CN205369231U - Steel -pipe pile is filled in drilling - Google Patents

Steel -pipe pile is filled in drilling Download PDF

Info

Publication number
CN205369231U
CN205369231U CN201620095038.6U CN201620095038U CN205369231U CN 205369231 U CN205369231 U CN 205369231U CN 201620095038 U CN201620095038 U CN 201620095038U CN 205369231 U CN205369231 U CN 205369231U
Authority
CN
China
Prior art keywords
pile
pipe
steel pipe
grouting
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620095038.6U
Other languages
Chinese (zh)
Inventor
朱长歧
刘海峰
王星
吴文娟
朱初初
秦月
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Institute of Rock and Soil Mechanics of CAS
Original Assignee
Wuhan Institute of Rock and Soil Mechanics of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Institute of Rock and Soil Mechanics of CAS filed Critical Wuhan Institute of Rock and Soil Mechanics of CAS
Priority to CN201620095038.6U priority Critical patent/CN205369231U/en
Application granted granted Critical
Publication of CN205369231U publication Critical patent/CN205369231U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

本实用新型公开了一种钻孔灌注钢管桩,涉及岩土力学的桩基工程技术。本实用新型的结构主要是:在钢管桩的外壁均匀垂直设置有4根侧壁注浆管,在钢管桩的内壁均匀垂直设置有4根后压浆注浆管,4根侧壁注浆管和4根后压浆注浆管互为均匀交错, 在钢管桩的外壁,沿纵向每隔50cm距离设置一圈横向的箍筋,箍筋在后压浆注浆管处断开,从而构成预制的桩体;在钻孔内垂直设置有上述预制的桩体;在钢管桩内浇筑有混凝土,在后压浆注浆管、侧壁注浆管内以及桩体以外的空隙内浇筑有水泥浆。与现有技术相比,本实用新型施工效率高,能够保证桩体的垂直度及其质量,可靠性好;桩群施工时,预制的桩体可安装高桩平台和码头。

The utility model discloses a bored perfusion steel pipe pile, which relates to the pile foundation engineering technology of rock and soil mechanics. The structure of the utility model is mainly as follows: 4 side wall grouting pipes are uniformly and vertically arranged on the outer wall of the steel pipe pile, 4 post-pressure grouting pipes are evenly and vertically arranged on the inner wall of the steel pipe pile, The grout pipes and the 4 post-pressure grouting pipes are evenly interlaced. On the outer wall of the steel pipe pile, a circle of horizontal stirrups is arranged at an interval of 50cm in the longitudinal direction. The stirrups are disconnected at the post-pressure grouting pipes. Thereby forming a prefabricated pile body; the above-mentioned prefabricated pile body is vertically arranged in the borehole; concrete is poured in the steel pipe pile, and poured in the post-pressure grouting pipe, the side wall grouting pipe and the gap outside the pile body There is grout. Compared with the prior art, the utility model has high construction efficiency, can ensure the verticality and quality of the pile body, and has good reliability; during the pile group construction, the prefabricated pile body can be installed with a high pile platform and a wharf.

Description

一种钻孔灌注钢管桩A bored steel pipe pile

技术领域 technical field

本实用新型涉及岩土力学的桩基工程技术,具体涉及到一种钻孔灌注钢管桩。 The utility model relates to the pile foundation engineering technology of rock and soil mechanics, in particular to a bored perfusion steel pipe pile.

背景技术 Background technique

在港口工程和离岸工程中,高承台桩和加固桩应用普遍。高承台桩的桩身出水面以上,结构为透空式,对波浪的反射小,易于靠泊;桩基础具有受力性能好和整体稳定性强的特点。 In port engineering and offshore engineering, high cap piles and reinforced piles are widely used. The pile body of the high cap pile is above the water surface, the structure is air-permeable, the reflection of waves is small, and it is easy to berth; the pile foundation has the characteristics of good mechanical performance and strong overall stability.

港口工程中的桩基大量采用混凝土预制桩和预制钢管桩,在基岩埋深较浅或软岩地基上大多采用钻孔灌注桩。通常的灌注桩采用钢筋笼作为骨架结构,但在海港工程中,由于桩身需要出水面指定高度,并需要与承台相连,所以采用钢筋笼作为骨架时,需要在桩身出水面以下位置焊接预留钢筋。 A large number of prefabricated concrete piles and prefabricated steel pipe piles are used for pile foundations in port projects, and bored piles are mostly used on shallow bedrock or soft rock foundations. Usually cast-in-situ piles use steel cages as the skeleton structure, but in harbor projects, since the pile body needs to be at a specified height above the water surface and needs to be connected to the cap, when using steel cages as the skeleton, it needs to be welded below the water surface of the pile body Reserve steel bars.

在裸露海床、珊瑚礁盘和软岩地基上,采用打入预制钢管桩的方法具有一定的困难,同时也会破坏软岩结构。在锤击过程中震动会影响珊瑚礁盘的生态环境。如果采用其他方式的桩基技术,施工难度大,效率低,工程造价增加。 On the exposed seabed, coral reef and soft rock foundation, the method of driving prefabricated steel pipe piles has certain difficulties, and it will also damage the soft rock structure. Vibration during hammering can affect the ecology of coral reefs. If other methods of pile foundation technology are adopted, the construction will be difficult, the efficiency will be low, and the project cost will increase.

因此需要一种高效、可靠性好、利用率高的桩基及其施工方法。 Therefore need a kind of efficient, reliable, high utilization rate pile foundation and its construction method.

实用新型内容 Utility model content

本实用新型的目的就在于克服现有技术存在的问题,提供一种钻孔灌注钢管桩。 The purpose of the utility model is to overcome the problems existing in the prior art and provide a bored steel pipe pile.

本实用新型的目的是这样实现的: The purpose of this utility model is achieved in that:

本实用新型包括钢管桩、后压浆注浆管、侧壁注浆管、混凝土注浆管、钻孔、箍筋和法兰; The utility model comprises a steel pipe pile, a post-pressure grouting pipe, a side wall grouting pipe, a concrete grouting pipe, a drill hole, a stirrup and a flange;

在钢管桩的外壁均匀垂直设置有4根侧壁注浆管,在钢管桩的内壁均匀垂直设置有4根后压浆注浆管,4根侧壁注浆管和4根后压浆注浆管互为均匀交错,在钢管桩的外壁,沿纵向每隔50cm距离设置一圈横向的箍筋,箍筋在后压浆注浆管处断开,从而构成预制的桩体; On the outer wall of the steel pipe pile, there are 4 side wall grouting pipes evenly and vertically, and on the inner wall of the steel pipe pile, there are 4 post-grouting pipes, 4 side wall grouting pipes and 4 post-grouting pipes The grouting pipes are uniformly interlaced with each other. On the outer wall of the steel pipe pile, a circle of horizontal stirrups is arranged at a distance of 50 cm along the longitudinal direction. The stirrups are disconnected at the post-pressing grouting pipes to form a prefabricated pile body;

在钻孔内垂直设置有上述预制的桩体; The above-mentioned prefabricated pile body is vertically arranged in the borehole;

在钢管桩的中心,垂直设置有1根混凝土注浆管(为施工临时构件,浇注完成后移出),混凝土注浆管由多分段通过法兰连接而成; In the center of the steel pipe pile, a concrete grouting pipe is vertically arranged (it is a temporary component for construction and will be removed after pouring), and the concrete grouting pipe is made of multi-sections connected by flanges;

在钢管桩内浇筑有混凝土,在后压浆注浆管、侧壁注浆管内以及桩体以外的空隙内浇筑有水泥浆。 Concrete is poured in the steel pipe pile, and cement slurry is poured in the post-pressure grouting pipe, the side wall grouting pipe and the gap outside the pile body.

与现有技术相比,本实用新型具有下列优点和积极效果: Compared with the prior art, the utility model has the following advantages and positive effects:

①施工效率高,能够保证桩体的垂直度及其质量,可靠性好; ①The construction efficiency is high, the verticality and quality of the pile body can be guaranteed, and the reliability is good;

②桩群施工时,预制的桩体可安装高桩平台和码头; ② During pile group construction, the prefabricated pile body can be installed with high pile platform and wharf;

③可避免传统钻孔灌注桩采用钢筋笼作为骨架时需要焊接等施工步骤,桩体的整体性强。 ③ It can avoid construction steps such as welding when the traditional bored pile uses the steel cage as the skeleton, and the integrity of the pile body is strong.

附图说明 Description of drawings

图1为本实用新型的结构示意图; Fig. 1 is the structural representation of the utility model;

图2为本实用新型截面的示意图。 Fig. 2 is a schematic diagram of a section of the utility model.

图中: In the picture:

1—钢管桩; 1—steel pipe pile;

2—后压浆注浆管; 2—Post-pressing grouting pipe;

3—侧壁注浆管; 3—side wall grouting pipe;

4—混凝土注浆管; 4—Concrete grouting pipe;

5—钻孔; 5—drilling;

6—箍筋; 6—stirrup;

7—法兰。 7—Flange.

具体实施方式 detailed description

下面结合附图对本实用新型详细说明。 Below in conjunction with accompanying drawing, the utility model is described in detail.

一、总体 1. Overall

如图1、2,本实用新型包括钢管桩1、后压浆注浆管2、侧壁注浆管3、混凝土注浆管4、钻孔5、箍筋6和法兰7; As shown in Figures 1 and 2, the utility model includes a steel pipe pile 1, a back grouting pipe 2, a sidewall grouting pipe 3, a concrete grouting pipe 4, a bore 5, a stirrup 6 and a flange 7;

在钢管桩1的外壁均匀垂直设置有4根侧壁注浆管3,在钢管桩1的内壁均匀垂直设置有4根后压浆注浆管2,4根侧壁注浆管3和4根后压浆注浆管2互为均匀交错,在钢管桩1的外壁,沿纵向每隔50cm距离设置一圈横向的箍筋6,箍筋6在后压浆注浆管2处断开,从而构成预制的桩体; Four side wall grouting pipes 3 are uniformly and vertically arranged on the outer wall of the steel pipe pile 1, and four post-pressure grouting pipes 2, four side wall grouting pipes 3 and The four post-pressure grouting pipes 2 are uniformly interlaced with each other. On the outer wall of the steel pipe pile 1, a circle of horizontal stirrups 6 is arranged at an interval of 50 cm in the longitudinal direction. open to form a prefabricated pile;

在钻孔5内垂直设置有上述预制的桩体; The above-mentioned prefabricated pile body is vertically arranged in the borehole 5;

在钢管桩1的中心,垂直设置有1根混凝土注浆管4(为施工临时构件,浇注完成后移出),混凝土注浆管4由多分段通过法兰7连接而成; In the center of the steel pipe pile 1, a concrete grouting pipe 4 is vertically arranged (it is a temporary component for construction, and is removed after pouring), and the concrete grouting pipe 4 is connected by multi-sections through flanges 7;

在钢管桩1内浇筑有混凝土,在后压浆注浆管2、侧壁注浆管3内以及桩体以外的空隙内浇筑有水泥浆。 Concrete is poured in the steel pipe pile 1, and cement slurry is poured in the post-pressure grouting pipe 2, the side wall grouting pipe 3 and the voids outside the pile body.

工作机理: Working mechanism:

预制的桩体在钻孔5内放置固定以后,通过侧壁注浆管3压入高压水泥浆,水泥浆由侧壁注浆管3的下部冒出,向上流动填充钢管桩1和钻孔5之间的空隙;在水泥浆凝结硬化后,利用混凝土注浆管4向钢管桩1内浇筑混凝土(混凝土注浆管4在浇筑过程中不断上提,并使混凝土注浆管4的端口至少保持在混凝土液面以下20cm);在混凝土凝结后通过后压浆注浆管2压入高压水泥浆;在钢管桩1外壁焊接的箍筋6可以提高钢管桩1和水泥浆的咬合力。 After the prefabricated pile body is placed and fixed in the borehole 5, high-pressure cement slurry is pressed through the sidewall grouting pipe 3, and the cement slurry emerges from the lower part of the sidewall grouting pipe 3, and flows upward to fill the steel pipe pile 1 and the borehole. 5; after the cement slurry has solidified and hardened, use the concrete grouting pipe 4 to pour concrete into the steel pipe pile 1 (the concrete grouting pipe 4 is continuously lifted during the pouring process, and the port of the concrete grouting pipe 4 keep at least 20cm below the concrete liquid level); after the concrete sets, press the high-pressure cement slurry through the post-pressing grouting pipe 2; the stirrup 6 welded on the outer wall of the steel pipe pile 1 can improve the bite of the steel pipe pile 1 and the cement slurry force.

二、功能部件 2. Functional components

1、钢管桩1 1. Steel pipe pile 1

钢管桩1是一种钢管,外径:60-100cm,壁厚:30-50mm;其功能是作为钻孔灌注钢管桩的主体骨架,抗压强度高,桩身稳定性好。 The steel pipe pile 1 is a steel pipe with an outer diameter of 60-100cm and a wall thickness of 30-50mm; its function is to serve as the main skeleton of the drilled steel pipe pile, with high compressive strength and good stability of the pile body.

2、后压浆注浆管2 2. Post-pressure grouting pipe 2

后压浆注浆管2为一种铁皮管,密封好,外径30mm,壁厚3mm;后压浆注浆管2均匀地焊接在钢管桩1的内壁上;在钢管桩1内浇筑混凝土后,在混凝土凝结硬化一段时间后,通过后压浆注浆管2压入高压水泥浆。 Post-grouting grouting pipe 2 is an iron pipe, sealed well, with an outer diameter of 30 mm and a wall thickness of 3 mm; post-grouting grouting pipe 2 is evenly welded on the inner wall of steel pipe pile 1; After the concrete, after the concrete sets and hardens for a period of time, the high-pressure grout is pressed through the post-pressing grouting pipe 2 .

3、侧壁注浆管3 3. Side wall grouting pipe 3

侧壁注浆管3为一种铁皮管,密封好,外径30mm,壁厚3mm;侧壁注浆管3 The side wall grouting pipe 3 is an iron pipe, well sealed, with an outer diameter of 30 mm and a wall thickness of 3 mm; the side wall grouting pipe 3

均匀的焊接在钢管桩1的侧壁上,并与后压浆注浆管2交错排列。在钢管桩1固定放置在钻孔5内后,通过侧壁注浆管3压入高压水泥浆,水泥浆可以填充钻孔5和钢管桩1的空隙。 Uniformly welded on the side wall of the steel pipe pile 1, and arranged in a staggered manner with the post-grouting grouting pipes 2. After the steel pipe pile 1 is fixedly placed in the borehole 5, high-pressure cement slurry is pressed through the side wall grouting pipe 3, and the cement slurry can fill the gap between the borehole 5 and the steel pipe pile 1.

4、混凝土注浆管4 4. Concrete grouting pipe 4

混凝土注浆管4为一种钢管,外径200mm,壁厚10mm;混凝土注浆管4在钢管桩1中心处,通过混凝土注浆管4向钢管桩1内浇筑混凝土。 The concrete grouting pipe 4 is a steel pipe with an outer diameter of 200 mm and a wall thickness of 10 mm; the concrete grouting pipe 4 is at the center of the steel pipe pile 1, and concrete is poured into the steel pipe pile 1 through the concrete grouting pipe 4 .

5、钻孔5 5. Drilling 5

钻孔5采用机械钻取,钻孔5的内径大于焊接完成后的桩体直径。 The borehole 5 is mechanically drilled, and the inner diameter of the borehole 5 is greater than the diameter of the pile body after welding.

6、箍筋6 6. Stirrup 6

箍筋6为普通螺纹钢筋,箍筋6焊接在钢管桩的圆周,在侧壁注浆管3处断开,沿纵向每隔50cm设置一圈箍筋。 The stirrups 6 are ordinary threaded steel bars, and the stirrups 6 are welded on the circumference of the steel pipe pile, disconnected at the side wall grouting pipe 3, and a circle of stirrups is arranged at intervals of 50 cm along the longitudinal direction.

7、法兰7 7. Flange 7

法兰7是市售规格商品,用于混凝土注浆管4的接头连接。 The flange 7 is a commercially available standard product, which is used for the joint connection of the concrete grouting pipe 4 .

三、施工方法 3. Construction method

施工流程分为:桩体预制、钻孔、清孔、埋放预制的桩体、压入侧壁水泥浆、浇注混凝土、压入后压浆。 The construction process is divided into: pile body prefabrication, drilling, hole clearing, embedding the prefabricated pile body, pressing the side wall cement slurry, pouring concrete, and pressing the grout after pressing.

1、在钢管桩1的内壁均匀分布焊接4根后压浆注浆管2,在钢管桩1外壁,均匀焊接4根侧壁注浆管3; 1. On the inner wall of the steel pipe pile 1, 4 post-grouting pipes 2 are evenly distributed, and on the outer wall of the steel pipe pile 1, 4 side wall grouting pipes 3 are evenly welded;

2、施工时,首先采用钻机钻出直径略大于桩体直径的钻孔,达到指定深度后清孔;利用吊机吊装埋放桩体,将桩体定位后通过高压注浆机,利用侧壁注浆管3,在桩体和钻孔5的内壁的空隙间注入水泥浆;水泥浆从侧壁注浆管3最下端冲出,充满空隙;在水泥浆达到终凝时间具有一定强度时,利用混凝土注浆管4向钢管桩1内浇筑混凝土,在浇筑结束12h内采用清水冲阀,并利用高压注浆机通过后压浆注浆管2压入水泥浆。 2. During construction, first use a drilling rig to drill a hole with a diameter slightly larger than the diameter of the pile body, and clear the hole after reaching the specified depth; use a crane to lift and bury the pile body, position the pile body, pass a high-pressure grouting machine, and use the side wall The grouting pipe 3 is used to inject cement slurry into the gap between the pile body and the inner wall of the borehole 5; the cement slurry is rushed out from the bottom end of the side wall grouting pipe 3 and filled with the gap; Use the concrete grouting pipe 4 to pour concrete into the steel pipe pile 1, use the clear water to flush the valve within 12 hours after pouring, and use a high-pressure grouting machine to press the grout through the post-pressing grouting pipe 2.

Claims (1)

1. a drill-pouring steel-pipe pile, it is characterised in that:
Including steel-pipe pile (1), post jacking Grouting Pipe (2), side wall grouting pipe (3), concrete grouting pipe (4), boring (5), stirrup (6) and flange (7);
Outer wall uniform vertical at steel-pipe pile (1) is provided with 4 side wall grouting pipes (3), inwall uniform vertical at steel-pipe pile (1) is provided with 4 post jacking Grouting Pipe (2), 4 side wall grouting pipes (3) and 4 post jacking Grouting Pipe (2) are uniformly interlocked each other, outer wall in steel-pipe pile (1), longitudinally the stirrup (6) that one circle is horizontal is set every 50cm distance, stirrup (6) disconnects at post jacking Grouting Pipe (2) place, thus constituting prefabricated pile body;
It is vertically installed with above-mentioned prefabricated pile body in boring (5);
At the center of steel-pipe pile (1), being vertically installed with 1 concrete grouting pipe (4), concrete grouting pipe (4) is formed by connecting by flange (7) by many segmentations;
In steel-pipe pile (1), build concrete, in the space in post jacking Grouting Pipe (2), side wall grouting pipe (3) and beyond pile body, build cement mortar.
CN201620095038.6U 2016-01-29 2016-01-29 Steel -pipe pile is filled in drilling Expired - Fee Related CN205369231U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620095038.6U CN205369231U (en) 2016-01-29 2016-01-29 Steel -pipe pile is filled in drilling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620095038.6U CN205369231U (en) 2016-01-29 2016-01-29 Steel -pipe pile is filled in drilling

Publications (1)

Publication Number Publication Date
CN205369231U true CN205369231U (en) 2016-07-06

Family

ID=56262353

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620095038.6U Expired - Fee Related CN205369231U (en) 2016-01-29 2016-01-29 Steel -pipe pile is filled in drilling

Country Status (1)

Country Link
CN (1) CN205369231U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592517A (en) * 2016-12-28 2017-04-26 中交航局第二工程有限公司 Construction method for constructing long piled wharf on land
CN108330817A (en) * 2018-03-16 2018-07-27 广东省冶金建筑设计研究院 It is a kind of to hold the Abutment Reinforcement structure and its construction method for tilting a miniature clump of piles using end
CN111778993A (en) * 2020-07-21 2020-10-16 上海市城市建设设计研究总院(集团)有限公司 Rapid construction of steel pipe pile enclosure structure and its construction method
CN113186903A (en) * 2021-06-10 2021-07-30 河南中城建设集团股份有限公司 Combined pile structure and construction method for treating insufficient bearing capacity of deep foundation pit construction pile by adopting combined pile structure
CN113622411A (en) * 2021-08-10 2021-11-09 上海市机械施工集团有限公司 Tubular pile side-rear grouting device and construction method
CN114808944A (en) * 2022-04-22 2022-07-29 上海同人里岩土工程技术有限公司 Grouting and expanding concrete-filled steel tubular column pile and its construction method
CN114808945A (en) * 2022-04-28 2022-07-29 中铁时代建筑设计院有限公司 A kind of foundation pit supporting cast-in-situ large-diameter pipe pile and construction method of pipe pile
CN115182369A (en) * 2022-07-29 2022-10-14 中交(南京)建设有限公司 Dewatering well structure and pile foundation construction method reconstructed by utilizing dewatering well

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592517A (en) * 2016-12-28 2017-04-26 中交航局第二工程有限公司 Construction method for constructing long piled wharf on land
CN108330817A (en) * 2018-03-16 2018-07-27 广东省冶金建筑设计研究院 It is a kind of to hold the Abutment Reinforcement structure and its construction method for tilting a miniature clump of piles using end
CN111778993A (en) * 2020-07-21 2020-10-16 上海市城市建设设计研究总院(集团)有限公司 Rapid construction of steel pipe pile enclosure structure and its construction method
CN113186903A (en) * 2021-06-10 2021-07-30 河南中城建设集团股份有限公司 Combined pile structure and construction method for treating insufficient bearing capacity of deep foundation pit construction pile by adopting combined pile structure
CN113622411A (en) * 2021-08-10 2021-11-09 上海市机械施工集团有限公司 Tubular pile side-rear grouting device and construction method
CN114808944A (en) * 2022-04-22 2022-07-29 上海同人里岩土工程技术有限公司 Grouting and expanding concrete-filled steel tubular column pile and its construction method
CN114808945A (en) * 2022-04-28 2022-07-29 中铁时代建筑设计院有限公司 A kind of foundation pit supporting cast-in-situ large-diameter pipe pile and construction method of pipe pile
CN115182369A (en) * 2022-07-29 2022-10-14 中交(南京)建设有限公司 Dewatering well structure and pile foundation construction method reconstructed by utilizing dewatering well

Similar Documents

Publication Publication Date Title
CN205369231U (en) Steel -pipe pile is filled in drilling
CN105201514B (en) A kind of water-bearing stratum shaft wall structure and construction method
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN102493437A (en) Grouting-type micro steel pipe pile and grouting reinforcement method
CN103422510B (en) Steel pipe frame type cofferdam structure and construction method
CN100507160C (en) A rock-socketed composite pile and its construction method
CN104018518A (en) Prefabricated underground diaphragm wall and method for constructing outer basement wall and floor slabs
CN102605767A (en) Precast pile reserved with grouting pipe and piling process of precast pile
CN108583796B (en) Large-scale deep sea oil and gas platform and construction method thereof
CN106930277A (en) A kind of construction of manual-excavation cast-in-place pile method
CN104389315B (en) Consolidation grouting drilled pile wall and construction method thereof
CN101691760B (en) Composite foundation combining anchor rods with excavation and construction method thereof
CN106836240A (en) Basement annular brace construction method for supporting
CN102808407A (en) Construction method of soft-foundation reinforced concrete cast-in-place pile
CN202187340U (en) Concrete Steel Tube Core Column Rock-socketed Pile
CN102418348B (en) Construction technology of using occlusive pile to form underground continuous wall
CN201459749U (en) A stable structure of deepwater steel pipe pile construction platform
CN103603345B (en) Cement mixing grouting pile foundations and forming method
CN105951874B (en) A kind of retaining wall reinforcement structure and its construction method
CN108914947A (en) Foundation pit anchor wall draws the construction method of anchor supporting and its supporting construction of drilling tool and formation
CN201502065U (en) A type of composite foundation for bolt combined excavation
CN201296932Y (en) Segmentation prefabricating sunken outer wall and guide wall thereof
CN111962522A (en) A combined support structure of inclined wedge piles and vertical pipe piles and construction method thereof
CN110792077A (en) Supporting disc pile device suitable for muddy soft soil and construction process thereof
CN102286971A (en) Concrete-filled steel tube core column socketed pile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160706

Termination date: 20220129