CN205097346U - Vertical tubulation equipment - Google Patents

Vertical tubulation equipment Download PDF

Info

Publication number
CN205097346U
CN205097346U CN201520844535.7U CN201520844535U CN205097346U CN 205097346 U CN205097346 U CN 205097346U CN 201520844535 U CN201520844535 U CN 201520844535U CN 205097346 U CN205097346 U CN 205097346U
Authority
CN
China
Prior art keywords
external mold
vertical
space
utility
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520844535.7U
Other languages
Chinese (zh)
Inventor
张声军
周磊
曹国巍
周立新
徐毅
石小虎
张伯华
陈炜宁
张伟宁
王谦
张晓强
果金颖
张金昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING JINDUN HUATONG TECHNOLOGY Co Ltd
Langfang Jindun Huatong Technology Co Ltd
Institute of Building Mechanization of Chinese Academy of Building Research
Langfang Kaibo Construction Machinery Technology Co Ltd
Original Assignee
BEIJING JINDUN HUATONG TECHNOLOGY Co Ltd
Langfang Jindun Huatong Technology Co Ltd
Institute of Building Mechanization of Chinese Academy of Building Research
Langfang Kaibo Construction Machinery Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING JINDUN HUATONG TECHNOLOGY Co Ltd, Langfang Jindun Huatong Technology Co Ltd, Institute of Building Mechanization of Chinese Academy of Building Research, Langfang Kaibo Construction Machinery Technology Co Ltd filed Critical BEIJING JINDUN HUATONG TECHNOLOGY Co Ltd
Priority to CN201520844535.7U priority Critical patent/CN205097346U/en
Application granted granted Critical
Publication of CN205097346U publication Critical patent/CN205097346U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a vertical tubulation equipment includes the external mold, its lower part of is provided with the bottom backing plate, and upper portion is provided with the opening, intermediate bottom, its detachably install in order evenly to cut apart into the external mold a plurality of first spaces in the external mold, be in with mandrel, its setting first space central authorities, wherein, external mold, well spacer sleeve and the vertical setting of mandrel. Through the multitube technological innovation of a vertical pouring mould, improved production efficiency greatly, practiced thrift the mould raw and other materials, reduced production equipment cost to the production space has been practiced thrift greatly to vertical structure, has gained extremely superior result of use.

Description

Vertical tubulation apparatus
Technical field
The utility model relates to a kind of vertical tubulation apparatus, particularly adopts casting to be used for the vertical tubulation apparatus of concrete duct.
Background technology
At present, when producing the rectangular ducts such as such as exhaust duct, a kind of semi-hand method adopts casting to produce, that is, external mold and core are assembled, Horizontal type is placed, and mould upstream opens wide, and slurry is progressively poured into a mould, until fill from top by suspension bucket is mobile vertically.The method needs after pouring slurry initial set, and re-use artificial that top is floating, and one set of die once can only produce a pipeline, not only production efficiency is low, and it is many to take mould, and production cost is high.
Therefore, in order to solve many deficiencies and the defect of above-mentioned prior art, be necessary a kind of vertical tubulation apparatus of research and technique thereof.
Utility model content
Consider at least one the problems referred to above and complete the utility model, and an object of the present utility model is to provide a kind of vertical tubulation apparatus and technique thereof, it is by the technological innovation of vertical pouring one mould multitube, substantially increase production efficiency, reduce production equipment cost, and vertical structure has saved production space greatly, achieve extremely superior result of use.Wherein, this vertical tubulation apparatus, is characterized in that comprising:
External mold, its underpart is provided with backing plate at bottom, and top is provided with opening;
Central dividing plate, it is removably mounted in external mold external mold to be evenly divided into multiple first space; With
Core, its be arranged on described first space central authorities;
Wherein, described external mold, middle spacer sleeve and the vertical setting of core.
According to the utility model on the other hand, described equipment also comprises external mold vibrator, and it is removably disposed on the outer wall of external mold.
According to the utility model on the other hand, described equipment also comprises grouting equipment and is arranged on the slurry inlet of backing plate at bottom or external mold lower end, and this grouting equipment is communicated with described first space by this slurry inlet.
According to the utility model on the other hand, the quantity in described multiple first space is two or more, and wherein the best is four, six, nine.
According to the utility model on the other hand, provide and a kind ofly utilize above-mentioned vertical tubulation apparatus to prepare the technique of concrete duct, it is characterized in that: use grouting equipment to enter described multiple first space from slurry inlet by concrete slurry pumping, until by full for its filling, then solidify formation concrete duct.
According to the utility model on the other hand, provide and a kind ofly utilize above-mentioned vertical tubulation apparatus to prepare the technique of concrete duct, it is characterized in that: raw material slurry pours into from upper opening, external mold vibrator vibrates simultaneously, make slurry inject bottom swimmingly and progressively by full for described multiple first space perfusion, then solidify formation concrete duct.
According to the utility model on the other hand, one-shot forming many concrete ducts.
According to the utility model on the other hand, do not establish described central dividing plate, only with external mold and a core, with shaping single concrete duct.
Compared with prior art, the beneficial effects of the utility model are:
By the technological innovation of vertical pouring one mould multitube, substantially increase production efficiency, saved base mould material, reduce production equipment cost, and vertical structure saves production space greatly, achieve extremely superior result of use.
Accompanying drawing explanation
Fig. 1 is the top view of the vertical tubulation apparatus part according to a kind of preferred embodiment of the utility model.
Fig. 2 is the vertical tubulation apparatus schematic diagram according to a kind of preferred embodiment of the utility model.
Fig. 3 is the vertical tubulation apparatus schematic diagram according to another preferred embodiment of the utility model.
Detailed description of the invention
Below in conjunction with accompanying drawing; by preferred embodiment, preferred forms of the present utility model is described; here detailed description of the invention is to explain the utility model; and should not be construed as restriction of the present utility model; when not departing from spirit of the present utility model and essential scope; can make various changes and modifications, these all should be included within protection domain of the present utility model.
Embodiment 1
See Fig. 1-3, the utility model provides a kind of vertical tubulation apparatus.Such as, this vertical tubulation apparatus, it is characterized in that comprising: external mold, its underpart is provided with backing plate at bottom, and top is provided with opening; Central dividing plate, it is removably mounted in external mold external mold to be evenly divided into multiple first space; With core, its be arranged on described first space central authorities; Wherein, described external mold, middle spacer sleeve and the vertical setting of core.
Preferably, described equipment also can comprise external mold vibrator, and it is removably disposed on the outer wall of external mold.Wherein, raw material slurry pours into from upper opening, and external mold vibrator vibrates simultaneously, makes slurry inject bottom swimmingly and progressively pours into full by described multiple first space.
Preferably, described equipment also comprises grouting equipment and is arranged on the slurry inlet of backing plate at bottom or external mold lower end, and this grouting equipment is communicated with described first space by this slurry inlet.
Preferably, the quantity in described multiple first space is two or more, and wherein the best is four, six, nine.
Preferably, provide and a kind ofly utilize above-mentioned vertical tubulation apparatus to prepare the technique of concrete duct, it is characterized in that: use grouting equipment concrete slurry pumping to be entered described multiple first space from slurry inlet, until by full for its filling, then solidify formation concrete duct.By such setting, make concrete slurry enter the first space from bottom and discharge air, make concrete slurry filling obtain under gravity more closely knit, end product quality is better.
Preferably, additionally provide and a kind ofly utilize above-mentioned vertical tubulation apparatus to prepare the technique of concrete duct, it is characterized in that: raw material slurry pours into from upper opening, external mold vibrator vibrates simultaneously, make slurry inject bottom swimmingly and progressively by full for described multiple first space perfusion, then solidify formation concrete duct.
Preferably, one-shot forming many concrete ducts.
Preferably, do not establish described central dividing plate, only with external mold and a core, with shaping single concrete duct.
Be understandable that, described vertical tube-making process and equipment can be made up of major parts such as external mold, middle spacer sleeve, core, backing plate at bottom, external mold vibrators.The vertical setting of mould, raw material slurry pours into from the cavity of top, and vibrator vibrates simultaneously, makes slurry inject bottom swimmingly and progressively cavity body is poured into full.Described technique can one-shot forming many piping articles.When removing or not establishing central dividing plate, only with external mold and 1 core, can shaping single pipe goods.Also grouting equipment can be used to be entered cavity by slurry pumping from bottom, until by full for cavity filling.It should be noted that this method can once-cast to form many pipelines (can be 1,2,3,4,5,6,7,8,9 ... even more).Substantially increase efficiency, and save base mould material.
In sum, the beneficial effects of the utility model are:
By the technological innovation of vertical pouring one mould multitube, substantially increase production efficiency, saved base mould material, reduce production equipment cost, and vertical structure saves production space greatly, achieve extremely superior result of use.
The utility model is not limited to above-mentioned specific embodiment.Be understandable that, when not departing from spirit of the present utility model and essential scope, can make various changes and modifications, these all should be included within protection domain of the present utility model.

Claims (5)

1. a vertical tubulation apparatus, is characterized in that comprising:
External mold, its underpart is provided with backing plate at bottom, and top is provided with opening;
Central dividing plate, it is removably mounted in external mold external mold to be evenly divided into multiple first space; With
Core, its be arranged on described first space central authorities;
Wherein, described external mold, middle spacer sleeve and the vertical setting of core.
2. equipment according to claim 1, it is characterized in that described equipment also comprises external mold vibrator, it is removably disposed on the outer wall of external mold.
3. equipment according to claim 1 and 2, is characterized in that described equipment also comprises grouting equipment and is arranged on the slurry inlet of backing plate at bottom or external mold lower end, and this grouting equipment is communicated with described first space by this slurry inlet.
4. equipment according to claim 3, is characterized in that the quantity in described multiple first space is two or more.
5. equipment according to claim 4, is characterized in that the quantity in described multiple first space is four, six or nine.
CN201520844535.7U 2015-10-28 2015-10-28 Vertical tubulation equipment Active CN205097346U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520844535.7U CN205097346U (en) 2015-10-28 2015-10-28 Vertical tubulation equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520844535.7U CN205097346U (en) 2015-10-28 2015-10-28 Vertical tubulation equipment

Publications (1)

Publication Number Publication Date
CN205097346U true CN205097346U (en) 2016-03-23

Family

ID=55513156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520844535.7U Active CN205097346U (en) 2015-10-28 2015-10-28 Vertical tubulation equipment

Country Status (1)

Country Link
CN (1) CN205097346U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105235057A (en) * 2015-10-28 2016-01-13 中国建筑科学研究院建筑机械化研究分院 Vertical pipe manufacturing device and technology thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105235057A (en) * 2015-10-28 2016-01-13 中国建筑科学研究院建筑机械化研究分院 Vertical pipe manufacturing device and technology thereof

Similar Documents

Publication Publication Date Title
CN101579890B (en) Vertical type vibratory molding process for concrete tube of lining type prestressed steel cylinder
CN105235057A (en) Vertical pipe manufacturing device and technology thereof
CN102765122B (en) Curb production system and method
CN107486939A (en) Lined Prestressed concrete cylinder pipe vertical vibrating shaped device
CN205097346U (en) Vertical tubulation equipment
CN102267177B (en) Self-compacting concrete moulding method for PCCP (prestressed concrete cylinder pipe) cores
CN106862514A (en) A kind of production method of ductile iron pipe with end face typefounding
CN102699273A (en) Precision casting method for large-scale aluminium alloy impeller
CN204955069U (en) Forming die of cement polyphenyl mould shell
CN204772928U (en) Cement flower bucket is pour and is used centre form
CN206374088U (en) A kind of silica gel for artistic sculpture makes mould
CN203371623U (en) Light wallboard vertical mould forming machine with movable modules
CN204321114U (en) A kind of evaporative pattern sandbox
CN204308162U (en) A kind of casing forming mold
CN207240452U (en) A kind of mould for foam concrete partition plate verticle mould shaping
CN205766777U (en) PCCP tube core is vertical pours quick homogenizing device
CN204034719U (en) A kind of gas-liquid allotter
CN102198692B (en) Die for production of three-row-hole recycled concrete
CN209566290U (en) A kind of gas, which rises, receives that expand can the flue mould that closes of multiple groups
CN203091673U (en) High-density die casting box
CN208197111U (en) Automatic expansion folding and unfolding tuber
CN214517412U (en) Lost foam mold with connecting piece
CN203919338U (en) Polystyrene wallboard manufacture device
CN203125667U (en) Ceramic sand blasting nozzle mold
CN205255248U (en) Pouring circle for crucible gypsum lap

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant