CN204960272U - Heavy -calibre well embeds hanging scaffold - Google Patents

Heavy -calibre well embeds hanging scaffold Download PDF

Info

Publication number
CN204960272U
CN204960272U CN201520687678.1U CN201520687678U CN204960272U CN 204960272 U CN204960272 U CN 204960272U CN 201520687678 U CN201520687678 U CN 201520687678U CN 204960272 U CN204960272 U CN 204960272U
Authority
CN
China
Prior art keywords
rigid platfor
well
buried frame
borehole wall
frame pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520687678.1U
Other languages
Chinese (zh)
Inventor
马天华
安世泽
张恒
廖禄云
王向东
刘文涛
王成锋
谢腾蛟
王显伟
邹维勇
周灵
徐江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Geological Engineering Exploration Institute Group Co., Ltd.
Original Assignee
SICHUAN INSTITUTE OF GEOLOGICAL ENGINEERING INVESTIGATION
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN INSTITUTE OF GEOLOGICAL ENGINEERING INVESTIGATION filed Critical SICHUAN INSTITUTE OF GEOLOGICAL ENGINEERING INVESTIGATION
Priority to CN201520687678.1U priority Critical patent/CN204960272U/en
Application granted granted Critical
Publication of CN204960272U publication Critical patent/CN204960272U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to a heavy -calibre well embeds hanging scaffold, including setting up below the well head three horizontally rigidity platform and a template layer rigidity platform of 3-5 meters, template layer rigidity platform sets up on the rigidity platform, the rigidity platform is equipped with pre -buried a set of pipe with the wall of a well and fixes. The utility model discloses compare in traditional scaffold braced system, hanging scaffold braced system practices thrift more than 50% in the consumption of NULL, duration of a project, manpower etc. And the well is darker, the bore is big more, and the saving degree is high more, the safe risk greatly reduced of construction, and the improvement efficiency of construction has better economic benefits.

Description

The built-in flying scaffold of large-diameter well
Technical field
The utility model relates to a kind of scaffold, the built-in flying scaffold of especially a kind of large-diameter well.
Background technology
At present, in all kinds of engineering construction, the well lid making of large-diameter well (as pressure well, sewage valve pit, collecting well etc.) is the difficult point in construction process always, its degree of depth is large, bore is large, load is large, the concrete feature adopting cast-in-place structural more, cause traditional well lid to make being adopting from bottom from lower to upper intensive steel pipe scaffold of setting up to support the template of well lid cast-in-situ concrete.The shortcoming of this support system be the material consumption amounts such as steel tube fastener large, take and tear that engineering quantity is large, the duration of a project long, manpower consumption amount is large, security risk is high open, it needs a large amount of human and material resources, financial resources to ensure carrying out smoothly of engineering.
Utility model content
In order to overcome the deficiency that in traditional well lid manufacturing process, steel concrete shuttering bracing frame is set up, the utility model provides a kind of large-diameter well built-in flying scaffold.
The utility model solves the technical scheme that its technical problem adopts: the built-in flying scaffold of large-diameter well, comprises, and is arranged at rigid platfor and a template layer rigid platfor of three levels of 3 ~ 5 meters, below well head; Template layer rigid platfor is arranged on rigid platfor;
Described rigid platfor and the borehole wall are fixed by the one group of pre-buried frame pipe be provided with, and pre-buried frame pipe inserts in the borehole wall by the preformed hole level that the borehole wall is provided with, and its degree of depth inserted in the borehole wall is more than 2/3rds of thickness of shaft wall; Often organizing pre-buried frame pipe in same level is uniformly distributed perpendicular to the borehole wall; Be provided with oblique drawbar between neighbouring two groups pre-buried frame pipes to connect, pre-buried frame pipe and oblique drawbar are connected and fixed by fastener, and the angle of the pre-buried frame pipe of described oblique drawbar and level is 60 ° ~ 80 °; Template layer rigid platfor is with between rigid platfor, be fixedly connected with by standard staging between the rigid platfor of three levels.
The beneficial effects of the utility model are, compared to traditional scaffold support system, flying scaffold support system saves more than 50% in the consumption of material usage, duration of a project, manpower etc., well is darker, bore is larger, saving degree is higher, the security risk of construction reduces greatly, greatly improves efficiency of construction, has good economic benefit.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is pre-buried frame pipe schematic diagram of the present utility model.
Component and numbering in figure:
1-rigid platfor; 2-template layer rigid platfor; The pre-buried frame pipe of 3-; 4-oblique drawbar.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is further illustrated.
As shown in Figures 1 to 3, the built-in flying scaffold of large-diameter well, comprises, and is arranged at rigid platfor 1 and a template layer rigid platfor 2 of three levels of 3 ~ 5 meters, below well head; Template layer rigid platfor 2 is arranged on rigid platfor 1;
Described rigid platfor 1 is fixed by the one group of pre-buried frame pipe 3 be provided with the borehole wall, and pre-buried frame pipe 3 inserts in the borehole wall by the preformed hole level that the borehole wall is provided with, and its degree of depth inserted in the borehole wall is more than 2/3rds of thickness of shaft wall; Often organizing pre-buried frame pipe 3 in same level is uniformly distributed perpendicular to the borehole wall; Be provided with oblique drawbar 4 between neighbouring two groups pre-buried frame pipes 3 to connect, pre-buried frame pipe 3 is connected and fixed by fastener with oblique drawbar 4, and described oblique drawbar 4 is 60 ° ~ 80 ° with the angle of the pre-buried frame pipe 3 of level; Between template layer rigid platfor 2 with rigid platfor 1, be fixedly connected with by standard staging between the rigid platfor 1 of three levels.
Implementation process:
The dynamic and static load that need carry according to flying scaffold before one, setting up and the bearing capacity at single reserved scaffold borehole wall place, calculate large-diameter well borehole wall preformed hole quantity, safety factor gets 2.
Two, the preformed hole of pre-buried frame pipe 3 is arranged under well lid within the scope of 3 ~ 5 meters, is three layers, and also visual manhole cover plate load is determined after calculating, and can increase or reduce; Interlamellar spacing is 1 ~ 1.5 meter.Every layer of preformed hole all at grade, perpendicular to the borehole wall, is uniformly distributed.
Three, the aperture of the preformed hole of the borehole wall is greater than the outer through 2mm of pre-buried frame pipe 3, and the reserved degree of depth is not less than 2/3rds of thickness of shaft wall.
Four, an interspersed pre-buried frame pipe 3 in each preformed hole, pre-buried frame pipe 3 adopts standard staging pipe, length about 1 meter, is convenient to remove and recycling, and pre-buried frame pipe 3 inserts for thickness of shaft wall in the borehole wall 2/3rds, exposes 0.6 meter inside the borehole wall.
Five, undermost rigid platfor 1 is set up with pre-buried frame pipe 3 in the plane for starting point.
A, every layer of reserved steel pipe standard staging and pre-buried frame pipe 3 to be coupled to each other, to form an entirety, form undermost rigid platfor 1.
B, with standard staging pipe, surrounding in well is connected into quadra, as shown in Figure 2.
C, the pre-buried frame pipe 3 of this quadra and the borehole wall of last layer to be connected by oblique drawbar 4 is oblique, the stability of the bar quadra described in increase and vertical bearing capacity.
D, on described quadra, set up transverse direction, vertical levels joint steel pipe, each 1 meter of spacing, as Fig. 1, form the rigidity platform 1 of the second layer.
Six, repeat after above-mentioned steps, complete setting up of third layer rigid platfor 1 and template layer rigid platfor 2.
Seven, after hound is put up, template is laid at scaffold top, carries out that passs is molded makes reinforcing bar and pouring concrete, completes well lid making.
The utility model is compared to traditional scaffold support system, flying scaffold support system saves more than 50% in the consumption of material usage, duration of a project, manpower etc., well is darker, bore is larger, saving degree is higher, construction safety risk reduces greatly, greatly improve efficiency of construction, and realize good economic benefit.

Claims (1)

1. the built-in flying scaffold of large-diameter well, is characterized in that, comprise, and is arranged at rigid platfor (1) and a template layer rigid platfor (2) of three levels of 3 ~ 5 meters, below well head; Template layer rigid platfor (2) is arranged on rigid platfor (1);
Described rigid platfor (1) is fixed by the one group of pre-buried frame pipe (3) be provided with the borehole wall, and pre-buried frame pipe (3) is inserted in the borehole wall by the preformed hole level that the borehole wall is provided with, and its degree of depth inserted in the borehole wall is more than 2/3rds of thickness of shaft wall; Often organizing pre-buried frame pipe (3) in same level is uniformly distributed perpendicular to the borehole wall; Be provided with oblique drawbar (4) between neighbouring two groups pre-buried frame pipes (3) to connect, pre-buried frame pipe (3) and oblique drawbar (4) are connected and fixed by fastener, and described oblique drawbar (4) is 60 ° ~ 80 ° with the angle of the pre-buried frame pipe (3) of level; Between template layer rigid platfor (2) with rigid platfor (1), be fixedly connected with by standard staging between the rigid platfor (1) of three levels.
CN201520687678.1U 2015-09-08 2015-09-08 Heavy -calibre well embeds hanging scaffold Expired - Fee Related CN204960272U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520687678.1U CN204960272U (en) 2015-09-08 2015-09-08 Heavy -calibre well embeds hanging scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520687678.1U CN204960272U (en) 2015-09-08 2015-09-08 Heavy -calibre well embeds hanging scaffold

Publications (1)

Publication Number Publication Date
CN204960272U true CN204960272U (en) 2016-01-13

Family

ID=55055346

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520687678.1U Expired - Fee Related CN204960272U (en) 2015-09-08 2015-09-08 Heavy -calibre well embeds hanging scaffold

Country Status (1)

Country Link
CN (1) CN204960272U (en)

Similar Documents

Publication Publication Date Title
CN103205965B (en) Root pressure grouting pile and construction method thereof
CN104775447B (en) Composite base framework used for power transmission tower in steep mountainous area and construction technology thereof
CN204151823U (en) Along building the one-sided cantilever hydraulic template trolley of side wall under covered back-digging structural slab
CN205676882U (en) A kind of novel supporting construction
CN106988319A (en) A kind of rapid constructing method of large deep foundation pit agent structure side wall
CN103122642A (en) Construction method of vertical post support change
CN205024719U (en) Pile foundation and integrated reverse construction vertical braces system of underground continuous wall
CN202247938U (en) Wedge-shaped foundation bolt preformed hole core formwork device
CN204960272U (en) Heavy -calibre well embeds hanging scaffold
CN203066083U (en) Supporting structure for two adjacent foundation pits
CN205975995U (en) Cast -in -place concrete floor indent steel tube frame
CN205776259U (en) A kind of deep basal pit retaining wall one side formwork constructing device
CN204679074U (en) A kind of novel surface observation pier structure
CN204080820U (en) A kind of concrete structure foundation ditch support replacement device
CN104652426B (en) A kind of saline soil area waterglass anticorrosion pile foundation construction method
CN103993612B (en) A kind of construction method of underwater concrete cushion cap
CN206722392U (en) A kind of structure of transvers plate of shear wall structure
CN105908773A (en) Two-stage socketed pile wind turbine foundation for shallow covering stratum foundation of offshore wind plant and construction method
CN203848836U (en) Column type marking pier
CN207392752U (en) For preventing the constructing device of grout leakage of formwork root
CN205857792U (en) Shear wall concrete replacement bottom provisions for grouting
CN205712162U (en) Marine wind electric field shallow overburden ground two-stage embedded rock pile blower foundation
CN205656170U (en) Sounding pipe's water injection device in steel core concrete column
CN206279534U (en) A kind of subway foundation pit building enclosure
CN205421332U (en) Contrary coincide underground continuous wall that does of a core section of thick bamboo

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 610072 No. 119 Xiqing Road, Chengdu City, Sichuan Province

Patentee after: Sichuan Geological Engineering Exploration Institute Group Co., Ltd.

Address before: 610072 No. 119 Xiqing Road, Chengdu City, Sichuan Province

Patentee before: Sichuan Institute of Geological Engineering Investigation

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160113

Termination date: 20200908

CF01 Termination of patent right due to non-payment of annual fee