliced impermeable delaying basin structure
Technical field
This utility model relates to delaying basin technical field, in particular to a kind of spliced impermeable delaying basin structure.
Background technology
Delaying basin has wide range of applications, and can be used for the undergrounds such as parking lot, street, community, park, even airport, plays the pondage capacity of rainwater, it is prevented that because of the urban waterlogging that rainwater causes.Delaying basin is collected and stores the rainwater through filtering, after directly being discharged by outlet pipe or being filtered by the filter after drain pipe, it is discharged into natural water or city planting ductwork again, so can significantly alleviate the pressure of sewage treatment plant, existing delaying basin structure is an one-piece casting structure, work on the spot amount is big, affected by environment greatly, poor for applicability to varying environment.
Utility model content
The purpose of this utility model seeks to solve the deficiency of above-mentioned background technology, a kind of spliced impermeable delaying basin structure is provided, this structure is spliced to form by multi-sheets, there is multiple assembly form, it is suitable for different environment, greatly reduce the amount of labour of site operation, there is good using value.
For realizing this purpose, spliced impermeable delaying basin structure designed by this utility model, it include middle part for water stream channel main member with coordinate fixing lower member bottom main member, and fit fixing with the front and back both side surface of main member, and bottom coordinates fixing headwall component with the both sides, front and back of lower member;Described main member, lower member and headwall component surround the delaying basin body of a closing, it is fixed with downflow weir in described main member, apopore is had bottom described downflow weir, surface, the described downflow weir left and right sides is fixing with the inner surface laminating of main member, bottom surface is fixing with lower member laminating, and before and after described delaying basin body, the headwall component of both sides connects water inlet pipe and outlet pipe respectively;The top of described main member is provided with inspection well casing.
The arrangement of disconnection type water stream channel: described main member includes at least one water stream channel, does not all connect between described water stream channel;Described main member includes the first main splice that the laminating of multiple head and the tail is fixing, described first main splice includes main splice top board, the left and right sides end face of described main splice top board is connected to vertical gripper shoe, and the central space of the first constituted structure of main splice that the laminating of the plurality of head and the tail is fixing is single water stream channel;Described main splice top board is arch sheet or flat board.
The arrangement of communication type water stream channel: described main member includes a plurality of water stream channel, has at least two water stream channels to be interconnected;Described main member includes the main splice that polylith head and the tail laminating is fixing, the central space of the constituted structure of main splice that the head and the tail laminating of described polylith is fixing is single water stream channel, described main splice includes the main splice of even numbered blocks second, described second main splice includes main splice top board, the left and right sides end face of described main splice top board is connected to vertical gripper shoe, the bottom center of the vertical gripper shoe of described second main splice side has current via, the vertical gripper shoe that each piece of vertical gripper shoe with current via all has current via with another block fits;Described main splice top board is arch sheet or flat board.
Further, described main splice also includes the 3rd main splice, described 3rd main splice includes main splice top board, and the left and right sides end face of described main splice top board is connected to vertical gripper shoe, and the bottom center of the vertical gripper shoe of described 3rd main splice both sides all has current via.
Further, described main splice also includes at least one piece of the first main splice, and described first main splice includes main splice top board, and the left and right sides end face of described main splice top board is connected to vertical gripper shoe.
Concrete, described headwall component includes polylith splicing end plate, the splicing end plate connection water inlet pipe of described delaying basin rear body, anterior splicing end plate connection outlet pipe;
Concrete, described lower member is for building base plate, the described left and right sides building base plate has and coordinates the first fixing groove bottom the vertical gripper shoe of main member, the width of described first groove is corresponding with the width of single vertical gripper shoe, the described both sides, front and back building base plate have the second groove that the splicing endplate root with headwall component coordinates, and described downflow weir bottom surface is fixed with building plate top surface laminating.
Preferably, described in build the middle part of base plate and have and the 3rd groove coordinated bottom two pieces of vertical gripper shoes, the width of described 3rd groove is corresponding with the twice of the width of single vertical gripper shoe.
The another kind of version of lower member: described lower member is the delaying basin base of a cuboid-type, including base plate and around the fixing four pieces of base side plates of base plate peripheral surface, the bottom surface of described base side plate is concordant with the bottom surface of base plate, and the height of base side plate is more than the thickness of base plate;Before and after described delaying basin base, the top of the base side plate of both sides has the first draw-in groove that the splicing endplate root with headwall component coordinates, the top of the base side plate of the described delaying basin base left and right sides has the second draw-in groove that the vertical gripper shoe with main member coordinates, and the width of described second draw-in groove is corresponding with the width of single vertical gripper shoe.
Preferably, described base plate is provided with fixed block along its length, and the top of described fixed block has and the 3rd draw-in groove coordinated bottom two pieces of vertical gripper shoes, and the width of described 3rd draw-in groove is corresponding with the twice of the width of single vertical gripper shoe.
Further, described base plate is provided with multiple fixed block, and the gap between the fixed block that the front and back of described base plate are two pieces adjacent is corresponding with the current via bottom vertical gripper shoe.
The beneficial effects of the utility model are: 1, the prefabricated components of modular design and seriation can meet the demand of not co-content delaying basin;2, prefabricated components span is little, and the overall delaying basin intensity of composition is high, and bearing capacity is strong;3, greatly reducing the workload at scene, shorten curing cycle, simple installation is efficient;4, assembled flexible, different global shapes can be assembled into according to underground environment (such as the non-disconnectable facility removed);5, prefabricated components can produce in locality, reduces cost of transportation;6, the quality of easily controllable modular unit;7, construction is affected little by on-the-spot weather.
Accompanying drawing explanation
Fig. 1 is the explosive view in this utility model to build the impermeable delaying basin based on base plate;
Fig. 2 is the left view in this utility model to build the impermeable delaying basin based on base plate;
Fig. 3 is the top view building base plate in this utility model;
Fig. 4 is the sectional view of A A in Fig. 3;
Fig. 5 is that in this utility model, the main splice of arch coordinates fixing structure sectional view with building base plate;
Fig. 6 is that this utility model main splice of middle plateform type coordinates fixing structure sectional view with building base plate;
Fig. 7 is the front view of the splicing end plate being connected with water inlet pipe in this utility model;
Fig. 8 is the left view splicing end plate in this utility model;
Fig. 9 is the front view of the splicing end plate being connected with outlet pipe in this utility model;
Figure 10 is the explosive view of the impermeable delaying basin in this utility model based on delaying basin base;
Figure 11 is the left view of the impermeable delaying basin in this utility model based on delaying basin base;
Figure 12 is the top view of delaying basin base in this utility model;
Figure 13 is the sectional view of B B in Figure 12;
Figure 14 is the structure sectional view that in this utility model, the main splice of arch is fixing with delaying basin base engagement;
Figure 15 is the structure sectional view that this utility model main splice of middle plateform type is fixing with delaying basin base engagement;
Figure 16 is the splicing construction one of the delaying basin designed by this utility model;
Figure 17 is the splicing construction two of the delaying basin designed by this utility model;
Figure 18 is the splicing construction three of the delaying basin designed by this utility model;
Wherein, 1 main member, 1.1 first main splices, 1.2 second main splices, 1.3 the 3rd main splices, 2 headwall components, 2.1 splicing end plates, 3 lower member, 3.1 build base plate, 3.2 delaying basin bases, 4 downflow weirs, 5 water inlet pipes, 6 outlet pipes, 7 check well casing, 8 main splice top boards, 9 vertical gripper shoes, 10 current vias, 11 first grooves, 12 second grooves, 13 the 3rd grooves, 14 base plates, 15 cat ladders, 16 base side plates, 17 first draw-in grooves, 18 second draw-in grooves, 19 fixed blocks, 20 the 3rd draw-in grooves, 21 apopores.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
This utility model devises the version of two kinds of lower member, a kind of for building base plate 3.1, the delaying basin based on this base plate, capacity is less, it is adaptable to the less demanding rainwater recycle environment of moisture storage capacity, and advantage is that processing is simple, splicing is convenient, and labor workload is little, convenient construction.Another kind is delaying basin base 3.2, and its moisture storage capacity of the delaying basin based on this base is big, it is adaptable to have certain requirements rainwater recycle environment to moisture storage capacity.
Hereinafter delaying basin two kinds basic is illustrated respectively:
One: to build delaying basin structure based on base plate 3.1 such as shown in Fig. 19:
Structure 1: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes at least one piece of the first main splice 1.1, and the first main splice 1.1 includes main splice top board 8, and the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9;Main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is for building base plate 3.1, the left and right sides building base plate 3.1 has and coordinates the first fixing groove 11 bottom the vertical gripper shoe 9 of main member 1, the width of the first groove 11 is corresponding with the width of single vertical gripper shoe 9, building the second groove 12 that the both sides, front and back of base plate 3.1 have and coordinate bottom the splicing end plate 2.1 of headwall component 2, downflow weir 4 bottom surface is fixed with building the laminating of base plate 3.1 end face.The middle part building base plate 3.1 has and the 3rd groove 13 coordinated bottom two pieces of vertical gripper shoes 9 as required, and the width of the 3rd groove 13 is corresponding with the twice of the width of single vertical gripper shoe 9.
Structure 2: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes the main splice 1.2 of even numbered blocks second, second main splice 1.2 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, the bottom center of the vertical gripper shoe 9 of the second main splice 1.2 side has current via 10, and the vertical gripper shoe 9 with current via 10 fits;Main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is for building base plate 3.1, the left and right sides building base plate 3.1 has and coordinates the first fixing groove 11 bottom the vertical gripper shoe 9 of main member 1, the width of the first groove 11 is corresponding with the width of single vertical gripper shoe 9, building the second groove 12 that the both sides, front and back of base plate 3.1 have and coordinate bottom the splicing end plate 2.1 of headwall component 2, downflow weir 4 bottom surface is fixed with building the laminating of base plate 3.1 end face.The middle part building base plate 3.1 has and the 3rd groove 13 coordinated bottom two pieces of vertical gripper shoes 9 as required, and the width of the 3rd groove 13 is corresponding with the twice of the width of single vertical gripper shoe 9.
Structure 3: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes at least one piece of the first main splice 1.1, and described first main splice 1.1 includes main splice top board 8, and the left and right sides end face of described main splice top board 8 is connected to vertical gripper shoe 9;Described main splice top board 8 is arch sheet or flat board.Also include the main splice 1.2 of even numbered blocks second, second main splice 1.2 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, the bottom center of the vertical gripper shoe 9 of the second main splice 1.2 side has current via 10, and the vertical gripper shoe 9 with current via 10 fits;Main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is for building base plate 3.1, the left and right sides building base plate 3.1 has and coordinates the first fixing groove 11 bottom the vertical gripper shoe 9 of main member 1, the width of the first groove 11 is corresponding with the width of single vertical gripper shoe 9, building the second groove 12 that the both sides, front and back of base plate 3.1 have and coordinate bottom the splicing end plate 2.1 of headwall component 2, downflow weir 4 bottom surface is fixed with building the laminating of base plate 3.1 end face.The middle part building base plate 3.1 has and the 3rd groove 13 coordinated bottom two pieces of vertical gripper shoes 9 as required, and the width of the 3rd groove 13 is corresponding with the twice of the width of single vertical gripper shoe 9.
Structure 4: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes the main splice 1.2 of even numbered blocks second, second main splice 1.2 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, and the bottom center of the vertical gripper shoe 9 of the second main splice 1.2 side has current via 10;Main member 1 also includes the 3rd main splice 1.3,3rd main splice 1.3 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, and the bottom center of the vertical gripper shoe 9 of the 3rd main splice 1.3 both sides all has current via 10;The vertical gripper shoe 9 that each piece of vertical gripper shoe 9 with current via 10 all has current via 10 with another block fits;Main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is for building base plate 3.1, the left and right sides building base plate 3.1 has and coordinates the first fixing groove 11 bottom the vertical gripper shoe 9 of main member 1, the width of the first groove 11 is corresponding with the width of single vertical gripper shoe 9, building the second groove 12 that the both sides, front and back of base plate 3.1 have and coordinate bottom the splicing end plate 2.1 of headwall component 2, downflow weir 4 bottom surface is fixed with building the laminating of base plate 3.1 end face.The middle part building base plate 3.1 has and the 3rd groove 13 coordinated bottom two pieces of vertical gripper shoes 9 as required, and the width of the 3rd groove 13 is corresponding with the twice of the width of single vertical gripper shoe 9.
Structure 5: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes at least one piece of the first main splice 1.1, the main splice of even numbered blocks second 1.2 and at least one piece of the 3rd main splice 1.3, first main splice 1.1 includes main splice top board 8, and the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9;Second main splice 1.2 includes main splice top board 8, and the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, and the bottom center of the vertical gripper shoe 9 of the second main splice 1.2 side has current via 10;3rd main splice 1.3 includes main splice top board 8, and the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, and the bottom center of the vertical gripper shoe 9 of the 3rd main splice 1.3 both sides all has current via 10;The vertical gripper shoe 9 that each piece of vertical gripper shoe 9 with current via 10 all has current via 10 with another block fits;Main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is for building base plate 3.1, the left and right sides building base plate 3.1 has and coordinates the first fixing groove 11 bottom the vertical gripper shoe 9 of main member 1, the width of the first groove 11 is corresponding with the width of single vertical gripper shoe 9, building the second groove 12 that the both sides, front and back of base plate 3.1 have and coordinate bottom the splicing end plate 2.1 of headwall component 2, downflow weir 4 bottom surface is fixed with building the laminating of base plate 3.1 end face.The middle part building base plate 3.1 has and the 3rd groove 13 coordinated bottom two pieces of vertical gripper shoes 9 as required, and the width of the 3rd groove 13 is corresponding with the twice of the width of single vertical gripper shoe 9.
Two: the delaying basin based on delaying basin base 3.2 is such as shown in Figure 10 15:
Structure 1: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes at least one piece of the first main splice 1.1, and the first main splice 1.1 includes main splice top board 8, and the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, and main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is the delaying basin base 3.2 of a cuboid-type, including base plate 14 and around the fixing four pieces of base side plates 16 of base plate 14 peripheral surface, the bottom surface of base side plate 16 is concordant with the bottom surface of base plate 14, and the height of base side plate 16 is more than the thickness of base plate 14;Before and after delaying basin base 3.2, the top of the base side plate 16 of both sides has and the first draw-in groove 17 coordinated bottom the splicing end plate 2.1 of headwall component 2, the top of the base side plate 16 of delaying basin base 3.2 left and right sides has the second draw-in groove 18 that the vertical gripper shoe 9 with main member 1 coordinates, and the width of the second draw-in groove 18 is corresponding with the width of single vertical gripper shoe 9.Base plate 14 is provided with fixed block 19 as required along its length, and the top of fixed block 19 has and the 3rd draw-in groove 20 coordinated bottom two pieces of vertical gripper shoes 9, and the width of the 3rd draw-in groove 20 is corresponding with the twice of the width of single vertical gripper shoe 9.
Structure 2: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes the main splice 1.2 of even numbered blocks second, second main splice 1.2 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, the bottom center of the vertical gripper shoe 9 of the second main splice 1.2 side has current via 10, and the vertical gripper shoe 9 with current via 10 fits;Main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is the delaying basin base 3.2 of a cuboid-type, including base plate 14 and around the fixing four pieces of base side plates 16 of base plate 14 peripheral surface, the bottom surface of base side plate 16 is concordant with the bottom surface of base plate 14, and the height of base side plate 16 is more than the thickness of base plate 14;Before and after delaying basin base 3.2, the top of the base side plate 16 of both sides has and the first draw-in groove 17 coordinated bottom the splicing end plate 2.1 of headwall component 2, the top of the base side plate 16 of delaying basin base 3.2 left and right sides has the second draw-in groove 18 that the vertical gripper shoe 9 with main member 1 coordinates, and the width of the second draw-in groove 18 is corresponding with the width of single vertical gripper shoe 9.Base plate 14 is provided with fixed block 19 as required along its length, and the top of fixed block 19 has and the 3rd draw-in groove 20 coordinated bottom two pieces of vertical gripper shoes 9, and the width of the 3rd draw-in groove 20 is corresponding with the twice of the width of single vertical gripper shoe 9.Base plate 14 is provided with multiple fixed block 19 as required, and the gap between the fixed block 19 that the front and back of base plate 14 are two pieces adjacent is corresponding with the current via 10 bottom vertical gripper shoe 9.
Structure 3: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes at least one piece of the first main splice 1.1, and described first main splice 1.1 includes main splice top board 8, and the left and right sides end face of described main splice top board 8 is connected to vertical gripper shoe 9;Described main splice top board 8 is arch sheet or flat board.Also include the main splice 1.2 of even numbered blocks second, second main splice 1.2 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, the bottom center of the vertical gripper shoe 9 of the second main splice 1.2 side has current via 10, and the vertical gripper shoe 9 with current via 10 fits;Main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is the delaying basin base 3.2 of a cuboid-type, including base plate 14 and around the fixing four pieces of base side plates 16 of base plate 14 peripheral surface, the bottom surface of base side plate 16 is concordant with the bottom surface of base plate 14, and the height of base side plate 16 is more than the thickness of base plate 14;Before and after delaying basin base 3.2, the top of the base side plate 16 of both sides has and the first draw-in groove 17 coordinated bottom the splicing end plate 2.1 of headwall component 2, the top of the base side plate 16 of delaying basin base 3.2 left and right sides has the second draw-in groove 18 that the vertical gripper shoe 9 with main member 1 coordinates, and the width of the second draw-in groove 18 is corresponding with the width of single vertical gripper shoe 9.Base plate 14 is provided with fixed block 19 as required along its length, and the top of fixed block 19 has and the 3rd draw-in groove 20 coordinated bottom two pieces of vertical gripper shoes 9, and the width of the 3rd draw-in groove 20 is corresponding with the twice of the width of single vertical gripper shoe 9.Base plate 14 is provided with multiple fixed block 19 as required, and the gap between the fixed block 19 that the front and back of base plate 14 are two pieces adjacent is corresponding with the current via 10 bottom vertical gripper shoe 9.
Structure 4: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes the main splice 1.2 of even numbered blocks second, second main splice 1.2 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, and the bottom center of the vertical gripper shoe 9 of the second main splice 1.2 side has current via 10;Main member 1 also includes the 3rd main splice 1.3,3rd main splice 1.3 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, and the bottom center of the vertical gripper shoe 9 of the 3rd main splice 1.3 both sides all has current via 10;The vertical gripper shoe 9 that each piece of vertical gripper shoe 9 with current via 10 all has current via 10 with another block fits;Main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is the delaying basin base 3.2 of a cuboid-type, including base plate 14 and around the fixing four pieces of base side plates 16 of base plate 14 peripheral surface, the bottom surface of base side plate 16 is concordant with the bottom surface of base plate 14, and the height of base side plate 16 is more than the thickness of base plate 14;Before and after delaying basin base 3.2, the top of the base side plate 16 of both sides has and the first draw-in groove 17 coordinated bottom the splicing end plate 2.1 of headwall component 2, the top of the base side plate 16 of delaying basin base 3.2 left and right sides has the second draw-in groove 18 that the vertical gripper shoe 9 with main member 1 coordinates, and the width of the second draw-in groove 18 is corresponding with the width of single vertical gripper shoe 9.Base plate 14 is provided with fixed block 19 as required along its length, and the top of fixed block 19 has and the 3rd draw-in groove 20 coordinated bottom two pieces of vertical gripper shoes 9, and the width of the 3rd draw-in groove 20 is corresponding with the twice of the width of single vertical gripper shoe 9.Base plate 14 is provided with multiple fixed block 19 as required, and the gap between the fixed block 19 that the front and back of base plate 14 are two pieces adjacent is corresponding with the current via 10 bottom vertical gripper shoe 9.
Structure 5: include main member 1 that middle part is water stream channel and coordinate fixing lower member 3 bottom main member 1, and fixing with the front and back both side surface laminating of main member 1, and bottom coordinates the headwall component 2 fixed with the both sides, front and back of lower member 3;Main member 1, lower member 3 and headwall component 2 surround the delaying basin body of a closing, downflow weir 4 it is fixed with in main member 1, apopore 21 is had bottom downflow weir 4, surface, downflow weir 4 left and right sides is fixing with the inner surface laminating of main member 1, bottom surface is fixing with lower member 3 laminating, and before and after delaying basin body, the headwall component 2 of both sides connects water inlet pipe 5 and outlet pipe 6 respectively;The top of main member 1 is provided with inspection well casing 7.
Main member 1 includes at least one piece of the first main splice 1.1, the main splice of even numbered blocks second 1.2 and at least one piece of the 3rd main splice 1.3, first main splice 1.1 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, second main splice 1.2 includes main splice top board 8, the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, and the bottom center of the vertical gripper shoe 9 of the second main splice 1.2 side has current via 10;3rd main splice 1.3 includes main splice top board 8, and the left and right sides end face of main splice top board 8 is connected to vertical gripper shoe 9, and the bottom center of the vertical gripper shoe 9 of the 3rd main splice 1.3 both sides all has current via 10;The vertical gripper shoe 9 that each piece of vertical gripper shoe 9 with current via 10 all has current via 10 with another block fits;Main splice top board 8 is arch sheet or flat board.
Headwall component 2 includes polylith splicing end plate 2.1, and the splicing end plate 2.1 of delaying basin rear body connects water inlet pipe 5, and anterior splicing end plate 2.1 connects outlet pipe 6;Lower member 3 is the delaying basin base 3.2 of a cuboid-type, including base plate 14 and around the fixing four pieces of base side plates 16 of base plate 14 peripheral surface, the bottom surface of base side plate 16 is concordant with the bottom surface of base plate 14, and the height of base side plate 16 is more than the thickness of base plate 14;Before and after delaying basin base 3.2, the top of the base side plate 16 of both sides has and the first draw-in groove 17 coordinated bottom the splicing end plate 2.1 of headwall component 2, the top of the base side plate 16 of delaying basin base 3.2 left and right sides has the second draw-in groove 18 that the vertical gripper shoe 9 with main member 1 coordinates, and the width of the second draw-in groove 18 is corresponding with the width of single vertical gripper shoe 9.Base plate 14 is provided with fixed block 19 as required along its length, and the top of fixed block 19 has and the 3rd draw-in groove 20 coordinated bottom two pieces of vertical gripper shoes 9, and the width of the 3rd draw-in groove 20 is corresponding with the twice of the width of single vertical gripper shoe 9.Base plate 14 is provided with multiple fixed block 19 as required, and the gap between the fixed block 19 that the front and back of base plate 14 are two pieces adjacent is corresponding with the current via 10 bottom vertical gripper shoe 9.
For convenience of the maintenance checking well casing 7 in this utility model, also on splicing end plate 2.1, it is provided with cat ladder 15.During rainfall, rainwater is after preliminary filtration, and cleaner rainwater enters storage in delaying basin, plays the pondage capacity of rainwater.After rainfall terminates, directly discharged by outlet pipe or after being filtered by the filter after drain pipe 6, then be discharged into natural water or city planting ductwork.
Downflow weir 4 it is provided with in delaying basin, the aperture in downflow weir 4 upper water-out hole 21 is significantly smaller than water inlet pipe 5 and the caliber of outlet pipe 6, when the flow of water inlet pipe 5 exceedes the flow in downflow weir 4 upper water-out hole 21, water level in delaying basin is gradually increasing, and inflow is when exceeding the water-retention volume of delaying basin, the unnecessary water yield will overflow across downflow weir 4 and be directly discharged to natural water or city planting ductwork by outlet pipe 6.Delaying basin base 3.2 or build base plate 3.1 and all can machine at the scene, is made as standard component can realize the quick assembling under various varying environments by main splice and splicing end plate 2.1.Main splice, splicing end plate 2.1 are precast concrete, and delaying basin base 3.2 is concrete cast in situs part with building base plate 3.1.
As shown in Figure 16 18, delaying basin can be spliced into different version according to environment, with satisfied construction needs.
The above, be only preferred embodiment of the present utility model, and structure of the present utility model is not done any pro forma restriction.Every any simple modification, equivalent variations and modification above example made according to technical spirit of the present utility model, all still falls within the scope of the technical solution of the utility model.

Claims (10)

1. a spliced impermeable delaying basin structure, it is characterized in that: it includes the main member (1) that middle part is water stream channel and coordinates fixing lower member (3) with main member (1) bottom, and fit fixing with the front and back both side surface of main member (1), and bottom coordinates fixing headwall component (2) with the both sides, front and back of lower member (3);Described main member (1), lower member (3) and headwall component (2) surround the delaying basin body of a closing, downflow weir (4) it is fixed with in described main member (1), described downflow weir (4) bottom has apopore (21), described downflow weir (4) surface, the left and right sides is fixing with the inner surface laminating of main member (1), bottom surface is fixing with lower member (3) laminating, and before and after described delaying basin body, the headwall component (2) of both sides connects water inlet pipe (5) and outlet pipe (6) respectively;The top of described main member (1) is provided with inspection well casing (7).
2. spliced impermeable delaying basin structure as claimed in claim 1, it is characterised in that: described main member (1) includes at least one water stream channel, does not all connect between described water stream channel;Described main member (1) includes the first main splice (1.1) that the laminating of multiple head and the tail is fixing, described first main splice (1.1) includes main splice top board (8), the left and right sides end face of described main splice top board (8) is connected to vertical gripper shoe (9), and the central space of the first main splice (1.1) constituted structure that the laminating of the plurality of head and the tail is fixing is single water stream channel;Described main splice top board (8) is arch sheet or flat board.
3. spliced impermeable delaying basin structure as claimed in claim 1, it is characterised in that: described main member (1) includes a plurality of water stream channel, has at least two water stream channels to be interconnected;Described main member (1) includes the main splice that polylith head and the tail laminating is fixing, the central space of the constituted structure of main splice that the head and the tail laminating of described polylith is fixing is single water stream channel, described main splice includes the main splice of even numbered blocks second (1.2), described second main splice (1.2) includes main splice top board (8), the left and right sides end face of described main splice top board (8) is connected to vertical gripper shoe (9), the bottom center of the vertical gripper shoe (9) of described second main splice (1.2) side has current via (10), the vertical gripper shoe (9) that each piece of vertical gripper shoe (9) with current via (10) all has current via (10) with another block fits;Described main splice top board (8) is arch sheet or flat board.
4. spliced impermeable delaying basin structure as claimed in claim 3, it is characterized in that: described main splice also includes the 3rd main splice (1.3), described 3rd main splice (1.3) includes main splice top board (8), the left and right sides end face of described main splice top board (8) is connected to vertical gripper shoe (9), and the bottom center of the vertical gripper shoe (9) of described 3rd main splice (1.3) both sides all has current via (10).
5. the spliced impermeable delaying basin structure as described in claim 3 or 4, it is characterized in that: described main splice also includes at least one piece of the first main splice (1.1), described first main splice (1.1) includes main splice top board (8), and the left and right sides end face of described main splice top board (8) is connected to vertical gripper shoe (9).
6. spliced impermeable delaying basin structure as claimed in claim 1, it is characterized in that: described headwall component (2) includes polylith splicing end plate (2.1), the splicing end plate (2.1) of described delaying basin rear body connects water inlet pipe (5), and anterior splicing end plate (2.1) connects outlet pipe (6);
Described lower member (3) is for building base plate (3.1), vertical gripper shoe (9) bottom that the described left and right sides building base plate (3.1) has with main member (1) coordinates fixing the first groove (11), the width of described first groove (11) is corresponding with the width of single vertical gripper shoe (9), the described both sides, front and back building base plate (3.1) have the second groove (12) that splicing end plate (2.1) bottom with headwall component (2) coordinates, described downflow weir (4) bottom surface is fixed with building the laminating of base plate (3.1) end face.
7. spliced impermeable delaying basin structure as claimed in claim 6, it is characterized in that: described in build the 3rd groove (13) that the middle part of base plate (3.1) has and two pieces of vertical gripper shoes (9) bottoms coordinate, the width of described 3rd groove (13) is corresponding with the twice of the width of single vertical gripper shoe (9).
8. spliced impermeable delaying basin structure as claimed in claim 1, it is characterized in that: described headwall component (2) includes polylith splicing end plate (2.1), the splicing end plate (2.1) of described delaying basin rear body connects water inlet pipe (5), and anterior splicing end plate (2.1) connects outlet pipe (6);
Described lower member (3) is the delaying basin base (3.2) of a cuboid-type, including base plate (14) and around the fixing four pieces of base side plates (16) of base plate (14) peripheral surface, the bottom surface of described base side plate (16) is concordant with the bottom surface of base plate (14), and the height of base side plate (16) is more than the thickness of base plate (14);Before and after described delaying basin base (3.2), the top of the base side plate (16) of both sides has the first draw-in groove (17) that splicing end plate (2.1) bottom with headwall component (2) coordinates, the top of the base side plate (16) of described delaying basin base (3.2) left and right sides has the second draw-in groove (18) that the vertical gripper shoe (9) with main member (1) coordinates, and the width of described second draw-in groove (18) is corresponding with the width of single vertical gripper shoe (9).
9. spliced impermeable delaying basin structure as claimed in claim 8, it is characterized in that: described base plate (14) is provided with fixed block (19) along its length, the top of described fixed block (19) has the 3rd draw-in groove (20) coordinated with two pieces of vertical gripper shoe (9) bottoms, and the width of described 3rd draw-in groove (20) is corresponding with the twice of the width of single vertical gripper shoe (9).
10. spliced impermeable delaying basin structure as claimed in claim 9, it is characterized in that: described base plate (14) is provided with multiple fixed block (19), the gap between the fixed block (19) that the front and back of described base plate (14) are two pieces adjacent is corresponding with the current via (10) of vertical gripper shoe (9) bottom.
CN201620059234.8U 2016-01-21 2016-01-21 Non - infiltration detention pond structure of concatenation formula Expired - Fee Related CN205369513U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620059234.8U CN205369513U (en) 2016-01-21 2016-01-21 Non - infiltration detention pond structure of concatenation formula

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620059234.8U CN205369513U (en) 2016-01-21 2016-01-21 Non - infiltration detention pond structure of concatenation formula

Publications (1)

Publication Number Publication Date
CN205369513U true CN205369513U (en) 2016-07-06

Family

ID=56274034

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620059234.8U Expired - Fee Related CN205369513U (en) 2016-01-21 2016-01-21 Non - infiltration detention pond structure of concatenation formula

Country Status (1)

Country Link
CN (1) CN205369513U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484352A (en) * 2016-01-21 2016-04-13 武汉美华禹水环境有限公司 Spliced impervious detention pond structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484352A (en) * 2016-01-21 2016-04-13 武汉美华禹水环境有限公司 Spliced impervious detention pond structure

Similar Documents

Publication Publication Date Title
TWI577275B (en) Building wall structure
CN105863019A (en) Sewage intercepting type environment-friendly gutter inlet device
CN110016886A (en) River near-nature forest eco-embankment
CN205369512U (en) Concatenation formula infiltration detention pond structure
CN205369513U (en) Non - infiltration detention pond structure of concatenation formula
CN209741602U (en) Drainage system for ground
CN206844095U (en) Grid type rain-water drainage and collection system
CN205530645U (en) Concatenation formula reservoir structure
CN105696698A (en) Spliced-type storage tank structure
CN208202091U (en) A kind of prefabricated stormwater channel of landscape type
CN208202075U (en) Assembled biology stranded belt suitable for Mountainous City
CN207277526U (en) A kind of rainwater depth-type filtration pond of modularization assembling and filtration apparatus
CN205475651U (en) Non - infiltration detention pond of rising to a height shape cast member
CN205369510U (en) Non - infiltration detention pond of rectangle frame cast member
CN214694950U (en) Municipal administration paving brick
CN212771825U (en) Garden road surface stone material laying structure
CN105484352A (en) Spliced impervious detention pond structure
CN211482089U (en) Be used for construction concatenation formula afforestation wall of industrial factory building
CN105544711A (en) Splicing type permeation detention pond structure
CN206189234U (en) Formula of catchmenting curb
CN110521439A (en) Assembled rainwater flower bed
CN201981714U (en) Novel siphon type rain strainer
CN204780503U (en) Road drainage structures
CN205742348U (en) Clear water storage system
CN212103537U (en) Town road paves road surface structure that permeates water

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160706

Termination date: 20220121