CN205011283U - Hoist and mount apparatus of large -scale rolling -mill housing - Google Patents
Hoist and mount apparatus of large -scale rolling -mill housing Download PDFInfo
- Publication number
- CN205011283U CN205011283U CN201520709624.0U CN201520709624U CN205011283U CN 205011283 U CN205011283 U CN 205011283U CN 201520709624 U CN201520709624 U CN 201520709624U CN 205011283 U CN205011283 U CN 205011283U
- Authority
- CN
- China
- Prior art keywords
- frame
- hoist
- lift
- mill housing
- rolling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to a large -scale equipment fixing field specifically is a hoist and mount apparatus of large -scale rolling -mill housing, characterized by: it includes frame -type support frame, cross braces and carries the drawing die piece that the top of frame -type support frame is equipped with horizontal cross braces, carry the drawing die piece and draw hydro -cylinder, hoist and steel halter including carrying, carry drawing and adopt the steel cable to be connected between hydro -cylinder and the hoist, the hoist includes gallows, connecting plate, revolving frame and goes up the pivot, carrying carrying of drawing die piece and drawing hydraulic cylinder to fix vertically on connecting the crossbeam, revolving frame is equipped with the rotation support frame with being connected between the crossbeam. The technology that the device had adopted synchronous hoisting device of steel halter hydraulic pressure and rotary balance to combine together will pass, carry and fall and rotate and combine together, strengthen the continuity of hoist and mount operations, effectively reduce operation personnel's input amount and working strength.
Description
Technical field
The utility model relates to main equipment installing area, specifically a kind of hoisting appliance of large-sized rolling mills frame.
Background technology
Driving load-carrying ability in factory building only meets the requirement of maintenance of equipment, daily production load-carrying ability usually, just pays attention to and solves when the lifting when the medium-and-large-sized equipment of factory building is installed and lifting require all in actual installation.Existing spin balancing method lift-on/lift-off system, solves the lifting construction of large-sized rolling mills frame.But when using above-mentioned hanging method to construct, rolling-mill housing, after slippage puts in place, needs to be played certain altitude by jacking under accumbency state, then rotates under plumbness, can fall to installation site.In this process, there is hidden danger: first, step by step frame jacking or decline are put in place by hydraulic jack, intermediate step is busy, by artificial adding, taking out cushion block mode spin balancing frame is raised to the height of pivot point in process, if frame is from ground jacking to the position of 5 ~ 6 meters high, along with the rising of top lifting height, with increase stability highly just worse and worse, Contraction in Site personnel hazard sexual factor significantly increases package unit.The second, the construction intensity of whole engineering is large, and rolling-mill housing corner all needs the human configuration of at least 6 people just can move cushion block, as long as construction at the beginning must continuous working, until rolling-mill housing installation.
Utility model content
The purpose of this utility model is, under the prerequisite ensureing Hoisting Security, reaches the labour intensity reducing operating personnel and the target improving operating efficiency.
In order to achieve the above object, the utility model is achieved in that
A kind of hoisting appliance of large-sized rolling mills frame, it comprises frame-type bracing frame, bearing beam and lift module, described frame-type bracing frame comprises column, connecting cross beam and pull bar, column has four and vertically arranges, connected by connecting cross beam between column and form frame-type bracing frame, the top of frame-type bracing frame is provided with horizontal bearing crossbeam, and bearing beam two ends are connected by pull bar with bottom bracing frame; Lift module comprises lift oil cylinder, suspender and steel strand cable, lift oil cylinder is connected with adopting steel strand cable between suspender, described suspender comprises over sling, connecting panel, rotating frame and upper rotating shaft, lower rotary shaft, connecting panel is located in over sling, its top is connected with the lower rotation of over sling by upper rotating shaft, rotating frame is positioned at the bottom of connecting panel, is rotationally connected between bottom its two ends and connecting panel by lower rotary shaft; The lift oil cylinder of described lift module is fixed on connecting cross beam vertically, is provided with rotating support between rotating frame and connecting cross beam.
This device have employed the technique that steel strand cable hydraulic synchronizing lifting device and spin balancing combine, and by passing, carries and to fall and rotation combines together, strengthen the continuity of lifting operation, effectively reduce input amount and the working strength of operating personnel.
The construction method of the hoisting appliance of described large-sized rolling mills frame, comprises the steps:
Step 1, by course lay sliding rail;
Step 2, assembled frame posture bracing frame and bearing beam, wherein, the column of frame-type bracing frame is erected at by piston shoes on sliding rail, and each connecting joint of frame-type bracing frame all connect with high strength bolt;
Step 3, on connecting cross beam erection lift module lift oil cylinder;
Step 4, build suspender, wherein, by assembled for rotating frame in rolling-mill housing, rotating frame and rolling-mill housing bias are assembled, namely the center of lower rotary shaft slightly biased in the center-of-gravity position 350-450mm of rolling-mill housing;
Step 5, use driving hold rolling-mill housing afterbody, prevent rolling-mill housing from rotating, start the slippage of frame-type bracing frame to assigned address;
Step 6, by after rolling-mill housing slippage to desired location, use lift oil cylinder start lift, (till rising to absolute altitude computed in advance, mounting seat and memorial archway holding-down bolt when the height namely promoted is to ensure that rolling-mill housing rotates, can be crossed);
Step 7, lifting start slippage limit, limit and rotate after putting in place, rolling-mill housing moved in respective seat, and make rolling-mill housing reach plumbness;
Step 8, rotate to after plumbness until rolling-mill housing, lift oil cylinder starts to decline and rolling-mill housing is in place, tightens holding-down bolt.
This device and construction method improve alerting ability and the reliability of on-site hoisting operation and construction organization, the input amount of effective minimizing lifting operation personnel and working strength, further enhancing the assurance to on-the-spot integral construction progress, features such as its " flexible, convenient, load-carrying ability is large, detachable, multi-functional ", can be large equipment from now on and installs and provide efficient hanging device.
Accompanying drawing explanation
Fig. 1 is the front view of this apparatus.
Fig. 2 is the lateral plan of this apparatus.
Fig. 3 is the structural representation one lifting module in this apparatus.
Fig. 4 is the structural representation two lifting module in this apparatus.
Fig. 5 is the hydraulic schematic of this apparatus.
Detailed description of the invention
The utility model is further illustrated below by way of specific embodiment.
As shown in Figure 1 and Figure 2, a kind of hoisting appliance of large-sized rolling mills frame, it comprises frame-type bracing frame, bearing beam 2 and lift module, described frame-type bracing frame comprises column 1, connecting cross beam 4 and pull bar 3, column 1 has four and vertically arranges, connected by connecting cross beam 4 between column 1 and form frame-type bracing frame, the top level of frame-type bracing frame is provided with bearing beam 2, and bearing beam 2 two ends are connected by pull bar 3 with bottom bracing frame; Lift module comprises lift oil cylinder 8, suspender 7 and steel strand cable 9, lift oil cylinder 8 is connected with adopting steel strand cable 9 between suspender 7, as shown in Figure 3, Figure 4, described suspender 7 comprises over sling 701, connecting panel 702, rotating frame 5 and upper rotating shaft 703, lower rotary shaft 704, connecting panel 702 is located in over sling 701, its top is connected with the lower rotation of over sling 701 by upper rotating shaft 703, rotating frame 5 is positioned at the bottom of connecting panel 702, is rotationally connected between bottom its two ends and connecting panel 702 by lower rotary shaft 704; The lift oil cylinder 8 of described lift module is fixed on connecting cross beam 4 vertically, is provided with rotating support 6 between rotating frame 5 and connecting cross beam.
This device have employed the technique that hydraulic pressure lift and spin balancing combine, and by passing, carries and to fall and rotation combines together, strengthen the continuity of lifting operation, effectively reduce input amount and the working strength of operating personnel.
The construction method of the hoisting appliance of described large-sized rolling mills frame, comprises the steps:
Step 1, lay sliding rail 9 ejection device 10 is set in rail end by course;
Step 2, assembled frame posture bracing frame and bearing beam, wherein, the column of frame-type bracing frame is erected on sliding rail 9 by piston shoes, each connecting joint of frame-type bracing frame all connect with high strength bolt;
Step 3, on connecting cross beam erection lift module lift oil cylinder;
Step 4, build suspender, wherein, by assembled for rotating frame in rolling-mill housing, rotating frame and rolling-mill housing bias are assembled, namely the center of lower rotary shaft slightly biased in the center-of-gravity position 350-450mm of rolling-mill housing;
Step 5, use driving hold rolling-mill housing afterbody, prevent rolling-mill housing from rotating, start the slippage of frame-type bracing frame to assigned address;
Step 6, by after rolling-mill housing slippage to desired location, use lift oil cylinder start lift, (till rising to absolute altitude computed in advance, mounting seat and memorial archway holding-down bolt when the height namely promoted is to ensure that rolling-mill housing rotates, can be crossed);
Step 7, lifting start slippage limit, limit and rotate after putting in place, rolling-mill housing moved in respective seat, and make rolling-mill housing reach plumbness;
Step 8, rotate to after plumbness until rolling-mill housing, lift oil cylinder starts to decline and rolling-mill housing is in place, tightens holding-down bolt.
This device and construction method improve alerting ability and the reliability of on-site hoisting operation and construction organization, the input amount of effective minimizing lifting operation personnel and working strength, further enhancing the assurance to on-the-spot integral construction progress, features such as its " flexible, convenient, load-carrying ability is large, detachable, multi-functional ", can be large equipment from now on and installs and provide efficient hanging device.
As shown in Figure 5, the hydraulic work system principle of this device is as follows:
During lifting, solenoid directional control valve Y31 is energized, and cylinder is stretched on main top; During decline, solenoid directional control valve YV32 is energized, main synthlipsis cylinder.Because lifting jack is provided with balance cock, time unloaded, contracting cylinder oil pressure can reach 7 ~ 10Mpa, increases contracting cylinder pressure reduce when band carries with load.During electromagnetic valve meta, system unloaded.
During YV12, YV22 energising, upper and lower clamper is tight anchor respectively; During YV11, YV21 energising, upper and lower clamper is loose anchor respectively.
When decline weight, if during the unforeseen circumstances such as generation systems dead electricity, confession shortage of oil, the hydraulic control one-way valve decompression in loop is closed, and weight stops declining.
Claims (1)
1. the hoisting appliance of a large-sized rolling mills frame, it is characterized in that: it comprises frame-type bracing frame, bearing beam and lift module, described frame-type bracing frame comprises column, connecting cross beam and pull bar, column has four and vertically arranges, connected by connecting cross beam between column and form frame-type bracing frame, the top of frame-type bracing frame is provided with horizontal bearing crossbeam, and bearing beam two ends are connected by pull bar with bottom bracing frame; Lift module comprises lift hydraulic ram, suspender and steel strand cable, lift oil cylinder is connected with adopting steel strand cable between suspender, described suspender comprises over sling, connecting panel, rotating frame and upper rotating shaft, lower rotary shaft, connecting panel is located in over sling, its top is connected with the lower rotation of over sling by upper rotating shaft, rotating frame is positioned at the bottom of connecting panel, is rotationally connected between bottom its two ends and connecting panel by lower rotary shaft; The lift oil cylinder of described lift module is fixed on connecting cross beam vertically, is provided with rotating support between rotating frame and connecting cross beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520709624.0U CN205011283U (en) | 2015-09-15 | 2015-09-15 | Hoist and mount apparatus of large -scale rolling -mill housing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520709624.0U CN205011283U (en) | 2015-09-15 | 2015-09-15 | Hoist and mount apparatus of large -scale rolling -mill housing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205011283U true CN205011283U (en) | 2016-02-03 |
Family
ID=55209897
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520709624.0U Active CN205011283U (en) | 2015-09-15 | 2015-09-15 | Hoist and mount apparatus of large -scale rolling -mill housing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205011283U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106241604A (en) * | 2016-08-16 | 2016-12-21 | 北京首钢建设集团有限公司 | Hoisting mill housing automatic central adjusting lifting device and using method |
CN106517009A (en) * | 2015-09-15 | 2017-03-22 | 上海宝冶集团有限公司 | Large decorated archway lifting tool and construction method thereof |
-
2015
- 2015-09-15 CN CN201520709624.0U patent/CN205011283U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106517009A (en) * | 2015-09-15 | 2017-03-22 | 上海宝冶集团有限公司 | Large decorated archway lifting tool and construction method thereof |
CN106241604A (en) * | 2016-08-16 | 2016-12-21 | 北京首钢建设集团有限公司 | Hoisting mill housing automatic central adjusting lifting device and using method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2017225082B2 (en) | Utility tower lifting apparatus and method | |
CN104060844B (en) | Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof | |
CA2869273C (en) | Tank-assembly process and devices for executing it | |
WO2013120419A1 (en) | Hydraulic lifting self-climbing template system | |
CN207294093U (en) | A kind of large span steel truss integral lifting apparatus | |
CN201367728Y (en) | Derrick-less hydraulic slip form device used for reinforced concrete water tower supporting tube construction | |
CN211971631U (en) | Pipeline lifting and transporting device | |
CN111472789B (en) | Pipe jacking construction process | |
CN205011283U (en) | Hoist and mount apparatus of large -scale rolling -mill housing | |
CN106517009B (en) | The hoisting appliance and its construction method of large-scale memorial archway | |
CN106088609A (en) | A kind of integral lifting method of large span steel structure vestibule | |
CN205773024U (en) | A kind of convenient pipeline lifting auxiliary device | |
CN103774841A (en) | Track type sliding formwork device | |
CN204663003U (en) | Anchor ear type vestibule truss Steel Structure hoisting hanger | |
CN108518081A (en) | A kind of construction method increasing the cell underground space newly using synchronization of jacking up shift unit | |
CN203867198U (en) | Slip equipment for high-rise steel structure transfer layer truss | |
CN104060836A (en) | Lifting and installation method of high curved-surface net racks | |
CN204059901U (en) | A kind of high-altitude construction operation platform | |
CN204645669U (en) | Vestibule truss Steel Structure promotes ground tackle | |
CN203486787U (en) | Integral lifting device for cabinet top of Wiggins coal gas cabinet | |
CN106744404A (en) | Using the method for portable pylon hoisting rolling mill housings | |
CN101818829B (en) | Construction method of cross-valley overhead pipeline | |
CN204082177U (en) | Tunnel steel arch frame fitting machine | |
CN206203763U (en) | Self-driving floor hanging apparatus | |
CN107311039A (en) | The method pulled for jumbo |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |