CN204940201U - 一种高桩码头的施工结构 - Google Patents
一种高桩码头的施工结构 Download PDFInfo
- Publication number
- CN204940201U CN204940201U CN201520747464.9U CN201520747464U CN204940201U CN 204940201 U CN204940201 U CN 204940201U CN 201520747464 U CN201520747464 U CN 201520747464U CN 204940201 U CN204940201 U CN 204940201U
- Authority
- CN
- China
- Prior art keywords
- pile
- taper pile
- cushion cap
- taper
- wharf
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 15
- 239000010959 steel Substances 0.000 claims abstract description 15
- 238000010276 construction Methods 0.000 abstract description 3
- 238000011065 in-situ storage Methods 0.000 abstract description 3
- 230000000694 effects Effects 0.000 abstract description 2
- 238000000034 method Methods 0.000 abstract description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本实用新型涉及高桩码头领域,具体为一种高桩码头的施工结构。该施工结构包括:码头承台、码头前沿垂直桩、斜桩、中间垂直桩,具体结构如下:码头承台的底部靠近码头前沿处设置码头前沿垂直桩,码头承台的底部中间部分设置中间垂直桩,码头承台的底部外侧设置斜桩,斜桩为钢管桩,形成斜桩与码头前沿垂直桩和中间垂直桩的配合结构。现浇混凝土桩,只能做成垂直桩,采用钢管桩的没有先例。而且钢管桩可以做成斜桩,斜桩可以有效地控制码头承台的平移,对于码头承台的稳定起到了至关重要的作用。采用本实用新型的施工结构,其工艺简单,易于施工,工期短。
Description
技术领域
本实用新型涉及高桩码头领域,具体为一种高桩码头的施工结构。
背景技术
在地处北方海洋工程码头泊位基础建设中,按着惯例都采用沉箱式或者重力块式,也有采用高桩式的,但都是采用现浇混凝土桩。高桩码头是我国重要的基础设施,但是高桩码头位于前沿的基桩容易受到靠泊船舶撞击而失去作用,使得对高桩码头的施工要求越来越高。
实用新型内容
本实用新型的目的在于提供一种高桩码头的施工结构,以增加码头承台的稳定性。
本实用新型的技术方案是:
一种高桩码头的施工结构,该施工结构包括:码头承台、码头前沿垂直桩、斜桩、中间垂直桩,具体结构如下:
码头承台的底部靠近码头前沿处设置码头前沿垂直桩,码头承台的底部中间部分设置中间垂直桩,码头承台的底部外侧设置斜桩,斜桩为钢管桩,形成斜桩与码头前沿垂直桩和中间垂直桩的配合结构。
所述的高桩码头的施工结构,斜桩分为前斜桩、后斜桩、左斜桩、右斜桩,码头承台的底部靠近码头前沿处设置前斜桩,码头承台的底部后面设置后斜桩,码头承台的底部左侧设置左斜桩,码头承台的底部右侧设置右斜桩,左斜桩和右斜桩相对设置,倾斜方向相反,前斜桩、后斜桩、左斜桩、右斜桩均为钢管桩,形成前斜桩、后斜桩、左斜桩、右斜桩与码头前沿垂直桩和中间垂直桩的配合结构。
所述的高桩码头的施工结构,码头前沿垂直桩、中间垂直桩均为钢管桩。
本实用新型的优点及有益效果是:
1、现浇混凝土桩,只能做成垂直桩,采用钢管桩的没有先例。而且钢管桩可以做成斜桩,斜桩可以有效地控制码头承台的平移,对于码头承台的稳定起到了至关重要的作用。
2、采用本实用新型的施工结构,其工艺简单,易于施工,工期短。
附图说明
图1为本实用新型的结构示意图之一。图中,1码头承台;2码头前沿垂直桩;3斜桩;4中间垂直桩。
图2为本实用新型的结构示意图之二。图中,1码头承台;2码头前沿垂直桩;4中间垂直桩;5前斜桩;6左斜桩;7右斜桩;8后斜桩。
具体实施方式
如图1所示,本实用新型高桩码头的施工结构,主要包括:码头承台1、码头前沿垂直桩2、斜桩3、中间垂直桩4等,具体结构如下:
码头承台1的底部靠近码头前沿处设置码头前沿垂直桩2,码头承台1的底部中间部分设置中间垂直桩4,码头承台1的底部外侧设置斜桩3,斜桩3为钢管桩,码头前沿垂直桩2、中间垂直桩4均为钢管桩。从而,斜桩3与码头前沿垂直桩2和中间垂直桩4配合使用,有效地控制码头承台1的平移,使码头承台1稳定。
如图2所示,本实用新型高桩码头的施工结构,主要包括:码头承台1、码头前沿垂直桩2、中间垂直桩4、前斜桩5、左斜桩6、右斜桩7、后斜桩8等,具体结构如下:
码头承台1的底部靠近码头前沿处设置码头前沿垂直桩2,码头承台1的底部中间部分设置中间垂直桩4,码头承台1的底部靠近码头前沿处设置前斜桩5,码头承台1的底部后面设置后斜桩8,码头承台1的底部左侧设置左斜桩6,码头承台1的底部右侧设置右斜桩7,左斜桩6和右斜桩7相对设置,倾斜方向相反。前斜桩5、左斜桩6、右斜桩7、后斜桩8均为钢管桩,码头前沿垂直桩2、中间垂直桩4均为钢管桩。从而,前斜桩5、后斜桩8、左斜桩6和右斜桩7与码头前沿垂直桩2和中间垂直桩4配合使用,可以更有效地控制码头承台1的平移,使码头承台1更加稳定。
Claims (3)
1.一种高桩码头的施工结构,其特征在于,该施工结构包括:码头承台、码头前沿垂直桩、斜桩、中间垂直桩,具体结构如下:
码头承台的底部靠近码头前沿处设置码头前沿垂直桩,码头承台的底部中间部分设置中间垂直桩,码头承台的底部外侧设置斜桩,斜桩为钢管桩,形成斜桩与码头前沿垂直桩和中间垂直桩的配合结构。
2.按照权利要求1所述的高桩码头的施工结构,其特征在于,斜桩分为前斜桩、后斜桩、左斜桩、右斜桩,码头承台的底部靠近码头前沿处设置前斜桩,码头承台的底部后面设置后斜桩,码头承台的底部左侧设置左斜桩,码头承台的底部右侧设置右斜桩,左斜桩和右斜桩相对设置,倾斜方向相反,前斜桩、后斜桩、左斜桩、右斜桩均为钢管桩,形成前斜桩、后斜桩、左斜桩、右斜桩与码头前沿垂直桩和中间垂直桩的配合结构。
3.按照权利要求1所述的高桩码头的施工结构,其特征在于,码头前沿垂直桩、中间垂直桩均为钢管桩。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520747464.9U CN204940201U (zh) | 2015-09-23 | 2015-09-23 | 一种高桩码头的施工结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520747464.9U CN204940201U (zh) | 2015-09-23 | 2015-09-23 | 一种高桩码头的施工结构 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204940201U true CN204940201U (zh) | 2016-01-06 |
Family
ID=55007643
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520747464.9U Expired - Fee Related CN204940201U (zh) | 2015-09-23 | 2015-09-23 | 一种高桩码头的施工结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204940201U (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115059063A (zh) * | 2022-07-22 | 2022-09-16 | 广州环投南沙环保能源有限公司 | 一种沉降较大桩基础及加固方法 |
-
2015
- 2015-09-23 CN CN201520747464.9U patent/CN204940201U/zh not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115059063A (zh) * | 2022-07-22 | 2022-09-16 | 广州环投南沙环保能源有限公司 | 一种沉降较大桩基础及加固方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204023578U (zh) | 双排桩支护结构 | |
CN201980397U (zh) | 一种船台水下滑道 | |
CN204940201U (zh) | 一种高桩码头的施工结构 | |
CN203977409U (zh) | 一种预制装配式混凝土桩基 | |
CN204492831U (zh) | 地铁暗挖隧道横通道施工构件 | |
CN202430726U (zh) | 正十字形自锁护坡混凝土砌块 | |
CN203978442U (zh) | 一种公铁合建水下隧道 | |
CN204940250U (zh) | 一种高桩码头钢管桩 | |
CN204530612U (zh) | 一种基坑围护型的沉箱码头结构 | |
CN203559398U (zh) | 一种简易水闸 | |
CN204530613U (zh) | 一种设有双壁围护墙的高桩码头结构 | |
CN202706043U (zh) | 钢管桩围堰锁扣 | |
CN202745058U (zh) | 一种预应力管桩内泥土清理工具 | |
CN102877453B (zh) | 一种水下抛石基床夯实装置 | |
CN204875811U (zh) | 一种复合式多排桩基坑支护结构 | |
CN201276707Y (zh) | 建筑基础长短组合桩桩基 | |
CN202557760U (zh) | 双壁钻孔灌注桩高桩承台坞墙结构 | |
CN203530995U (zh) | 一种水上铺排架 | |
CN203782505U (zh) | 一种地下道路、地面桥梁与高架桥梁的合建结构 | |
CN103276691B (zh) | 壁桩框架结构 | |
CN203796284U (zh) | 滑坡地段隧道支护结构 | |
CN204279891U (zh) | 一种双坞并联的中间坞墙结构 | |
CN204608829U (zh) | 一种安装快捷的新型挡土墙结构 | |
CN201850655U (zh) | 一种新旧建筑物t型连接器 | |
CN204225033U (zh) | 一种用于建构堤防的筑墙块 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |