CN204986318U - Electric power iron tower vertical direction equipment fixing fastener - Google Patents

Electric power iron tower vertical direction equipment fixing fastener Download PDF

Info

Publication number
CN204986318U
CN204986318U CN201520568056.7U CN201520568056U CN204986318U CN 204986318 U CN204986318 U CN 204986318U CN 201520568056 U CN201520568056 U CN 201520568056U CN 204986318 U CN204986318 U CN 204986318U
Authority
CN
China
Prior art keywords
electric power
vertical direction
equipment
iron tower
double
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520568056.7U
Other languages
Chinese (zh)
Inventor
文凯
付伟平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LUOHE POWER SUPPLY COMPANY STATE GRID HENAN ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Original Assignee
LUOHE POWER SUPPLY COMPANY STATE GRID HENAN ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by LUOHE POWER SUPPLY COMPANY STATE GRID HENAN ELECTRIC POWER Co Ltd, State Grid Corp of China SGCC filed Critical LUOHE POWER SUPPLY COMPANY STATE GRID HENAN ELECTRIC POWER Co Ltd
Priority to CN201520568056.7U priority Critical patent/CN204986318U/en
Application granted granted Critical
Publication of CN204986318U publication Critical patent/CN204986318U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an electric power iron tower vertical direction equipment fixing fastener, including angle steel for iron tower, last setting of angle steel for iron tower and the double -deck fastening device of angle steel for iron tower matched with, the rotation support mechanism of double -deck fastening device through setting gradually from bottom to top, fixed establishment and fixed establishment and the perpendicular union coupling of installing of buckling slide, set up equipment fastening bolt on the perpendicular installation pipe. The utility model discloses a double -deck fastening device is not providing basic to under the circumstances of angle steel for iron tower drilling to whole equipment fixing fastener, and angle modulation and support that the rethread is 3 realize realizing equipment fixing, debugging fast to the fastening of electric power iron tower vertical direction equipment, reduce constructor intensity of labour by a wide margin, the engineering of being convenient for construction.

Description

A kind of electric power tower Vertical direction equipment installs securing means
Technical field
The utility model relates to electric force pole tower technical field, is specifically related to a kind of electric power tower Vertical direction equipment and installs securing means.
Background technique
According to the particular/special requirement of mechanical structure, its edge angle steel capital of electric power tower is not be 90 degree of vertical angles with ground, often forms 60 degree to 90 degree angles with ground.Meanwhile, according to regulations stipulate, can not hole on electric power tower, weld.In these contexts, electric power tower is installed the article or equipment (as flag, antenna, lightning conductor etc.) that need vertical placement, and install and adjust perpendicularity is all cumbersome, not only time and effort consuming, and toward not reaching vertical requirement.
Model utility content
Problem to be solved in the utility model is to provide a kind of electric power tower Vertical direction equipment and installs securing means, when not holing to steel tower corner iron, securing means is installed to whole equipment by double-deck retention mechanism and basis is provided, again by angle adjustment and the support of 3, realize fastening to electric power tower Vertical direction equipment, the equipment that realizes fast is installed, debugging, significantly reduce workmen's labor intensity, be convenient to engineering construction.
A kind of electric power tower Vertical direction equipment installs securing means, comprise steel tower corner iron, described steel tower corner iron is arranged the double-deck retention mechanism matched with steel tower corner iron, described double-deck retention mechanism is connected with at right angle setting pipe with bending fixed mechanism by the rotary support mechanism that sets gradually from bottom to top, slip fixed mechanism, and described at right angle setting pipe arranges equipment clamping bolt.
Further, described double-deck retention mechanism comprises interior angle steel and outboard angle, and described interior angle steel and described outboard angle edge arrange clamping bolt.
Further, described rotary support mechanism comprises rotating basis, and described rotating basis arranges running shaft, and described running shaft is connected with described at right angle setting pipe lower end.
Further, described slip fixed mechanism comprises fixed support, and described fixed support arranges sliding sleeve by chute A and adjusting bolt A, is inserted in described at right angle setting pipe in described sliding sleeve.
Further, described bending fixed mechanism comprises bent pedestal, and described bent pedestal front end arranges chute B, and the corresponding described chute B in described at right angle setting pipe top arranges adjusting bolt B.
Further, described bent pedestal arranges swivel bolt.
The utility model provides a kind of electric power tower Vertical direction equipment and installs securing means, mainly carry out fixing whole securing means by double-deck retention mechanism, while boring not being caused to steel tower corner iron, utilize the principle of double-deck clamping basic as what fix, equipment clamping bolt is fixed the vertically arranged equipment of needs.Double-deck retention mechanism coordinates parcel steel tower corner iron by interior angle steel and outboard angle, fixed, form the basis that whole equipment installs securing means by clamping bolt.Double-deck retention mechanism is connected with at right angle setting pipe with bending fixed mechanism by the rotary support mechanism that sets gradually from bottom to top, slip fixed mechanism, rotary support mechanism is connected with at right angle setting pipe lower end, the effect of support can be played at right angle setting pipe, and by rotating the angle that can regulate at right angle setting pipe, adjusted to perpendicular to the ground, meet the vertically arranged requirement of equipment, running shaft on pedestal can be bolt, can be fixed it by bolt after adjusting to proper angle, increase the effect that whole device supports.Slip fixed mechanism plays the effect of midfoot support, mainly add to prevent the too heavy installation of steel tower equipment insecure, the medium position of at right angle setting pipe is set in by sliding sleeve, sliding sleeve is connected with fixed support with adjusting bolt A by chute A, plays the effect fixed effect and the angle of at right angle setting pipe midfoot support.Bending fixed mechanism is arranged in order to level height when tackling at right angle setting pipe different amount is different, can be regulated the fixed position bending fixed mechanism, well can be connected with the top of at right angle setting pipe by bending.The bending bending fixed mechanism realizes mainly through bent pedestal, realizes the angle adjustment to bent pedestal in the middle of bent pedestal by the degree of tightness of swivel bolt.
The utility model is installed securing means when not holing to steel tower corner iron to whole equipment by double-deck retention mechanism and is provided basis, again by angle adjustment and the support of 3, realize fastening to electric power tower Vertical direction equipment, the equipment that realizes fast is installed, debugging, significantly reduce workmen's labor intensity, be convenient to engineering construction.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the utility model is further described:
Fig. 1 is the structural representation that the utility model electric power tower Vertical direction equipment installs securing means;
Fig. 2 is the structural representation of the double-deck retention mechanism of the utility model;
Fig. 3 is the structural representation of the utility model slip fixed mechanism;
Fig. 4 is the structural representation of the utility model bending fixed mechanism.
Embodiment
As shown in Figures 1 to 4: the utility model provides a kind of electric power tower Vertical direction equipment and installs securing means, comprise steel tower corner iron 1, described steel tower corner iron 1 is arranged the double-deck retention mechanism 2 matched with steel tower corner iron 1, described double-deck retention mechanism 2 is connected with at right angle setting pipe 3 with bending fixed mechanism 6 by the rotary support mechanism 4 that sets gradually from bottom to top, slip fixed mechanism 5, and described at right angle setting pipe 3 arranges equipment clamping bolt 7.
Described double-deck retention mechanism 2 comprises interior angle steel 8 and outboard angle 9, and described interior angle steel 8 and described outboard angle 9 edge arrange clamping bolt 10.
Described rotary support mechanism 4 comprises rotating basis 11, and described rotating basis 11 arranges running shaft 12, and described running shaft 12 is connected with described at right angle setting pipe 3 lower end.
Described slip fixed mechanism 5 comprises fixed support 13, and described fixed support 13 arranges sliding sleeve 15 by chute A14 and adjusting bolt A19, is inserted in described at right angle setting pipe 3 in described sliding sleeve 15.
Described bending fixed mechanism 6 comprises bent pedestal 16, and described bent pedestal 16 front end arranges chute B18, and the corresponding described chute B18 in described at right angle setting pipe 3 top arranges adjusting bolt B20.
Described bent pedestal 16 arranges swivel bolt 17.
The utility model provides a kind of electric power tower Vertical direction equipment and installs securing means, mainly carry out fixing whole securing means by double-deck retention mechanism, while boring not being caused to steel tower corner iron, utilize the principle of double-deck clamping basic as what fix, equipment clamping bolt is fixed the vertically arranged equipment of needs.Double-deck retention mechanism coordinates parcel steel tower corner iron by interior angle steel and outboard angle, fixed, form the basis that whole equipment installs securing means by clamping bolt.Double-deck retention mechanism is connected with at right angle setting pipe with bending fixed mechanism by the rotary support mechanism that sets gradually from bottom to top, slip fixed mechanism, rotary support mechanism is connected with at right angle setting pipe lower end, the effect of support can be played at right angle setting pipe, and by rotating the angle that can regulate at right angle setting pipe, adjusted to perpendicular to the ground, meet the vertically arranged requirement of equipment, running shaft on pedestal can be bolt, can be fixed it by bolt after adjusting to proper angle, increase the effect that whole device supports.Slip fixed mechanism plays the effect of midfoot support, mainly add to prevent the too heavy installation of steel tower equipment insecure, the medium position of at right angle setting pipe is set in by sliding sleeve, sliding sleeve is connected with fixed support with adjusting bolt A by chute A, plays the effect fixed effect and the angle of at right angle setting pipe midfoot support.Bending fixed mechanism is arranged in order to level height when tackling at right angle setting pipe different amount is different, can be regulated the fixed position bending fixed mechanism, well can be connected with the top of at right angle setting pipe by bending.The bending bending fixed mechanism realizes mainly through bent pedestal, realizes the angle adjustment to bent pedestal in the middle of bent pedestal by the degree of tightness of swivel bolt.

Claims (6)

1. an electric power tower Vertical direction equipment installs securing means, comprise steel tower corner iron, it is characterized in that: described steel tower corner iron is arranged the double-deck retention mechanism matched with steel tower corner iron, described double-deck retention mechanism is connected with at right angle setting pipe with bending fixed mechanism by the rotary support mechanism that sets gradually from bottom to top, slip fixed mechanism, and described at right angle setting pipe arranges equipment clamping bolt.
2. electric power tower Vertical direction equipment as claimed in claim 1 installs securing means, and it is characterized in that: described double-deck retention mechanism comprises interior angle steel and outboard angle, described interior angle steel and described outboard angle edge arrange clamping bolt.
3. electric power tower Vertical direction equipment as claimed in claim 1 installs securing means, and it is characterized in that: described rotary support mechanism comprises rotating basis, described rotating basis arranges running shaft, described running shaft is connected with described at right angle setting pipe lower end.
4. electric power tower Vertical direction equipment as claimed in claim 1 installs securing means, it is characterized in that: described slip fixed mechanism comprises fixed support, described fixed support arranges sliding sleeve by chute A and adjusting bolt A, is inserted in described at right angle setting pipe in described sliding sleeve.
5. electric power tower Vertical direction equipment as claimed in claim 1 installs securing means, it is characterized in that: described bending fixed mechanism comprises bent pedestal, described bent pedestal front end arranges chute B, and the corresponding described chute B in described at right angle setting pipe top arranges adjusting bolt B.
6. electric power tower Vertical direction equipment as claimed in claim 5 installs securing means, it is characterized in that: described bent pedestal arranges swivel bolt.
CN201520568056.7U 2015-07-31 2015-07-31 Electric power iron tower vertical direction equipment fixing fastener Active CN204986318U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520568056.7U CN204986318U (en) 2015-07-31 2015-07-31 Electric power iron tower vertical direction equipment fixing fastener

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520568056.7U CN204986318U (en) 2015-07-31 2015-07-31 Electric power iron tower vertical direction equipment fixing fastener

Publications (1)

Publication Number Publication Date
CN204986318U true CN204986318U (en) 2016-01-20

Family

ID=55120686

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520568056.7U Active CN204986318U (en) 2015-07-31 2015-07-31 Electric power iron tower vertical direction equipment fixing fastener

Country Status (1)

Country Link
CN (1) CN204986318U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013931A (en) * 2016-07-26 2016-10-12 安徽饰界广告有限公司 Movable road flag
CN108006533A (en) * 2017-11-03 2018-05-08 姚宝佳 A kind of municipal road lamp for being easy to fly a national flag and national flag handler
CN108019680A (en) * 2017-11-03 2018-05-11 姚宝佳 The device of red-letter day national flag is loaded and unloaded on a kind of urban district street lamp and street lamp
CN113619451A (en) * 2020-09-07 2021-11-09 江苏大盛铁塔制造有限公司 High-speed railway contact net double pin H shaped steel post convenient to installation
CN114754261A (en) * 2022-05-17 2022-07-15 国家电网有限公司 Displacement monitoring camera mounting platform and manufacturing method thereof
CN114754261B (en) * 2022-05-17 2024-05-03 国家电网有限公司 Displacement monitoring camera mounting platform and manufacturing method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013931A (en) * 2016-07-26 2016-10-12 安徽饰界广告有限公司 Movable road flag
CN106013931B (en) * 2016-07-26 2018-08-21 安徽饰界广告有限公司 A kind of removable road flag
CN108006533A (en) * 2017-11-03 2018-05-08 姚宝佳 A kind of municipal road lamp for being easy to fly a national flag and national flag handler
CN108019680A (en) * 2017-11-03 2018-05-11 姚宝佳 The device of red-letter day national flag is loaded and unloaded on a kind of urban district street lamp and street lamp
CN113619451A (en) * 2020-09-07 2021-11-09 江苏大盛铁塔制造有限公司 High-speed railway contact net double pin H shaped steel post convenient to installation
CN114754261A (en) * 2022-05-17 2022-07-15 国家电网有限公司 Displacement monitoring camera mounting platform and manufacturing method thereof
CN114754261B (en) * 2022-05-17 2024-05-03 国家电网有限公司 Displacement monitoring camera mounting platform and manufacturing method thereof

Similar Documents

Publication Publication Date Title
CN204986318U (en) Electric power iron tower vertical direction equipment fixing fastener
CN204435979U (en) A kind of protection device for installing of electric power facility
CN204213480U (en) Floor heating pipe installs embedded part
CN205488999U (en) Lightning protection device striking pole mounting bracket
CN207122039U (en) A kind of ceiling joist
CN202501101U (en) Cable support arm
CN201450302U (en) Sliding cable clamp component
CN205790962U (en) The universal mounting bracket of earth leakage protective device
CN205479723U (en) Novel support for cable
CN204729760U (en) A kind of cable bearer of universal rotational
CN205226638U (en) A adjustable bracket for pipe laying
CN204569072U (en) A kind of erecting frame of cage guide
CN204573523U (en) High-order expansion buffer water tank lowering or hoisting gear
CN204809786U (en) Horizontal well well logging well head cable guider
CN204416944U (en) A kind of hoisting crane conduction rack
CN202440976U (en) Integrated equipment belt mounting structure
CN207194477U (en) A kind of crossbeam positioner
CN204681026U (en) The cable fixture of cable shaft and junction, cable tunnel
CN203421308U (en) Cable hook
CN204288941U (en) To shake the head dish erection support
CN209244292U (en) A kind of cladding panel installation bottom levelling device
CN204005128U (en) A kind of mounting bracket of wall mounting telephone
CN209591366U (en) A kind of dedicated installation frame structure of display screen
CN203352111U (en) Coal plough and cable channel limiting device thereof
CN202544318U (en) Floor board bilateral fixing card

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant