CN205152818U - Girder system is traded all to whole sideslip of bridge - Google Patents

Girder system is traded all to whole sideslip of bridge Download PDF

Info

Publication number
CN205152818U
CN205152818U CN201520949615.9U CN201520949615U CN205152818U CN 205152818 U CN205152818 U CN 205152818U CN 201520949615 U CN201520949615 U CN 201520949615U CN 205152818 U CN205152818 U CN 205152818U
Authority
CN
China
Prior art keywords
bridge
new
superstructure
pier
traversing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520949615.9U
Other languages
Chinese (zh)
Inventor
程慧林
梁志新
高占军
彭程
王治斌
郭亚娟
李闻
罗九林
罗红春
李力亨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Fifth Survey and Design Institute Group Co Ltd
Original Assignee
China Railway Fifth Survey and Design Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Fifth Survey and Design Institute Group Co Ltd filed Critical China Railway Fifth Survey and Design Institute Group Co Ltd
Priority to CN201520949615.9U priority Critical patent/CN205152818U/en
Application granted granted Critical
Publication of CN205152818U publication Critical patent/CN205152818U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a girder system is traded all to whole sideslip of bridge inserts on the horizontal bridge of existing bridge pier is to the axis and makes a call to one row of steel -pipe pile and interim pier no. 1 to install the sideslip slide of existing bridge, insert on the new horizontal bridge of pier is to the axis and make a call to one row of steel -pipe pile and interim pier no. 2 to install the sideslip slide of new bridge, connect into whole with existing superstructure and new superstructure through the connecting elements to outer end at the sideslip slide of new bridge sets up the jack. Under circuit operation condition, finish the construction of new bridge structures, then be connected to existing superstructure and new superstructure together, in the short -term confined time quantum of route, it's time to design the bridge location with new superstructure sideslip, shift out existing superstructure beyond the bridge location. The quick replacement new bridge can break off under the condition of traffic in the short -term.

Description

A kind of integral bridge is traversing changes girder system system
Technical field
The utility model relates to a kind of Bridge Construction technology, particularly relates to the traversing girder system of changing of a kind of integral bridge and unites.
Background technology
In technical field of civil engineering, especially in Bridge Construction technical field, under circuit operation condition, if exist curves is not suitable for continuing to be on active service, so need to suspend traffic, dismounting is carried out to bridge and rebuilds.If vehicle operating twocouese bridge is arranged separately, so can run by single width, two width bridges are alternately removed and are again built.The time of so general needs is long, and the time that suspends traffic is long, even generally can reach several years several months, very big to the pressure of traffic impact.
Also first can build near track plan one just line be open to traffic temporarily, then alignment type bridge carry out dismounting rebuild.Do like this and traffic pressure can be reduced, but shoofly to build the investment of removing with the later stage large, must not be the measure then taked.
Utility model content
The purpose of this utility model is to provide a kind of can system in the traversing girder system of changing of the integral bridge of short-term quick-replaceable new bridge.
The purpose of this utility model is achieved through the following technical solutions:
Integral bridge of the present utility model is traversing changes girder system system, on exist curves bridge pier direction across bridge axis, inserted to play one arranges steel pipe pile and interim bridge pier one, and the traversing slideway of exist curves is installed on exist curves bridge pier, steel pipe pile and interim bridge pier one, exist curves superstructure is placed on the traversing slideway of described exist curves;
At the new bridge pier of lower structure of exist curves, and inserted to play one arranges steel pipe pile and interim bridge pier two on new bridge pier direction across bridge axis, and the traversing slideway of new bridge is installed on new bridge pier, steel pipe pile and interim bridge pier two, new bridge superstructure is placed on the traversing slideway of described new bridge;
Described exist curves superstructure and new bridge superstructure are connected into entirety by connecting elements, and jack is set in the outer end of the traversing slideway of new bridge.
The technical scheme provided as can be seen from above-mentioned the utility model, the integral bridge that the utility model embodiment provides is traversing changes girder system system, can in short-term---within being generally a few hours or within a couple of days---and under the condition suspended traffic, quick-replaceable new bridge.
Accompanying drawing explanation
The traversing section structure schematic diagram changing girder system system of integral bridge that Fig. 1 provides for the utility model embodiment.
The traversing plane structure schematic diagram changing girder system system of integral bridge that Fig. 2 provides for the utility model embodiment.
In figure:
1, exist curves superstructure, 2, new bridge superstructure, 3, exist curves sliding crossbeam, 4, new bridge sliding crossbeam, 5, existing bridge pier, 6, newly bridge pier, 7, temporarily bridge pier one, 8, interim bridge pier two, 9, connecting elements, 10, back seat, 11, connecting pin, 12, jack, 13, pumping plant control centre.
Detailed description of the invention
To be described in further detail the utility model embodiment below.
Integral bridge of the present utility model is traversing changes girder system system, its preferably detailed description of the invention be:
On exist curves bridge pier direction across bridge axis, inserted to play one arranges steel pipe pile and interim bridge pier one, and the traversing slideway of exist curves is installed on exist curves bridge pier, steel pipe pile and interim bridge pier one, exist curves superstructure is placed on the traversing slideway of described exist curves;
At the new bridge pier of lower structure of exist curves, and inserted to play one arranges steel pipe pile and interim bridge pier two on new bridge pier direction across bridge axis, and the traversing slideway of new bridge is installed on new bridge pier, steel pipe pile and interim bridge pier two, new bridge superstructure is placed on the traversing slideway of described new bridge;
Described exist curves superstructure and new bridge superstructure are connected into entirety by connecting elements, and jack is set in the outer end of the traversing slideway of new bridge.
There is back seat the outer end of the traversing slideway of described new bridge, and the outside of described new bridge superstructure is provided with connecting pin, and the cylinder bottom of described jack is against on described back seat, and cylinder bar is connected on described connecting pin.
Integral bridge of the present utility model is traversing changes the method that girder system system realizes changing beam, comprises step:
On exist curves bridge pier direction across bridge axis, inserted to play one arranges steel pipe pile, in order to install the traversing slideway of exist curves;
On new bridge pier direction across bridge axis, many inserted to plays one arrange steel pipe pile, in order to install the traversing slideway of new bridge;
Exist curves superstructure and new bridge superstructure are connected into entirety, simultaneously traversing pushing tow;
Under circuit operation condition, New Bridge is constructed complete, then exist curves superstructure is connected together with new bridge superstructure, within the time period that operating line short-term is closed, by traversing for new bridge superstructure to design bridge location while, exist curves superstructure is shifted out beyond bridge location, realizes new bridge at short notice and be on active service.
Integral bridge of the present utility model is traversing changes girder system system, can in short-term---within being generally a few hours or within a couple of days---under the condition suspended traffic, quick-replaceable new bridge.
Know-why of the present utility model is:
Beyond the safe distance that the upstream or downstream that need the exist curves changed are certain, and on the axis parallel with line midline, under the not affected condition of guarantee exist curves normal operation, assembled good new bridge superstructure in advance.Exist curves superstructure and new bridge superstructure are connected into entirety, and install pushing tow jack in the side, rear in new bridge superstructure horizontal sliding direction, a jack installed by every pier.All jack are connected to pumping plant control centre, and pumping plant control centre can ensure all jack synchronization jobs.Then short-term closed-loop, is separated the superstructure of exist curves with circuit, and by new bridge superstructure pushing tow to design bridge location place, exist curves superstructure just leaves place on line simultaneously.New bridge can begin one's duty.Then can remove original bridge and construction equipment after circuit operation, complete exchanging bridge.
Specific embodiment:
As shown in Figure 1 and Figure 2, comprising: exist curves superstructure 1, new bridge superstructure 2, exist curves sliding crossbeam 3, new bridge sliding crossbeam 4, existing bridge pier 5, new bridge pier 6, interim bridge pier 1, interim bridge pier 28, connecting elements 9, back seat 10, connecting pin 11, jack 12, pumping plant control centre 13.
Under circuit normal operation uninterrupted traffic condition, at exist curves both sides inserted to play steel pipe pile, i.e. described new bridge pier, interim bridge pier one, interim bridge pier two.Existing bridge pier and interim bridge pier one arrange described exist curves sliding crossbeam, new bridge pier and described interim bridge pier two arranges described new bridge sliding crossbeam, material is thus formed the sliding rail of exist curves and new bridge.
Described exist curves superstructure and described new bridge superstructure are fixed by described connecting elements, connects into entirety.
Described back seat is set at the rear of the sideslip direction of described new bridge sliding crossbeam, described connecting pin is set in the side, rear of the sideslip direction of described new bridge superstructure, described jack is connected on described back seat and described connecting pin.
Described jack on each described new bridge sliding crossbeam is connected to described pumping plant control centre, and described pumping plant control centre controls described jack synchronization job by computer and servo-fluid pressure valve, ensures to be advanced by pushing tow object is synchronously traversing.
Operating line temporary blockage, suspend traffic a few hours or a couple of days, described exist curves superstructure and existing line are disconnected, while described new bridge superstructure traversing pushing tow to bridge location, described exist curves superstructure leaves existing bridge location simultaneously, by described new bridge superstructure in connection, circuit can open operation.
Remove described connecting elements, remove described exist curves superstructure, remove described interim bridge pier one, described interim bridge pier two, remove the construction equipments such as described back seat, described connecting pin, so just complete exist curves in the short period of time and more change jobs.
The beneficial effects of the utility model may be summarized to be:
(1) within the maintenance time of circuit operation, exist curves can be changed, affects circuit normal operation hardly.
(2) do not need to build sidewalk to be open to traffic temporarily, significantly saved construction costs.
(3) construction equipment is simple.
The above; be only the utility model preferably detailed description of the invention; but protection domain of the present utility model is not limited thereto; anyly be familiar with those skilled in the art in the technical scope that the utility model discloses; the change that can expect easily or replacement, all should be encompassed within protection domain of the present utility model.Therefore, protection domain of the present utility model should be as the criterion with the protection domain of claims.

Claims (2)

1. the traversing girder system of changing of integral bridge is united, it is characterized in that, on exist curves bridge pier direction across bridge axis, inserted to play one arranges steel pipe pile and interim bridge pier one, and the traversing slideway of exist curves is installed on exist curves bridge pier, steel pipe pile and interim bridge pier one, exist curves superstructure is placed on the traversing slideway of described exist curves;
At the new bridge pier of lower structure of exist curves, and inserted to play one arranges steel pipe pile and interim bridge pier two on new bridge pier direction across bridge axis, and the traversing slideway of new bridge is installed on new bridge pier, steel pipe pile and interim bridge pier two, new bridge superstructure is placed on the traversing slideway of described new bridge;
Described exist curves superstructure and new bridge superstructure are connected into entirety by connecting elements, and jack is set in the outer end of the traversing slideway of new bridge.
2. integral bridge according to claim 1 is traversing changes girder system system, it is characterized in that, there is back seat the outer end of the traversing slideway of described new bridge, and the outside of described new bridge superstructure is provided with connecting pin, the cylinder bottom of described jack is against on described back seat, and cylinder bar is connected on described connecting pin.
CN201520949615.9U 2015-11-25 2015-11-25 Girder system is traded all to whole sideslip of bridge Active CN205152818U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520949615.9U CN205152818U (en) 2015-11-25 2015-11-25 Girder system is traded all to whole sideslip of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520949615.9U CN205152818U (en) 2015-11-25 2015-11-25 Girder system is traded all to whole sideslip of bridge

Publications (1)

Publication Number Publication Date
CN205152818U true CN205152818U (en) 2016-04-13

Family

ID=55688530

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520949615.9U Active CN205152818U (en) 2015-11-25 2015-11-25 Girder system is traded all to whole sideslip of bridge

Country Status (1)

Country Link
CN (1) CN205152818U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350462A (en) * 2015-11-25 2016-02-24 中铁第五勘察设计院集团有限公司 Bridge overall transversely-moving beam replacing system and method
CN109235292A (en) * 2018-10-18 2019-01-18 石家庄铁道大学 Railroad bridge changes beam process and changes girder system system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350462A (en) * 2015-11-25 2016-02-24 中铁第五勘察设计院集团有限公司 Bridge overall transversely-moving beam replacing system and method
CN109235292A (en) * 2018-10-18 2019-01-18 石家庄铁道大学 Railroad bridge changes beam process and changes girder system system

Similar Documents

Publication Publication Date Title
CN102182147B (en) Steel box girder erection method
CN101586328B (en) Anchor ear angle-table bracket building method for bridge sidespan closure segment construction
CN204703066U (en) The built-in cable channel in inter-city passenger rail T beam sidewalk
CN100540809C (en) The replacing supporters for continuous beam without breaking off traffic method
CN109468960A (en) The quick change method and replacement system of highway line bridge
CN205152818U (en) Girder system is traded all to whole sideslip of bridge
CN105350462A (en) Bridge overall transversely-moving beam replacing system and method
CN103437254A (en) Reinforcing device for railway turnout area circuit during jacking for frame bridge
CN209260577U (en) The replacement system of highway line bridge
CN103276647B (en) A kind of rail beam emergency first-aid repair replacement system
CN105442453A (en) Construction method for suspension bridge tower crossbeam combination support
CN104314009A (en) Large segment lifting mechanism and use method thereof
CN103498427B (en) Quick replacement method of overpass bridge section
CN105648912A (en) Construction method for integrally transferring and splicing movable formwork
CN104612031A (en) Reinforced concrete continuous rigid frame arch bridge and construction method thereof
CN105714691A (en) Staggered arrangement and transversely-moving construction method for hanging baskets of curve extradosed cable-stayed bridge
CN202055271U (en) Reinforcing structure of foundation of high-temperature furnace
KR100865752B1 (en) Shift method of bridge bearing of railroad
CN101880994A (en) Replacing technology for special track switch
CN102767140B (en) Construction method for rapidly mounting and dismounting temporary support of continuous girder bridge pier
CN204644820U (en) Protective device built by pavement concrete
CN109468937A (en) Bridge and its method for dismounting with falsework
CN104894983A (en) Recovery steel beam for high-speed railways
CN204919348U (en) Supplementary head tower of using of self anchored suspension bridge installation
CN204551226U (en) A kind of crossstructure of interim pedestrian overcrossing

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant