CN205046851U CN201520703967.6U CN201520703967U CN205046851U CN 205046851 U CN205046851 U CN 205046851U CN 201520703967 U CN201520703967 U CN 201520703967U CN 205046851 U CN205046851 U CN 205046851U
Authority
CN
China
Prior art keywords
threaded rod
junction plate
connecting hole
gripper shoe
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520703967.6U
Other languages
Chinese (zh)
Inventor
韩荣国
吕念
马祖健
杨福忠
焦平文
郝同亮
骆鹏
何勇军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Electric Power Transmission and Substation Engineering Co
Original Assignee
Shandong Electric Power Transmission and Substation Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Electric Power Transmission and Substation Engineering Co filed Critical Shandong Electric Power Transmission and Substation Engineering Co
Priority to CN201520703967.6U priority Critical patent/CN205046851U/en
Application granted granted Critical
Publication of CN205046851U publication Critical patent/CN205046851U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides a building template mainly solves and has wrong platform when building template is assembled among the prior art, leaks the problem that thick liquid etc. Seriously influences the concrete placement effect. It includes panel, horizontal, stupefied, first, two connecting plates of the vertical back of the body, and double hook connector, this double hook connector includes the backup pad, threaded rod and clamp plate, the backup pad for the lower extreme be equipped with the coupling hook (img file='DDA0000801188500000011. TIF'wi='128'he='57' /) the shape structure, the threaded rod runs through the setting in the horizontally connect of backup pad portion with screw thread connection, the threaded rod outer end is the slab structure in band -pass hole, threaded rod the inner is equipped with can relative its pivoted U -shaped clamp plate, first connecting plate is equipped with the first connecting hole that supplies the coupling hook to penetrate, and the second connecting plate is equipped with the supplier and appears the bolt and penetrate the quad slit of connection, rotates threaded rod clamp plate and the common matched mould flange frame of coupling hook and applys the pulling force and make between board and the board frame very level and smooth, solves the problem of leaking thick liquid and wrong platform, plays the dual function who consolidates and flatten.

Description

A kind of construction formwork
Technical field
The utility model belongs to technical field of building construction, specifically a kind of construction formwork.
Background technology
The construction formwork used in current building field is multi-disc template to be needed assembled according to practice of construction, as shown in Figure 1, construction formwork generally comprises panel 13, is arranged on horizontal 15 on rear side of panel and vertical back cord 14, and be positioned at the first junction plate 11 of the panel left and right sides and be positioned at panel upper and lower sides second junction plate 12, wherein the first junction plate 11 and the second junction plate 12 are equipped with connecting hole.In assembled process, between the first junction plate between adjacent two templates, and common Steel Bolt between the second junction plate, is mostly directly adopted directly to connect, although can effectively improve dismounting efficiency to a certain extent; But, there is larger impact to construction effect in the problem such as faulting of slab ends, spillage that this kind of connected mode often makes construction formwork produce in this connection.For this reason, how effectively solving the problem such as faulting of slab ends, spillage existed in prior art is those skilled in the art's technical issues that need to address.
Utility model content
For the problem that there is faulting of slab ends, spillage etc. when construction formwork is assembled in prior art and have a strong impact on concreting effect, the purpose of this utility model is to provide a kind of construction formwork, it effectively solves the problem such as faulting of slab ends, spillage, improve the globality of split between construction formwork, improve and concretely build effect.
The technical scheme in the invention for solving the technical problem is: a kind of construction formwork, comprise panel, be located at vertical back cord on rear side of panel and horizontal back cord, and be located at the first junction plate of the panel left and right sides and the second junction plate of the upper and lower both sides of panel;
It is characterized in that, also comprise double hook connector, described double hook connector comprises gripper shoe, threaded rod and pressing plate, and described gripper shoe is shape structure, and gripper shoe described in this is provided with the first breach run through in side in the middle, described first breach is cutting out butt hook near described gripper shoe two supporting leg bottom position;
Described threaded rod runs through with thread connecting mode and is arranged in the level connection joint portion of described gripper shoe, described threaded rod outer end is the slab structure of band through hole, described pressing plate is U-shaped structure, it is arranged on described threaded rod inner opposite end in the mode of outward opening, and described threaded rod can relatively described press plate rotary;
Described first junction plate is provided with many groups and is uniformly distributed the first connecting hole, and often organizing the first connecting hole has two, and centered by described first connecting hole, place is with the rectangular through-hole of symmetrical arc v notch v; Described second junction plate is provided with equally distributed second connecting hole, and described second connecting hole is square opening.
Further, described threaded rod is provided with nut, and described nut is fixedly installed on described level connection joint portion medial surface.
Further, it also comprises steel ladder, and described steel ladder side is provided with uniform support column, and described support column is provided with the junction plate of band connecting hole, and the connecting hoop be set on described horizontal back cord utilizes connecting bolt and described junction plate to be connected and fixed.
Further, the second junction plate of upside is provided with suspension ring, and described suspension ring are outward-dipping.
Further, described horizontal back cord is two channel-section steels be arranged in parallel.
The beneficial effects of the utility model are:
1, double hook connector imitates claws of a hawk principle, install, dismantle flexibly and easily, its butt hook to snap on the first junction plate between two panels template in the first connecting hole, can exert a force to butt hook by rotating threaded rod, and adjacent two panels first junction plate is fixed by pressing plate, by the acting in conjunction of pressing plate and butt hook, pulling force is applied to Form board frame, make frame between plate and plate very smooth, and extruding force is applied to frame, make piece not spillage between plate, play the dual-use function reinforced and flatten.
2, the second junction plate is provided with uniform square opening, the square bolt adapted to it can be adopted to connect, can effectively solve the problem such as faulting of slab ends, spillage between adjacent two templates.
3, steel ladder adopts the connecting hoop be set on horizontal back cord to be connected and fixed, can according to the operating mode needs of reality, and the position of lateral adjustments steel ladder, meets the installation requirement of Various Complex operating mode; Horizontal back cord adopts channel-section steel simultaneously, when steel ladder is connected and fixed, can carry out certain elastic deformation under the extruding of the junction plate of channel-section steel biside plate, effectively can reduce the generation that connecting bolt loosens naturally.
4, template is complained to the higher authorities about an injustice and request fair settlement and is provided with outward-dipping suspension ring, template can be carried out assembled rear integral lifting in bottom surface, can reduce lifting times further in practice of construction process.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is part preferred embodiment of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
The structural representation of positive apparent direction when Fig. 1 is the utility model split;
Fig. 2 is the structural representation overlooking direction in Fig. 1;
Fig. 3 is the structural representation of right apparent direction in Fig. 1;
Fig. 4 is the partial structurtes schematic diagram along A direction in Fig. 1;
Fig. 5 is the partial structurtes schematic diagram along B direction in Fig. 1;
Fig. 6 is the partial structurtes schematic diagram utilizing double hook connector to connect construction formwork;
Fig. 7 overlooks direction structure schematic diagram in Fig. 6;
Fig. 8 is the structural representation of connecting hoop;
In figure: 1 construction formwork, 11 first junction plates, 111 first connecting holes, 12 second junction plates, 121 second connecting holes, 13 panels, 14 vertical back cords, 15 horizontal back cords, 151 angle steel, 152 gussets, 16 suspension ring, 2 steel ladders, 21 support columns, 211 junction plates, 22 connecting hoops, 221 the 3rd connecting holes, 3 double hook connectors, 31 gripper shoes, 311 first breach, 312 butt hooks, 313 level connection joint portions, 32 threaded rods, 321 nuts, 33 pressing plates.
Detailed description of the invention
As shown in Figures 1 to 8, a kind of construction formwork that the utility model provides, comprise panel 13, be located at vertical back cord 14 on rear side of panel 13 and horizontal back cord 15, and be located at the first junction plate 11 of panel 13 left and right sides and the second junction plate 12 of panel about 13 both sides.It is characterized in that, also comprise double hook connector 3, as shown in Figure 6 and Figure 7, described double hook connector 3 comprises gripper shoe 31, threaded rod 32 and pressing plate 33, and described gripper shoe 31 is shape structure, and gripper shoe 31 described in this is provided with the first breach 311 run through in side in the middle, described first breach 311 is cutting out butt hook 312 near described gripper shoe 31 liang of supporting leg bottom positions.
As shown in Figure 6 and Figure 7, described threaded rod 32 run through with thread connecting mode be arranged on described gripper shoe 31 level connection joint portion 313 on, described threaded rod 32 outer end is the slab structure of band through hole, described pressing plate 33 is U-shaped structure, it is arranged on described threaded rod 32 inner opposite end in the mode of outward opening, described threaded rod 32 can rotate relative to described pressing plate 33 (as pressing plate 33 is nested with on the terminal of matched in clearance with it, then this terminal is fixedly connected with threaded rod 32, and such set-up mode those skilled in the art can be readily embodied in this and be not described in detail.
As shown in Figure 4, described first junction plate 11 is provided with many groups and is uniformly distributed the first connecting hole 111, often organize the first connecting hole 111 and have two, centered by described first connecting hole 111, place (is provided with symmetrical arc v notch v to be mainly used to prevent the first connecting hole side plate when pretightning force is larger from occurring that volume sticks up with the rectangular through-hole of symmetrical arc v notch v, be convenient to butt hook simultaneously and carry out certain changing of the relative positions at arc notch place, be convenient to installation and removal).In concrete use, as shown in Figure 6 and Figure 7, double hook connector imitates claws of a hawk principle, install, dismantle flexibly and easily, its butt hook to snap on the first junction plate between two panels template in the first connecting hole, can exert a force to butt hook by rotating threaded rod, and adjacent two panels first junction plate is fixed by pressing plate, by the acting in conjunction of pressing plate and butt hook, pulling force is applied to Form board frame, make frame between plate and plate very smooth, and extruding force is applied to frame, make piece not spillage between plate, play the dual-use function reinforced and flatten.
As shown in Figure 5, described second junction plate 12 is provided with equally distributed second connecting hole 121, and described second connecting hole 121 is square opening; The square bolt adapted to it can be adopted to connect between adjacent two templates during concrete use, can effectively solve the problem such as faulting of slab ends, spillage.
In specific embodiment, as shown in Figure 6, described threaded rod 32 is provided with nut 321, and described nut 321 is fixedly installed on described level connection joint portion 313 medial surface; Certainly, this nut 321 can be set directly on level connection joint portion 313 lateral surface.
In specific embodiment, owing to arranging according to concreting body of wall when steel plate mould splices, sometimes steel plate mould can splice very high; Therefore in a lot of situation, corresponding climbing steel ladder will be set.In the utility model as shown in Figure 3, described steel ladder 2 side is provided with uniform support column 21, described support column 21 is provided with the junction plate 211 of band connecting hole, the connecting hoop 22 be set on described horizontal back cord 15 utilizes connecting bolt and described junction plate 211 to be connected and fixed, this kind of set-up mode can need the position of lateral adjustments steel ladder according to the operating mode of reality, meet the installation requirement of Various Complex operating mode.
And in specific embodiment, as shown in Figure 3, described horizontal back cord 15 is two channel-section steels be arranged in parallel, like this when steel ladder specifically links, channel-section steel biside plate can carry out certain elastic deformation under the extruding of junction plate, effectively can reduce the generation that connecting bolt loosens naturally.
In specific embodiment, as shown in Fig. 1 and soil, the second junction plate 12 on the upside of steel plate mould is provided with suspension ring 16, described suspension ring 16 are outward-dipping, in actual fabrication process, the outward-dipping angle of these suspension ring is between 30 °-45 °, and template can be carried out assembled rear integral lifting by it in practice of construction process in bottom surface, reduce lifting times further.
Except the technical characteristic described in manual, be the known technology of those skilled in the art.
The above has made detailed description to preferred embodiment of the present utility model and embodiment by reference to the accompanying drawings; but the utility model is not limited to the above-described embodiment and examples; for those skilled in the art; without departing from the concept of the premise utility; can also make some improvement and modification, these improve and modification also should be considered as protection domain of the present utility model.

Claims (5)

1. a construction formwork, comprise panel (13), be located at vertical back cord (14) and the horizontal back cord (15) of panel (13) rear side, and be located at first junction plate (11) of panel (13) left and right sides and second junction plate (12) of the upper and lower both sides of panel (13);
It is characterized in that, also comprise double hook connector (3), described double hook connector (3) comprises gripper shoe (31), threaded rod (32) and pressing plate (33), and described gripper shoe (31) is shape structure, and gripper shoe described in this (31) is provided with the first breach (311) run through in side in the middle, described first breach (311) is cutting out butt hook (312) near described gripper shoe (31) two supporting leg bottom position;
Described threaded rod (32) runs through with thread connecting mode and is arranged in the level connection joint portion (313) of described gripper shoe (31), described threaded rod (32) outer end is the slab structure of band through hole, described pressing plate (33) is U-shaped structure, it is arranged on described threaded rod (32) inner opposite end in the mode of outward opening, and described threaded rod (32) can rotate relative to described pressing plate (33);
Described first junction plate (11) is provided with many groups and is uniformly distributed the first connecting hole (111), often organize the first connecting hole (111) and have two, centered by described first connecting hole (111), place is with the rectangular through-hole of symmetrical arc v notch v; Described second junction plate (12) is provided with equally distributed second connecting hole (121), and described second connecting hole (121) is square opening.
2. a kind of construction formwork according to claim 1, it is characterized in that, described threaded rod (32) is provided with nut (321), and described nut (321) is fixedly installed on described level connection joint portion (313) medial surface.
3. a kind of construction formwork according to claim 1 and 2, it is characterized in that, it also comprises steel ladder (2), described steel ladder (2) side is provided with uniform support column (21), described support column (21) is provided with the junction plate (211) of band connecting hole, and the connecting hoop (22) be set on described horizontal back cord (15) utilizes connecting bolt and described junction plate (211) to be connected and fixed.
4. a kind of construction formwork according to claim 1, is characterized in that, second junction plate (12) of upside is provided with suspension ring (16), and described suspension ring (16) are outward-dipping.
5. a kind of construction formwork according to claim 1, is characterized in that, described horizontal back cord (15) is two channel-section steels be arranged in parallel.
CN201520703967.6U 2015-09-11 2015-09-11 Building template Active CN205046851U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520703967.6U CN205046851U (en) 2015-09-11 2015-09-11 Building template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520703967.6U CN205046851U (en) 2015-09-11 2015-09-11 Building template

Publications (1)

Publication Number Publication Date
CN205046851U true CN205046851U (en) 2016-02-24

Family

ID=55340445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520703967.6U Active CN205046851U (en) 2015-09-11 2015-09-11 Building template

Country Status (1)

Country Link
CN (1) CN205046851U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107059627A (en) * 2017-01-25 2017-08-18 中铁大桥局集团有限公司 A kind of bridge coxopodite pier shaft pours leakproof sizing device and bridge pier shaft casting method
CN107558312A (en) * 2017-09-07 2018-01-09 中铁五局集团第二工程有限责任公司 The plate-type non-fragment orbit self-compaction edge sealing template mistake proofing table apparatus of CRTS III
CN112324136A (en) * 2020-10-15 2021-02-05 中铁八局集团第三工程有限公司 Sealing strip for building secondary structure template caulking and sealing construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107059627A (en) * 2017-01-25 2017-08-18 中铁大桥局集团有限公司 A kind of bridge coxopodite pier shaft pours leakproof sizing device and bridge pier shaft casting method
CN107558312A (en) * 2017-09-07 2018-01-09 中铁五局集团第二工程有限责任公司 The plate-type non-fragment orbit self-compaction edge sealing template mistake proofing table apparatus of CRTS III
CN112324136A (en) * 2020-10-15 2021-02-05 中铁八局集团第三工程有限公司 Sealing strip for building secondary structure template caulking and sealing construction method
CN112324136B (en) * 2020-10-15 2022-05-17 中铁八局集团第三工程有限公司 Sealing strip for building secondary structure template caulking and sealing construction method

Similar Documents

Publication Publication Date Title
CN205046851U (en) Building template
CN205314542U (en) Construction liquid die plate device that climbs
CN204298742U (en) For the supporting and protection structure of Bridge High-pier construction
CN204040450U (en) A kind of for angle connector in tools type section steel builder's jack
CN207218161U (en) A kind of cable bridge
CN202416881U (en) Steel girder mounting auxiliary appliance
CN206458091U (en) A kind of constructional form fixing apparatus
CN205778885U (en) A kind of shield machine reaction frame
CN204282391U (en) A kind of heel foundation formwork erecting structure
CN202031309U (en) Suspending operation platform for structural concrete constructions
CN203654739U (en) Built-up plate
CN103195079B (en) Installing type template, installing type template group and complete installing type plate device
CN206360358U (en) A kind of external corner connecting elements
CN205132926U (en) Special well word hoist of hydroelectric set tail water ell
CN105113776B (en) The support meanss and building method of pole inner top platform on a kind of spherical tank
CN204960324U (en) Suspension type floor formwork support device
CN209959259U (en) Water stop belt positioning and fastening plug board device for tunnel trolley lining construction
CN203878779U (en) Rectangular concrete-filled steel tube column and I-steel beam rebar penetrating type joint
CN208539499U (en) Portable pre-buried electronic box support frame
CN203361165U (en) Supporting beam connection structure for building foundation pit support
CN204040452U (en) A kind of Corner Link for tools type section steel builder's jack
CN203769327U (en) Tower concrete pump pipe fixing device
CN203160251U (en) Connecting device for joints of steel and wood templates
CN209244372U (en) A kind of high intensity wind resistance electric power tower
CN202689560U (en) Fixing device and vertical template system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant