CN205314091U - Slip casing by pressure boundling of administering shallow layer landslide shaped steel tubular pile structure that declines - Google Patents

Slip casing by pressure boundling of administering shallow layer landslide shaped steel tubular pile structure that declines Download PDF

Info

Publication number
CN205314091U
CN205314091U CN201521032266.0U CN201521032266U CN205314091U CN 205314091 U CN205314091 U CN 205314091U CN 201521032266 U CN201521032266 U CN 201521032266U CN 205314091 U CN205314091 U CN 205314091U
Authority
CN
China
Prior art keywords
steel
pipe pile
pile
pipe
slip casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201521032266.0U
Other languages
Chinese (zh)
Inventor
马郧
龙晓东
周国安
曾雯
李松
刘佑祥
张晓玉
雷宏达
程莉
郭运
范晓峰
张杨
朱佳
罗春雨
易丽丽
孙盼
倪欣
张德乐
余舜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongnan Survey And Design Institute (hubei) Co Ltd
Original Assignee
Zhongnan Survey And Design Institute (hubei) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongnan Survey And Design Institute (hubei) Co Ltd filed Critical Zhongnan Survey And Design Institute (hubei) Co Ltd
Priority to CN201521032266.0U priority Critical patent/CN205314091U/en
Application granted granted Critical
Publication of CN205314091U publication Critical patent/CN205314091U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a slip casing by pressure boundling of administering shallow layer landslide shaped steel tubular pile structure that declines, including steel -pipe pile, pile bolck guan liang and crossbeam, the per campshed of forming more than two lines or two lines of steel -pipe pile, each campshed top is equipped with a pile bolck guan liang, and the steel -pipe pile top in each campshed all imbeds pile bolck guanliang and is connected with pile bolck guanliang, links to each other through the crossbeam between the adjacent pile bolck hat roof beam. The utility model discloses space layout is nimble, adaptive capacity to environment strong, the construction is simple and convenient, need not to use large -scale machinery equipment, to all ring edge border disturbances little, save the time limit for a project.

Description

A kind of slip casing by pressure cluster type miniature steel pipe pilework administering shallow failure
Technical field
This utility model relates to a kind of slip casing by pressure cluster type miniature steel pipe pilework, it is adaptable to shallow failure harnessing project.
Background technology
Along with urban land day is becoming tight, surrounding enviroment are more and more complicated, engineering construction inevitably runs into shallow failure governing problem, such often small scale that comes down, but the environment caused after generation sliding failure, social influence are bigger, for avoiding having a negative impact, need it is carried out rapid reinforcement process, but traditional landslip treatmant mode is such as arranged that friction pile, antiskid retaining wall etc. be less economical, complicated organization, duration are longer, construction site is required higher by plant equipment, it is impossible to implement in the landslide control engineering of the type. Therefore, shallow failure harnessing project proposition quickly Landslide Remedial Measures on Some effective, convenient construction nervous for surrounding enviroment, that construction site is narrow and small is particularly important.
Summary of the invention
Problem to be solved in the utility model is to provide a kind of slip casing by pressure cluster type miniature steel pipe pilework administering shallow failure, this utility model space flexible arrangement, adaptive capacity to environment are strong, easy construction, without using heavy mechanical equipment, surrounding enviroment disturbance is little, save the duration.
Technical solution of the present utility model is: a kind of slip casing by pressure cluster type miniature steel pipe pilework administering shallow failure, including steel-pipe pile, stake apical cap beam and crossbeam, every two row of described steel-pipe pile or two row composition described above one campsheds, each campshed top is provided with an apical cap beam, steel-pipe pile top in each campshed all embeds an apical cap beam and is connected with stake apical cap beam, is connected by crossbeam between adjacent studs apical cap beam.
Described steel-pipe pile adopts the miniature steel pipe pile of perforate, and stake apical cap beam adopts reinforced beam with crossbeam.
This utility model also includes steel pipe stake holes, and steel pipe stake holes aperture is more than steel-pipe pile external diameter, and steel-pipe pile inserts in steel pipe stake holes, gap between described steel-pipe pile outer wall and steel pipe stake holes hole wall and be filled with cement grout or cement mortar in steel-pipe pile.
Described cement grout and cement mortar technical parameter are as follows:
(1) ratio of mud of cement grout and cement mortar all desirable 0.6 ~ 1.0, the cement-sand ratio of cement mortar is preferably 1.5 ~ 2, and grouting water pH cannot be less than 4;
(2) flow of slip casting desirable (7 ~ 10) L/min, adopts hole-bottom slurry-injection, and grouting pressure dynamically can control according to on-site actual situations.
The beneficial effects of the utility model are: for shallow failure harnessing project, by arranging slip casing by pressure cluster type miniature steel pipe pilework, improve slope stability, it is ensured that the safety of side slope and surrounding enviroment, construction machinery is marched into the arena conveniently, without using large-scale heavy duty equipment, reducing the disturbance to formation and surrounding enviroment, space flexible arrangement in work progress, adaptive capacity to environment is strong, efficiency of construction is high, it is possible to save significantly on the duration.
Accompanying drawing explanation
Fig. 1 is plane graph of the present utility model;
Fig. 2 is the A-A profile of Fig. 1;
Fig. 3 is the B-B profile of Fig. 1;
Fig. 4 is the skiagraph of this utility model steel-pipe pile 1;
Fig. 5 is the plane outspread drawing of this utility model steel-pipe pile 1;
Fig. 6 is the C-C profile of this utility model steel-pipe pile 4;
Fig. 7 is the D-D profile of this utility model steel-pipe pile 4.
Detailed description of the invention
Referring to Fig. 1 ~ 7, this utility model includes steel-pipe pile 1, stake apical cap beam 2, crossbeam 3, every two row of described steel-pipe pile 1 or two row composition described above one campsheds, each campshed top is provided with an apical cap beam 2, steel-pipe pile 1 top in each campshed all embeds an apical cap beam 2 and is connected with stake apical cap beam 2, is connected by crossbeam 3 between adjacent studs apical cap beam 2.
Described steel-pipe pile 1 adopts the miniature steel pipe pile of perforate, and stake apical cap beam 2 and crossbeam 3 adopt reinforced beam.
This utility model also includes steel pipe stake holes, and steel pipe stake holes aperture is more than steel-pipe pile external diameter, and steel-pipe pile 1 inserts in steel pipe stake holes, gap between described steel-pipe pile 1 outer wall and steel pipe stake holes hole wall 4 and be filled with cement grout or cement mortar in steel-pipe pile.
Enforcement step of the present utility model is: first carry out the stake holes drilling construction of steel-pipe pile 1, pore-forming aperture is more than the external diameter of steel-pipe pile 1, the sequence of construction of steel-pipe pile 1 should adopt jumping to dig method construction, until after stake holes drilling construction arrives designed elevation, insert the steel-pipe pile 1 of perforate, the strict stake top mark height controlling steel-pipe pile 1, it is ensured that the steel-pipe pile 1 insert depth in stake apical cap beam 2; Then inside steel-pipe pile 1, insert Grouting Pipe, adopt cement grout or cement mortar carry out hole-bottom slurry-injection by the gap between steel-pipe pile 1 outer wall and hole wall 4 and in steel-pipe pile filling closely knit, slip casing by pressure needs in time; Finally according to designing requirement, construction stake apical cap beam 2 and crossbeam 3, ultimately form slip casing by pressure cluster type miniature steel pipe pilework.
The shallow failure harnessing project that this utility model is nervous for surrounding enviroment, construction site is narrow and small, adopts slip casing by pressure cluster type miniature steel pipe pilework to carry out landslide control. Every two row of steel-pipe pile or two row composition described above one are arranged, steel-pipe pile should pass sliding surface, enter the sliding bed certain depth of lower stabilizer, row can flexible arrangement according to actual needs, steel-pipe pile stake top arranges concrete Guan Liang, arrange concrete beam between adjacent two row's steel-pipe pile stake apical cap beams to connect, form the reinforcement system with certain space structure. Wherein gap between steel-pipe pile outer wall and hole wall and to adopt cement grout or cement mortar to carry out slip casing by pressure filling in steel-pipe pile closely knit.
This utility model has the advantage that
(1) space flexible arrangement, adaptive capacity to environment are strong: adaptable to environment of slip casing by pressure cluster type miniature steel pipe pilework, do not limited by place scope and landform, the steel-pipe pile of any row can be set according to actual needs, and peripheral steel pipe row of piles can be arranged according to the boundary shape of gliding mass, space is arranged very flexible;
(2) easy construction, save the duration: needed for miniature steel pipe pile, construction equipment is less, and associated construction technique is simple, and efficiency of construction is high, can save significantly on the duration;
(3) surrounding enviroment impact is little: construction is without using heavy mechanical equipment, and miniature steel pipe pile pore-forming aperture is less, and the disturbance of formation and surrounding enviroment is little;
(4) significantly improving slope stability: slip casing by pressure cluster type miniature steel pipe pilework defines the reinforcement system with certain space structure, globality is strong, is greatly improved slope stability.

Claims (3)

1. the slip casing by pressure cluster type miniature steel pipe pilework administering shallow failure, it is characterized in that: include steel-pipe pile, stake apical cap beam and crossbeam, every two row of described steel-pipe pile or two row composition described above one campsheds, each campshed top is provided with an apical cap beam, steel-pipe pile top in each campshed all embeds an apical cap beam and is connected with stake apical cap beam, is connected by crossbeam between adjacent studs apical cap beam.
2. administer the slip casing by pressure cluster type miniature steel pipe pilework of shallow failure as claimed in claim 1, it is characterised in that: described steel-pipe pile adopts the miniature steel pipe pile of perforate, stake apical cap beam and crossbeam to adopt reinforced beam.
3. administer the slip casing by pressure cluster type miniature steel pipe pilework of shallow failure as claimed in claim 2, it is characterized in that: also include steel pipe stake holes, steel pipe stake holes aperture is more than steel-pipe pile external diameter, steel-pipe pile inserts in steel pipe stake holes, gap between described steel-pipe pile outer wall and steel pipe stake holes hole wall and be filled with cement grout or cement mortar in steel-pipe pile.
CN201521032266.0U 2015-12-14 2015-12-14 Slip casing by pressure boundling of administering shallow layer landslide shaped steel tubular pile structure that declines Active CN205314091U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521032266.0U CN205314091U (en) 2015-12-14 2015-12-14 Slip casing by pressure boundling of administering shallow layer landslide shaped steel tubular pile structure that declines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521032266.0U CN205314091U (en) 2015-12-14 2015-12-14 Slip casing by pressure boundling of administering shallow layer landslide shaped steel tubular pile structure that declines

Publications (1)

Publication Number Publication Date
CN205314091U true CN205314091U (en) 2016-06-15

Family

ID=56184921

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521032266.0U Active CN205314091U (en) 2015-12-14 2015-12-14 Slip casing by pressure boundling of administering shallow layer landslide shaped steel tubular pile structure that declines

Country Status (1)

Country Link
CN (1) CN205314091U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677924A (en) * 2018-07-13 2018-10-19 武汉市市政建设集团有限公司 Double miniature steel pipe pile slip casting is at wall partition-type structures and method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677924A (en) * 2018-07-13 2018-10-19 武汉市市政建设集团有限公司 Double miniature steel pipe pile slip casting is at wall partition-type structures and method

Similar Documents

Publication Publication Date Title
CN102155232B (en) Construction method of large-span asymmetrical double-arch railway tunnel under terrain bias pressure condition
CN104631438B (en) Long auger guncreting uplift pile construction method
CN104805854A (en) Method for constructing deep-water ultra-long steel plate pile cofferdam in tide environment
CN205012284U (en) Build dam dam foundation seepage prevention structure on overburden
CN105201001A (en) Composite seepage preventing structure for large karst cave in karst region and construction method thereof
CN107503362A (en) A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN103437370A (en) Method and supporting structure for slip resisting and soil retaining of abrupt slope
CN105569051A (en) Foundation pit support system of sandy pebble boulder geological stratification and construction method
CN207211165U (en) A kind of compound antiskid piling wall retaining structure suitable for reservoir stability
CN104878719A (en) Mutually-embedded reinforced ecological retaining wall construction method
CN104074183A (en) Drilling and concrete injected root composite pile implanting pile structure and construction method
CN205062827U (en) Compound seepage prevention structure of large -scale solution cavity in karst area
CN106120822B (en) A kind of method for protecting support and device that prevent mud stone from coming down
CN105350575B (en) A kind of reversed construction method of diaphram wall
CN205024710U (en) Adopt raft foundation structure of anti prestressed anchorage of floating cable
CN204780990U (en) Combined type retaining wall structure
CN103628890A (en) Soft phyllite tunnel excavation deformation control method
CN203878532U (en) Processing structure for deep, steep and inclined fault crack
CN205314091U (en) Slip casing by pressure boundling of administering shallow layer landslide shaped steel tubular pile structure that declines
CN204212168U (en) A kind of dam water-retaining structure utilizing solution cavity to combine to build a dam
CN204252119U (en) The special-shaped supporting pile structure of X
CN203977433U (en) Soft Deep Foundation Pit engineering composite supporting construction
CN104594367B (en) A kind of combined type cofferdam structure and construction method
CN103966981B (en) Force transferring structure and the construction method thereof of arch dam is built on weathering rock mass
CN105484274B (en) The shallow failure administering method that high-pressure rotary jet grouting pile is combined with cluster type miniature steel pipe pile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant