CN205012952U - Synchronous drawbench of multi -cylinder - Google Patents

Synchronous drawbench of multi -cylinder Download PDF

Info

Publication number
CN205012952U
CN205012952U CN201520757392.6U CN201520757392U CN205012952U CN 205012952 U CN205012952 U CN 205012952U CN 201520757392 U CN201520757392 U CN 201520757392U CN 205012952 U CN205012952 U CN 205012952U
Authority
CN
China
Prior art keywords
drawbench
hydraulic jack
cylinder
top board
hydraulic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520757392.6U
Other languages
Chinese (zh)
Inventor
张光西
徐键
张道云
甘雨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Water Conservancy And Hydropower Construction Co Ltd
Sichuan Western Exploration And Geotechnical Engineering Co Ltd
PowerChina Chengdu Engineering Co Ltd
Original Assignee
Chengdu Water Conservancy And Hydropower Construction Co Ltd
Sichuan Western Exploration And Geotechnical Engineering Co Ltd
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Water Conservancy And Hydropower Construction Co Ltd, Sichuan Western Exploration And Geotechnical Engineering Co Ltd, PowerChina Chengdu Engineering Co Ltd filed Critical Chengdu Water Conservancy And Hydropower Construction Co Ltd
Priority to CN201520757392.6U priority Critical patent/CN205012952U/en
Application granted granted Critical
Publication of CN205012952U publication Critical patent/CN205012952U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a synchronous drawbench of multi -cylinder belongs to water and electricity hydraulic engineering drilling equipment field. Synchronous drawbench of multi -cylinder including roof, bottom plate and hydraulic cylinder, is provided with the sleeve pipe that supplies the sleeve pipe to pass respectively and perforates on roof and bottom plate, hydraulic cylinder be provided with be no less than three, the even distribution in a plurality of hydraulic cylinder intervals made progress in fenestrate week of sleeve pipe to every hydraulic cylinder's base end is articulated with the bottom plate, and hydraulic cylinder's ejector pin end is articulated with the roof. The utility model discloses an adopt many hydro -cylinders structure, on the one hand can improve the sleeve pipe pull -out degree of depth, stability when on the other hand can improve drawbench pull -out, simultaneously, under the circumstances of guaranteeing the same pull -out power, for the pull -out machine of double -cylinder structure can the significantly reduce overall dimension and the weight of every hydro -cylinder, the pull -out sheathed tube operation and operating the relocation of equipment be convenient for more.

Description

Multi-cylinder synchronous drawbench
Technical field
The utility model relates to water power hydraulic engineering drilling equipment field, particularly relates to a kind of drawbench of multi-cylinder work compound.
Background technology
In recent years, along with the fast development of water power hydraulic engineering construction cause, overburden cover is increasing, from about 40m to about 100m, about 200m, about 300m, about 400m, even more than 500m, this is challenge again and again to water power hydraulic engineering drilling technique, it requires that water power water conservancy driller author constantly pushes away to deposit and makes new advances, and being ready for the challenge again and again, reaches probing object.Along with the development of explosion pipe-following drilling technology, the sleeve pipe follow-up degree of depth is increasing, and the difficulty of case pulling and recycling is also more and more higher.And the case pulling method generally adopted at present be adopt top on rig to coordinate sash weight is counter to be beaten, it is limited that this method works the degree of depth of pulling out sleeve pipe, is usually no more than 200m, and usually can not rise completely and pull out; The drawbench adopted in prior art, is mainly two cylinder structure, and its pulling force, generally at 60t ~ 80t, rises and pulls out the needs that tubing depth can not meet the complicated covering layer probing of water power hydraulic engineering ultra-deep.In addition, adopt two cylinder structure, rise pull out sleeve pipe time usually because its unbalance stress run-off the straight causes sleeve pipe to pull off, sleeve pipe such as can not to extract completely at the situation; Meanwhile, adopt two oil cylinder will meet enough pulling forces, often need to increase single oil cylinder appearance and size and weight, make troubles to tube drawing operation and relocation equipment.
Utility model content
The technical problem that the utility model solves is to provide one and can improves the case pulling degree of depth, has improved the multi-cylinder synchronous drawbench pulling out stability simultaneously.
The utility model solves the technical scheme that its technical problem adopts: multi-cylinder synchronous drawbench, comprise top board, base plate and hydraulic jack, top board and base plate are respectively arranged with the cased perforated of passing for sleeve pipe, described hydraulic jack is no less than three, described multiple hydraulic jack interval is evenly distributed in the circumference of cased perforated, and the base end of each hydraulic jack and base plate hinged, the push rod end of hydraulic jack and top board hinged.
Further: also comprise Hydraulic Station, the input hydraulic pressure oil circuit of described multiple hydraulic jack and output hydraulic pressure oil circuit in parallel respectively after be communicated with Hydraulic Station.
Further: the base end of each hydraulic jack is connected by hinge with base plate, the push rod end of hydraulic jack and top board pass through hinge.
Further: each hydraulic jack and the connection between base plate and top board are for removably connecting.
Further: the axis of each bearing pin and the axes intersect of sleeve pipe.
Further: above top board, be also provided with slips and slip spider.
Further: described top board and base plate are all in square, and described cased perforated is arranged on above-mentioned foursquare center, and described hydraulic jack has four, four hydraulic jacks respectively with foursquare four right angle one_to_one corresponding.
Further: on top board and base plate, be provided with handle.
The beneficial effects of the utility model are: by adopting Multi-cylinder structure, can improve the case pulling degree of depth on the one hand, can improve drawbench on the other hand and work stability when pulling out; Simultaneously, when ensureing identical pulling force, work appearance and size and the weight of pulling out and can greatly reduce every oil cylinder for machine relative to double-cylinder structure, time like this by each oil cylinder being adopted removably installation, being more convenient to pull out the operation of sleeve pipe and the resettlement of equipment is operated.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the schematic diagram of hydraulic circuit of the present utility model;
Be labeled as in figure: top board 1, base plate 2, hydraulic jack 3, sleeve pipe 4, base end 31, push rod end 32, Hydraulic Station 5, input hydraulic pressure oil circuit 51, output hydraulic pressure oil circuit 52, bearing pin 6, slips 7, slip spider 8, handle 9.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is further illustrated.
As shown in fig. 1, multi-cylinder synchronous drawbench described in the utility model, comprise top board 1, base plate 2 and hydraulic jack 3, top board 1 and base plate 2 are respectively arranged with the cased perforated of passing for sleeve pipe 4, described hydraulic jack 3 is provided with and is no less than three, described multiple hydraulic jack 3 interval is evenly distributed in the circumference of cased perforated, and the base end 31 of each hydraulic jack 3 is hinged with base plate 2, and the push rod end 32 of hydraulic jack 3 is hinged with top board 1.
Wherein, arrange and be no less than three hydraulic jacks 3, the circumference of hydraulic jack 3 along cased perforated is distributed simultaneously, its objective is in order to ensure the stability of drawbench when tube drawing operation.As shown in fig. 1, can preferably by top board 1 and base plate 2 all in square, described cased perforated is arranged on above-mentioned foursquare center, and described hydraulic jack 3 has four, four hydraulic jacks 3 respectively with foursquare four right angle one_to_one corresponding.
In addition, can synchronization job in order to ensure multiple hydraulic jack 3, when arranging Hydraulic Station 5, be communicated with Hydraulic Station 5 after further the input hydraulic pressure oil circuit 51 of multiple hydraulic jack 3 and output hydraulic pressure oil circuit 52 is in parallel respectively; Concrete hydraulic circuit can refer to annexation shown in Fig. 2.
In addition, the base end 31 of each hydraulic jack 3 can be articulated and connected by bearing pin 6 with base plate 2, the push rod end 32 of hydraulic jack 3 is hinged by bearing pin 6 with top board 1.So more be convenient to the dismounting to hydraulic jack 3; Under normal circumstances, now each hydraulic jack 3 and the connection between base plate 2 and top board 1 can be set to removably connect, namely conveniently can carry out disassembling operations to hydraulic jack 3 by the dismounting of bearing pin 6, be convenient to carry out resettlement operation to equipment; In this case, in order to improve stability, the axis of each bearing pin 6 and the axes intersect of sleeve pipe 4 can be preferably set further; Specifically can refer to structure shown in Fig. 1.
In addition, under normal circumstances, be also provided with the structure such as slips 7 and slip spider 8, and be arranged on above top board 1, by slips 7, sleeve pipe 4 is surrounded, then by slip spider 8, slips 7 and sleeve pipe 4 are adjacent to fixing; By the force of top board 1 pair of slip spider 8, realize pulling out operation to rising of sleeve pipe 4.
In addition, for the ease of operation of carrying top board 1 and base plate 2 or sling, handle 9 structure can be provided with on top board 1 and base plate 2.
To sum up, multi-cylinder synchronous drawbench described in the utility model, can meet the requirement that the case pulling degree of depth is darker, can guarantee the stability of drawbench during tube drawing operation simultaneously.As during actual job by arranging four oil cylinder structure of hydraulic, improve tube drawing operation time drawbench self stability; And pulling force is large, and reality can reach 120t, and the tube drawing degree of depth can reach 320m, has met and has pulled out the darker requirement of the degree of depth; And single cylinder weight only 60kg, for tube drawing operation and relocation equipment convenient.

Claims (8)

1. multi-cylinder synchronous drawbench, comprise top board (1), base plate (2) and hydraulic jack (3), top board (1) and base plate (2) are respectively arranged with the cased perforated of passing for sleeve pipe (4), it is characterized in that: described hydraulic jack (3) is no less than three, described multiple hydraulic jack (3) interval is evenly distributed in the circumference of cased perforated, and the base end (31) of each hydraulic jack (3) is hinged with base plate (2), the push rod end (32) of hydraulic jack (3) is hinged with top board (1).
2. multi-cylinder synchronous drawbench as claimed in claim 1, it is characterized in that: also comprise Hydraulic Station (5), be communicated with Hydraulic Station (5) after the input hydraulic pressure oil circuit (51) of described multiple hydraulic jack (3) and the parallel connection of output hydraulic pressure oil circuit (52) difference.
3. multi-cylinder synchronous drawbench as claimed in claim 1, it is characterized in that: base end (31) and the base plate (2) of each hydraulic jack (3) are articulated and connected by bearing pin (6), the push rod end (32) of hydraulic jack (3) is hinged by bearing pin (6) with top board (1).
4. multi-cylinder synchronous drawbench as claimed in claim 3, is characterized in that: each hydraulic jack (3) and the connection between base plate (2) and top board (1) are for removably connecting.
5. multi-cylinder synchronous drawbench as claimed in claim 3, is characterized in that: the axis of each bearing pin (6) and the axes intersect of sleeve pipe (4).
6. multi-cylinder synchronous drawbench as claimed in claim 1, is characterized in that: be also provided with slips (7) and slip spider (8) in top board (1) top.
7. the multi-cylinder synchronous drawbench according to any one of claim 1 to 6, it is characterized in that: described top board (1) and base plate (2) are all in square, described cased perforated is arranged on above-mentioned foursquare center, described hydraulic jack (3) has four, four hydraulic jacks (3) respectively with foursquare four right angle one_to_one corresponding.
8. multi-cylinder synchronous drawbench as claimed in claim 1, is characterized in that: on top board (1) and base plate (2), be provided with handle (9).
CN201520757392.6U 2015-09-28 2015-09-28 Synchronous drawbench of multi -cylinder Active CN205012952U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520757392.6U CN205012952U (en) 2015-09-28 2015-09-28 Synchronous drawbench of multi -cylinder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520757392.6U CN205012952U (en) 2015-09-28 2015-09-28 Synchronous drawbench of multi -cylinder

Publications (1)

Publication Number Publication Date
CN205012952U true CN205012952U (en) 2016-02-03

Family

ID=55211561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520757392.6U Active CN205012952U (en) 2015-09-28 2015-09-28 Synchronous drawbench of multi -cylinder

Country Status (1)

Country Link
CN (1) CN205012952U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469451A (en) * 2018-12-28 2019-03-15 中国水电基础局有限公司 A kind of vibrational structure, hydraulic tube drawing bench and application method using vibrating mechanism
CN113006723A (en) * 2021-03-12 2021-06-22 中国电建集团江西省电力设计院有限公司 Butterfly type twist drill pulling tool and drilling pulling method thereof
CN113202432A (en) * 2021-04-21 2021-08-03 梅宗禄 High-pressure non-releasing pressure well head replacement main control valve device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469451A (en) * 2018-12-28 2019-03-15 中国水电基础局有限公司 A kind of vibrational structure, hydraulic tube drawing bench and application method using vibrating mechanism
CN109469451B (en) * 2018-12-28 2024-02-13 中国水电基础局有限公司 Vibration structure, hydraulic tube drawing machine applying vibration mechanism and use method
CN113006723A (en) * 2021-03-12 2021-06-22 中国电建集团江西省电力设计院有限公司 Butterfly type twist drill pulling tool and drilling pulling method thereof
CN113006723B (en) * 2021-03-12 2022-05-24 中国电建集团江西省电力设计院有限公司 Butterfly type twist drill pulling tool and drilling pulling method thereof
CN113202432A (en) * 2021-04-21 2021-08-03 梅宗禄 High-pressure non-releasing pressure well head replacement main control valve device

Similar Documents

Publication Publication Date Title
CN205012952U (en) Synchronous drawbench of multi -cylinder
CN205562159U (en) Shield constructs section of jurisdiction mechanical testing machine
CN102108843A (en) Coiled tubing unit
CN204164492U (en) Direct-burried underground spigot and socket type pressure piping fitting machine
CN206368387U (en) A kind of jumbolter air pump water system
CN102877466A (en) Rotary expansion cast-in-place pile and construction method thereof
CN204248812U (en) Flange device for spreading
CN209780875U (en) Portable quick sampling device of rig and sampling system
CN206440550U (en) A kind of pipeline compressive resistance experimental rig
CN205355694U (en) Non - excavation cable push pipe
CN105401598B (en) Automatic formwork lowering system hoisting device and method for top-down construction
CN203201483U (en) Drill floor mechanism in petroleum drilling and repairing equipment
CN205557610U (en) Wind turbine foundation finish rolling twisted steel changes and uses reinforcing bar draw -out device
CN203156100U (en) Drilling instrument for suspended ceiling construction
CN206598528U (en) A kind of cold pipe steel wire expanding machines of 1kV for being easy to steel wire to extract out
CN205205860U (en) Automatic all hoist device of module system that fall of reverse construction method
CN205012958U (en) Dabber hanger that can exchange with slips hanger
CN206225906U (en) A kind of PVC sleeve pipes threading tooling
CN218598176U (en) Drilling machine tubular column system
CN204343329U (en) A kind of Novel top pipe well
CN203891006U (en) Protection plate for joint of underground continuous walls
CN104120979A (en) Matched drill floor mechanism for petroleum drilling and repairing
CN202520263U (en) Drill rod extractor
CN202970469U (en) Perpendicularity positioner of electric transmission line pole and tower compound foundation drill hole
CN205477408U (en) Fixed tubular construction of a complete set of pipe full -rotating drill stand opening

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant