CN207392218U - A kind of novel water discharge device applied to construction site foundation pit - Google Patents

A kind of novel water discharge device applied to construction site foundation pit Download PDF

Info

Publication number
CN207392218U
CN207392218U CN201721423655.5U CN201721423655U CN207392218U CN 207392218 U CN207392218 U CN 207392218U CN 201721423655 U CN201721423655 U CN 201721423655U CN 207392218 U CN207392218 U CN 207392218U
Authority
CN
China
Prior art keywords
foundation pit
construction site
discharge device
sealing ring
air bag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721423655.5U
Other languages
Chinese (zh)
Inventor
杨亦贵
缪永骏
郑佳
张红兵
周喜寿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUOQIANG CONSTRUCTION GROUP CO Ltd
Original Assignee
GUOQIANG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUOQIANG CONSTRUCTION GROUP CO Ltd filed Critical GUOQIANG CONSTRUCTION GROUP CO Ltd
Priority to CN201721423655.5U priority Critical patent/CN207392218U/en
Application granted granted Critical
Publication of CN207392218U publication Critical patent/CN207392218U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of novel water discharge device applied to construction site foundation pit.The novel water discharge device applied to construction site foundation pit includes filter grid;Outer framework;Air bag;Accommodation space;Water pump;Level control structure for water, the level control structure for water extends to the accommodation space through the air bag, the level control structure for water includes raising the nose above water to breathe, connecting rod, sealing ring, resetting spring, slide bar, protective jacket and contact structures, the protective jacket is fixed on the air bag, the protective jacket is internally provided with the sealing ring, the bottom of the sealing ring is equipped with the connecting rod, the connecting rod is equipped with the floating head away from one end of the sealing ring, the sealing ring is equipped with the slide bar away from one end of the connecting rod, the slide bar is connected to the contact structures, the resetting spring is equipped between the protective jacket and the sealing ring.Novel water discharge device draining provided by the utility model applied to construction site foundation pit, energy-efficient performance are good.

Description

A kind of novel water discharge device applied to construction site foundation pit
Technical field
The utility model is related to technical field of building construction more particularly to a kind of new rows applied to construction site foundation pit Water installations.
Background technology
Foundation pit is the heatable adobe sleeping platform excavated in basic engineering position by substrate absolute altitude and basic plane size, is combined after excavation existing Nearby buildings situation, and perform water-proof drainage work, drainage system refer to the collection of draining, conveying, the processing of water quality and The totality that the facilities such as discharge are combined into a certain way, the use of drainage arrangement are effectively protected excavation slope, improve and apply The quality of work, reduces difficulty of construction.
However the drainage arrangement of traditional construction site foundation pit cannot determine the break-make of draining automatically according to water level, cause one The surely waste in source.
It is asked therefore, it is necessary to provide a kind of new novel water discharge device applied to construction site foundation pit and solve above-mentioned technology Topic.
Utility model content
The technical issues of the utility model solves be to provide it is a kind of can automatic pumping, energy saving be applied to construction site foundation pit Novel water discharge device.
In order to solve the above technical problems, the novel water discharge device provided by the utility model applied to construction site foundation pit, Including:Filter grid;Outer framework, the outer framework are fixed on the filter grid;Air bag, the air bag are sticked in the outline border Frame;Accommodation space surrounds the accommodation space between the air bag and the filter grid;Water pump, the water pump are fixed on institute State air bag;Level control structure for water, the level control structure for water extend to the accommodation space, the water level through the air bag Control structure includes floating head, connecting rod, sealing ring, resetting spring, slide bar, protective jacket and contact structures, and the protective jacket is fixed In the air bag, the protective jacket is internally provided with the sealing ring, and the bottom of the sealing ring is equipped with the connecting rod, described Connecting rod is equipped with the floating head away from one end of the sealing ring, and the sealing ring is equipped with described away from one end of the connecting rod Slide bar, the slide bar are connected to the contact structures, and the contact structures are fixed on the protective jacket, the protective jacket with it is described The resetting spring is equipped between sealing ring, institute's contact structures are electrically connected with the water pump.
Preferably, the filter grid is truncated cone-shaped structure, and the filter grid is threadedly coupled with the outer framework.
Preferably, the outer framework includes outer guard bar and connecting pole, and the outer guard bar is threadedly coupled with the filter grid, The connecting pole is equipped with multiple with the outer guard bar, and multiple connecting poles are uniformly fixed between multiple outer guard bars.
Preferably, the outer guard bar is cirque structure, and the air bag is engaged between the outer guard bar, and the air bag is circle Column structure.
Preferably, the level control structure for water further includes limited block and fixture block, and the fixture block is fixed on the slide bar, described Limited block is fixed on the madial wall of the protective jacket.
Preferably, the slide bar and the fixture block be through the resetting spring, and the resetting spring be fixed on it is described Between fixture block and the sealing ring.
Preferably, the protective jacket includes cover board and sleeve, and the sleeve is threadedly coupled with the air bag, the cover board and The bush whorl connection, the sleeve are internally provided with the limited block and the fixture block.
Preferably, the sealing ring is slidably connected with the sleeve, and the limited block is fixed on the inside of the sleeve Wall.
Preferably, the limited block is arranged between the resetting spring and the cover board, and institute's slide bar and the limited block It is slidably connected.
Preferably, the contact structures include the first wiring shrapnel and the second wiring shrapnel, and the first wiring shrapnel is consolidated Due to the sleeve close to the side wall of one end of the cover board, the second wiring shrapnel is fixed on the slide bar.
Compared with correlation technique, the novel water discharge device provided by the utility model applied to construction site foundation pit has Following advantageous effect:
The utility model provides a kind of novel water discharge device applied to construction site foundation pit, and the protective jacket is fixed on institute Air bag is stated, the protective jacket is internally provided with the sealing ring, and the bottom of the sealing ring is equipped with the connecting rod, the connection Bar is equipped with the floating head away from one end of the sealing ring, and the sealing ring is equipped with the cunning away from one end of the connecting rod Bar, the slide bar are connected to the contact structures, and the contact structures are fixed on the protective jacket, the protective jacket with it is described close The resetting spring is equipped between seal, institute's contact structures are electrically connected with the water pump, are raised the nose above water to breathe described in pump process The connecting rod is promoted to be slided in the protective jacket under the buoyancy of water, the connecting rod promotes the sealing ring and its institute Internal slide of the slide bar in the protective jacket is stated, the contact structures is made to connect the water pump, makes the pump working, works as water level During less than the floating head, the slide bar slides under the elastic force effect of the resetting spring to the floating head end, disconnects institute automatically Water pump is stated, the automatic opening of the water pump is realized, effectively saves electric energy.
Description of the drawings
Fig. 1 is a kind of preferred embodiment of the novel water discharge device provided by the utility model applied to construction site foundation pit Structure diagram;
Fig. 2 is the attachment structure schematic diagram of level control structure for water shown in FIG. 1 and outer framework;
Fig. 3 is A portions shown in Fig. 2 enlarged diagram.
Figure label:1st, filter grid, 2, air bag, 3, level control structure for water, 31, raise the nose above water to breathe, 32, connecting rod, 33, sealing Circle, 34, resetting spring, 35, slide bar, 36, protective jacket, 361, cover board, 362, sleeve, 37, contact structures, the 371, first wiring bullet Piece, the 372, second wiring shrapnel, 38, limited block, 39, fixture block, 4, water pump, 5, outer framework, 51, outer guard bar, 52, connecting pole, 6, Accommodation space.
Specific embodiment
The utility model is described in further detail with embodiment below in conjunction with the accompanying drawings.
Fig. 1, Fig. 2 and Fig. 3 are please referred to, wherein, Fig. 1 is provided by the utility model applied to construction site foundation pit A kind of structure diagram of preferred embodiment of novel water discharge device;Fig. 2 is level control structure for water shown in FIG. 1 and outer framework Attachment structure schematic diagram;Fig. 3 is A portions shown in Fig. 2 enlarged diagram.Applied to the novel water discharge device of construction site foundation pit, Including:Filter grid 1;Outer framework 5, the outer framework 5 are fixed on the filter grid 1;Air bag 2, the air bag 2 are sticked in institute State outer framework 5;Accommodation space 6 surrounds the accommodation space 6 between the air bag 2 and the filter grid 1;Water pump 4, it is described Water pump 4 is fixed on the air bag 2;Level control structure for water 3, the level control structure for water 3 extend to described through the air bag 2 Accommodation space 6, the level control structure for water 3 include raising the nose above water to breathe 31, connecting rod 32, sealing ring 33, resetting spring 34, slide bar 35, anti- Sheath 36 and contact structures 37, the protective jacket 36 are fixed on the air bag 2, and the protective jacket 36 is internally provided with the sealing Circle 33, the bottom of the sealing ring 33 are equipped with the connecting rod 32, and the connecting rod 32 is set away from one end of the sealing ring 33 There is the floating head 31, the sealing ring 33 is equipped with the slide bar 35 away from one end of the connecting rod 32, and the slide bar 35 connects In the contact structures 37, the contact structures 37 are fixed on the protective jacket 36, the protective jacket 36 and the sealing ring 33 Between be equipped with the resetting spring 34, institute's contact structures 37 are electrically connected with the water pump 4.
In order to improve the strainability of device, the air bag 2 is effectively protected, prevents the water pump 4 from directly contacting base The mud of bottom is cheated, influences the water absorbing properties of device, while improves the stability of device, the filter grid 1 is truncated cone-shaped Structure, and the filter grid 1 is threadedly coupled with the outer framework 5, the outer framework 5 includes outer guard bar 51 and connecting pole 52, The outer guard bar 51 is threadedly coupled with the filter grid 1, the connecting pole 52 be equipped with the outer guard bar 51 it is multiple, it is multiple The connecting pole 52 is uniformly fixed between multiple outer guard bars 51, the outer guard bar 51 be cirque structure, the outer shield The air bag 2 is engaged between bar 51, the air bag 2 is cylindrical structure.
In order to be effectively protected the contact structures 37, prevent the contact structures 37 from, due to the excessive damage of pressure, improving The working performance of device, the level control structure for water 3 further include limited block 38 and fixture block 39, and the fixture block 39 is fixed on the cunning Bar 35, the limited block 38 are fixed on the madial wall of the protective jacket 36, and the slide bar 35 and the fixture block 39 are through described Resetting spring 34, and the resetting spring 34 is fixed between the fixture block 39 and the sealing ring 33.
For the ease of adjusting the height of the level control structure for water 3 according to the actual conditions of foundation pit, the protective jacket 36 wraps Cover board 361 and sleeve 362 are included, the sleeve 362 is threadedly coupled with the air bag 2, the cover board 361 and 362 spiral shell of sleeve Line connects, and the sleeve 362 is internally provided with the limited block 38 and the fixture block 39, the sealing ring 33 and the sleeve 362 are slidably connected, and the limited block 38 is fixed on the madial wall of the sleeve 362, and the limited block 38 is arranged on the reset Between spring 34 and the cover board 361, and institute's slide bar 35 is slidably connected with the limited block 38, and the contact structures 37 include the One wiring shrapnel 371 and the second wiring shrapnel 372, the first wiring shrapnel 371 are fixed on the sleeve 362 close to the lid The side wall of one end of plate 361, the second wiring shrapnel 372 are fixed on the slide bar 35.
When the utility model is used, the water level control is adjusted according to the number of the mud of the inside of draining foundation pit first Distance of the structure 3 processed apart from the bottom of the outer framework 5, then places a device into foundation pit, when excessive rainfall, described Under the action of air bag 2, device is swum on the water surface, and the floating head 31 promotes the connecting rod 32 in institute under the buoyancy of water It states in protective jacket 36 and slides, the connecting rod 32 promotes the sealing ring 33 and its slide bar 35 in the protective jacket 36 Portion is slided, and the contact structures 37 is made to connect the water pump 4, the water pump 4 is made to work, when water level is less than floating head 31, The slide bar 35 slides under the elastic force effect of the resetting spring 34 to 31 ends of the floating head, disconnects the water pump 4 automatically, real The automatic opening of the existing water pump 4, the filter grid 1 of device after use dismantled and cleared up.
Compared with correlation technique, the novel water discharge device provided by the utility model applied to construction site foundation pit has Following advantageous effect:
The utility model provides a kind of novel water discharge device applied to construction site foundation pit, and the protective jacket 36 is fixed on The air bag, the protective jacket 36 are internally provided with the sealing ring 33, and the bottom of the sealing ring 33 is equipped with the connecting rod 32, the connecting rod 32 is equipped with the floating head 31 away from one end of the sealing ring 33, and the sealing ring 33 deviates from the connection One end of bar 32 is equipped with the slide bar 35, and the slide bar 35 is connected to the contact structures 37, and the contact structures 37 are fixed on The protective jacket 36, between the protective jacket 36 and the sealing ring 33 be equipped with the resetting spring 34, institute's contact structures 37 with The water pump 4 is electrically connected, and floating head 31 promotes the connecting rod 32 in institute under the buoyancy of water described in pump process It states in protective jacket 36 and slides, the connecting rod 32 promotes the sealing ring 33 and its slide bar 35 in the protective jacket 36 Portion is slided, and the contact structures 37 is made to connect the water pump 4, the water pump 4 is made to work, when water level is less than floating head 31, The slide bar 35 slides under the elastic force effect of the resetting spring 34 to 31 ends of the floating head, disconnects the water pump 4 automatically, real The automatic opening of the existing water pump 4, effectively saves electric energy.
The above description is only the embodiments of the present invention, and it does not limit the scope of the patent of the present invention, every Equivalent structure or equivalent flow shift made based on the specification and figures of the utility model, is directly or indirectly used in Other relevant technical fields, are equally included in the patent within the scope of the utility model.

Claims (10)

1. a kind of novel water discharge device applied to construction site foundation pit, which is characterized in that including:
Filter grid;
Outer framework, the outer framework are fixed on the filter grid;
Air bag, the air bag are sticked in the outer framework;
Accommodation space surrounds the accommodation space between the air bag and the filter grid;
Water pump, the water pump are fixed on the air bag;
Level control structure for water, the level control structure for water extend to the accommodation space, the water level control through the air bag Structure processed includes floating head, connecting rod, sealing ring, resetting spring, slide bar, protective jacket and contact structures, and the protective jacket is fixed on The air bag, the protective jacket are internally provided with the sealing ring, and the bottom of the sealing ring is equipped with the connecting rod, the company Extension bar is equipped with the floating head away from one end of the sealing ring, and the sealing ring is equipped with the cunning away from one end of the connecting rod Bar, the slide bar are connected to the contact structures, and the contact structures are fixed on the protective jacket, the protective jacket with it is described close The resetting spring is equipped between seal, institute's contact structures are electrically connected with the water pump.
2. the novel water discharge device according to claim 1 applied to construction site foundation pit, which is characterized in that the filtering Grid is truncated cone-shaped structure, and the filter grid is threadedly coupled with the outer framework.
3. the novel water discharge device according to claim 1 applied to construction site foundation pit, which is characterized in that the outline border Frame includes outer guard bar and connecting pole, and the outer guard bar is threadedly coupled with the filter grid, the connecting pole and the outer guard bar It is equipped with multiple, multiple connecting poles are uniformly fixed between multiple outer guard bars.
4. the novel water discharge device according to claim 3 applied to construction site foundation pit, which is characterized in that the outer shield Bar is cirque structure, and the air bag is engaged between the outer guard bar, and the air bag is cylindrical structure.
5. the novel water discharge device according to claim 1 applied to construction site foundation pit, which is characterized in that the water level Control structure further includes limited block and fixture block, and the fixture block is fixed on the slide bar, and the limited block is fixed on the protective jacket Madial wall.
6. the novel water discharge device according to claim 5 applied to construction site foundation pit, which is characterized in that the slide bar With the fixture block through the resetting spring, and the resetting spring is fixed between the fixture block and the sealing ring.
7. the novel water discharge device according to claim 5 applied to construction site foundation pit, which is characterized in that the protection Set includes cover board and sleeve, and the sleeve is threadedly coupled with the air bag, and the cover board is connected with the bush whorl, the set Cylinder is internally provided with the limited block and the fixture block.
8. the novel water discharge device according to claim 7 applied to construction site foundation pit, which is characterized in that the sealing Circle is slidably connected with the sleeve, and the limited block is fixed on the madial wall of the sleeve.
9. the novel water discharge device according to claim 7 applied to construction site foundation pit, which is characterized in that the /V Block is arranged between the resetting spring and the cover board, and institute's slide bar is slidably connected with the limited block.
10. the novel water discharge device according to claim 7 applied to construction site foundation pit, which is characterized in that described to connect Touching structure includes the first wiring shrapnel and the second wiring shrapnel, and the first wiring shrapnel is fixed on the sleeve close to the lid The side wall of one end of plate, the second wiring shrapnel are fixed on the slide bar.
CN201721423655.5U 2017-10-31 2017-10-31 A kind of novel water discharge device applied to construction site foundation pit Expired - Fee Related CN207392218U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721423655.5U CN207392218U (en) 2017-10-31 2017-10-31 A kind of novel water discharge device applied to construction site foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721423655.5U CN207392218U (en) 2017-10-31 2017-10-31 A kind of novel water discharge device applied to construction site foundation pit

Publications (1)

Publication Number Publication Date
CN207392218U true CN207392218U (en) 2018-05-22

Family

ID=62327378

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721423655.5U Expired - Fee Related CN207392218U (en) 2017-10-31 2017-10-31 A kind of novel water discharge device applied to construction site foundation pit

Country Status (1)

Country Link
CN (1) CN207392218U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111622248A (en) * 2020-05-27 2020-09-04 安徽伟基基础工程有限公司 Drainage device is used in construction site foundation pit construction
CN112227393A (en) * 2020-09-19 2021-01-15 湖南凡工建筑工程有限公司 Be applied to novel drainage device of building site foundation ditch
CN112663645A (en) * 2021-01-23 2021-04-16 北京滕宇翔建设工程有限公司 Foundation pit construction drainage system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111622248A (en) * 2020-05-27 2020-09-04 安徽伟基基础工程有限公司 Drainage device is used in construction site foundation pit construction
CN112227393A (en) * 2020-09-19 2021-01-15 湖南凡工建筑工程有限公司 Be applied to novel drainage device of building site foundation ditch
CN112663645A (en) * 2021-01-23 2021-04-16 北京滕宇翔建设工程有限公司 Foundation pit construction drainage system
CN112663645B (en) * 2021-01-23 2022-01-11 北京滕宇翔建设工程有限公司 Foundation pit construction drainage system

Similar Documents

Publication Publication Date Title
CN207392218U (en) A kind of novel water discharge device applied to construction site foundation pit
CN205382501U (en) Tower crane basis automatic drainage system
CN203947568U (en) A kind of intelligent substation water drainage device
CN203684244U (en) Automatic control system for dewatering and drainage of foundation pit
CN205776391U (en) A kind of Safety well cover
CN108118710A (en) A kind of foundation pit construction drainage system for building
CN208831041U (en) A kind of drift dewatering structure
CN205000350U (en) Closed automatic precipitation device
CN202666253U (en) Underground anti-collision fire hydrant
CN211898560U (en) Integrated pump well equipment
CN104335977A (en) Water supply and drainage system used for leech culture pond and provided with escape prevention device
CN207452954U (en) A kind of basement anti-floating pressure-release assembly
CN209958504U (en) Lifting type foundation structure of foundation engineering
CN207405663U (en) A kind of self-suspending resets town road manhole lid device
CN204061275U (en) A kind of submersible pump protecting seat
CN207567891U (en) Building engineering construction scene Rainwater collection system
CN204728366U (en) A kind of light current well dewatering installation
CN206737106U (en) Prefabricated pumping plant Lift-on/Lift-off System
CN205296343U (en) Be applied to waste fitting discharging in workshop
CN212405233U (en) Automatic water lowering device for tower crane foundation
CN211714673U (en) Solar water pump rainproof awning
CN204312311U (en) A kind of submersible pump protecting seat
CN205350550U (en) Waterproof cable crane span structure
CN209324422U (en) A kind of tunnel water plug
CN207183798U (en) A kind of climbing type construction lightning rod

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180522

Termination date: 20211031

CF01 Termination of patent right due to non-payment of annual fee