CN204920317U - Workshop factory building device - Google Patents

Workshop factory building device Download PDF

Info

Publication number
CN204920317U
CN204920317U CN201520492534.0U CN201520492534U CN204920317U CN 204920317 U CN204920317 U CN 204920317U CN 201520492534 U CN201520492534 U CN 201520492534U CN 204920317 U CN204920317 U CN 204920317U
Authority
CN
China
Prior art keywords
factory building
main body
water tank
body factory
described main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520492534.0U
Other languages
Chinese (zh)
Inventor
吴光武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Hengtong Zhaoye Precision Machinery Co Ltd
Original Assignee
Chengdu Hengtong Zhaoye Precision Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Hengtong Zhaoye Precision Machinery Co Ltd filed Critical Chengdu Hengtong Zhaoye Precision Machinery Co Ltd
Priority to CN201520492534.0U priority Critical patent/CN204920317U/en
Application granted granted Critical
Publication of CN204920317U publication Critical patent/CN204920317U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Abstract

The utility model discloses a workshop factory building device includes: the main part factory building, main part factory building upper surface is equipped with first water tank, main part factory building lower surface is equipped with the second water tank, first water tank side middle part is equipped with the wash port, drain pipe one end with the wash port is connected, the drain pipe other end extends to in the second water tank, first water tank upper surface is equipped with solar cell panel and wind power generation ware, and temperature sensor fixes on the main part factory building inner wall, temperature sensor passes through control switch and is connected with the air conditioner, main part factory building side surface is equipped with one deck aluminium foil layer, has realized that the device is energy -concerving and environment -protective, and the cost is lower, the better technological effect of operational environment.

Description

A kind of production department factory building device
Technical field
The utility model relates to field of machining and machinebuilding technology, particularly relates to a kind of production department factory building device.
Background technology
In the prior art, the construction of production department or the construction cost of factory building are comparatively large, and the comfortable production department difficulty of built environment is larger, production department power consumption of the prior art is larger, and working environment is poor, as temperature is higher, producers' condition of work is caused to reduce.
In sum, present inventor, in the process realizing utility model technical scheme in the embodiment of the present application, finds that above-mentioned technology at least exists following technical problem:
In the prior art, it is comparatively large to there is power consumption in existing production department or factory building, and cost is higher, the technical problem that working environment is poor.
Utility model content
The utility model provides a kind of production department factory building device, and solving existing production department or factory building, to there is power consumption comparatively large, and cost is higher, the technical problem that working environment is poor, achieve device energy-conserving and environment-protective, cost is lower, the good technique effect of working environment.
For solving the problems of the technologies described above, the embodiment of the present application provides a kind of production department factory building device, and described device comprises:
Main body factory building, described main body factory building is rectangular-shaped, described main body factory building inside is hollow-core construction, described main body factory building upper surface is provided with the first water tank, described main body factory building soffit is provided with the second water tank, described first water tank upper surface is net structure, drain hole is provided with in the middle part of described first water tank side, screen pack is provided with in described drain hole, gutter one end is connected with described drain hole, the described gutter other end extends in described second water tank, supervisor one end is positioned at described second water tank, all be connected with N number of arm after described supervisor's other end is connected with water pump, described first water tank upper surface is provided with solar panel and wind turbine generator, battery is provided with in described main body factory building, described solar panel is all connected with described battery with described wind turbine generator, described main body factory building side is provided with M steam vent, described N, M is the positive integer being more than or equal to 1, ventilation fan is provided with in described steam vent, temperature pick up is fixed on described main body factory building inwall, described temperature pick up is connected with air-conditioning by gauge tap, described main body factory building side exterior surface is provided with one deck aluminium foil layer.
Wherein, described main body factory building adopts angle steel to make, and described main body factory building surface scribbles rustproof paint.
Wherein, described first water tank is identical with described second tank size, the upper surface size of described first water tank and the upper surface of described main body factory building measure-alike, described second water tank is embedded in below earth's surface.
Wherein, described N number of arm is evenly distributed in described main body factory building, and described arm is provided with water valve.
Wherein, in described main body factory building, upper surface is provided with LED illumination lamp, and described LED illumination lamp is connected with described battery.
Technical scheme in above-mentioned the embodiment of the present application, at least has following technique effect or advantage:
Owing to have employed the production department factory building apparatus design of energy-conserving and environment-protective as comprising: main body factory building, described main body factory building is rectangular-shaped, described main body factory building inside is hollow-core construction, described main body factory building upper surface is provided with the first water tank, described main body factory building soffit is provided with the second water tank, described first water tank upper surface is net structure, drain hole is provided with in the middle part of described first water tank side, screen pack is provided with in described drain hole, gutter one end is connected with described drain hole, the described gutter other end extends in described second water tank, supervisor one end is positioned at described second water tank, all be connected with N number of arm after described supervisor's other end is connected with water pump, described first water tank upper surface is provided with solar panel and wind turbine generator, battery is provided with in described main body factory building, described solar panel is all connected with described battery with described wind turbine generator, described main body factory building side is provided with M steam vent, described N, M is the positive integer being more than or equal to 1, ventilation fan is provided with in described steam vent, temperature pick up is fixed on described main body factory building inwall, described temperature pick up is connected with air-conditioning by gauge tap, described main body factory building side exterior surface is provided with the technical scheme of one deck aluminium foil layer, namely solar panel and wind turbine generator generating is utilized, then charge a battery, for workshop provides electric energy, energy-conserving and environment-protective, and be provided with the first water tank at main body factory building upper surface, when rainy, first water tank is collected rainwater, when the rainwater collected is greater than a half of tank height, unnecessary rainwater is transferred to the second water tank by gutter, water in second water tank can be supplied to the production and application in workshop by water pump and arm, energy-conserving and environment-protective, and also surplusly in the first water tank have half chests water, when the sun from directly over irradiate time, water in first water tank can absorb heat, keep nice and cool in factory building, avoid directly being heated, and be provided with temperature pick up, when temperature is higher, as more than 25 degrees Celsius, at this moment the temperature pre-set has been exceeded, then gauge tap controls air-conditioning work, lower the temperature in factory building, safeguard work amenity, and be provided with in exhaust fan guarantee factory building with fresh air, and be also provided with aluminium foil layer, can reflect Yanguan Pass, unnecessary reflect heat is gone out, avoiding factory building to absorb unnecessary thermal conductance, to cause temperature too high, so, efficiently solving existing production department or factory building, to there is power consumption larger, cost is higher, the technical problem that working environment is poor, and then achieve device energy-conserving and environment-protective, cost is lower, the good technique effect of working environment.
Accompanying drawing explanation
Fig. 1 is the structural representation of production department factory building device in the embodiment of the present application one;
Wherein, 1-main body factory building, 2-first water tank, 3-second water tank, 4-gutter, 5-is responsible for, 6-water pump, 7-arm, 8-solar panel, 9-wind turbine generator, 10-battery, 11-temperature pick up, 12-gauge tap, 13 air-conditionings.
Detailed description of the invention
The utility model provides a kind of production department factory building device, and solving existing production department or factory building, to there is power consumption comparatively large, and cost is higher, the technical problem that working environment is poor, achieve device energy-conserving and environment-protective, cost is lower, the good technique effect of working environment.
Technical scheme during the application implements is for solving the problems of the technologies described above.General thought is as follows:
To have employed the production department factory building apparatus design of energy-conserving and environment-protective as comprising: main body factory building, described main body factory building is rectangular-shaped, described main body factory building inside is hollow-core construction, described main body factory building upper surface is provided with the first water tank, described main body factory building soffit is provided with the second water tank, described first water tank upper surface is net structure, drain hole is provided with in the middle part of described first water tank side, screen pack is provided with in described drain hole, gutter one end is connected with described drain hole, the described gutter other end extends in described second water tank, supervisor one end is positioned at described second water tank, all be connected with N number of arm after described supervisor's other end is connected with water pump, described first water tank upper surface is provided with solar panel and wind turbine generator, battery is provided with in described main body factory building, described solar panel is all connected with described battery with described wind turbine generator, described main body factory building side is provided with M steam vent, described N, M is the positive integer being more than or equal to 1, ventilation fan is provided with in described steam vent, temperature pick up is fixed on described main body factory building inwall, described temperature pick up is connected with air-conditioning by gauge tap, described main body factory building side exterior surface is provided with the technical scheme of one deck aluminium foil layer, namely solar panel and wind turbine generator generating is utilized, then charge a battery, for workshop provides electric energy, energy-conserving and environment-protective, and be provided with the first water tank at main body factory building upper surface, when rainy, first water tank is collected rainwater, when the rainwater collected is greater than a half of tank height, unnecessary rainwater is transferred to the second water tank by gutter, water in second water tank can be supplied to the production and application in workshop by water pump and arm, energy-conserving and environment-protective, and also surplusly in the first water tank have half chests water, when the sun from directly over irradiate time, water in first water tank can absorb heat, keep nice and cool in factory building, avoid directly being heated, and be provided with temperature pick up, when temperature is higher, as more than 25 degrees Celsius, at this moment the temperature pre-set has been exceeded, then gauge tap controls air-conditioning work, lower the temperature in factory building, safeguard work amenity, and be provided with in exhaust fan guarantee factory building with fresh air, and be also provided with aluminium foil layer, can reflect Yanguan Pass, unnecessary reflect heat is gone out, avoiding factory building to absorb unnecessary thermal conductance, to cause temperature too high, so, efficiently solving existing production department or factory building, to there is power consumption larger, cost is higher, the technical problem that working environment is poor, and then achieve device energy-conserving and environment-protective, cost is lower, the good technique effect of working environment.
In order to better understand technique scheme, below in conjunction with Figure of description and concrete embodiment, technique scheme is described in detail.
Embodiment one:
In embodiment one, provide a kind of production department factory building device, please refer to Fig. 1, described device comprises:
Main body factory building 1, described main body factory building is rectangular-shaped, described main body factory building inside is hollow-core construction, described main body factory building upper surface is provided with the first water tank 2, described main body factory building soffit is provided with the second water tank 3, described first water tank upper surface is net structure, drain hole is provided with in the middle part of described first water tank side, screen pack is provided with in described drain hole, gutter 4 one end is connected with described drain hole, the described gutter other end extends in described second water tank, be responsible for 5 one end and be positioned at described second water tank, all be connected with N number of arm 7 after described supervisor's other end is connected with water pump 6, described first water tank upper surface is provided with solar panel 8 and wind turbine generator 9, battery 10 is provided with in described main body factory building, described solar panel is all connected with described battery with described wind turbine generator, described main body factory building side is provided with M steam vent, described N, M is the positive integer being more than or equal to 1, ventilation fan is provided with in described steam vent, temperature pick up 11 is fixed on described main body factory building inwall, described temperature pick up is connected with air-conditioning 13 by gauge tap 12, described main body factory building side exterior surface is provided with one deck aluminium foil layer.
Wherein, in the embodiment of the present application, described main body factory building adopts angle steel to make, and described main body factory building surface scribbles rustproof paint.
Wherein, in the embodiment of the present application, adopt angle steel can the intensity of ensuring equipment, Tu rustproof paint can prevent from getting rusty.
Wherein, in the embodiment of the present application, described first water tank is identical with described second tank size, the upper surface size of described first water tank and the upper surface of described main body factory building measure-alike, described second water tank is embedded in below earth's surface.
Wherein, in the embodiment of the present application, described N number of arm is evenly distributed in described main body factory building, and described arm is provided with water valve.
Wherein, in the embodiment of the present application, in described main body factory building, upper surface is provided with LED illumination lamp, and described LED illumination lamp is connected with described battery.
Wherein, in the embodiment of the present application, utilize temperature pick up to obtain temperature, then utilize gauge tap to control air-conditioning and belong to the technological means commonly used in prior art, namely when temperature is higher than certain preset value, air-conditioning natural starting.
Technical scheme in above-mentioned the embodiment of the present application, at least has following technique effect or advantage:
Owing to have employed the production department factory building apparatus design of energy-conserving and environment-protective as comprising: main body factory building, described main body factory building is rectangular-shaped, described main body factory building inside is hollow-core construction, described main body factory building upper surface is provided with the first water tank, described main body factory building soffit is provided with the second water tank, described first water tank upper surface is net structure, drain hole is provided with in the middle part of described first water tank side, screen pack is provided with in described drain hole, gutter one end is connected with described drain hole, the described gutter other end extends in described second water tank, supervisor one end is positioned at described second water tank, all be connected with N number of arm after described supervisor's other end is connected with water pump, described first water tank upper surface is provided with solar panel and wind turbine generator, battery is provided with in described main body factory building, described solar panel is all connected with described battery with described wind turbine generator, described main body factory building side is provided with M steam vent, described N, M is the positive integer being more than or equal to 1, ventilation fan is provided with in described steam vent, temperature pick up is fixed on described main body factory building inwall, described temperature pick up is connected with air-conditioning by gauge tap, described main body factory building side exterior surface is provided with the technical scheme of one deck aluminium foil layer, namely solar panel and wind turbine generator generating is utilized, then charge a battery, for workshop provides electric energy, energy-conserving and environment-protective, and be provided with the first water tank at main body factory building upper surface, when rainy, first water tank is collected rainwater, when the rainwater collected is greater than a half of tank height, unnecessary rainwater is transferred to the second water tank by gutter, water in second water tank can be supplied to the production and application in workshop by water pump and arm, energy-conserving and environment-protective, and also surplusly in the first water tank have half chests water, when the sun from directly over irradiate time, water in first water tank can absorb heat, keep nice and cool in factory building, avoid directly being heated, and be provided with temperature pick up, when temperature is higher, as more than 25 degrees Celsius, at this moment the temperature pre-set has been exceeded, then gauge tap controls air-conditioning work, lower the temperature in factory building, safeguard work amenity, and be provided with in exhaust fan guarantee factory building with fresh air, and be also provided with aluminium foil layer, can reflect Yanguan Pass, unnecessary reflect heat is gone out, avoiding factory building to absorb unnecessary thermal conductance, to cause temperature too high, so, efficiently solving existing production department or factory building, to there is power consumption larger, cost is higher, the technical problem that working environment is poor, and then achieve device energy-conserving and environment-protective, cost is lower, the good technique effect of working environment.
Although described preferred embodiment of the present utility model, those skilled in the art once obtain the basic creative concept of cicada, then can make other change and amendment to these embodiments.So claims are intended to be interpreted as comprising preferred embodiment and falling into all changes and the amendment of the utility model scope.
Obviously, those skilled in the art can carry out various change and modification to the utility model and not depart from spirit and scope of the present utility model.Like this, if these amendments of the present utility model and modification belong within the scope of the utility model claim and equivalent technologies thereof, then the utility model is also intended to comprise these change and modification.

Claims (5)

1. a production department factory building device, is characterized in that, described device comprises:
Main body factory building, described main body factory building is rectangular-shaped, described main body factory building inside is hollow-core construction, described main body factory building upper surface is provided with the first water tank, described main body factory building soffit is provided with the second water tank, described first water tank upper surface is net structure, drain hole is provided with in the middle part of described first water tank side, screen pack is provided with in described drain hole, gutter one end is connected with described drain hole, the described gutter other end extends in described second water tank, supervisor one end is positioned at described second water tank, all be connected with N number of arm after described supervisor's other end is connected with water pump, described first water tank upper surface is provided with solar panel and wind turbine generator, battery is provided with in described main body factory building, described solar panel is all connected with described battery with described wind turbine generator, described main body factory building side is provided with M steam vent, described N, M is the positive integer being more than or equal to 1, ventilation fan is provided with in described steam vent, temperature pick up is fixed on described main body factory building inwall, described temperature pick up is connected with air-conditioning by gauge tap, described main body factory building side exterior surface is provided with one deck aluminium foil layer.
2. device according to claim 1, is characterized in that, described main body factory building adopts angle steel to make, and described main body factory building surface scribbles rustproof paint.
3. device according to claim 1, is characterized in that, described first water tank is identical with described second tank size, the upper surface size of described first water tank and the upper surface of described main body factory building measure-alike, described second water tank is embedded in below earth's surface.
4. device according to claim 1, is characterized in that, described N number of arm is evenly distributed in described main body factory building, and described arm is provided with water valve.
5. device according to claim 1, is characterized in that, in described main body factory building, upper surface is provided with LED illumination lamp, and described LED illumination lamp is connected with described battery.
CN201520492534.0U 2015-07-10 2015-07-10 Workshop factory building device Expired - Fee Related CN204920317U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520492534.0U CN204920317U (en) 2015-07-10 2015-07-10 Workshop factory building device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520492534.0U CN204920317U (en) 2015-07-10 2015-07-10 Workshop factory building device

Publications (1)

Publication Number Publication Date
CN204920317U true CN204920317U (en) 2015-12-30

Family

ID=54969455

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520492534.0U Expired - Fee Related CN204920317U (en) 2015-07-10 2015-07-10 Workshop factory building device

Country Status (1)

Country Link
CN (1) CN204920317U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989130A (en) * 2015-07-10 2015-10-21 成都亨通兆业精密机械有限公司 Energy-saving and environment-friendly production workshop factory building device
CN108458403A (en) * 2018-03-19 2018-08-28 齐斌贤 A kind of spinning and weaving workshop temperature-adjusting device and its adjusting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989130A (en) * 2015-07-10 2015-10-21 成都亨通兆业精密机械有限公司 Energy-saving and environment-friendly production workshop factory building device
CN108458403A (en) * 2018-03-19 2018-08-28 齐斌贤 A kind of spinning and weaving workshop temperature-adjusting device and its adjusting method

Similar Documents

Publication Publication Date Title
CN203893355U (en) Industrial humidification system
CN104061698B (en) Salar light-gathering formula thermal-arrest baking oven
CN204442279U (en) A kind of photovoltaic plant solar panels highly efficient cooling device
CN205811299U (en) A kind of outdoor power equipment cabinet
CN204920317U (en) Workshop factory building device
CN104989130A (en) Energy-saving and environment-friendly production workshop factory building device
CN206149008U (en) Walnut drying equipment
CN205753598U (en) A kind of emperature-lowering energy-saving system for building
CN103438595B (en) Solar water heater wind energy motive power pipeline water circulation defroster
CN204894186U (en) Solar energy curing kiln
CN103982381A (en) Wind power tower
CN206683031U (en) Photovoltaic, thermal current integrated generation heating plant
CN203657050U (en) Solar radiation control floor heating system
CN105705872A (en) Intelligent energy-saving air conditioning system
CN205607112U (en) Energy -efficient hot -air drying case
CN204854009U (en) A solar water heating system for high -rise building
CN204963055U (en) Heat facility falls
CN204392908U (en) Energy-conservation intelligent mushroom
CN206724516U (en) Solar air source heat pumps combined unit
CN205116789U (en) Energy -efficient template room
CN204404409U (en) A kind of solar domestic aircondition
CN104429609A (en) Energy-saving intelligent mushroom house
CN205202225U (en) A boiler system for rubber processing
CN203421838U (en) Multifunctional solar water heater
CN203514666U (en) Solar roof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151230

Termination date: 20160710

CF01 Termination of patent right due to non-payment of annual fee