CN205036070U - Device is set up in complete pre -buried installation of cantilever frame roof beam side - Google Patents

Device is set up in complete pre -buried installation of cantilever frame roof beam side Download PDF

Info

Publication number
CN205036070U
CN205036070U CN201520626652.6U CN201520626652U CN205036070U CN 205036070 U CN205036070 U CN 205036070U CN 201520626652 U CN201520626652 U CN 201520626652U CN 205036070 U CN205036070 U CN 205036070U
Authority
CN
China
Prior art keywords
strong point
iron
steel pipe
concrete wall
fastening devices
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201520626652.6U
Other languages
Chinese (zh)
Inventor
赵拯卫
叶柏龙
苏灿
赵梓元
蒋青青
蒋竞舶
蒋金津
童玲玲
刘应松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUNAN ZHENG WEI CONSTRUCTION SCIENCE AND TECHNOLOGY Co Ltd
Original Assignee
HUNAN ZHENG WEI CONSTRUCTION SCIENCE AND TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN ZHENG WEI CONSTRUCTION SCIENCE AND TECHNOLOGY Co Ltd filed Critical HUNAN ZHENG WEI CONSTRUCTION SCIENCE AND TECHNOLOGY Co Ltd
Priority to CN201520626652.6U priority Critical patent/CN205036070U/en
Application granted granted Critical
Publication of CN205036070U publication Critical patent/CN205036070U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a device is set up in complete pre -buried installation of cantilever frame roof beam side, including I -steel and pre -buried device, the I -steel is provided with the steel sheet base, the I -steel pass through the bolt with the pre -buried device I fixed connection who sets up in the concrete wall, concrete wall was kept away from to the I -steel one end lower part be provided with one can free angle regulation strong point fixing device I, strong point fixing device I is connected with the strong point fixing device II that concrete wall went up the setting through supporting the steel pipe, strong point fixing device II passes through the bolt and is connected with the interior pre -buried device II who sets up of concrete wall, it is equipped with trapezoidal thread to support steel pipe two inside, well upper portion is equipped with positive inverse taper tooth adjusting screw, strong point fixing device I, strong point fixing device II respectively is equipped with the trapezoidal screw rod of can be adjusted freely angle, trapezoidal screw rod is connected with the inside thread that supports the steel pipe both ends respectively. The utility model discloses the convenience is demolishd in simple structure, installation, and material saving has improved the progress greatly.

Description

Device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one
Technical field
The utility model relates generally to building operations auxiliary equipment field, specifically discloses the encorbelment complete pre-buried installation in side of setting a roof beam in place of one and sets up device.
Background technology
When tradition suspension scaffold i iron is installed, as shown in Figure 1, i iron b passes through shear wall, be laid on flooring a, flooring is fixed on again, because too heaviness causes installation very tired and trouble, consuming time, when by shear wall with reinforcing bar c, can destroy wall section causes design strength to give a discount, and causes carpenter's formwork erection difficulty to increase.Difficult especially during dismounting, the I-shaped outrigger running through shear wall sometimes two people is taken half talent and is got out, if take hang less than position, safety is a very large hidden danger especially.Body of wall more can be caused after dismounting everywhere riddled with gaping wounds, make people startling, having a greatly reduced quality to construction quality, (rear hole intensity of mending can give a discount and not say, not accommodating doubting also is cause seepage maximum root, i beam also can cause the seepage in later stage after the permanent position of indoor is removed), also delayed construction speed greatly simultaneously.
The patent No. is ZL201420608654.8, name is called a kind of multipurpose wall-connecting piece, by installing built-in fitting in advance in concrete wall, be provided with flat thread in built-in fitting, wall-connecting piece is a steel pipe, is provided with round nut in steel pipe, built-in fitting and steel pipe are bolted fixing, the nut be fixed in built-in fitting is square nut, ensures to rotate along with the rotation of bolt, and when ensure that bolt screws in or screws out, one end is definitely firm; The caliber of the main pipe fittings part of built-in fitting is consistent with the diameter of bolt close simultaneously, ensure that bolt be selected into fixing after there will not be off normal situation, great minimizing off normal even loosens the generation of situation, secure and reliable connection, and installation and removal are all easy to, versatility is good, the length of steel pipe does not limit, and can be directly used in lifting weight, or for connecting pin hand cradle, also may be used for protection, for multiple occasions such as supports.
The utility model utilizes this wall-connecting piece to improve traditional suspension scaffold i iron mounting structure.
Utility model content
The purpose of this utility model is the weak point overcome in prior art, provides the complete pre-buried installation in side of setting a roof beam in place of encorbelmenting that is few, that greatly improve construction speed of a kind of easy accessibility, consumptive material to set up device.
For achieving the above object, the technical scheme that the utility model provides is: device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one, comprise the i iron and pre-embedded device that are connected with concrete wall, described pre-embedded device comprises the main pipe fittings be embedded in concrete wall, be fixed on the non-rotatable square nut in bottom main pipe fittings, by the plastic protection lid of square nut buckle closure in main pipe fittings, described i iron is provided with steel plate base, i iron is fixedly connected with the pre-embedded device I arranged in described concrete wall by bolt, described i iron is provided with one away from the bottom, one end of concrete wall can the strong point fastening devices I of free adjustment angle, strong point fastening devices I is connected with the strong point fastening devices II that concrete wall is arranged by supporting steel pipe, described strong point fastening devices II is connected with the pre-embedded device II arranged in concrete wall by bolt, inside, described supporting steel pipe two is provided with trapezoidal thread, middle and upper part is provided with positive inverse taper tooth adjusting screw(rod), described strong point fastening devices I, strong point fastening devices II is respectively provided with can the trapezoidal screw of free adjustment angle, described trapezoidal screw is connected with the inside thread at supporting steel pipe two ends respectively.
Preferably, described steel plate base is provided with two symmetrical bolts hole, bolt is arranged in described bolt hole and connects pre-embedded device I, the diameter of bolt is consistent with the caliber of pre-embedded device I main pipe fittings, bolt one end is connected with steel plate base, the other end inserts in pre-embedded device I main pipe fittings and is connected with square nut, and described steel plate base plane is fixedly connected with the two-sided full weld of i iron cross section electric welding.
Preferably, described i iron, away from the top of the side of concrete wall, also can arrange fastening devices, forms draw high device with supporting steel pipe together with the pre-embedded device of concrete wall beam upper lateral part.
Preferably, described supporting steel pipe can also be connected in hinged way with strong point fastening devices I.
Preferably, described supporting steel pipe is provided with elastomeric element, when the stressed generation vertical displacement of i iron, arranges the effect that elastomeric element can play force balance.
Preferably, described i iron outermost end points up can exceed 10mm-20mm and install, slightly install toward upwarping 10mm-20mm when i iron is installed, considering that i iron and concrete anchor are solidly connected this characteristic of curve shift that stressed rear outer end has normal 10mm-20mm, therefore allowing when designing and producing or install the outer end of i iron have the level of 10mm-20mm to upwarp more reasonable.
Preferably, described adjusting screw(rod) No. 45 steel are made.
Preferably, the longitudinal axis of the vertical axis of symmetry of described i iron and supporting steel pipe in same vertical plane, to ensure that suspension scaffold is applied to the vertical force on i iron.
Preferably, described pre-embedded device I and pre-embedded device II center, on same vertical line, produce unstable failure to prevent setting up device.
A technical scheme tool in technique scheme has the following advantages or beneficial effect: device is set up in the complete pre-buried installation in employing beam side of the present utility model, not only greatly can save material, during installation, i beam is by short and become light and handy, greatly provide programming, farthest decrease delaying work the time of fraternal teams and groups, and become more simple during i beam dismounting, just can remove as long as the screw rod of each tie point is twisted off.Whole assembling and disassembling process, can accomplish neither to destroy Building Design structure, can give simultaneously follow-uply to build a wall, in the teams and groups that construct such as to whitewash a complete interference-free operating area be provided, whole subsequent construction is made to become very smooth and easy, improve construction safety, also ensure that construction quality greatly.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, simple introduction is done below by the accompanying drawing used required in embodiment or description of the prior art, apparently, accompanying drawing in the following describes is embodiments more of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the utility model prior art structural representation;
Fig. 2 is the utility model structural representation;
Fig. 3 is that i iron is connected partial schematic diagram with concrete wall;
Fig. 4 is strong point fastening devices II structural representation;
Fig. 5 is pre-embedded device structural representation;
Fig. 6 is supporting steel pipe partial structurtes schematic diagrames;
Fig. 7 draws high device schematic diagram;
Fig. 8 is supporting steel pipe structural representation;
Fig. 9 is supporting steel pipe elastomeric element structural representation;
Figure 10 is fastener-style steel pipe scaffolding elevational schematic view;
Figure 11 is fastener-style steel pipe scaffolding A-A sectional drawing;
In figure: 1, i iron; 2, steel plate base; 3, bolt hole; 4, strong point fastening devices I; 5, supporting steel pipe; 6, strong point fastening devices II; 7, trapezoidal tooth adjusting screw(rod); 8, pre-embedded device I; 9, pre-embedded device II; 10, bolt; 11, main pipe fittings; 12, square nut; 13, plastic protection lid; 14, device is drawn high; 15, building structure; 16, outer vertical rod; 17, interior vertical rod; 18, vertical equity bar; 19, transverse horizontal bar; 20, scaffold floor; 21, removable wall-connecting piece bolt; 22, laterally outer support; 23, bridging; 24, laterally foot lever is swept; 25, longitudinally foot lever is swept; 26, elastomeric element.
Detailed description of the invention
In prior art, as shown in Figure 10,11, according to " steel pipe scaffold specification ", the maximum scaffolding height of scaffold is that 18m adds 1.5m railing 19.5m altogether; Interior vertical rod 17 is apart from building structure 15 wall face 0.3m, and interior vertical rod 17, outer vertical rod 16 transfer are 0.9m, and advance is 1.5m, and step pitch is 1.8m.At i iron 1 end face 200mm At The Height, laterally sweep the floor bar 24 and bar 25 of longitudinally sweeping the floor are set.Bar 24 of laterally sweeping the floor is fixed on bottom of upright rod with fastener, then on bar 24 of laterally sweeping the floor, bar 25 of longitudinally sweeping the floor is fixed on bottom of upright rod with fastener, to guarantee the resistance to overturning of fastener-style steel pipe scaffolding.The outer side elevation of fastener-style steel pipe scaffolding is abound with 4 across the bridging 23 of 6m, and between the outer vertical rod 16 and interior vertical rod 17 of per pass bridging 23 side, arrange the laterally outer support 22 that a track pitch is 6m, horizontal outer support 22 is arranged in continuous in a zigzag from bottom to the top at same internode.Wall-connecting piece adopt 2 steps 3 across, vertical spacing 3.6m, level interval 4.5m.Removable wall-connecting piece bolt 21 is adopted to be connected between wall-connecting piece with building structure 15 body of wall.The outer vertical rod 16 of the scaffold of operation layer arranges 1.2m height guard rail and the high foot guard plate of 300mm.Operation layer must be paved with scaffold floor 20, and establishes Horizontal load-bearing safety net at its lower pocket.Choose within the scope of outstanding height 19.5m at each, scaffold floor 20 lays 4 layers altogether.When to operate the number of plies in work progress be one deck, working face characteristic value of load must not be greater than 3KN/mm 2.Operating the number of plies in work progress must not exceed two-layer simultaneously, and when there being 2 operation layer operations in same span simultaneously, its working face characteristic value of load summation must not be greater than 5KN/mm 2.
Scaffolding steel pipe all adopts the Q235 type 48.3*3.6 steel pipe and supporting fastener that meet GB, and vertical rod and vertical equity bar 18 steel pipe length 4-6m, transverse horizontal bar 19 steel pipe length is 1.2m.Scaffold floor adopts the related request meeting existing industry standard " building operations scaffold technical specification of security ", Q235 steel tension, resistance to compression and flexural strength design load f=205N/mm 2, section steel beam flexural strength design load, looks into existing national standards " Code for design of steel structures " (GB50017-2003) and shows 3.4.1-1, get f=215N/mm 2, national elastic modulus E=2.06*10 5n/mm 2.Steel shear strength design load, f=125N/mm 2.By " steel pipe scaffold specification ", when not combining wind load, calculate the axial force design load N=12.81KN of bottom vertical rod section, be provided with interior vertical rod and outer vertical rod two vertical rods, namely the power be applied in theory on i iron is about 2.6 tons.Calculating 14mm bolt tensile capacity is 19.22KN.
Below in conjunction with accompanying drawing, the utility model is described:
The utility model is that device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one, as shown in Figure 2, comprise the i iron 1 and pre-embedded device that are connected with concrete wall, as shown in Figure 5, pre-embedded device comprises the main pipe fittings 11 be embedded in concrete wall, be fixed on the non-rotatable square nut 12 in bottom main pipe fittings 11, by the plastic protection lid 13 of square nut 12 buckle closure in main pipe fittings 11, screw thread is provided with in main pipe fittings 11, as Fig. 2, shown in Fig. 3, i iron is provided with steel plate base 2, i iron 1 is fixedly connected with the pre-embedded device I8 arranged in concrete wall by bolt 10, be specially in steel plate base 2 and be provided with two symmetrical bolts hole 3, bolt 10 is arranged in bolt hole 3 and connects pre-embedded device I8, the diameter of bolt 10 is consistent with the caliber of pre-embedded device I8 main pipe fittings 11, bolt 10 one end is connected with steel plate base 2, the other end inserts in pre-embedded device I8 main pipe fittings 11 and is connected with square nut 12, steel plate base 2 plane is fixedly connected with the two-sided full weld of i iron 1 cross section electric welding.
As shown in Figure 2, i iron 1 is provided with one away from the bottom, one end of concrete wall can the strong point fastening devices I4 of free adjustment angle, strong point fastening devices I4 is connected with the strong point fastening devices II6 that concrete wall is arranged by supporting steel pipe 5, and supporting steel pipe 5 is that 60mm*4mm seamless steel pipe is better.As shown in Figure 4, strong point fastening devices II6 is connected with the pre-embedded device II9 arranged in concrete wall by bolt, and pre-embedded device I8 and pre-embedded device II9 center, on same vertical line, produce unstable failure to prevent setting up device.Inside, supporting steel pipe 5 two is provided with the long trapezoidal thread of 40mm, as shown in Figure 6, middle and upper part is provided with positive inverse taper tooth adjusting screw(rod) 7, can free adjustment support bar length, strong point fastening devices I4, strong point fastening devices II6 are respectively provided with can the trapezoidal screw of free adjustment angle, and trapezoidal screw is connected with the inside thread at supporting steel pipe 5 two ends respectively.The longitudinal axis of the vertical axis of symmetry of i iron 1 and supporting steel pipe 5 in same vertical plane, to ensure that suspension scaffold is applied to the vertical force on i iron.Adjusting screw(rod) 7 No. 45 steel are made.
As shown in Figure 7, i iron 1, away from the top of the side of concrete wall, also can arrange fastening devices, forms draw high device 14 with supporting steel pipe together with the pre-embedded device of concrete wall beam upper lateral part.
As shown in Figure 8, supporting steel pipe can also be connected by articulated manner with strong point fastening devices I.
As shown in Figure 9, the utility model can also install elastomeric element 26 at supporting steel pipe, when the stressed generation vertical displacement of i iron 1, arranges the effect that elastomeric element 26 can play force balance.Consider that i iron and concrete anchor are solidly connected this characteristic of curve shift that stressed rear outer end has normal 10mm-20mm, therefore allow when designing and producing or install the outer end of i iron up exceed 10mm-20mm and install, more rationally.
The pre-embedded device II9(that must just start to arrange the pre-buried good i iron outrigger strong point during use in advance before builder's jack layer descends the concrete of one deck to water to smash again is in order to can be more efficient at builder's jack layer, complete the first step erection of suspension scaffold efficiently, other teams and groups' normal constructions can be supplied in advance, advise after beam side is removed, install all strong point fastening devices II6 when just can take out in advance and supporting steel pipe 5 bottom is all connected with strong point fastening devices II6), and then builder's jack layer concrete water smash before pre-set the pre-embedded device I8(of pre-buried good i beam base pre-buried time must as far as possible perpendicular to the strong point fastening devices II6 that bottom has set), then after waiting until that builder's jack layer beam side is removed, just i iron 1 can be directly installed.It is to be noted that to be connected to the pre-embedded device I8 in builder's jack layer beam side by screw rod 10 when every root i iron 1 steel plate base 2 after, i iron 1 must be connected on the i iron supporting steel pipe 5 of design cooperation away from the strong point fastening devices I4 of concrete wall one end simultaneously, and regulate the length of supporting steel pipe, make itself and pre-embedded device I8 producing balanced forces.As encountered because structure change i iron 1 needs to lengthen position, an interim gravity can be done again in i iron 1 outermost end and sharing the strong point, then upper strata concrete water smash before pre-set and pre-buriedly draw a little, then do one with wire rope and hang and draw reinforcing.
Below by being described the utility model in theory:
Set up 160mm*90mm*1300mm i iron 1, i iron 1 arranges the 160mm*180mm*12mm steel plate base 2 can reserving two 22mm bolts hole 3, is bolted on building structure side bar side with two 20mm; Bolt hole 3 is located at the long cross-point locations place of measuring 90mm to position along limit toward interior 35mm, short position from top to bottom of steel plate base 2, and steel plate base 2 plane and the two-sided full weld of i iron 1 cross section connecting portion electric welding are fixed; I iron 1 to arrange one away from bottom, concrete wall one end bead toward position centered by interior 300mm can the strong point fastening devices I4 of free adjustment angle, strong point fastening devices I4 comprises the thick steel plate of the 20mm of two 24mm bolts hole, get 45# steel excellent in diameter 60mm*4mm() supporting steel pipe 5 top 22mm bolt is connected; Supporting steel pipe 5 bottom is connected by 1 20mm bolt with substrustion structure side bar side.
I iron overall length is set to 1300mm, and i iron and strong point fastening devices II6 distance are 3600mm, and strong point fastening devices I4 is arranged on i iron 1000mm place.
For i iron, calculating the left cross section of i iron strong point fastening devices I, to bear axial tension be 5.34KN, and it is 12.81N that shearing is born in i iron cross section, and moment of flexure is 2.56KN.m, and shearing is-6.40KN; Right section moment of flexure is 2.56KN.m, shearing 12.81KN, and calculating the anti-stretch bending strength of i iron by " steel pipe scaffold technical specification of security " formula 5.6.3 is 21N/mm 2<f=205N/mm 2, the anti-stretch bending strength of i iron meets the demands.Calculate by " Code for design of steel structures " formula 4.1.2 by curved real its shear strength of abdomen component in principal plane, show that shear strength design load is 16N/mm 2<f=125N/mm 2, the curved intensity of shearing resistance of i iron meets the demands.Calculate by " steel pipe scaffold specification " formula 5.6.4, show that i iron flexural strength design load is 19.98N/mm 2<f=215N/mm 2, the resistance to overturning of i iron meets the demands.With the layer control displacement calculating of structural mechanics, the vertical displacement obtaining steel I-beam outer end is 0.76mm<L/250=1300/250=5.2mm, meets the demands.
Show that supporting steel pipe and bolt also meet each side requirement as calculated equally.
Below by test data, the utility model is described.
Design two groups of crossbeams, first group of top rail waters and smash the concrete time is two days, setting that lower transverse beam is liftoff; Second group of top rail waters and smash the concrete time is one week, setting that lower transverse beam is liftoff; Two groups of top rails be arranged in parallel, distance between lower and upper cross-member is 3.4 meters, i iron is installed in two groups of top rail beam sides, i iron overall length 1.6 meters, strong point fastening devices I is installed in bottom distance top rail 1.05 meters of i iron, connect supporting steel pipe, supporting steel pipe connects lower transverse beam beam side pre-embedded device by 1 bolt.
Experiment 1, removes supporting steel pipe, and test is watered and smash i iron stressing conditions on concrete first group of top rail of two days:
Experiment 2, removes supporting steel pipe, and test is watered and smash i iron stressing conditions on concrete second group of crossbeam of a week:
As can be seen from experiment 1 and experiment 2, under not having the prerequisite of supporting steel pipe, the holding capacity of i iron can meet the demand applying power about 2.6 tons in theory.
Experiment 3, installs the test after supporting steel pipe, as can be seen from test data.
Experiment draws, strong point fastening devices II fixes preferably by two bolts, to overcome the error because implementing in the middle of installation.
Apply specific embodiment herein to set forth principle of the present utility model and embodiment, the explanation of above embodiment just understands method of the present utility model and core concept thereof for helping.The above is only preferred embodiment of the present utility model, should be understood that, due to the finiteness of literal expression, and objectively there is unlimited concrete structure, for those skilled in the art, under the prerequisite not departing from the utility model principle, some improvement, retouching or change can also be made, also above-mentioned technical characteristic can be combined by rights; These improve retouching, change or combination, or the design of utility model and technical scheme are directly applied to other occasion without improving, and all should be considered as protection domain of the present utility model.

Claims (9)

1. device is set up in the complete pre-buried installation in side of setting a roof beam in place of encorbelmenting, comprise the i iron and pre-embedded device that are connected with concrete wall, described pre-embedded device comprises the main pipe fittings be embedded in concrete wall, be fixed on the non-rotatable square nut in bottom main pipe fittings, by the plastic protection lid of square nut buckle closure in main pipe fittings, it is characterized in that: described i iron is provided with steel plate base, i iron is fixedly connected with the pre-embedded device I arranged in described concrete wall by bolt, described i iron is provided with one away from the bottom, one end of concrete wall can the strong point fastening devices I of free adjustment angle, strong point fastening devices I is connected with the strong point fastening devices II that concrete wall is arranged by supporting steel pipe, described strong point fastening devices II is connected with the pre-embedded device II arranged in concrete wall by bolt, inside, described supporting steel pipe two is provided with trapezoidal thread, supporting steel pipe is provided with positive inverse taper tooth adjusting screw(rod), described strong point fastening devices I, strong point fastening devices II is respectively provided with can the trapezoidal screw of free adjustment angle, described trapezoidal screw is connected with the inside thread at supporting steel pipe two ends respectively.
2. device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one according to claim 1, it is characterized in that: described steel plate base is provided with two bolts hole, bolt is arranged in described bolt hole and connects pre-embedded device I, the diameter of bolt is consistent with the caliber of pre-embedded device I main pipe fittings, bolt one end is connected with steel plate base, the other end inserts in pre-embedded device I main pipe fittings and is connected with square nut, and described steel plate base plane is fixedly connected with the two-sided full weld of i iron cross section electric welding.
3. device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one according to claim 1, it is characterized in that: described i iron is away from the top of the side of concrete wall, fastening devices is set, forms together with the pre-embedded device of concrete wall beam upper lateral part with supporting steel pipe and draw high device.
4. device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one according to claim 1, it is characterized in that: described supporting steel pipe is connected in hinged way with strong point fastening devices I.
5. device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one according to claim 4, it is characterized in that: described supporting steel pipe is provided with elastomeric element.
6. device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one according to claim 4, it is characterized in that: described i iron outermost end points up exceeds 10mm-20mm and installs.
7. device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one according to claim 1, it is characterized in that: described adjusting screw(rod) No. 45 steel are made.
8. device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one according to claim 1, it is characterized in that: the longitudinal axis of the vertical axis of symmetry of described i iron and supporting steel pipe is in same vertical plane.
9. device is set up in the encorbelment complete pre-buried installation in side of setting a roof beam in place of one according to claim 1, it is characterized in that: described pre-embedded device I and pre-embedded device II center are on same vertical line.
CN201520626652.6U 2015-03-25 2015-08-19 Device is set up in complete pre -buried installation of cantilever frame roof beam side Withdrawn - After Issue CN205036070U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520626652.6U CN205036070U (en) 2015-03-25 2015-08-19 Device is set up in complete pre -buried installation of cantilever frame roof beam side

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201510132589 2015-03-25
CN2015101325895 2015-03-25
CN201520626652.6U CN205036070U (en) 2015-03-25 2015-08-19 Device is set up in complete pre -buried installation of cantilever frame roof beam side

Publications (1)

Publication Number Publication Date
CN205036070U true CN205036070U (en) 2016-02-17

Family

ID=54661872

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201510510391.6A Active CN105113781B (en) 2015-03-25 2015-08-19 Device is set up in a kind of overhanging complete pre-buried installation in side of setting a roof beam in place
CN201520626652.6U Withdrawn - After Issue CN205036070U (en) 2015-03-25 2015-08-19 Device is set up in complete pre -buried installation of cantilever frame roof beam side

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201510510391.6A Active CN105113781B (en) 2015-03-25 2015-08-19 Device is set up in a kind of overhanging complete pre-buried installation in side of setting a roof beam in place

Country Status (1)

Country Link
CN (2) CN105113781B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105113781A (en) * 2015-03-25 2015-12-02 湖南拯卫建设科技有限公司 Cantilever frame beam side all-embedded mounting and erecting device
CN109853752A (en) * 2019-02-22 2019-06-07 上海智平基础工程有限公司 Steel construction and concrete embedded connection structure

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110029808A (en) * 2019-04-11 2019-07-19 中建四局第六建筑工程有限公司 A kind of gondola-hanging mechanism and its construction method on steel construction cant beam
CN113605677A (en) * 2021-09-02 2021-11-05 重庆万力新材料有限公司 Wall connecting piece for building construction and use method thereof

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201169907Y (en) * 2008-03-18 2008-12-24 启东建筑集团有限公司 Inclined strut type suspension supporting rack
WO2010060137A1 (en) * 2008-11-27 2010-06-03 Grocon Pty Limited Guardrail post support
CN102704663A (en) * 2012-06-27 2012-10-03 江苏正威建设有限公司 Down-stayed type suspension style scaffold
CN103306477A (en) * 2013-06-29 2013-09-18 梁苏珊 Inclined strut device for supporting side plate of building beam
CN103485524B (en) * 2013-10-11 2016-03-23 四川省第四建筑工程公司 Corbel type builder's jack and construction when setting up thereof
CN203660974U (en) * 2013-12-11 2014-06-18 神华集团有限责任公司 Adjustable fixed bracket for photovoltaic modules
CN204186058U (en) * 2014-10-21 2015-03-04 湖南拯卫建设科技有限公司 A kind of multipurpose wall-connecting piece
CN105113781B (en) * 2015-03-25 2018-08-03 湖南拯卫建设科技有限公司 Device is set up in a kind of overhanging complete pre-buried installation in side of setting a roof beam in place

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105113781A (en) * 2015-03-25 2015-12-02 湖南拯卫建设科技有限公司 Cantilever frame beam side all-embedded mounting and erecting device
CN105113781B (en) * 2015-03-25 2018-08-03 湖南拯卫建设科技有限公司 Device is set up in a kind of overhanging complete pre-buried installation in side of setting a roof beam in place
CN109853752A (en) * 2019-02-22 2019-06-07 上海智平基础工程有限公司 Steel construction and concrete embedded connection structure
CN109853752B (en) * 2019-02-22 2024-02-13 上海智平基础工程有限公司 Steel construction and pre-buried connection structure of concrete

Also Published As

Publication number Publication date
CN105113781B (en) 2018-08-03
CN105113781A (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN106702910B (en) A kind of main girder construction technique of the double rope face low-pylon cable-stayed bridges of double tower
CN101570961B (en) Fastening method for fractured girder of bridge
CN205036070U (en) Device is set up in complete pre -buried installation of cantilever frame roof beam side
CN104988844B (en) Two times tensioning prestressing force assembled Wavelike steel webplate combination beam
CN105839510A (en) Steel-ultra-high-performance concrete combined continuous beam bridge structure and construction method thereof
CN104018581A (en) Prestress concrete F slab and framework structure system
CN111677327A (en) Prestressed brace reinforced concrete beam structure
CN104060542B (en) Compound beam cable stayed bridge direction across bridge prestress application device and applying method thereof
CN107905114A (en) A kind of construction method of large span Successive interference cancellation
CN102619331B (en) Once molding construction method of beam-type conversion layer of high-rise building by steel pipe supporting and laminated pouring
CN101781878A (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN100460613C (en) Suspension holder construction method
CN107237437A (en) Combined type reinforced truss floor support plate and its construction method
CN103321155A (en) Viaduct pier construction platform system and method for building system and pouring piers
CN202914107U (en) Roadway support truss
CN207092331U (en) Combined type reinforced truss floor support plate
CN202000265U (en) Concrete construction formwork for high pier of bridge
CN109235280A (en) The operation platform and construction method of bridge coping
CN206448549U (en) The beam slab double deck type bracing members frame of encorbelmenting of steadiness can be improved
CN104018427A (en) All-welded box girder combination section constructing method
CN103835238B (en) A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing
CN101793012A (en) Novel non-bracket bridge constructing method
CN205474785U (en) Steel - ultra high performance concrete combination continuous bridge structure
CN109024685A (en) A kind of mass concrete invert reinforcing steel support system and its construction method
CN210369983U (en) High-rise building segmentation construction protection canopy

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20160217

Effective date of abandoning: 20180803