CN205226741U - Preliminary treatment steel support system is restoreed to non - excavation of pipeline - Google Patents

Preliminary treatment steel support system is restoreed to non - excavation of pipeline Download PDF

Info

Publication number
CN205226741U
CN205226741U CN201520987745.1U CN201520987745U CN205226741U CN 205226741 U CN205226741 U CN 205226741U CN 201520987745 U CN201520987745 U CN 201520987745U CN 205226741 U CN205226741 U CN 205226741U
Authority
CN
China
Prior art keywords
pipeline
excavation
utility
vertical steel
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520987745.1U
Other languages
Chinese (zh)
Inventor
安关峰
张万辉
梁豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Municipal Engineering Group Co Ltd
Original Assignee
Guangzhou Municipal Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Municipal Engineering Group Co Ltd filed Critical Guangzhou Municipal Engineering Group Co Ltd
Priority to CN201520987745.1U priority Critical patent/CN205226741U/en
Application granted granted Critical
Publication of CN205226741U publication Critical patent/CN205226741U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a preliminary treatment steel support system is restoreed to non - excavation of pipeline, it includes a plurality of support element, adjacent two support element is sharp distribution, and support element includes the two blocks of upright steel sheets that can fix on wall or tu bi, two standing and having arranged between the steel sheet that a plurality of roots are horizontal and support, two up end crossbearers that found steel sheets have an arc steel sheet, the up end of arc steel sheet is fixed on wall or tu bi. Form through adopting a plurality of support element to assemble, two adjacent support element's distance is adjusted to the upright steel sheet of chooseing different length for use and different radial arc steel sheet, adjusts support system's high, width and length, can be applied to the restoration of the disease pipeline of different pipe diameters and length to this system simple manufacture, simple to operate, the utility model discloses better application prospect has. The utility model is suitable for a during the non - excavation of pipeline is restoreed.

Description

Pipeline non-excavation rehabilitation pretreatment bracing members system
Technical field
The utility model relates to a kind of support system in pipeline rehabilitation Study on pretreatment field, particularly a kind of pipeline non-excavation rehabilitation pretreatment bracing members system.
Background technique
Cities and towns water supply and sewerage pipeline is the important component part of Municipal facility, is again simultaneously the underground life line in city, and it bears the discharge function of the supply of tap water and rainwater, sewage.Along with the expansion of urban size, the construction speed of pipe engineering and scale also reach unprecedentedly high level, and the pipeline mileage of such as GuangzhouCity center district reaches 1297.495km.Along with expanding economy, the scale of urban construction is increasing, and the drainage pipe of laying is also more and more longer, and pipeline is also shorter and shorter for remaining service life.Since two thousand one China's urban discharging pipeline is with the speed of 22441.7km/ in increase according to statistics, and the total length of cut-off China's urban discharging pipeline in 2008 is 315220km.Along with the construction of China's drainage pipe, lay pipeline of the remote past and also in succession reach lifetime.The duct length that China laid the eighties in the past is according to statistics 21860km, accounts for 6.93% of drainage pipe overall length.China's drainage pipe face the life-span overdue while, along with the increase of urban water consumption, municipal drainage amount is corresponding reinforcement mouth also, the load that drainage pipe bears is also more and more heavier, and China's insufficient investment in the maintenance, reparation of drainage pipe, cause China's drainage pipe corruption candle, seepage serious, pipeline damage, distortion, the uneven situations such as sedimentation that hook happen occasionally.Pipeline configuration defect and functional defect cause drainage pipe can not play due effect, and rainwater runs, emits, leaks, and block traffic, rainwater can not be got rid of in time, makes troubles to urban construction and people's lives.When 2010 " 5.7 ", liang field, " 5.14 " Guangzhou, rainfall rate is more than the cloudburst of 100mm, many streets, retail shop, parking lot etc. meet with water I, economic loss surpasses 1,000,000,000 yuan, has appeared the problem of drainage pipe impeded drainage suddenly.
The traditional remodeling method of drainage pipe is that excavation lays a new pipeline, but because drainage pipe is generally all laid in urban district that is populous, business prosperity, tube circumference fills other municipal pipeline and the facilities such as sewage, rainwater, coal gas, heating power, electric power, communication cable, ride above part pipeline and press against building or be crushed on completely below road, therefore improvement project implements to there is sizable difficulty.For addressing this problem, no-dig technique pipe rehabilitation technology is applied and gives birth to.Trenchless sewer repair technique is as the new and high technology of development in recent years, and this technology has the features such as construction site is little, construction is simple, avoid the generation of the phenomenon of similar roadbed subsidence or large size water, cost is lower, is widely applied.Pipeline spray repair method is a kind of process engineering representative in non-excavation repairing technique, and the method is applicable to the pipeline of the Large Diameter Pipeline of more than 800mm or the in-situ immobilization of canal case.The method is as sprayed on material using epoxy resin, by the rotary nozzle under the effect of winch pulling force or manual method, material is sprayed successively in old pipeline or canal case, form certain thickness back-up coat, form pipeline-lined compound pipe, reach the entirety reparation to old pipe or canal case.This technology can improve the withstand voltage, corrosion-resistant of pipeline and abrasion resistance properties, extends pipeline or canal case life-span.But the spraying reparation of large pipeline or canal case needs operator to operate in inside, the personal safety of structural instability to operator of pipeline or canal case constitutes titanic peril; If pipeline to be repaired or canal case are positioned at level of ground water higher position, will occur seriously to ooze, leak, have a strong impact on the quality that spraying is repaired; Before the spraying of under ground piping or canal case is repaired, generally all to carry out pretreatment to pipeline or canal case, preprocessing process generally all can adopt the machineries such as percussion drill, electric planer, grinder to process tube wall, and the stability that pipeline or the vibrations of canal inner box-machine tool will destroy pipeline or canal case causes part to cave in.
Drainage pipe pretreatment for structural disease generally adopts method such as polishing cutting, slip casting soil stabilization, pad repairing material etc., and this method is used in pipeline and less mismatch or diafiltration occur, and inapplicable for the pipeline seriously caved in.And at present good preprocess method is not also had to the big-diameter pipeline caved in.At present for this kind of situation, the main cut and cover method that adopts adopts new pipeline to replace by occurring that the pipeline section seriously caved in digs out.Although this method easy construction, cost are lower, construction is considered carefully very fast, are only limitted to open space, traffic flow is less, other pipeline is less, away from the area of building.And at major urban arterial highway, due to large, the various pipeline of traffic flow be interspersed, road periphery tall building stands in great numbers, particularly disease tube circumference in old town generally has more heritage building, just cannot carry out trenchless rehabilitation in this case, original position pretreatment must be carried out in underground to pipeline and recover its pipe shape for non-excavation rehabilitation condition is provided.
Model utility content
The purpose of this utility model, the preprocessing process at the position that caves in for drainage pipe, provides a kind of pipeline non-excavation rehabilitation pretreatment bracing members system, its make in advance simple, easy for installation, utilization efficiency is high, and cost of use is low.
The solution that the utility model solves its technical problem is: pipeline non-excavation rehabilitation pretreatment bracing members system, it comprises multiple support unit, two adjacent described support units linearly distribute, support unit comprises two blocks of vertical steel plates that can be fixed on wall or Tu Bi, some cross-brace are furnished with between two blocks of described vertical steel plates, the upper-end surface crossbearer of two blocks of vertical steel plates has curved plate, and the upper-end surface of described curved plate is fixed on wall or Tu Bi.
As the further improvement of technique scheme, the upper-end surface of described vertical steel plate is provided with groove, groove screw is set in described groove, the two ends of described curved plate are provided with arc-shaped steel screw, and the two ends of described curved plate to be inserted after the groove of two blocks of vertical steel plates by bolt respectively through fixing after groove screw and arc-shaped steel screw.
As the further improvement of technique scheme, described cross-brace comprises the upper cross-brace of arranging from top to bottom, middle cross-brace and lower cross-brace.
As the further improvement of technique scheme, all described support units linearly distribute.
As the further improvement of technique scheme, described vertical steel plate is bolted on wall or Tu Bi.
The beneficial effects of the utility model are: the utility model is by adopting multiple support unit assembled, select the vertical steel plate of different length and the curved plate of different radii, adjust the distance of two adjacent support units, regulate the height of support system, width and length, the reparation of the disease pipeline of different tube diameters and length can be applied to, and this system makes simple, and easy for installation, the utility model has good application prospect.The utility model is applicable in pipeline non-excavation rehabilitation.
Accompanying drawing explanation
In order to be illustrated more clearly in the technological scheme in the utility model embodiment, below the accompanying drawing used required in describing embodiment is briefly described.Obviously, described accompanying drawing is a part of embodiment of the present utility model, instead of whole embodiment, and those skilled in the art, under the prerequisite not paying creative work, can also obtain other design proposals and accompanying drawing according to these accompanying drawings.
Fig. 1 is the sectional view of support unit of the present utility model;
Fig. 2 is the side view of support unit of the present utility model.
Embodiment
Be clearly and completely described below with reference to embodiment and the accompanying drawing technique effect to design of the present utility model, concrete structure and generation, to understand the purpose of this utility model, characteristic sum effect fully.Obviously; described embodiment is a part of embodiment of the present utility model, instead of whole embodiment, based on embodiment of the present utility model; other embodiments that those skilled in the art obtains under the prerequisite not paying creative work, all belong to the scope of the utility model protection.In addition, all connection/annexations mentioned in literary composition, not singly refer to that component directly connects, and refer to and according to concrete performance, can connect auxiliary by adding or reducing, and form more excellent connecting structure.
With reference to Fig. 1 ~ Fig. 2, vertical steel plate 1 stands steel plate and the right side by a left side and founds steel plate and form, all adopt thick 6mm × 0.3m wide × steel plate that 0.8m is high, the spacing that steel plate is found on left vertical steel plate and the right side is 0.8m.A described left side is stood steel plate and the right side and is stood between steel plate and lay three road cross-brace 3, is distributed as cross-brace, middle cross-brace and lower cross-brace.In vertical steel plate 1, the height of 0.2m, 0.5m and the 0.7m at distance steel panel edges 0.1m place, both sides respectively arranges three screws.The upper end of vertical steel plate 1 arranges the groove 4 of a wide 3mm × high 50mm, its steel plate edge of two lateral extents of groove 4 0.1m, respectively apart from the 25mm place, upper end of vertical steel plate arranges a groove screw.Curved plate 2 adopts corrosion resistant plate after thick 2.5mm, its 0.1m place, edge, left and right sides of curved plate 2 middle distance, arranges each arc-shaped steel apart from 25mm place, lower end is each.Left vertical steel plate and the right side are stood on the body of wall or Tu Bi that steel plate is fixed on pipeline both sides by the screw on it, be connected, and adopt bolt to be fixed by groove screw and arc-shaped steel screw with curved plate 2 by groove 4.
Below the embodiment of the utility model when applying:
Draw in the process of digging, should first draw to dig with jack supporting first and after within the scope of drilling depth, draw dig half side, then draw to dig within the scope of the first drilling depth and first draw dig half side; Orient the position in vertical steel plate 1 at pipeline both sides body of wall, and punch with percussion drill; Two edge-on steel plate 1 symmetries are installed to pipeline body of wall both sides, and adopt stainless steel bolt to fix; Fixed by two edge-on steel plates 1 cross-brace 3 points of upper, middle and lowers three kinds of positions, cross-brace 3 is tool type stull; By the groove 4 of vertical steel plate 1, curved plate 2 is in place, and by groove screw and arc-shaped steel screw bolt, vertical steel plate 1 and curved plate 2 is fixed; The installation of first paragraph support unit to be done, will repair stand and advance 0.3m, and carry out the installation of next section of support unit.All described support units linearly distribute.
More than that better embodiment of the present utility model is illustrated, but the invention is not limited to described embodiment, those of ordinary skill in the art also can make all equivalent modifications or replacement under the prerequisite without prejudice to the utility model spirit, and these equivalent modification or replacement are all included in the application's claim limited range.

Claims (5)

1. pipeline non-excavation rehabilitation pretreatment bracing members system, it is characterized in that: it comprises multiple support unit, two adjacent described support units linearly distribute, support unit comprises two blocks of vertical steel plates that can be fixed on wall or Tu Bi, some cross-brace are furnished with between two blocks of described vertical steel plates, the upper-end surface crossbearer of two blocks of vertical steel plates has curved plate, and the upper-end surface of described curved plate is fixed on wall or Tu Bi.
2. pipeline non-excavation rehabilitation pretreatment bracing members system according to claim 1, it is characterized in that: the upper-end surface of described vertical steel plate is provided with groove, groove screw is set in described groove, the two ends of described curved plate are provided with arc-shaped steel screw, and the two ends of described curved plate to be inserted after the groove of two blocks of vertical steel plates by bolt respectively through fixing after groove screw and arc-shaped steel screw.
3. pipeline non-excavation rehabilitation pretreatment bracing members system according to claim 1, is characterized in that: described cross-brace comprises the upper cross-brace of arranging from top to bottom, middle cross-brace and lower cross-brace.
4. pipeline non-excavation rehabilitation pretreatment bracing members system according to claim 1, is characterized in that: all described support units linearly distribute.
5. pipeline non-excavation rehabilitation pretreatment bracing members system according to claim 1, is characterized in that: described vertical steel plate is bolted on wall or Tu Bi.
CN201520987745.1U 2015-12-01 2015-12-01 Preliminary treatment steel support system is restoreed to non - excavation of pipeline Active CN205226741U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520987745.1U CN205226741U (en) 2015-12-01 2015-12-01 Preliminary treatment steel support system is restoreed to non - excavation of pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520987745.1U CN205226741U (en) 2015-12-01 2015-12-01 Preliminary treatment steel support system is restoreed to non - excavation of pipeline

Publications (1)

Publication Number Publication Date
CN205226741U true CN205226741U (en) 2016-05-11

Family

ID=55901807

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520987745.1U Active CN205226741U (en) 2015-12-01 2015-12-01 Preliminary treatment steel support system is restoreed to non - excavation of pipeline

Country Status (1)

Country Link
CN (1) CN205226741U (en)

Similar Documents

Publication Publication Date Title
CN204898721U (en) Steel construction city utility tunnel
CN105064400A (en) Urban comprehensive pipe rack of steel corrugated plate structure
CN104727425A (en) Traction-type non-excavation pipeline repairing method
CN207268009U (en) A kind of underground pipe gallery drainage system based on existing blowdown canal
CN205226741U (en) Preliminary treatment steel support system is restoreed to non - excavation of pipeline
CN205637048U (en) Drainage pipe spraying restoration construction car
CN202228785U (en) Jack type pipe-jacking head for long transmission pipeline
CN104455889A (en) Integrated underground pipe gallery with compensation device
CN206396789U (en) A kind of comprehensive pipe gallery structure for being easy to sewage collecting to discharge
CN101725766B (en) Adjustable lifting support device for heavy-caliber water conveying pipe in subsidence area
CN208748461U (en) It is a kind of for protecting the environmental type road of shallow embedding pipeline
CN206616601U (en) A kind of inspection shaft non-excavation rehabilitation inner-tube structure
CN215104799U (en) Town road bridge crack reinforced structure
CN205134332U (en) Municipal administration delivery pipeline hole groove supporting construction
CN205893897U (en) Be applied to flexible float tube bridge of floating pump station
CN201242014Y (en) Large caliber inner lining restoring composite pipeline
CN212270806U (en) Efficient dust fall maintenance system special for large-area yard behind wharf
CN204959623U (en) Top is advanced construction and is cut arc culvert with steel bell socket
CN203795512U (en) Rainwater recycling device
CN207003608U (en) A kind of municipal water supply and sewerage pipeline stainless steel inner lining tube digging-free safeguards observation well
CN201666412U (en) Adjustable lifting support seat device for large-caliber water pipe in settling region
CN217815501U (en) Pipeline connecting structure for municipal water supply and drainage
CN216741525U (en) Rich sand bed drainage construction is with simple and easy shield structure device
CN215210292U (en) Municipal works road laying structure