CN204983517U - Mounting structure of dalle - Google Patents

Mounting structure of dalle Download PDF

Info

Publication number
CN204983517U
CN204983517U CN201520678032.7U CN201520678032U CN204983517U CN 204983517 U CN204983517 U CN 204983517U CN 201520678032 U CN201520678032 U CN 201520678032U CN 204983517 U CN204983517 U CN 204983517U
Authority
CN
China
Prior art keywords
production board
mounting structure
exterior wall
wall
dalle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520678032.7U
Other languages
Chinese (zh)
Inventor
周觐
彭泽润
汪小山
王洁
陈炳连
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan No8 Engineering Co Ltd
Original Assignee
Hunan No8 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan No8 Engineering Co Ltd filed Critical Hunan No8 Engineering Co Ltd
Priority to CN201520678032.7U priority Critical patent/CN204983517U/en
Application granted granted Critical
Publication of CN204983517U publication Critical patent/CN204983517U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model provides a mounting structure of dalle belongs to including installing in the production board of outer wall, and production board smears the thick liquid with the outer wall through a plurality of punctiform and bonds, is provided with anchor assembly between production board and the outer wall, and production board passes through anchor assembly fixed connection with the outer wall. The utility model provides an on mounting structure of dalle, anchor assembly can block production board and be fixed in the outer wall with production board to production board smears the thick liquid with the outer wall through the punctiform and bonds, receives great vertical braces power and a plurality of power of clamp with the outer wall when making production board be connected, forms many first atress systems, thereby makes production board very firm with being connected of outer wall, is difficult for coming off. Adopt the punctiform to smear the thick liquid bonding, what adopt promptly is the empty method of pasting, compares with full the current image of buddha, has significantly reduced and has smeared the oar rate, has practiced thrift oar body material greatly, and the punctiform is smeared to starch and is separated production board and outer wall moreover, forms an air bed space, makes the external wall insulation effect better.

Description

The mounting structure of dalle
Technical field
The utility model relates to dalle technical field of construction, in particular to a kind of mounting structure of dalle.
Background technology
Decorating outer wall of building widely uses in modern architecture, and architectural decoration is the abbreviation of Building decorating and repairs engineering.Architectural decoration is the agent structure of architecture protection thing, the physical property improving building, using function and beautifying constructure, adopts the various processing procedures that decorating and renovating material or jewelry carry out the surfaces externally and internally of building and space.
The construction technology of existing dalle is very complicated, and dalle is installed on exterior wall and usually adopts full subsides method to paste, and the stickup of dalle and exterior wall is fixing firm not, dalle easily comes off, easily cause danger, and it is more to paste the oar body material used, labour intensity is larger.
Utility model content
The utility model provides a kind of mounting structure of dalle, is intended to improve the problems referred to above.
The utility model is achieved in that
A kind of mounting structure of dalle, comprise the production board being installed on exterior wall, described production board and described exterior wall are smeared to starch by some point-like and are bondd, and be provided with anchoring piece between described production board and described exterior wall, described production board is fixedly connected with by described anchoring piece with described exterior wall.
Further, described anchoring piece comprises the anchor slab of L shape, and described anchor slab is fixedly connected with described exterior wall, and a side of described anchor slab is provided with clip, described clip is provided with the fin that two bearing of trends are contrary, two described fins insert two adjacent production boards respectively.
Clip can block production board by two fins and can be fixed on exterior wall by adjacent two production boards, slurry bonding is smeared again by point-like, larger vertical supporting power and multiple grip force is subject to when production board is connected with exterior wall, form polynary stress system, also it is firm to connect between adjacent two production boards, thus make the connection of production board and exterior wall very firm, difficult drop-off.
Further, described anchor slab comprises base plate and side plate, and described base plate is connected with described side plate and forms L shape, described base plate is provided with the first through hole of strip, be provided with screw in described first through hole, described base plate can be slided and is connected with described exterior wall by screw on described exterior wall.
Be slidably connected between anchor slab and exterior wall, the position of anchor slab on exterior wall can be regulated, in practice of construction, can regulate and in the short transverse of exterior wall, anchor slab be regulated, thus make to be on same level line between multiple anchor slab.
Further, described side plate and described clip are slidably connected.
Clip can slide by side plate relatively, thus can realize the adjustment of two fins, can adjust fin well to best position.
Further, described clip comprises clamp, two described fins are arranged on the side of described clamp respectively, and extend along two rightabouts vertical with described clamp, described clamp is provided with the second through hole, described side plate is provided with screwed hole, and described clamp and described side plate are connected by screw.
When clamp is connected with side plate, screw is through the second through hole on clamp and the screwed hole on side plate, and when not twisting dead by screw, clamp can regulate relative to the position of side plate, after being adjusted to correct position, only screw need be twisted dead.Like this, easy for installation, be fixedly easy to operation, can regulate easily.
Further, the back side of described production board is provided with in-line groove, and described point-like is smeared slurry and can be embedded in described in-line groove.
By arranging in-line groove, point-like is smeared slurry and is embedded in in-line groove, when production board is bonded on exterior wall, it is firmly chimeric with in-line groove that point-like smears slurry, from and formed an adhesion stress, enhance the bonding between production board and exterior wall, make connection more firm.
Further, described point-like is smeared slurry and is comprised 7 fonts and smear oar and circular point-like smears slurry, and the corner that oar is arranged at the back side of described production board smeared in described 7 fonts, and described circular point-like smears the middle part that slurry is distributed in described production board.
Smear 7 fonts in the corner at the production board back side and smear oar, production board and exterior wall have adhesion stress with vertical direction in the horizontal direction, also have vertical supporting power, define corner supporting plane stress system, make production board respectively to uniform force; Smear circular point-like in plate and smear the bonding that slurry further enhances production board and exterior wall.
Further, described production board is external wall energy-saving decoration integrated board, and described external wall energy-saving decoration integrated board comprises interconnective panel and warming plate.
Further, also comprise the snap fit of L shape, inserting between described panel and described warming plate of the L shape of described snap fit.
Exterior window trim, parapet are beared down on one, the side fascia at external corner place, the snap fit of L shape can be adopted to strengthen fixing, make overall structure more firm, sheet material difficult drop-off.
Further, fluid sealant is provided with between two adjacent described production boards.By arranging fluid sealant, well two adjacent production boards can be connected sealing, improve the fixing of mounting structure, improve weatherability.
The beneficial effects of the utility model are: the mounting structure of the dalle that the utility model is obtained by above-mentioned design, anchoring piece can block production board and be fixed on exterior wall by production board, and production board and exterior wall are smeared to starch by point-like and are bondd, larger vertical supporting power and multiple grip force is subject to when production board is connected with exterior wall, form polynary stress system, thus make the connection of production board and exterior wall very firm, difficult drop-off.In addition, point-like is adopted to smear slurry bonding, what namely adopt is empty subsides method, completely paste compared with method with existing, greatly reduce and smear oar rate, greatly saved oar body material, and point-like smear slurry production board and exterior wall are separated, form an air layer space, air layer can play function of heat insulation, makes exterior-wall heat insulation better effects if.
Accompanying drawing explanation
In order to be illustrated more clearly in the technical scheme of the utility model embodiment, be briefly described to the accompanying drawing used required in embodiment below, be to be understood that, the following drawings illustrate only some embodiment of the present utility model, therefore the restriction to scope should be counted as, for those of ordinary skill in the art, under the prerequisite not paying creative work, other relevant accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of the mounting structure of the dalle that the utility model embodiment provides;
Fig. 2 is the installment state schematic diagram of the anchoring piece of the mounting structure of the dalle that the utility model embodiment provides;
Fig. 3 is the structural representation that the point-like of the mounting structure of the dalle that the utility model embodiment provides smears slurry;
Fig. 4 be the anchoring piece of the mounting structure of the dalle that the utility model embodiment provides face structural representation;
Fig. 5 is the side-looking structural representation of the anchoring piece of the mounting structure of the dalle that the utility model embodiment provides;
View when Fig. 6 is the clip slip of the anchoring piece of the mounting structure of the dalle that the utility model embodiment provides;
Fig. 7 be the anchor slab of the anchoring piece of the mounting structure of the dalle that the utility model embodiment provides face structural representation;
Fig. 8 is the side-looking structural representation of the anchor slab of the anchoring piece of the mounting structure of the dalle that the utility model embodiment provides;
Fig. 9 be the clip of the anchoring piece of the mounting structure of the dalle that the utility model embodiment provides face structural representation;
Figure 10 is the side-looking structural representation of the clip of the anchoring piece of the mounting structure of the dalle that the utility model embodiment provides;
Figure 11 is the perspective view of the clip of the anchoring piece of the mounting structure of the dalle that the utility model embodiment provides.
Figure acceptance of the bid note is respectively:
Exterior wall 100;
Production board 200; Panel 201; Warming plate 202; Fluid sealant 203; Polyethylene foamed pole 204;
Point-like smears slurry 300; Oar 301 smeared in 7 fonts; Circular point-like smears slurry 302;
Anchoring piece 400; Anchor slab 401; Clip 402; Fin 403; Base plate 404; Side plate 405; First through hole 406; Clamp 407; Second through hole 408.
Detailed description of the invention
For making the object of the utility model embodiment, technical scheme and advantage clearly, below in conjunction with the accompanying drawing in the utility model embodiment, technical scheme in the utility model embodiment is clearly and completely described, obviously, described embodiment is the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.Therefore, below to the detailed description of the embodiment of the present utility model provided in the accompanying drawings and the claimed scope of the present utility model of not intended to be limiting, but selected embodiment of the present utility model is only represented.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.
Embodiment
Refer to Fig. 1 and Fig. 2, present embodiments provide a kind of mounting structure of dalle, namely dalle is installed on the overall structure that exterior wall 100 is formed, and dalle can be multiple existing plate construction, and the present embodiment is referred to as production board 200.
This mounting structure comprises the production board 200 being installed on exterior wall 100, production board 200 and exterior wall 100 are smeared slurry 300 by some point-like and are bondd, be provided with anchoring piece 400 between production board 200 and exterior wall 100, production board 200 is fixedly connected with by anchoring piece 400 with exterior wall 100.
The mounting structure of the dalle that the utility model provides, anchoring piece 400 can block production board 200 and be fixed on exterior wall 100 by production board 200, and production board 200 and exterior wall 100 are smeared slurry 300 by point-like and are bondd, larger vertical supporting power and multiple grip force is subject to when production board 200 is connected with exterior wall 100, form polynary stress system, thus make production board 200 very firm with the connection of exterior wall 100, difficult drop-off.In addition, adopt point-like to smear slurry 300 to bond, what namely adopt is empty subsides method, completely paste compared with method with existing, greatly reduce and smear oar rate, greatly saved oar body material, and point-like is smeared slurry 300 production board 200 and exterior wall 100 is separated, form an air layer space, air layer can play function of heat insulation, makes exterior wall 100 better heat preservation.
On the technical scheme basis of the mounting structure of the dalle provided at above-described embodiment, further, refer to Fig. 4 ~ Figure 11, anchoring piece 400 comprises the anchor slab 401 of L shape, anchor slab 401 is fixedly connected with exterior wall 100, a side of anchor slab 401 is provided with clip 402, and fin 403, two fins 403 clip 402 being provided with two bearing of trends contrary insert two adjacent production boards 200 respectively.
Clip 402 can block production board 200 by two fins 403 and can be fixed on exterior wall 100 by adjacent two production boards 200, smear slurry 300 by point-like again to bond, larger vertical supporting power and multiple grip force is subject to when production board 200 is connected with exterior wall 100, form polynary stress system, also it is firm to connect between adjacent two production boards 200, thus make production board 200 very firm with the connection of exterior wall 100, difficult drop-off.
Specifically, refer to Fig. 4 ~ Figure 11, anchor slab 401 comprises base plate 404 and side plate 405, base plate 404 is connected with side plate 405 and forms L shape, base plate 404 is provided with the first through hole 406 of strip, be provided with screw in first through hole 406, base plate 404 can be slided and is connected with exterior wall 100 by screw on exterior wall 100.
Be slidably connected between base plate 404 and exterior wall 100, can the position of regulating base board 404 on exterior wall 100, in practice of construction, can regulate and in the short transverse of exterior wall 100, anchor slab 401 be regulated, thus make to be on same level line between multiple anchor slab 401.
Side plate 405 and clip 402 are slidably connected.Clip 402 can slide by side plate 405 relatively, thus can realize the adjustment of two fins 403, can adjust fin 403 to best position well.
Clip 402 comprises clamp 407, two fins 403 are arranged on the side of clamp 407 respectively, and extend along two rightabouts vertical with clamp 407, clamp 407 are provided with the second through hole 408, side plate 405 is provided with screwed hole, and clamp 407 and side plate 405 are connected by screw.
When clamp 407 is connected with side plate 405, screw is through the second through hole 408 on clamp 407 and the screwed hole on side plate 405, and when not twisting dead by screw, clamp 407 can regulate relative to the position of side plate 405, after being adjusted to correct position, only screw need be twisted dead.Like this, easy for installation, be fixedly easy to operation, can regulate easily.
The back side of production board 200 is provided with in-line groove, and point-like is smeared slurry 300 and can be embedded in in-line groove.
By arranging in-line groove, point-like is smeared slurry 300 and is embedded in in-line groove, when production board 200 is bonded on exterior wall 100, it is firmly chimeric with in-line groove that point-like smears slurry 300, from and formed an adhesion stress, enhance the bonding between production board 200 and exterior wall 100, make connection more firm.
Refer to Fig. 3, point-like is smeared slurry 300 and is comprised 7 fonts and smear oar 301 and circular point-like smears slurry 302, and the corner that oar 301 is arranged at the back side of production board 200 smeared in 7 fonts, and circular point-like smears the middle part that slurry 302 is distributed in production board 200.
Smear 7 fonts in the corner at production board 200 back side and smear oar 301, production board 200 and exterior wall 100 have adhesion stress with vertical direction in the horizontal direction, also have vertical supporting power, define corner supporting plane stress system, make production board 200 each to uniform force; Smear circular point-like in plate and smear the bonding that slurry 302 further enhances production board 200 and exterior wall 100.
Refer to Fig. 1 and Fig. 2, in the present embodiment, production board 200 is exterior wall 100 integrative energy-saving and decorative plate, and exterior wall 100 integrative energy-saving and decorative plate comprises interconnective panel 201 and warming plate 202.
This mounting structure also comprises the snap fit of L shape, between the insertion panel 201 of the L shape of snap fit and warming plate 202.
Exterior window trim, parapet are beared down on one, exterior wall 100 plate at external corner place, the snap fit of L shape can be adopted to strengthen fixing, make overall structure more firm, sheet material difficult drop-off.
Refer to Fig. 1, between two adjacent production boards 200, be provided with fluid sealant 203.By arranging fluid sealant 203, well two adjacent production boards 200 can be connected sealing, improve the fixing of mounting structure, improve integrally-built weatherability.
In addition, at the splicing tape edge of two production boards 200, polyethylene foamed pole 204 can be set near the position of exterior wall 100, and then fluid sealant 203 is set, by firm for the sealing of the splicing tape edge of two production boards 200.
Refer to Fig. 1 ~ Figure 11, the construction technology concrete technology flow process of the mounting structure of this dalle is as follows:
Preparation of construction:
1, special construction plan, demand schedule for employment, material planning, schedule organizing construction is worked out.
2, carry out surveying setting-out according to special construction plan, design drawing, whether planar substrate situation, each absolute altitude, the size at various hole, position are checked and adjusted typesetting.Pinpoint the problems and propose in time, solve.
3, check whether vertical transport facility meets the demands, and whether work well, material and accessory will be purchased to scene, and qualified by inspection after, correctly stack.Debugging efforts preparation etc. carried out by material facility.
4, carry out site technology to tell somebody what one's real intentions are.
Base course wall process:
Integrated board anchoring construction, lower to basic level requirement, anchor can be passed through, pad adjustment planeness, verticality, negative and positive angle Founder are straight, but within deviation can be controlled in 30mm, reduce the labour intensity of basic unit's operation.
Snap the line setting-out typesetting:
According to typesetting figure, from big angle, horizontal direction and the equal snap the line of vertical direction, logical every layer, the line of horizontal direction must one or more, and logical line must close, two, each angle of logical line of vertical direction, the each bar frame bar of bullet again, calculates the vertical typesetting situation in each face, then calculates the horizontal typesetting situation in each face, in process of typeset, there is the lines space of a whole page of below 50mm width in strict control; Hole, concavo-convex edge line lines, as adjusted, must adjust before sticky anchor.
The processing of production board 200 scene:
According to designed typesetting figure, to dalle cutting, obtain production board 200.
According to the typesetting figure at scene, calculate the quantity of all size of every one deck.Utilize mounted cutting machine, auger, vacuum cleaner, the plant equipment such as general expression portable cutter, by material list processing cutting, then use each drill two holes of auger upper and lower side, and isolated edge 15 cm (position consistency, dark: 25-30mm); The sheet material of inner corner trim, larger one piece, excises the thickness (as: 36mm) of integrated board, is rejected by warming plate 202 with small scoop by warming plate 202; The sheet material of drip, warming plate 202 is excised 15mm by drip place, is rejected by warming plate 202 with small scoop; The sheet material of exterior window trim, also excises the thickness of integrated board by warming plate 202.
The processing of production board 200 can organize batch production streamline to process, and according to specification and shape that typesetting figure adjusts sheet material, greatly reduces the waste of material, decreases the round transport of material.
Anchoring piece 400 is installed:
Anchoring piece 400 comprises the anchor slab 401 of L shape, a side of anchor slab 401 is provided with clip 402, anchor slab 401 and clip 402 are slidably connected, anchor slab 401 can be slided and is fixedly connected with exterior wall 100 by screw on exterior wall 100, clip 402 is provided with the fin 403 that two bearing of trends are contrary, the two ends up and down of production board 200 are respectively arranged with hole, and two fins 403 can insert in the hole of two adjacent production boards 200 respectively.
When anchoring piece 400 is installed, according to the frame bar ejected and the good hole position (side 150mm is to anchor slab 401 center line) of sheet fabrication, with cement steel screw (50mm is long to be advisable), by anchor slab 401 upward, anchor slab 401 can up-down adjustment, adjustment anchor slab 401 to same level line, at the back side, side of anchor slab 401, clip 402 is installed, adjustment clip 402 is in the position in vertical wall direction, anchor slab 401 is fixing with on exterior wall 100 by screw, the fin of two on clip 402 403 is inserted respectively in the hole of two adjacent production boards 200.
Clip 402 can block production board 200 and can be fixed on exterior wall 100 by adjacent two production boards 200, smear slurry 300 by point-like again to bond, larger vertical supporting power and multiple grip force is subject to when production board 200 is connected with exterior wall 100, form polynary stress system, also it is firm to connect between adjacent two production boards 200, thus make production board 200 very firm with the connection of exterior wall 100, difficult drop-off.
First row anchoring piece 400 is below installed, on adjustment anchor slab 401 to same level line, after first row anchoring piece 400 is installed and is fixed, installing second row, the 3rd above more successively arranges until last row's anchor slab 401, anchor slab 401 all upward, except the anchoring piece 400 of first row is fixing, other respectively row only install, do not fix.
All bored two holes up and down because production board 200 adds man-hour, upper and lower clip 402 all will be inserted in upper and lower two holes, needs when pasting production board 200, the position of up-down adjustment anchoring piece 400, then when installing with screw, is difficult in the same horizontal line.
Paste production board 200:
1, prepare adhesive mortar: special adhesive mortar, by the proportions of special messenger by regulation, stirs with electric mixer, amount of preparation is advisable to be finished in 2-3 hour, if having overdrying phenomenon in use, suitably can add 801 glue and again stir.The material composition of adhesive mortar: silty sand, 32.5 cement, 801 glue.
2, utilize vertical transport equipment, the sheet material processed is transported to construction floor, vertically lean to body of wall and place, do not keep flat, this room need be cleaned out.
3, adhesive mortar is coated with: oar smeared in seven fonts first smearing 50-60mm wide in corner, production board 200 bottom surface; Lay bonding point at the plate heart by plum blossom row again, namely circular point-like smears slurry 302, its spacing 150mm-200mm, diameter 200mm, apart from frame 50-150mm; The position of metope institute pasting board is spread upon by this requirement, more convenient to operate simple and direct.Production board 200 effectively bonding area is about 50%.
4, production board 200 is installed and is pasted: first paste first row plate below, when the sheet material having scraped adhesive mortar is pasted toward metope, according to the installation position line that metope ejects, firmly press toward metope equably, guarantee that adhesive mortar contacts with metope closely, and the hole of two is below inserted in corresponding clip 402, according to the planar smoothness control line drawn, control planeness well, second row anchoring piece 400 corresponding more down adjusts position, clip 402 is inserted in corresponding aperture, if clip 402 can not directly in patchhole, clip 402 position can be regulated, after installation pastes, anchor slab 401 and clip 402 are fixed.Construct successively again.Go up most a row sheet material top to fix, utilize another anchor structure, be the snap fit of L-type, after installation pastes and goes up row's sheet material most, install the snap fit of fixed L type at parapet end face, snap fit inserts in panel 201 and warming plate 202.
5, detailed treatment: drip, exterior window trim, parapet bear down on one, external corner, during the sheet fabrication of drip, the length of lower tip cut-off warming plate 202: thickness of slab+15mm; The sheet material that exterior wall 100 is corresponding with two sides of exterior window trim, adding the length of excising warming plate 202 man-hour is the thickness of sheet material; It is the thickness of sheet material that window sill adds the length of excising warming plate 202 man-hour; Parapet coping adds the thickness+10mm that the length of excising warming plate 202 man-hour is sheet material; The external corner plate sheet material that wherein area is large, adding the length of excising warming plate 202 man-hour is the thickness of sheet material.All root out with putty during stickup.Exterior window trim, parapet bear down on one, the exterior wall at external corner place 100 plate is all strengthened fixing with the snap fit of L shape, and snap fit inserts in panel 201 and warming plate 202.
6, plate seams and puts: horizontal direction plate seam 10-14mm, vertical direction plate seam 6-10mm, individual plates area is large, and plate seam takes large values, and single-block area is few, and plate seam gets the small value, and can adjust when typesetting, eliminates bar Yangtze plate as far as possible.
7, inspection of quality: flush with adjacent exterior wall 100 integrative energy-saving and decorative plate, planeness and verticality is checked at any time with 2M guiding ruler and cable inlet bracket, notice during haftplatte that adhesive mortar does not overflow edges of boards edge, if overflow to use in time and touch cloth cleaning, make between plate and plate without " ash of meeting and discussing ", plate seam (horizontal direction 12mm, vertical direction 8mm are advisable, and can adjust when typesetting) splicing rationally.Adjacent each plate is corrected simultaneously, the relative flatness of adjacent panels and plate seam width are adjusted.Check and correction periphery reference line and surfacing control line is noted during installation.If there is pressing excessively, when plate face is starkly lower than planeness datum, plate need be removed rear benefit and scrape adhesive mortar and re-start stickup.Ensure that the position of plate is accurate, angle is suitable, firmly smooth.Should be noted: when sheet material is installed, the hole of upper end will insert in mounted corresponding anchoring piece 400 clip 402.
Plate seam note fluid sealant:
After integrated board adjustment, stickup, after mortar bonding agent drying to be bonded, just can take away the cushion block between plate seam and cross clip chi, deburring process is carried out to wall limit, top, bottom etc.
Plate face is cleaned totally, and inject the materials such as jointing agent in the gap between production board 200, injecting should in conjunction with the construction thickness of design drawing attentional manipulation jointing agent, full, can not have space or bubble, grey cutter should at the uniform velocity move along seam, and extruding jointing agent strength also should be even; Jointing agent too thin being unfavorable for ensures airtight quality and prevents rain leakage, and the tensile stress produced expanding with heat and contract with cold because of exterior wall 100 integrative energy-saving and decorative plate is also unfavorable; But can not be too thick, when jointing agent is by pulling force, be too thickly easily pulled off destruction, sealing and antiseep were lost efficacy.
When breaking fluid sealant 203, first the diaphragm of assembled for production board 200 tape edge is uncovered 150mm, paper self-adhesive tape is sticked in the requirement according to glue-line width.To get the jump in dividing joint with sealing and stamp fluid sealant 203 evenly in right amount, then strike off fluid sealant 203 with flat scraper, require that fluid sealant 203 thickness is onboard 2-4mm, the degree of depth in dividing joint is not less than 3mm.After applying glue, paper self-adhesive tape is pulled off.The time that paper self-adhesive tape is pasted onto on plate face must not more than 2 hours.In order to avoid cause the destruction of plate top-coat paint film.Green pepper seam width difference is not less than 2mm, without vestige, without dirt, smoothly straight.
The cleaning of plate face, examination:
In work progress, the glue-line, panel etc. of External Wall 100 takes safeguard measure, after fluid sealant 203 solidifies and reaches and should have intensity, takes diaphragm off in time and by eliminating impurities, cleans plate face simultaneously, and guards against and scratch plate face, carries out civilized construction.
Behind clean surface, whether smooth, vertical harmonizing yinyang angle, inspection plate face be upright.To undesirable timely replacing.
To sum up, the mounting structure of the dalle that the utility model embodiment provides, has the following advantages:
1, two clips: anchoring piece 400 clip 402 blocks integrated board; Bonding slurry is smeared at production board 200 back side, is combined into multiple compound clip 402 blocks integrated board with the integrated board back side one word groove, and the clamp card jail integrated board of diplobiont system, makes plate be subject to larger vertical supporting power and multiple grip force.
2, point-like is smeared slurry 300 and is bondd: slurry smeared in 7 fonts smearing point-like in back corner, and production board 200 and body of wall have adhesion stress with vertical direction in the horizontal direction, also have vertical supporting power, define corner supporting plane stress system, make sheet material respectively to uniform force; Smear circular point-like in plate and smear the bonding that slurry 302 further enhances wall and plate.
3, repeatedly superimposed: to form adhesion for the first time superimposed by extrude for warming plate 202 and panel 201; Corner smear 7 fonts smear slurry and other circular point-like smear slurry 302, multiple spot paste, multiple spot is stressed, forms many adhesion stresss secondary superimposed; Integrated board back side in-line groove, makes corner smear 7 fonts and smears oar 301 and circular point-like and smear slurry 302 and embed in integrated board, form multiple clamp, forms solid space three times superimposed; The clip 402 of upper and lower two ends anchoring piece 400 is jointly stressed with point-like glue card, forms many hinges four times superimposed; Stress system is made to become polynary stress system.
4, matrices stress system: above-mentioned four times superimposed, make integrated board and exterior wall 100 form diversification and link, define complicated matrices stress system.This some processes, make the fixation that bonds of heat-insulation/decoration integrated plate and exterior wall 100 reliable, can not come off and hurt sb.'s feelings, substantially prolongs the application life of skin 100 ornament materials, its cycle in application life is almost consistent with building structure life cycle, solve exterior wall 100 external heat insulation cementing bulk and hold a caducous building circle difficult problem, also solve the building circle difficult problem (be only 1/3rd) of application life much smaller than building structure life cycle for constructure decorative material simultaneously, avoid secondary in use, even repeatedly transform decoration three times.
5, point pasting method: exterior wall 100 bulk decoration construction practices well is: completely paste method.Can adopt empty subsides method after adopting anchoring piece 400, smear slurry rate about 50%, paste materials can save about 50%.
6, Double layer thermal insulation layer is defined: integrated board is heat preserving and insulating material inherently, utilize this engineering method to construct, point-like is smeared slurry 300 and integrated board and exterior wall 100 basic unit is separated, and forms an air layer space, air layer also plays function of heat insulation, makes exterior wall 100 better heat preservation; Also environmental protection construction category is belonged to.
In description of the present utility model, it will be appreciated that, term " " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", " on ", D score, " front ", " afterwards ", " left side ", " right side ", " vertically ", " level ", " top ", " end " " interior ", " outward ", " clockwise ", orientation or the position relationship of the instruction such as " counterclockwise " are based on orientation shown in the drawings or position relationship, only the utility model and simplified characterization for convenience of description, instead of indicate or imply that the equipment of indication or element must have specific orientation, with specific azimuth configuration and operation, therefore can not be interpreted as restriction of the present utility model.
In addition, term " first ", " second " only for describing object, and can not be interpreted as instruction or hint relative importance or imply the quantity indicating indicated technical characteristic.Thus, be limited with " first ", the feature of " second " can express or impliedly comprise one or more these features.In description of the present utility model, the implication of " multiple " is two or more, unless otherwise expressly limited specifically.
In the utility model, unless otherwise clearly defined and limited, the term such as term " installation ", " being connected ", " connection ", " fixing " should be interpreted broadly, and such as, can be fixedly connected with, also can be removably connect, or integral; Can be mechanical connection, also can be electrical connection; Can be directly be connected, also indirectly can be connected by intermediary, can be the connection of two element internals or the interaction relationship of two elements.For the ordinary skill in the art, the concrete meaning of above-mentioned term in the utility model can be understood as the case may be.
In the utility model, unless otherwise clearly defined and limited, fisrt feature second feature it " on " or D score can comprise the first and second features and directly contact, also can comprise the first and second features and not be directly contact but by the other characterisation contact between them.And, fisrt feature second feature " on ", " top " and " above " comprise fisrt feature directly over second feature and oblique upper, or only represent that fisrt feature level height is higher than second feature.Fisrt feature second feature " under ", " below " and " below " comprise fisrt feature immediately below second feature and tiltedly below, or only represent that fisrt feature level height is less than second feature.
The foregoing is only preferred embodiment of the present utility model, be not limited to the utility model, for a person skilled in the art, the utility model can have various modifications and variations.All within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (10)

1. the mounting structure of a dalle, it is characterized in that, comprise the production board being installed on exterior wall, described production board and described exterior wall are smeared to starch by some point-like and are bondd, be provided with anchoring piece between described production board and described exterior wall, described production board is fixedly connected with by described anchoring piece with described exterior wall.
2. the mounting structure of dalle according to claim 1, it is characterized in that, described anchoring piece comprises the anchor slab of L shape, described anchor slab is fixedly connected with described exterior wall, a side of described anchor slab is provided with clip, described clip is provided with the fin that two bearing of trends are contrary, two described fins insert two adjacent production boards respectively.
3. the mounting structure of dalle according to claim 2, it is characterized in that, described anchor slab comprises base plate and side plate, described base plate is connected with described side plate and forms L shape, described base plate is provided with the first through hole of strip, be provided with screw in described first through hole, described base plate can be slided and is connected with described exterior wall by screw on described exterior wall.
4. the mounting structure of dalle according to claim 3, is characterized in that, described side plate and described clip are slidably connected.
5. the mounting structure of dalle according to claim 4, it is characterized in that, described clip comprises clamp, two described fins are arranged on the side of described clamp respectively, and extend along two rightabouts vertical with described clamp, described clamp is provided with the second through hole, described side plate is provided with screwed hole, described clamp and described side plate are connected by screw.
6. the mounting structure of dalle according to claim 1, is characterized in that, the back side of described production board is provided with in-line groove, and described point-like is smeared slurry and can be embedded in described in-line groove.
7. the mounting structure of dalle according to claim 1, it is characterized in that, described point-like is smeared slurry and is comprised 7 fonts and smear oar and circular point-like smears slurry, and the corner that oar is arranged at the back side of described production board smeared in described 7 fonts, and described circular point-like smears the middle part that slurry is distributed in described production board.
8. the mounting structure of dalle according to claim 1, is characterized in that, described production board is external wall energy-saving decoration integrated board, and described external wall energy-saving decoration integrated board comprises interconnective panel and warming plate.
9. the mounting structure of dalle according to claim 8, is characterized in that, also comprises the snap fit of L shape, inserting between described panel and described warming plate of the L shape of described snap fit.
10. the mounting structure of dalle according to claim 1, is characterized in that, is provided with fluid sealant between two adjacent described production boards.
CN201520678032.7U 2015-09-01 2015-09-01 Mounting structure of dalle Active CN204983517U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520678032.7U CN204983517U (en) 2015-09-01 2015-09-01 Mounting structure of dalle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520678032.7U CN204983517U (en) 2015-09-01 2015-09-01 Mounting structure of dalle

Publications (1)

Publication Number Publication Date
CN204983517U true CN204983517U (en) 2016-01-20

Family

ID=55117899

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520678032.7U Active CN204983517U (en) 2015-09-01 2015-09-01 Mounting structure of dalle

Country Status (1)

Country Link
CN (1) CN204983517U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089246A (en) * 2015-09-01 2015-11-25 湖南省第八工程有限公司 Installation structure and construction technology for decoration board

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089246A (en) * 2015-09-01 2015-11-25 湖南省第八工程有限公司 Installation structure and construction technology for decoration board

Similar Documents

Publication Publication Date Title
EP3269895A1 (en) Metal roofing material, and roofing structure and roofing method using same
CN106284706A (en) The construction method of external wall outer insulation rock cotton board
CN203795655U (en) Keel partition wall
CN111305410B (en) Anti-cracking wall and construction method thereof
CN104912275A (en) Integrated external wall insulation decorating plate structure and construction technology thereof
CN102140848A (en) Expansion joint-adjustable dual-waterproof installation construction process
CN107489216B (en) A kind of composite plate cell cube and its curtain wall system and mounting process
CN105625650B (en) A kind of parapet of roofing flashing protective layer construction method
CN204983517U (en) Mounting structure of dalle
CN111608280A (en) External wall heat insulation construction method
CN105089246A (en) Installation structure and construction technology for decoration board
CN204662719U (en) A kind of indoor seamless spliced secondary light partition wall system
CN106759993A (en) A kind of external heat insulating wall and construction method
CN211523726U (en) Be applied to reentrant corner module of assembly fitment furred ceiling of building engineering
CN108083740A (en) Mortar and the two-in-one compound material of putty and preparation method thereof
CN211473152U (en) Energy-saving building decorative plate
CN103711208A (en) Heat reflection heat-insulation energy-saving system for outer wall and manufacturing method thereof
CN208858174U (en) A kind of double-layer brick is laid bricks device
CN205777216U (en) A kind of press strip anchoring type integration is combined veneer construction assembling structure
CN207314721U (en) Integrated exterior wall board mounting structure
CN105019633A (en) New-technology wallpaper-groove stitching structure
CN215166947U (en) Waterproof stone curtain wall mounting structure
CN104018591A (en) Mechanized construction method for wall thermal insulation
CN218597608U (en) Dry-hanging type ceramic tile installation structure
CN205637437U (en) Wall wraps mounting structure who lays one's hand on skin firmly

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant