CN205077723U - Interim plugging device of steel core concrete column - Google Patents
Interim plugging device of steel core concrete column Download PDFInfo
- Publication number
- CN205077723U CN205077723U CN201520736763.2U CN201520736763U CN205077723U CN 205077723 U CN205077723 U CN 205077723U CN 201520736763 U CN201520736763 U CN 201520736763U CN 205077723 U CN205077723 U CN 205077723U
- Authority
- CN
- China
- Prior art keywords
- steel core
- concrete column
- core concrete
- cover plate
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Fencing (AREA)
Abstract
The utility model provides an interim plugging device of steel core concrete column, include: the closing cap is in the orificial apron of steel core concrete column, the apron size is greater than the steel core concrete column pipe diameter, locate the hoist and mount piece of steel core concrete column surface, and connect in the apron with the connecting piece of hoist and mount piece. The utility model discloses a to lap at the steel core concrete column top mouth of pipe to through the connecting piece connect in lap and locate the hoist and mount piece of steel core concrete column surface to solved the steel core concrete column circumstances of falling into debris suitable for reading, avoided the concrete quality defect because of there being debris to lead to the fact in the steel core concrete column, and this apron can have enough to meet the need the use, realize green construction, the potential safety hazard of personnel's operation when having solved steel core concrete column upper end opening simultaneously.
Description
Technical field
The utility model relates to a kind of steel core concrete column temporary blocking device.
Background technology
Along with the rise of domestic and international super highrise building, turret structure form has Core Walls Structure+housing steel core concrete column to combine more.In housing steel pipe column work progress, first lift steel pipe column, then concreting, complete Construction of Steel Pipe Concrete Column.But after lifting steel pipe column, steel pipe column is suitable for reading is opening, easily falls into foreign material, as sleety weather or sandstorm weather, thus causes steel tube concrete quality defect.And there is operator safety hidden danger in steel pipe column upper end open.
Utility model content
For overcoming the defect existing for prior art, now providing a kind of steel core concrete column temporary blocking device, easily causing the problems such as mass defect because falling into foreign material in pipe etc. to solve steel core concrete column when constructing.
For solving the problem, a kind of steel core concrete column temporary blocking device, comprising: the cover plate being covered in the steel core concrete column mouth of pipe, and described cover plate size is greater than described steel core concrete column caliber; Be located at the lifting part of described concrete filled steel tube outer surface of column; And be connected to the connector of described cover plate and described lifting part.
The further improvement of the utility model steel core concrete column temporary blocking device is, described lifting part is the hanger being arranged at described concrete filled steel tube outer surface of column.
The further improvement of the utility model steel core concrete column temporary blocking device is, the quantity of described hanger is four, and four described hangers are uniformly distributed in described steel core concrete column sustained height.
The further improvement of the utility model steel core concrete column temporary blocking device is, described cover plate is provided with the sleeve corresponding with described hanger, and the two ends of described connector are connected to described sleeve and described hanger.
The further improvement of the utility model steel core concrete column temporary blocking device is, described connector comprises the fake that is sheathed on described sleeve and is connected to described fake, hook for hanger described in hook.
The beneficial effects of the utility model are, by cover plate being covered at the steel core concrete column top mouth of pipe, and be connected to described cover plate by connector and be located at the lifting part of described concrete filled steel tube outer surface of column, thus solve the steel core concrete column situation falling into foreign material suitable for reading, avoid the quality defect of concrete caused because having foreign material in steel core concrete column, and this cover plate can have enough to meet the need use, achieve green construction, solve the potential safety hazard of human users during steel core concrete column upper end open simultaneously.
Accompanying drawing explanation
Fig. 1 is the top view of the utility model steel core concrete column temporary blocking device.
Fig. 2 is the lateral view of the utility model steel core concrete column temporary blocking device.
Detailed description of the invention
For the benefit of to the understanding of structure of the present utility model, be described below in conjunction with drawings and Examples.
Please refer to Fig. 1 and Fig. 2, Fig. 1 is the top view of the utility model steel core concrete column temporary blocking device, and Fig. 2 is the lateral view of the utility model steel core concrete column temporary blocking device.
As depicted in figs. 1 and 2, the utility model provides a kind of steel core concrete column temporary blocking device, comprising: the cover plate 2 being covered in steel core concrete column 1 mouth of pipe, and cover plate 2 size is greater than steel core concrete column 1 caliber; Be located at the lifting part 3 of steel core concrete column 1 external surface; And be connected to the connector 4 of cover plate 2 and lifting part 3.
Below said modules is described in detail.
As depicted in figs. 1 and 2, cover plate 2 can be the steel plate selecting 2mm thick, and cover plate 2 covers on steel core concrete column 1 mouth of pipe, and preferably, cover plate 2 is round plate.Cover plate 2 is at least good than the large 100mm of steel core concrete column 1 top outer diameter, and for steel core concrete column 1 top diameter for 1500mm, cover plate 2 diameter now can be 1600mm.
As depicted in figs. 1 and 2, lifting part 3 is for being arranged at the hanger of steel core concrete column 1 external surface, and described hanger closes on steel core concrete column 1 top.The quantity of described hanger can be multiple, and preferably, the quantity of described hanger is four, and as shown in Figure 2, four described hangers are uniformly distributed in steel core concrete column 1 sustained height.
As depicted in figs. 1 and 2, cover plate 2 is provided with the sleeve corresponding with described hanger, and the two ends of connector 4 are connected to described sleeve and described hanger, and the quantity of described sleeve corresponds to described hanger, the quantity of described sleeve is four, and four described sleeves are uniformly distributed in cover plate 2 surrounding.Connector 4 fake and be connected to the hook of described fake, described fake is sheathed on described sleeve, and described hook is hooked in described hanger.
After there is said structure feature, composition graphs 1 and Fig. 2, the utility model can by following implementation Process: according to often saving steel core concrete column 1 top maximum size design cover plate 2 size, be convenient to all steel core concrete columns can use, cover plate 2 can select 2mm steel plate, connector 4 is utilized cover plate 2 to be installed and connected in the described hanger of concrete filled steel tube column top, thus solve steel core concrete column 1 situation falling into foreign material suitable for reading, avoid the quality defect of concrete caused because having foreign material in steel core concrete column 1.Cover plate 2 can be removed when steel core concrete column 1 concreting, cover plate 2 is continued to cover steel core concrete column 1 top after concreting, until remove cover plate 2 when lower joint steel core concrete column 1 is installed, after upper joint steel core concrete column 1 installs, cover upper joint steel core concrete column 1 top again.
The beneficial effects of the utility model are:
By cover plate being covered at the steel core concrete column top mouth of pipe, and be connected to described cover plate by connector and be located at the lifting part of described concrete filled steel tube outer surface of column, thus solve the steel core concrete column situation falling into foreign material suitable for reading, avoid the quality defect of concrete caused because having foreign material in steel core concrete column, and this cover plate can have enough to meet the need use, achieve green construction, solve the potential safety hazard of human users during steel core concrete column upper end open simultaneously.
Below embodiment has been described in detail the utility model by reference to the accompanying drawings, and those skilled in the art can make many variations example to the utility model according to the above description.Thus, some details in embodiment should not formed restriction of the present utility model, the utility model by the scope that defines using appended claims as protection domain.
Claims (5)
1. a steel core concrete column temporary blocking device, is characterized in that, comprising:
Be covered in the cover plate of the steel core concrete column mouth of pipe, described cover plate size is greater than described steel core concrete column caliber;
Be located at the lifting part of described concrete filled steel tube outer surface of column; And
Be connected to the connector of described cover plate and described lifting part.
2. steel core concrete column temporary blocking device according to claim 1, is characterized in that, described lifting part is the hanger being arranged at described concrete filled steel tube outer surface of column.
3. steel core concrete column temporary blocking device according to claim 2, is characterized in that, the quantity of described hanger is four, and four described hangers are uniformly distributed in described steel core concrete column sustained height.
4. steel core concrete column temporary blocking device according to claim 2, is characterized in that, described cover plate is provided with the sleeve corresponding with described hanger, and the two ends of described connector are connected to described sleeve and described hanger.
5. steel core concrete column temporary blocking device according to claim 4, is characterized in that, described connector comprises the fake that is sheathed on described sleeve and is connected to described fake, hook for hanger described in hook.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520736763.2U CN205077723U (en) | 2015-09-22 | 2015-09-22 | Interim plugging device of steel core concrete column |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520736763.2U CN205077723U (en) | 2015-09-22 | 2015-09-22 | Interim plugging device of steel core concrete column |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205077723U true CN205077723U (en) | 2016-03-09 |
Family
ID=55430137
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520736763.2U Expired - Fee Related CN205077723U (en) | 2015-09-22 | 2015-09-22 | Interim plugging device of steel core concrete column |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205077723U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110863609A (en) * | 2019-11-20 | 2020-03-06 | 河北水利电力学院 | Latch hook connected H-shaped steel and channel steel assembled cross-shaped special-shaped column |
-
2015
- 2015-09-22 CN CN201520736763.2U patent/CN205077723U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110863609A (en) * | 2019-11-20 | 2020-03-06 | 河北水利电力学院 | Latch hook connected H-shaped steel and channel steel assembled cross-shaped special-shaped column |
CN110863609B (en) * | 2019-11-20 | 2021-11-30 | 河北水利电力学院 | Latch hook connected H-shaped steel and channel steel assembled cross-shaped special-shaped column |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104420640A (en) | Heterosexual chimney construction platform | |
CN205077723U (en) | Interim plugging device of steel core concrete column | |
CN204492142U (en) | A kind of pre embedded bolt wall-connecting piece | |
CN207392218U (en) | A kind of novel water discharge device applied to construction site foundation pit | |
CN204139627U (en) | The anti-wear cover cage of wire rope | |
CN103939103B (en) | Equipped with ash system under the shaft of vertical well of secondary stirring device | |
CN208430425U (en) | A kind of high-speed railway pier top protective device of installation easy to disassemble | |
CN203475797U (en) | Special-shaped chimney construction platform | |
CN105863192B (en) | A kind of balcony guardrail | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN204282850U (en) | Steel work-concrete combined floor reserved opening protective net frame | |
CN204252082U (en) | Arch dam bracket plate device | |
CN204098465U (en) | Lifting false work falls in a kind of frame guide rail formula | |
CN202969944U (en) | Concrete pouring blanking appliance | |
CN205975620U (en) | Underwater concrete pours device | |
CN205875410U (en) | A hang module system all for tube structure room panel construction | |
CN204199783U (en) | Line protecting apparatus is drawn in deep settlement monitoring | |
CN201391080Y (en) | Embedded sleeve barrel of attached type lifting scaffold | |
CN205055290U (en) | Remote husky pond of fire control of sandblasting | |
CN204510768U (en) | A kind of without support operation frame | |
CN205348823U (en) | External protector of high formwork support | |
CN204174913U (en) | Disc type scaffold upright rod and fixed disk Split type structure | |
CN204080639U (en) | A kind of device for installing the main muscle of pier stud | |
CN219826058U (en) | Entrance to a cave protector | |
CN203701559U (en) | Guiding device for external scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160309 Termination date: 20210922 |
|
CF01 | Termination of patent right due to non-payment of annual fee |