CN205153148U - Double steel pipe concrete beam column node - Google Patents
Double steel pipe concrete beam column node Download PDFInfo
- Publication number
- CN205153148U CN205153148U CN201520733527.5U CN201520733527U CN205153148U CN 205153148 U CN205153148 U CN 205153148U CN 201520733527 U CN201520733527 U CN 201520733527U CN 205153148 U CN205153148 U CN 205153148U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- semi
- girder
- component
- upper limbs
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model belongs to double steel pipe concrete beam column node in the frame core section of thick bamboo structure system of civil structure engineering field, including the outer steel pipe of steel core concrete column, interior steel pipe, hoop stiffener, concrete water smashes the hole, bolt hole, semi -girder upper limbs component and semi -girder low limbs component submit in on the outer steel pipe, interior steel pipe is arranged in in the outer steel pipe, semi -girder upper limbs component, semi -girder low limbs component extend to through horizontal stiffener level respectively interior steel pipe, and with outer steel pipe, interior steel pipe and hoop stiffener weld along the girth, it has the concrete to water to smash the hole to open on each horizontal hoop stiffener, the edge girth welds in the crossing plane of semi -girder upper limbs component, semi -girder low limbs component and outer steel pipe, and it is more reasonable that horizontal hoop stiffener enables the atress of semi -girder upper limbs component, semi -girder low limbs component.
Description
Technical field
The utility model relates to civil structure engineering field, espespecially in Frame-Shear wall system, and a kind of special bean column node when frame column adopts steel core concrete column.
Background technology
Along with super highrise building application increasingly extensive, Frame-Shear wall system is applied in the middle of design of building structures continually, Core Walls Structure generally adopts concrete structure, adopt the Frame-Shear wall of profile steel concrete column, especially more difficult in the node area construction having semi-girder component to cross in beam column node area, construction quality is more difficult to get guarantee; Adopt the Frame-Shear wall of steel core concrete column, construction quality easily ensures, can improve the compressive strength of post inner concrete outside post with inner side steel pipe, but under the effect of semi-girder component pulling force, steel pipe column post jamb easily and post inner concrete depart from, post inner concrete is also easily by drawing crack.
Summary of the invention
The utility model patent is a kind of two steel tube concrete beam and column node, and this device can reach bean column node and effectively be rigidly connected, and occurs the situation loosening landing when solving beam-to-column joint.
The utility model patent is a kind of two steel tube concrete beam and column node, comprise the outer steel pipe of steel core concrete column, interior steel pipe, ring stiffener, casting and compacting of concrete hole, bolt hole, semi-girder upper limbs component and semi-girder lower limb component, it is characterized in that, described semi-girder upper limbs component and semi-girder lower limb component intersect on outer steel pipe, interior steel pipe is placed in described outer steel pipe, described semi-girder upper limbs component, semi-girder lower limb component extends horizontally to described interior steel pipe respectively by ring stiffener, and with described outer steel pipe, interior steel pipe and ring stiffener weld along girth, described each ring stiffener has casting and compacting of concrete hole, described semi-girder upper limbs component, weld along girth in the plane that semi-girder lower limb component is crossing with outer steel pipe, ring stiffener can make semi-girder upper limbs component, semi-girder lower limb component stressed more reasonable.
As improvement, interior steel pipe is connected by ring stiffener with outer steel pipe.
As improvement, semi-girder upper limbs component, semi-girder lower limb component extend to described interior steel pipe respectively by lateral stiffening plate level.
As improvement, ring stiffener has 4 casting and compacting of concrete holes.
The beneficial effects of the utility model make steel pipe inner concrete stressed relatively more even, and most of concrete in tension is converted into pressurized, and stress form becomes more reasonable, and node is reliably safer.
Four. accompanying drawing explanation
Fig. 1 is structure graphics of the present utility model.
Fig. 2 is plan view of the present utility model.
(1) interior steel pipe in Fig. 1, (2) outer steel pipe, (3) casting and compacting of concrete hole, (4) bolt hole, (5) semi-girder upper limbs component, (6) ring stiffener, (7) semi-girder lower limb component.
Five. detailed description of the invention
Be illustrated in figure 1 the bean column node that semi-girder upper limbs component 5, semi-girder lower limb component 7 and hoop stiffening rib 6 intersect at the outer steel pipe 2 of steel core concrete column, hoop stiffening rib 6 is identical with the root absolute altitude of semi-girder lower limb component 7 with the end absolute altitude of lower flange of girder listrium, hoop stiffening rib 6 is identical with the elevation of top of the high same semi-girder upper limbs component 5 of the top mark of top flange plate, the present embodiment is only a kind of signal, as horizontal ring stiffener should according to various situation, be arranged in plane that semi-girder upper limbs component, semi-girder lower limb component and upper and lower frange plate and outer steel pipe collide.
Making and the assembled step of the utility model embodiment are as follows: by outer steel pipe 2 as on moulding bed, interior steel pipe 1 is positioned, overlap outside in steel pipe 2, ring stiffener 6 welds along girth with outer steel pipe 2 and interior steel pipe 1 respectively, semi-girder upper limbs component 5 welds with outer steel pipe 2 transmission being carried out power by hoop stiffening rib 6, semi-girder lower limb component 7 welds with outer steel pipe 2 transmission being carried out power by hoop stiffening rib 6, concrete is undertaken being filled between two steel pipes by the casting and compacting of concrete hole on hoop stiffening rib, make stressed evenly.Above the scheme that the utility model embodiment provides is introduced in detail, for one of ordinary skill in the art, according to the thought of the utility model embodiment, all will change in specific embodiments and applications.
As improvement, interior steel pipe (1) is connected by ring stiffener (6) with outer steel pipe (2).
As improvement, semi-girder upper limbs component (5), semi-girder lower limb component (7) extend horizontally to described interior steel pipe (1) respectively by ring stiffener (6).
As improvement, ring stiffener has 4 casting and compacting of concrete holes.
Claims (3)
1. a two steel tube concrete beam and column node, draw together the outer steel pipe (2) of steel core concrete column, interior steel pipe (1), ring stiffener (6), casting and compacting of concrete hole (3), bolt hole (4), semi-girder upper limbs component (5) and semi-girder lower limb component (7) intersect on described outer steel pipe (2), interior steel pipe (1) is placed in described outer steel pipe (2), described semi-girder upper limbs component (5), semi-girder lower limb component (7) extends horizontally to described interior steel pipe (1) respectively by ring stiffener (6), and with described outer steel pipe (2), interior steel pipe (1) and ring stiffener (6) weld along girth, ring stiffener (6) has casting and compacting of concrete hole (3), described semi-girder upper limbs component (5), weld along girth in the plane that semi-girder lower limb component (7) is crossing with outer steel pipe (2), horizontal ring stiffener (6) can make semi-girder upper limbs component (5), semi-girder lower limb component (7) stressed more reasonable.
2. the two steel tube concrete beam and column node of one according to claim 1, it is characterized in that: in the plane that horizontal ring stiffener (6) is arranged on described semi-girder upper limbs component (5), semi-girder lower limb component (7) intersects, and weld along girth with the outside of described outer steel pipe (2) inwall, interior steel pipe (1) respectively.
3. the two steel tube concrete beam and column node of one according to claim 1 and 2, is characterized in that: at the bolt hole (4) according to actual requirement layout of described semi-girder upper limbs component (5) and semi-girder lower limb component (7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520733527.5U CN205153148U (en) | 2015-09-22 | 2015-09-22 | Double steel pipe concrete beam column node |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520733527.5U CN205153148U (en) | 2015-09-22 | 2015-09-22 | Double steel pipe concrete beam column node |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205153148U true CN205153148U (en) | 2016-04-13 |
Family
ID=55688860
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520733527.5U Expired - Fee Related CN205153148U (en) | 2015-09-22 | 2015-09-22 | Double steel pipe concrete beam column node |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205153148U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107338872A (en) * | 2017-08-23 | 2017-11-10 | 青岛理工大学 | Double sleeve steel-structure beam-column nodes and installation method |
-
2015
- 2015-09-22 CN CN201520733527.5U patent/CN205153148U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107338872A (en) * | 2017-08-23 | 2017-11-10 | 青岛理工大学 | Double sleeve steel-structure beam-column nodes and installation method |
CN107338872B (en) * | 2017-08-23 | 2019-02-05 | 青岛理工大学 | Double sleeve steel-structure beam-column nodes and installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204789157U (en) | Static test device about anti performance research that collapses of beam column minor structure | |
CN203878780U (en) | Connecting joint of cylindrical rib penetrating type steel pipe concrete column and steel beam | |
CN103850363B (en) | Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall | |
CN202017346U (en) | Late poured band hanging formwork structure | |
CN104372967B (en) | A kind of cooling stack inclined strut structure and construction method thereof | |
CN202248298U (en) | Node of steel reinforced concrete framework | |
CN103953123A (en) | H-shaped steel frame node with partially restricted beam end and construction method thereof | |
CN203487640U (en) | Beam column connection T type node applied in top-down method | |
CN104005569A (en) | Construction method for supporting beam and removing columns | |
CN201883532U (en) | Steel column and beam steel connecting joint structure in stiff structure | |
CN203769116U (en) | Prefabricated through hole assembly type reinforced concrete shear wall | |
CN205153148U (en) | Double steel pipe concrete beam column node | |
CN202138969U (en) | Tower crane wall-attaching device used in cast-in-place concrete structure | |
CN204357167U (en) | A kind of cooling stack inclined strut structure | |
CN208343121U (en) | Prefabricated assembled steel structure concrete wallboard mould | |
CN105113640B (en) | The mechanical anchor formula connecting joint structure of steel core concrete column and reinforced beam | |
CN106351245A (en) | Tower crane foundation base and construction method thereof | |
CN207436278U (en) | A kind of assembly concrete-filled steel tube column-girder steel punching node | |
CN102031832A (en) | Reinforcement steel-tube concrete column node | |
CN202672353U (en) | Panel constraint type concrete filled steel tube composite column-steel beam joint | |
CN204456068U (en) | Box-shaped steel plate occlusion diaphragm wall | |
CN105133788A (en) | CFST-RC horizontal batten plate-lattice column structure and construction method thereof | |
CN201614601U (en) | Well lid structure | |
CN201924456U (en) | Steel-pipe concrete column joint for reinforced layer | |
CN203284893U (en) | Connecting device of section steel columns and steel bars of beam column joints |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160413 Termination date: 20160922 |
|
CF01 | Termination of patent right due to non-payment of annual fee |