CN205232248U - Automatic secondary equipment fault handling device of power dispatching based on GIS - Google Patents

Automatic secondary equipment fault handling device of power dispatching based on GIS Download PDF

Info

Publication number
CN205232248U
CN205232248U CN201521073539.6U CN201521073539U CN205232248U CN 205232248 U CN205232248 U CN 205232248U CN 201521073539 U CN201521073539 U CN 201521073539U CN 205232248 U CN205232248 U CN 205232248U
Authority
CN
China
Prior art keywords
unit
fault
gis
running status
collecting unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201521073539.6U
Other languages
Chinese (zh)
Inventor
于学海
任稷松
刘慧超
张金晔
秦荣海
赵昌健
贾培伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Heli Innovation Polytron Technologies Inc
State Grid Corp of China SGCC
Datong Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Original Assignee
Shanxi Heli Innovation Technology Co Ltd
State Grid Corp of China SGCC
Datong Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Heli Innovation Technology Co Ltd, State Grid Corp of China SGCC, Datong Power Supply Co of State Grid Shanxi Electric Power Co Ltd filed Critical Shanxi Heli Innovation Technology Co Ltd
Priority to CN201521073539.6U priority Critical patent/CN205232248U/en
Application granted granted Critical
Publication of CN205232248U publication Critical patent/CN205232248U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model belongs to the technical field of electric power dispatching automation secondary equipment fault handling, the problem of the technique is solved for: provide automatic secondary equipment fault handling device of power dispatching based on GIS, can carry out location processing to the trouble fast, the technical scheme who adopts does: automatic secondary equipment fault handling device of power dispatching based on GIS includes: the main control unit, and respectively with operating data acquisition unit and operating data fault handling unit that the main control unit links to each other, its characterized in that: the operating data fault handling unit includes: trouble information classification unit, failure analysis unit and trouble show unit, failure analysis unit respectively with trouble information classification unit and trouble show unit link to each other, trouble show unit includes: based on GIS's trouble show unit and independent GIS's trouble show unit, the device is suitable for the electric power system.

Description

Based on the power network schedule automation secondary device fault treating apparatus of GIS
Technical field
The utility model belongs to the technical field of power dispatching automation secondary device troubleshooting.
Background technology
Power scheduling is the maincenter that modern power systems normally runs, and it is the basis ensureing power network safety operation; Along with deepening continuously of grid company intelligent grid construction, power dispatching automation electrical secondary system is in guarantee power grid security, high-quality, economical operation, improve the aspects such as the dispatching management level of IT application and played important function, become the technological means that operation of power networks controls, commander is produced in scheduling and modern management is indispensable.
Power dispatching automation electrical secondary system comprises the equipment such as a large amount of network equipments, server, database, middleware, GPS timing device, ups power, this kind of secondary device is being carried out in the monitoring system of centralized monitor and alert analysis, usually gather the data of the said equipment by harvester and carry out discriminatory analysis by the processing unit on backstage, thus generating warning information; But, the alarm mode of conventional electric power system is only generation warning information, and pass through the mode of voice or image, prompting staff, due to electric power system background work, personnel scarcely possess troubleshooting capability, when a failure occurs it, need this kind of fault message to notify that the maintenance work personnel of specialty carry out troubleshooting in the mode such as phone, mail; This mode, the troubleshooting cycle is long, inefficiency, is unfavorable for the safe operation of electrical network.
In addition, because existing power dispatching automation electrical secondary system does not form integrated treatment to the fault of secondary device, all isolated to the collection of the fault message of secondary device, the process of each link such as judgement and breakdown repair, lack contact each other, so, can realize a Search and Orientation for the acquisition monitoring before secondary device fault and fault point, and the electric grid secondary equipment obstacle management device that can realize failure response fast just seems particularly important.
Utility model content
The utility model overcomes the deficiency that prior art exists, and technical problem to be solved is: provide the power network schedule automation secondary device fault treating apparatus based on GIS, can position process fast to fault.
In order to solve the problems of the technologies described above, the technical solution adopted in the utility model is:
Based on the power network schedule automation secondary device fault treating apparatus of GIS, comprising: main control unit, and the service data collecting unit be connected with described main control unit respectively and service data fault processing unit; Described service data fault processing unit comprises: fault message taxon, accident analysis unit and fault display unit, and accident analysis unit is connected with fault display unit with described fault message taxon respectively; Described fault display unit comprises: based on the fault display unit of GIS and the fault display unit of independent GIS.
Described service data collecting unit comprises: communication main station running status collecting unit, time synchronism apparatus running status collecting unit, protection service apparatus running status collecting unit, UPS plant running state acquisition unit, and described communication main station running status collecting unit, time synchronism apparatus running status collecting unit, protection service apparatus running status collecting unit, UPS plant running state acquisition unit are connected with described main control unit respectively by power private network; Described main control unit comprises: basic data filter element and data storage cell, and described basic data filter element is connected with data storage cell with service data collecting unit, fault message taxon respectively; Described fault treating apparatus also comprises: fault alarm unit, and described fault alarm unit is connected with described accident analysis unit; Described fault alarm unit comprises: mobile phone short message reminding unit, and described mobile phone short message reminding unit is connected with the handheld terminal of staff by communication network.
The utility model compared with prior art has following beneficial effect:
1, the running status that the service data collecting unit in the utility model is used for being arranged on on-the-spot all kinds of power dispatching automation secondary devices gathers, and this image data is sent in main control unit, after the basic data filter element of described main control unit filters this image data, on the one hand the data after filtration are sent in fault message taxon and process, on the other hand the data after filtration are sent to data storage cell to store, are convenient to reviewing of late problems; Described fault message taxon is classified to the data received, and sorted data are sent in accident analysis unit process, shorten the response time of staff to fault, improve operating efficiency, improve managerial skills when fault occurs; The utility model structure is simple, practical.
2, in the utility model, place and the fault effects region of fault generation can be understood in time by fault display unit staff, improve staff to the fault pre-alarming of electrical secondary system and disposing capacity, reduce the failure risk of power dispatching automation electrical secondary system, improve the managerial skills of work about electric power personnel, avoid the expansion of accident.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the utility model is described in more detail.
Fig. 1 is electrical block diagram of the present utility model;
In figure: 1 is main control unit; 2 is service data collecting unit; 3 is service data fault processing unit; 4 is fault message taxon; 5 is accident analysis unit; 6 is fault display unit; 7 is communication main station running status collecting unit; 8 is time synchronism apparatus running status collecting unit, and 9 is protection service apparatus running status collecting unit, and 10 is UPS plant running state acquisition unit; data filtering units based on 11; 12 is data storage cell, and 13 is fault alarm unit, and 14 is handheld terminal.
Embodiment
As shown in Figure 1, based on the power network schedule automation secondary device fault treating apparatus of GIS, comprising: main control unit 1, and the service data collecting unit 2 be connected with described main control unit 1 respectively and service data fault processing unit 3; Described service data fault processing unit 3 comprises: fault message taxon 4, accident analysis unit 5 and fault display unit 6, and accident analysis unit 5 is connected with fault display unit 6 with described fault message taxon 4 respectively; Described fault display unit 6 comprises: based on the fault display unit 15 of GIS and the fault display unit 16 of independent GIS.
Particularly; described service data collecting unit 2 comprises: communication main station running status collecting unit 7, time synchronism apparatus running status collecting unit 8, protection service apparatus running status collecting unit 9, UPS plant running state acquisition unit 10, and described communication main station running status collecting unit 7, time synchronism apparatus running status collecting unit 8, protection service apparatus running status collecting unit 9, UPS plant running state acquisition unit 10 are connected with described main control unit 1 respectively by power private network.
Further, described main control unit 1 comprises: basic data filter element 11 and data storage cell 12, and described basic data filter element 11 is connected with data storage cell 12 with service data collecting unit 2, fault message taxon 4 respectively; Described fault treating apparatus also comprises: fault alarm unit 13, described fault alarm unit 13 is connected with described accident analysis unit 5, described fault alarm unit 13 comprises: mobile phone short message reminding unit, and described mobile phone short message reminding unit is connected with the handheld terminal 14 of staff by communication network.
In the present embodiment, described accident analysis unit 5 comprehensively can be analyzed scope belonging to the lasting duration of the time started of fault, fault, fault etc., described accident analysis unit 5 also comprises fault disposal unit, is preset with the fault plan for emergency handling of reply different faults in described fault disposal unit.
The utility model in use, first, described service data collecting unit 2 is for gathering the running status being arranged on on-the-spot all kinds of secondary devices, and this image data is sent in main control unit 1, after the basic data filter element 11 of described main control unit 1 filters this image data, on the one hand the data after filtration are sent in fault message taxon 4 and process, on the other hand the data after filtration are sent to data storage cell 12 to store, are convenient to reviewing of late problems; Secondly, described fault message taxon 4 is classified to the data received, and sorted data are sent in accident analysis unit 5 process, the fault plan for emergency handling of reply different faults is preset with in accident analysis unit 5, when fault rank is generic failure, staff processes fault timely by fault plan for emergency handling, shortens the response time of staff to fault, improves operating efficiency; When fault is significant trouble, fault message is sent to electric power overhaul personnel and the director of specialty by fault alarm unit 13 by accident analysis unit 5 in time, improves managerial skills when fault occurs.
In the present embodiment, described fault display unit 6 comprises: based on the fault display unit 15 of GIS and the fault display unit 16 of independent GIS, staff can understand place and the fault effects region of fault generation in time, improve staff to the fault pre-alarming of electrical secondary system and disposing capacity, reduce the failure risk of electrical secondary system, improve the managerial skills of work about electric power personnel, avoid the expansion of accident; Particularly, by the described fault display unit 15 based on GIS, staff can inquire about the data relevant to fault point, picture, image, map, technical data, managerial knowledge etc.
To sum up, the utility model has substantive distinguishing features and progress, by reference to the accompanying drawings embodiment of the present utility model is explained in detail above, but the utility model is not limited to above-described embodiment, in the ken that those of ordinary skill in the art possess, various change can also be made under the prerequisite not departing from the utility model aim.

Claims (5)

1. based on the power network schedule automation secondary device fault treating apparatus of GIS, comprising: main control unit (1), and the service data collecting unit (2) be connected with described main control unit (1) respectively and service data fault processing unit (3);
It is characterized in that: described service data fault processing unit (3) comprising: fault message taxon (4), accident analysis unit (5) and fault display unit (6), accident analysis unit (5) is connected with fault display unit (6) with described fault message taxon (4) respectively; Described fault display unit (6) comprising: based on the fault display unit (15) of GIS and the fault display unit (16) of independent GIS.
2. the power network schedule automation secondary device fault treating apparatus based on GIS according to claim 1, it is characterized in that: described service data collecting unit (2) comprising: communication main station running status collecting unit (7), time synchronism apparatus running status collecting unit (8), protection service apparatus running status collecting unit (9), UPS plant running state acquisition unit (10), described communication main station running status collecting unit (7), time synchronism apparatus running status collecting unit (8), protection service apparatus running status collecting unit (9), UPS plant running state acquisition unit (10) is connected with described main control unit (1) respectively by power private network.
3. the power network schedule automation secondary device fault treating apparatus based on GIS according to claim 1 and 2, it is characterized in that: described main control unit (1) comprising: basic data filter element (11) and data storage cell (12), described basic data filter element (11) is connected with data storage cell (12) with service data collecting unit (2), fault message taxon (4) respectively.
4. the power network schedule automation secondary device fault treating apparatus based on GIS according to claim 1 and 2, it is characterized in that: described fault treating apparatus also comprises: fault alarm unit (13), described fault alarm unit (13) is connected with described accident analysis unit (5).
5. the power network schedule automation secondary device fault treating apparatus based on GIS according to claim 1 and 2, it is characterized in that: described fault alarm unit (13) comprising: mobile phone short message reminding unit, described mobile phone short message reminding unit is connected with the handheld terminal (14) of staff by communication network.
CN201521073539.6U 2015-12-22 2015-12-22 Automatic secondary equipment fault handling device of power dispatching based on GIS Active CN205232248U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201521073539.6U CN205232248U (en) 2015-12-22 2015-12-22 Automatic secondary equipment fault handling device of power dispatching based on GIS

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201521073539.6U CN205232248U (en) 2015-12-22 2015-12-22 Automatic secondary equipment fault handling device of power dispatching based on GIS

Publications (1)

Publication Number Publication Date
CN205232248U true CN205232248U (en) 2016-05-11

Family

ID=55907288

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201521073539.6U Active CN205232248U (en) 2015-12-22 2015-12-22 Automatic secondary equipment fault handling device of power dispatching based on GIS

Country Status (1)

Country Link
CN (1) CN205232248U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106559741A (en) * 2016-10-18 2017-04-05 中国电力科学研究院 A kind of safe debugging maintenance method and system of equipment noncontact

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106559741A (en) * 2016-10-18 2017-04-05 中国电力科学研究院 A kind of safe debugging maintenance method and system of equipment noncontact
CN106559741B (en) * 2016-10-18 2021-12-03 中国电力科学研究院 Equipment non-contact safety debugging maintenance method and system

Similar Documents

Publication Publication Date Title
CN103728536B (en) Multi-source data grid fault identification method
CN103607042B (en) The distribution network failure processing method of long fault indicator for overhead lines towards outskirts of a town
CN103714437A (en) Power line repair commanding method based on CIS and movable operation
CN203806884U (en) Elevator cloud system allowing manufacturers to be responsible for elevators for life
CN107742925B (en) Transformer substation hard pressing plate inspection method based on three-level network
CN102361351A (en) Remote monitoring diagnosis system of power system
CN105305641A (en) Relay protection information data collection and uploading method
CN103970098A (en) Intelligent substation auxiliary system integrated monitoring platform
CN104539879A (en) Patrol device for infrared probe in remote control zone of unattended substation
CN104237735A (en) Modeling and fault analysis method combining fault indicator and power distribution terminal
CN210422883U (en) Multi-wind-field fan electric centralized control system based on c/s framework
CN205232248U (en) Automatic secondary equipment fault handling device of power dispatching based on GIS
CN110033393A (en) A kind of power system information method for safety monitoring
CN105913126A (en) Transformer station intelligent alarm model method for big data and cloud environment
CN103197200A (en) Method and system for rapidly collecting and transmitting fault ranging information of power grid line
CN202772610U (en) Monitoring system for battery management systems of electric vehicles
CN202978437U (en) Intelligent routing inspection system for transformer substations
CN201946087U (en) Device for avoiding mistaken or failing removal of ground wires
CN204759716U (en) Remote terminal warning system
CN203455712U (en) Transformer station equipment centralized control and inspection tour online-monitoring system
CN205453295U (en) Electric power dispatching automation secondary equipment operational monitoring alarm system
CN204142367U (en) A kind of substation transformer temperature anomaly warning system with remote notification function
CN204789872U (en) Distribution system trouble on -line monitoring system
CN203435091U (en) Remote intelligent monitoring system
CN208688553U (en) A kind of Transformer Condition Monitoring System

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 100031 Xicheng District, Chang'an Avenue, No. 86,

Patentee after: State Grid Corporation of China

Patentee after: DATONG POWER SUPPLY COMPANY, STATE GRID SHANXI ELECTRIC POWER CO., LTD.

Patentee after: Shanxi Heli innovation Polytron Technologies Inc

Address before: 100031 Xicheng District, Chang'an Avenue, No. 86,

Patentee before: State Grid Corporation of China

Patentee before: DATONG POWER SUPPLY COMPANY, STATE GRID SHANXI ELECTRIC POWER CO., LTD.

Patentee before: SHANXI HELI INNOVATION TECHNOLOGY CO., LTD.