CN205172591U - Tunnel concrete placement new plastic formworking jumbo - Google Patents

Tunnel concrete placement new plastic formworking jumbo Download PDF

Info

Publication number
CN205172591U
CN205172591U CN201520919653.XU CN201520919653U CN205172591U CN 205172591 U CN205172591 U CN 205172591U CN 201520919653 U CN201520919653 U CN 201520919653U CN 205172591 U CN205172591 U CN 205172591U
Authority
CN
China
Prior art keywords
frames
screw
tunnel
formwork
plastic formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520919653.XU
Other languages
Chinese (zh)
Inventor
徐维刚
周彩云
鲁满库
黄谱
李涛
李玉才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Engineering Bureau 4 Co Ltd
Original Assignee
Sinohydro Engineering Bureau 4 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Engineering Bureau 4 Co Ltd filed Critical Sinohydro Engineering Bureau 4 Co Ltd
Priority to CN201520919653.XU priority Critical patent/CN205172591U/en
Application granted granted Critical
Publication of CN205172591U publication Critical patent/CN205172591U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本实用新型公开了一种隧洞混凝土浇筑新型模板台车,旨在提供一种省时省力的隧洞混凝土浇筑新型塑料模板台车。它包括两侧的框架,连接支撑两框架内侧的多根水平向的调节螺杆,设置于框架下端的行走轮,安装于框架外侧的塑料模板,以及连接框架的斜撑杆;所述框架均包括两根平行设置的槽钢,以及多根竖直设置且固定连接两槽钢外侧的、由方木制成的围檩;所述塑料模板安装于围檩上;所述调节螺杆包括螺杆套,两根分别螺接于螺杆套两端的螺杆,两根螺杆的端部分别采用螺栓或圆柱销与两框架位置相对应槽钢的内侧连接。本实用新型设置合理,可有效增加整体台车架变形的能力,保证其施工效率。

The utility model discloses a new formwork trolley for concrete pouring in a tunnel, aiming at providing a novel plastic formwork trolley for concrete pouring in a tunnel which saves time and labor. It includes frames on both sides, a plurality of horizontal adjustment screws connecting and supporting the inner sides of the two frames, traveling wheels arranged at the lower end of the frames, plastic formwork installed on the outside of the frames, and diagonal braces connecting the frames; the frames all include Two channel steels arranged in parallel, and a plurality of purlins made of square wood that are vertically arranged and fixedly connected to the outside of the two channel steels; the plastic formwork is installed on the purlins; the adjusting screw includes a screw sleeve, Two screw rods are respectively screwed to the two ends of the screw sleeves, and the ends of the two screw rods are respectively connected with the inner sides of the channel steel corresponding to the positions of the two frames by bolts or cylindrical pins. The utility model has reasonable settings, can effectively increase the deformation capacity of the whole trolley frame, and ensure its construction efficiency.

Description

一种隧洞混凝土浇筑新型塑料模板台车A new plastic formwork trolley for tunnel concrete pouring

技术领域 technical field

本实用新型涉及隧洞施工设备技术领域,尤其是涉及一种隧洞混凝土浇筑新型塑料模板台车。 The utility model relates to the technical field of tunnel construction equipment, in particular to a novel plastic formwork trolley for concrete pouring in a tunnel.

背景技术 Background technique

钢塑料模板台车,是一种传统的隧洞混凝土浇筑使用的浇筑工具,其特点是自身重量大,液压系统的零部件多,行走移动需要安装专门的轨道系统。初期购入成本大,运输成本大,使用时安装费时费力;使用期操作难,行走移动慢,耽误有效的施工时间。后期拆除工作量大,存放场地需求大,难保管。 The steel-plastic formwork trolley is a traditional pouring tool used for concrete pouring in tunnels. It is characterized by its heavy weight, many parts of the hydraulic system, and a special track system needs to be installed for walking and moving. The initial purchase cost is high, the transportation cost is high, and the installation is time-consuming and laborious during use; the operation is difficult during the use period, and the walking movement is slow, which delays the effective construction time. In the later stage, the demolition workload is heavy, the storage space needs to be large, and it is difficult to keep.

实用新型内容 Utility model content

本实用新型克服了现有技术中的缺点,提供了一种成本低,使用简单方便、省时省力的隧洞混凝土浇筑新型塑料模板台车。 The utility model overcomes the disadvantages of the prior art and provides a novel plastic formwork trolley for tunnel concrete pouring with low cost, simple and convenient use, time-saving and labor-saving.

为了解决上述技术问题,本实用新型是通过以下技术方案实现的: In order to solve the above technical problems, the utility model is achieved through the following technical solutions:

一种隧洞混凝土浇筑新型模板台车,其包括两侧的框架,连接支撑两框架内侧的多根水平向的调节螺杆,设置于框架下端的行走轮,安装于框架外侧的塑料模板,以及连接框架的斜撑杆;所述框架均包括两根平行设置的槽钢,以及多根竖直设置且固定连接两槽钢外侧的、由方木制成的围檩;所述塑料模板安装于围檩上;所述调节螺杆包括螺杆套,两根分别螺接于螺杆套两端的螺杆,两根螺杆的端部分别采用螺栓或圆柱销与两框架位置相对应槽钢的内侧连接。 A new formwork trolley for concrete pouring in a tunnel, which includes frames on both sides, a plurality of horizontal adjustment screws connecting and supporting the inner sides of the two frames, walking wheels arranged at the lower end of the frames, plastic formwork installed on the outside of the frames, and connecting frames Diagonal bracing rods; the frame includes two channel steels arranged in parallel, and a plurality of purlins made of square wood that are vertically arranged and fixedly connected to the outside of the two channel steels; the plastic formwork is installed on the purlins Above; the adjusting screw includes a screw sleeve, two screws respectively screwed to both ends of the screw sleeve, and the ends of the two screw rods are respectively connected with the inner sides of the channel steel corresponding to the positions of the two frames by bolts or cylindrical pins.

优选的是,所述斜撑杆通过螺栓与框架连接。 Preferably, the diagonal braces are connected to the frame by bolts.

优选的是,所述围檩与槽钢采用螺栓连接。 Preferably, the purlin and the channel steel are connected by bolts.

优选的是,所述螺杆套的中部设置供工具插入的通孔。 Preferably, a through hole for inserting a tool is provided in the middle of the screw sleeve.

优选的是,所述螺杆套的中部设置有供扳手夹持的夹持部。 Preferably, the middle part of the screw sleeve is provided with a clamping portion for clamping by a wrench.

与现有技术相比,本实用新型具有如下优点: Compared with the prior art, the utility model has the following advantages:

(1)本实用新型通过对目前市场上现有的新型复合塑料模板进行加工、组合使用,进而极大的降低模板采购成本,使用新型塑料模板在保证施工质量的同时,不但提高了施工效率,节约劳动力;还能节约投资,有效节省施工成本,本实用新型可重复多次利用,且可回收,资源浪费少,缩短了移动时间,提高了施工效率。 (1) This utility model greatly reduces the purchase cost of the formwork by processing and combining the existing new composite plastic formwork currently on the market. The use of the new plastic formwork not only improves the construction efficiency while ensuring the construction quality, Save labor force; also save investment, effectively save construction cost, the utility model can be reused many times, and can be recycled, less waste of resources, shortened moving time, and improved construction efficiency.

(2)本实用新型使用塑料模板浇筑的混凝土表面颜色均匀,平整度误差可控制在1mm以内,其光洁度可达到清水混凝土的效果;塑料模板吸水率小,在浇筑过程前浇水过多时不会出现塑料模板变形,浇筑后能很好保持混凝土的水分,较少混凝土容易出现的干裂缝,加快混凝土强度增长,确保混凝土质量。混凝土浇筑前无需涂刷脱模剂,减少了清洁、保养费用,拆模方便,破损较少;塑料模板重量轻、支拆方便,搬运操作劳动强度低、施工效率高。使用寿命长,周转使用次数可达40-100次。塑料模板无毒、无害、无污染,施工使用报废后,可以按比例100%全部回收,是一种绿色施工的环保塑料模板。 (2) The surface color of the concrete poured by using plastic formwork in the utility model is uniform, the flatness error can be controlled within 1mm, and its smoothness can reach the effect of fair-faced concrete; the water absorption rate of the plastic formwork is small, and it will not The deformation of the plastic formwork occurs, and the moisture of the concrete can be well maintained after pouring, and the dry cracks that are easy to appear in the concrete are reduced, the strength of the concrete is accelerated, and the quality of the concrete is ensured. There is no need to apply a release agent before concrete pouring, which reduces cleaning and maintenance costs, and is easy to remove the formwork with less damage; the plastic formwork is light in weight, easy to support and disassemble, low labor intensity in handling operations, and high construction efficiency. The service life is long, and the number of turnover can reach 40-100 times. The plastic formwork is non-toxic, harmless, and non-polluting. After construction and use, it can be recycled 100% in proportion. It is an environmentally friendly plastic formwork for green construction.

(3)本实用新型设置合理,可有效增加整体台车架变形的能力,保证其施工效率。 (3) The utility model has reasonable settings, which can effectively increase the deformation capacity of the whole trolley frame and ensure its construction efficiency.

附图说明 Description of drawings

为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。 In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are only some embodiments of the utility model, and those skilled in the art can also obtain other drawings according to these drawings without any creative effort.

图1为本实用新型的结构示意图。 Fig. 1 is the structural representation of the utility model.

图2为图1的俯视图。 FIG. 2 is a top view of FIG. 1 .

具体实施方式 detailed description

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有付出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。 The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

图1-2所示的隧洞混凝土浇筑新型模板台车,其包括两侧的框架1,连接支撑两框架1内侧的多根水平向的调节螺杆2,设置于框架1下端的行走轮3,安装于框架1外侧的塑料模板4,以及连接框架1的斜撑杆5;所述框架1均包括两根平行设置的槽钢11,以及多根竖直设置且固定连接两槽钢11外侧的、由方木制成的围檩12;所述塑料模板4安装于围檩12上;所述调节螺杆2包括螺杆套21,两根分别螺接于螺杆套21两端的螺杆22,两根螺杆22的端部分别采用螺栓或圆柱销与两框架1位置相对应槽钢11的内侧连接。 The new formwork trolley for tunnel concrete pouring shown in Figure 1-2 includes frames 1 on both sides, multiple horizontal adjustment screws 2 that connect and support the inner sides of the two frames 1, and walking wheels 3 that are arranged at the lower end of the frame 1. The plastic template 4 on the outside of the frame 1, and the diagonal braces 5 connecting the frame 1; the frame 1 includes two channel steels 11 arranged in parallel, and a plurality of vertically arranged and fixedly connected to the outside of the two channel steels 11, A purlin 12 made of square wood; the plastic template 4 is installed on the purlin 12; the adjusting screw 2 includes a screw sleeve 21, two screw rods 22 respectively screwed to both ends of the screw sleeve 21, and two screw rods 22 The ends of the two frames 1 are respectively connected with the inner sides of the corresponding channel steel 11 by bolts or cylindrical pins.

其中,所述斜撑杆5优选通过螺栓与框架1连接,所述围檩12与槽钢11优选采用螺栓连接,所述螺杆套21的中部设置供工具插入的通孔6,便于调节。显然,也可以在螺杆套21的中部设置有供扳手夹持的夹持部。 Wherein, the diagonal brace 5 is preferably connected to the frame 1 by bolts, the purlin 12 and the channel steel 11 are preferably connected by bolts, and the middle part of the screw sleeve 21 is provided with a through hole 6 for tool insertion, which is convenient for adjustment. Apparently, a clamping portion for clamping by a wrench may also be provided in the middle of the screw sleeve 21 .

使用时,在施工现场将框架、行走轮、塑料模板及调节螺杆进行组装,之后旋拧调节螺杆使框架上的塑料模板外移到达浇筑位置,并安装上斜撑杆即可浇筑。浇筑完成后,移除斜撑杆,调松调节螺杆即可移动模板台车进入下一浇筑工段。 When in use, the frame, walking wheels, plastic formwork and adjusting screw are assembled on the construction site, and then the adjusting screw is screwed to move the plastic formwork on the frame to the pouring position, and the upper diagonal brace is installed to pour. After the pouring is completed, remove the diagonal brace and loosen the adjusting screw to move the formwork trolley to the next pouring section.

本实用新型有效的避免了常规钢制模板拼装费时费力和钢模台车移动不便的问题,进而有效避免因常规模板台车笨重、装拆不便而带来的费时费力,有效加快现场施工的进度。 The utility model effectively avoids the time-consuming and labor-intensive assembly of conventional steel formwork and the inconvenience of moving the steel formwork trolley, thereby effectively avoiding the time-consuming and laborious problems caused by the heavy conventional formwork trolley and inconvenient assembly and disassembly, and effectively speeding up the progress of on-site construction .

以上所述仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。 The above descriptions are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present utility model shall be included in the Within the protection scope of the present utility model.

Claims (5)

1.一种隧洞混凝土浇筑新型模板台车,其特征在于:包括两侧的框架,连接支撑两框架内侧的多根水平向的调节螺杆,设置于框架下端的行走轮,安装于框架外侧的塑料模板,以及连接框架的斜撑杆;所述框架均包括两根平行设置的槽钢,以及多根竖直设置且固定连接两槽钢外侧的、由方木制成的围檩;所述塑料模板安装于围檩上;所述调节螺杆包括螺杆套,两根分别螺接于螺杆套两端的螺杆,两根螺杆的端部分别采用螺栓或圆柱销与两框架位置相对应槽钢的内侧连接。 1. A new formwork trolley for concrete pouring in a tunnel, characterized in that: it includes frames on both sides, a plurality of horizontal adjustment screw rods connecting and supporting the inner sides of the two frames, a walking wheel arranged at the lower end of the frame, and a plastic frame mounted on the outside of the frame. formwork, and diagonal bracing rods connecting the frames; the frames each include two channel steels arranged in parallel, and multiple purlins made of square wood that are vertically arranged and fixedly connected to the outer sides of the two channel steels; the plastic The formwork is installed on the purlin; the adjusting screw includes a screw sleeve, two screw rods screwed to both ends of the screw sleeve respectively, and the ends of the two screw rods are respectively connected with the inner sides of the channel steels corresponding to the positions of the two frames by bolts or cylindrical pins . 2.根据权利要求1所述的隧洞混凝土浇筑新型塑料模板台车,其特征在于:所述斜撑杆通过螺栓与框架连接。 2. The new plastic formwork trolley for pouring tunnel concrete according to claim 1, characterized in that: the diagonal braces are connected to the frame by bolts. 3.根据权利要求1或2所述的隧洞混凝土浇筑新型塑料模板台车,其特征在于:所述围檩与槽钢采用螺栓连接。 3. The tunnel concrete pouring new type plastic formwork trolley according to claim 1 or 2, characterized in that: said purlins and channel steel are connected by bolts. 4.根据权利要求3所述的隧洞混凝土浇筑新型塑料模板台车,其特征在于:所述螺杆套的中部设置供工具插入的通孔。 4. The new plastic formwork trolley for pouring tunnel concrete according to claim 3, wherein a through hole for tool insertion is provided in the middle of the screw sleeve. 5.根据权利要求3所述的隧洞混凝土浇筑新型塑料模板台车,其特征在于:所述螺杆套的中部设置有供扳手夹持的夹持部。 5. The new type plastic formwork trolley for tunnel concrete pouring according to claim 3, characterized in that: the middle part of the screw sleeve is provided with a clamping part for a wrench to clamp.
CN201520919653.XU 2015-11-18 2015-11-18 Tunnel concrete placement new plastic formworking jumbo Expired - Fee Related CN205172591U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520919653.XU CN205172591U (en) 2015-11-18 2015-11-18 Tunnel concrete placement new plastic formworking jumbo

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520919653.XU CN205172591U (en) 2015-11-18 2015-11-18 Tunnel concrete placement new plastic formworking jumbo

Publications (1)

Publication Number Publication Date
CN205172591U true CN205172591U (en) 2016-04-20

Family

ID=55736594

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520919653.XU Expired - Fee Related CN205172591U (en) 2015-11-18 2015-11-18 Tunnel concrete placement new plastic formworking jumbo

Country Status (1)

Country Link
CN (1) CN205172591U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107269302A (en) * 2017-07-25 2017-10-20 中国矿业大学(北京) A kind of self-locking tunnel top side suspension device
CN108265730A (en) * 2018-01-10 2018-07-10 朱新科 A kind of geotechnical engineering is special to build machine
CN109826437A (en) * 2019-03-22 2019-05-31 方远建设集团股份有限公司 A support system for integral lifting in a cylinder
CN110761320A (en) * 2019-11-07 2020-02-07 福建省鸿官通信工程有限公司 Communication pipeline bed pouring tool
CN113309147A (en) * 2021-06-04 2021-08-27 中国水利水电第三工程局有限公司 Rectangular vertical well hole concrete construction method
CN114645522A (en) * 2022-04-07 2022-06-21 宁夏公路桥梁建设有限公司 A kind of construction formwork without tie rod for cover plate culvert body

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107269302A (en) * 2017-07-25 2017-10-20 中国矿业大学(北京) A kind of self-locking tunnel top side suspension device
CN108265730A (en) * 2018-01-10 2018-07-10 朱新科 A kind of geotechnical engineering is special to build machine
CN109826437A (en) * 2019-03-22 2019-05-31 方远建设集团股份有限公司 A support system for integral lifting in a cylinder
CN109826437B (en) * 2019-03-22 2024-05-03 方远建设集团股份有限公司 Supporting system for integrally lifting in cylinder
CN110761320A (en) * 2019-11-07 2020-02-07 福建省鸿官通信工程有限公司 Communication pipeline bed pouring tool
CN110761320B (en) * 2019-11-07 2024-12-24 福建省鸿官通信工程有限公司 A communication pipeline foundation pouring tool
CN113309147A (en) * 2021-06-04 2021-08-27 中国水利水电第三工程局有限公司 Rectangular vertical well hole concrete construction method
CN114645522A (en) * 2022-04-07 2022-06-21 宁夏公路桥梁建设有限公司 A kind of construction formwork without tie rod for cover plate culvert body

Similar Documents

Publication Publication Date Title
CN203684658U (en) Early-dismantled template system of dropping prevention plate
CN103195450B (en) Hydraulic pressure tunnel invert operation trolley and inverted arch construction method
CN111236639B (en) Structural beam template reinforcing device and method free of split bolts
CN105275203B (en) Extensible canopy and the adjustable die system and the construction method of the mould bases using its making
CN108035741A (en) A kind of backform trolley
CN205171393U (en) A formworking jumbo for arch culvert construction
CN108252504A (en) Tube shear wall concrete structure large form hoisting type construction method and constructing device
CN211816278U (en) Removable supporting is used in building engineering construction
CN205743931U (en) Self-propelled tunnel inverted arch lining template trolley for baffle
CN106979023A (en) The adjustable concrete end mould of Tunnel Second Lining width and its adjusting method
CN104308961A (en) Integrally-drawing-type prefabricated box beam inner die device
CN204608825U (en) A kind of three-chip type stone bolt locating rack
CN204510814U (en) Beam for building jacking
CN204235678U (en) A kind of overall pulling type prefabricated box girder inner formwork device
CN104018655B (en) A kind of assembly type monomer bracing frame
CN101864835B (en) Early-dismantling support of aluminum alloy top plate
CN210976608U (en) Can have enough to meet need latticed beam formwork of stereotyping and prop up and establish system
CN206128630U (en) Die carrier is with flexible roof beam of adjustable how many fonts
CN207700216U (en) Piping lane construction formwork system
CN204781977U (en) Quick reinforcing apparatus of detachable pump line
CN203271126U (en) An indoor cast-in-place concrete door lintel support mold
CN221053292U (en) Arc dome station shaped steel bearing structure convenient to install and remove
CN206784933U (en) A kind of shear wall structure door opening form bracing system
CN206000188U (en) Rim of a cup basis steel column installs perpendicularity adjustment holding device
CN221032647U (en) A hydraulic tunnel inverted arch trestle type mobile formwork

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160420

CF01 Termination of patent right due to non-payment of annual fee