CN205079771U - Disconnect -type settlement observation point - Google Patents
Disconnect -type settlement observation point Download PDFInfo
- Publication number
- CN205079771U CN205079771U CN201520891165.2U CN201520891165U CN205079771U CN 205079771 U CN205079771 U CN 205079771U CN 201520891165 U CN201520891165 U CN 201520891165U CN 205079771 U CN205079771 U CN 205079771U
- Authority
- CN
- China
- Prior art keywords
- buried
- observation point
- steel slab
- embedded steel
- settlement observation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
The utility model relates to a building field provides a disconnect -type settlement observation point very much, including the external part of pre -buried subtotal, pre -buried part comprises pre -buried steel sheet, buried sleeve and dowel, and pre -buried steel sheet is fixed on the wall of needs installation settlement observation point, connects buried sleeve at the center of pre -buried steel sheet, and just open at the center of pre -buried steel sheet has the connecting hole unanimous with the hollow horizontal section size of buried sleeve, and two piece at least dowels are fixed the tip of pre -buried steel sheet, external partial one end is the link, and one end is for observing the end, and the link end can be followed pre -buried steel sheet connecting hole and inserted buried sleeve. The utility model discloses a set up earlier pre -buried part in the wall body, the follow -up sight time measuring that needs avoids follow -up work progress to cause the damage to the exposed part externally of settlement observation point the pre -buried part of external partially insert, is external part installation simultaneously and protects the box, has further strengthened the protection to settlement observation point.
Description
Technical field
The utility model relates to building field, specifically provides a kind of separate type settlement observation point.
Background technology
When carrying out external wall construction, settlement observation point is indispensable equipment.Settlement observation point will meet the observation requirement of each construction stage, particularly will consider that decoration stage is because of breakage in installation or cover settlement observation point, can not Continuous Observation and lose observation meaning.Common settlement observation point wall inner fixed part and external observation part are integrated; do not have device to protect it in the subsequent construction stage, settlement observation point be easy to by weight pound deform or decorated material contamination impact use and can not get settling amount accurately.
Utility model content
In order to solve the problem, the utility model provides a kind of separate type settlement observation point, by first arranging pre-buried part in body of wall, External connecting part is inserted pre-buried part during observation by follow-up needs, avoids subsequent construction process to cause damage to the naked part be exposed on the external of settlement observation point.
The utility model is achieved in that a kind of separate type settlement observation point, comprising:
Pre-buried part, be made up of pre-embedded steel slab, service sleeve and dowel, pre-embedded steel slab be fixed on need install settlement observation point metope on, service sleeve is connected at the center of pre-embedded steel slab, and the center of pre-embedded steel slab has the connecting hole with service sleeve hollow cross-section consistent size, at least two dowels are fixed on the end of pre-embedded steel slab; And
External connecting part, one end is link, and one end is for inserting service sleeve from pre-embedded steel slab connecting hole in observation end, link termination.
Further, External connecting part is provided with protective device, and protective device comprises track and protection box, and track is fixed on two ends, pre-embedded steel slab left and right, track lower end closed, and protection box can insert track from track upper end, is fixed on External connecting part periphery.
Further, service sleeve hollow cross-section and External connecting part link xsect are regular pentagon.
Further, pre-embedded steel slab is square, and dowel has 4, is separately fixed at 4 limits place of pre-embedded steel slab.
Further, dowel is set to bending away from one end of pre-embedded steel slab.
Compared with prior art, the utility model has the advantage of:
1, the utility model is divided into pre-buried part and External connecting part, pre-buried part was arranged in the structure construction stage, reach the object observing sedimentation with buildings the same period, External connecting part connects when needs are observed, and avoids in work progress due to inconvenience that the protrusion of External connecting part causes;
2, when installing External connecting part, the protection to External connecting part can be strengthened further at its peripheral protection box arranged, preventing the subsequent construction stage from being pounded by weight or being polluted by coating;
3, preferably pre-buried part and the joint face of External connecting part can be set to regular pentagon, expanding screw hydrant more in the past is so set and screw screw-in more easily operates and can control the direction of termination accurately and conveniently;
4, arrange many with dowel, and dowel is set to bending away from one end of pre-embedded steel slab, pre-buried part and the strength of joint of body of wall can be strengthened, can not come off and cause the later stage to observe.
Accompanying drawing explanation
Below in conjunction with drawings and the embodiments, the utility model is described in further detail:
Fig. 1 does not establish a separate type settlement observation point left side for protection box to look cross-sectional view;
Fig. 2 is the separate type settlement observation point top view cross section structural representation arranging protection box;
Fig. 3 is connecting hole and orbital position relation schematic diagram on pre-embedded steel slab.
Embodiment
In order to make the purpose of this utility model, technical scheme and advantage clearly understand, below in conjunction with drawings and Examples, the utility model is further elaborated.Should be appreciated that specific embodiment described herein only for explaining the utility model, and be not used in restriction the utility model.
In order to solve settlement observation point whole installation in prior art and there is no protective device, the problem of easily being pounded by weight in the subsequent construction stage or being polluted by coating, the utility model provides a kind of separate type settlement observation point, with reference to figure 1, comprise pre-buried part 1 and External connecting part 2, preburying part divides and comprises pre-embedded steel slab 11, service sleeve 12 and dowel 13, pre-embedded steel slab 11 is fixed on buildings to be needed arbitrarily to observe on the metope of settling height point, fix in interior insert-type, at the center of pre-embedded steel slab 11, connecting hole 111 is set, with reference to figure 3, the size of connecting hole 111 and the consistent size of service sleeve 12 hollow cross-section, service sleeve 12 correspond to the side that connecting hole 111 is fixed on pre-embedded steel slab 11, dowel 13 is connected to the marginal end of pre-embedded steel slab 11, be used for strengthening the strength of joint of pre-buried part 1 and body of wall, External connecting part 2 one end is link 21, and one end is observation end 22, and service sleeve 12 can be inserted from the connecting hole 111 of pre-embedded steel slab 11 in the termination of link 21.
In the utility model, settlement observation point be divide into pre-buried part and External connecting part, compared with settlement observation point whole installation in prior art, preburying part can to divide in the preorder construction stage and is arranged in body of wall by the utility model, carry out the subsequent construction stage again, when needs are observed building settlement distance, External connecting part is inserted in pre-buried part, can observe, prevent subsequent construction part to the damage of observation station.
In order to further protect settlement observation point; especially protect External connecting part, as the improvement of technical scheme, protective device 3 is set to External connecting part 2; with reference to figure 2; comprise track 31 and protection box 32, track 31 is fixed on the two ends, left and right of pre-embedded steel slab 11, the lower end closed of track 31; protection box 32 refers to open system; the size of its right and left is mated with the size of track, can be inserted by protection box 32, be fixed on the periphery of External connecting part 2 from the upper end of track 31.
In order to utilize regular pentagon base be flat limit be easy to construction levelling, and regular pentagon summit is easy to the advantage of the observation station termination aimed at upwards between two parties, as the improvement of technical scheme, be regular pentagon by service sleeve 12 hollow cross-section and External connecting part 2 link 21 xsect, with reference to figure 2.
Pre-buried part 1 links except the bonding by pre-embedded steel slab 11 and wall with External connecting part 2, dowel also further enhances the two strength of joint, as the improvement of technical scheme, pre-embedded steel slab 11 is set to square, in foursquare four edges, 4 dowels 13 are set respectively, further preferably, dowel is set to bending away from one end of pre-embedded steel slab 11.
Claims (5)
1. a separate type settlement observation point, is characterized in that, comprising:
Pre-buried part, be made up of pre-embedded steel slab, service sleeve and dowel, described pre-embedded steel slab be fixed on need install settlement observation point metope on, described service sleeve is connected at the center of pre-embedded steel slab, and the center of pre-embedded steel slab has the connecting hole with service sleeve hollow cross-section consistent size, at least two dowels are fixed on the end of described pre-embedded steel slab; And
External connecting part, one end is link, and one end is observation end, and described service sleeve can be inserted from described pre-embedded steel slab connecting hole in described link termination.
2. according to separate type settlement observation point according to claim 1; it is characterized in that; described External connecting part is provided with protective device; protective device comprises track and protection box; track is fixed on two ends, pre-embedded steel slab left and right; track lower end closed, described protection box can insert track from track upper end, is fixed on described External connecting part peripheral.
3. according to separate type settlement observation point according to claim 1, it is characterized in that, described service sleeve hollow cross-section and described External connecting part link xsect are regular pentagon.
4. according to separate type settlement observation point according to claim 1, it is characterized in that, described pre-embedded steel slab is square, and described dowel has 4, is separately fixed at 4 limits place of described pre-embedded steel slab.
5. according to separate type settlement observation point according to claim 4, it is characterized in that, described dowel is set to bending away from one end of described pre-embedded steel slab.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520891165.2U CN205079771U (en) | 2015-11-10 | 2015-11-10 | Disconnect -type settlement observation point |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520891165.2U CN205079771U (en) | 2015-11-10 | 2015-11-10 | Disconnect -type settlement observation point |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205079771U true CN205079771U (en) | 2016-03-09 |
Family
ID=55432173
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520891165.2U Active CN205079771U (en) | 2015-11-10 | 2015-11-10 | Disconnect -type settlement observation point |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205079771U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107727064A (en) * | 2017-11-09 | 2018-02-23 | 中建八局第二建设有限公司 | A kind of new take-off observation device |
CN110409626A (en) * | 2019-07-24 | 2019-11-05 | 中国十七冶集团有限公司 | A kind of pre-buried hanging ring and installation process method |
-
2015
- 2015-11-10 CN CN201520891165.2U patent/CN205079771U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107727064A (en) * | 2017-11-09 | 2018-02-23 | 中建八局第二建设有限公司 | A kind of new take-off observation device |
CN110409626A (en) * | 2019-07-24 | 2019-11-05 | 中国十七冶集团有限公司 | A kind of pre-buried hanging ring and installation process method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205079771U (en) | Disconnect -type settlement observation point | |
CN205804904U (en) | A kind of leveling unit | |
CN203769274U (en) | Horizontal floor tile laying positioning device | |
CN204152231U (en) | Socket type safety guard rail | |
CN203403056U (en) | Central calibration device for furnace head in building of coke furnace | |
CN204624225U (en) | Building engineering pipeline member organizer | |
CN202731258U (en) | Floor tile paving tool | |
CN204282817U (en) | Door-window opening mould plate installs structure | |
CN204418627U (en) | A kind of building operations roof beam structure | |
CN108824819B (en) | Modular building structure building system | |
CN105625667A (en) | Fixing and installing method for stone pendant through vertical steel belt | |
CN105839884B (en) | A kind of adjustable connection component | |
CN205445132U (en) | Curtain wall penel | |
CN204782025U (en) | Stair that construction was used external corner protector of marking time | |
CN204570733U (en) | Plug-in type municipal administration cable shaft | |
CN201127208Y (en) | Wall hanging type flower bed | |
CN205077987U (en) | Guardrail bar is prevented to scalable movable type | |
CN204304343U (en) | Cable trench joint | |
CN105064673A (en) | Flat steel scaffold pulling joint structure | |
CN204174913U (en) | Disc type scaffold upright rod and fixed disk Split type structure | |
CN204940887U (en) | The on-hook of stone curtain wall cloth | |
CN204507670U (en) | The special rack of a kind of building ground pipeline | |
CN204040282U (en) | A kind of keel connecting member | |
CN211341505U (en) | Elevator layer shows beautifies plate structure | |
CN204326547U (en) | Control the device of cement floor absolute altitude planeness |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |