CN204898683U - Underground structure of high strength - Google Patents

Underground structure of high strength Download PDF

Info

Publication number
CN204898683U
CN204898683U CN201520598580.9U CN201520598580U CN204898683U CN 204898683 U CN204898683 U CN 204898683U CN 201520598580 U CN201520598580 U CN 201520598580U CN 204898683 U CN204898683 U CN 204898683U
Authority
CN
China
Prior art keywords
pile
foundation ditch
prestressed pipe
anchor
side slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520598580.9U
Other languages
Chinese (zh)
Inventor
罗璇
余益军
叶高翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Keyuan Construction Group Co., Ltd.
Original Assignee
SHENZHEN KEYUAN CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN KEYUAN CONSTRUCTION GROUP CO Ltd filed Critical SHENZHEN KEYUAN CONSTRUCTION GROUP CO Ltd
Priority to CN201520598580.9U priority Critical patent/CN204898683U/en
Application granted granted Critical
Publication of CN204898683U publication Critical patent/CN204898683U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses an underground structure of high strength, the technical problem that solve are the intensity that improves supporting construction. The utility model discloses an anchor net of setting in the side slope of foundation ditch, the stake of one row of first stress tube in advance, second stress tube stake have in advance been buried in the top of foundation ditch and the lower extreme of side slope respectively, the lower extreme that extends to the side slope along the side of foundation ditch is netted to the anchor, the upper portion of anchor net is parallel with the axis of first stress tube in advance stake, the upper end of anchor net and the upper end fixed connection of first stress tube in advance stake, the lower extreme of anchor net and second be the upper end fixed connection of stress tube stake in advance, all be equipped with the anchor pipe in the side of foundation ditch and side slope. Compared with the prior art, the adoption all sets up one row of stress tube stake in advance in the top of foundation ditch, the lower extreme of side slope and the bottom of foundation ditch to improve underground structure of high strength's intensity, avoided leading to the not enough potential safety hazard that causes of supporting intensity because of rainwater weather.

Description

The foundation pit supporting construction of high strength
Technical field
The utility model relates to a kind of building structure, particularly a kind of foundation pit supporting construction of high strength.
Background technology
At present, the supporting and protection structure in shallow foundation hole is all lay bolting with wire mesh in the side of foundation ditch, and the anchor tube that anchor Netcom is crossed on foundation ditch side is solid, and this spline structure, because southern area rainwater is more, easily occurs that supporting intensity is not high enough, there is potential safety hazard.
Summary of the invention
The purpose of this utility model is to provide a kind of foundation pit supporting construction of high strength, and the technical problem that solve improves the intensity of supporting and protection structure.
For solving the problem, the utility model realizes by the following technical solutions: a kind of foundation pit supporting construction of high strength, comprise the anchor net be arranged in the side slope of foundation ditch, be embedded with one respectively in the top of described foundation ditch and the lower end of side slope and ranked first pile for prestressed pipe, second pile for prestressed pipe, described anchor net extends to the lower end of side slope along the side of foundation ditch, the top of described anchor net and the axis being parallel of the first pile for prestressed pipe, the upper end of described anchor net is fixedly connected with the upper end of the first pile for prestressed pipe, the lower end of anchor net is fixedly connected with the upper end of the second pile for prestressed pipe, the described side at foundation ditch and side slope are equipped with anchor tube, in the side that described anchor tube inserts foundation ditch and side slope, the rear end of anchor tube is fixedly connected with anchor net.
First pile for prestressed pipe described in the utility model is equal with the spacing of the second pile for prestressed pipe.
The side surface thereof of foundation ditch described in the utility model is provided with one and ranked third pile for prestressed pipe, and the upper end of described 3rd pile for prestressed pipe withstands on the side of foundation ditch, and the lower end of the 3rd pile for prestressed pipe is inserted in the bottom of foundation ditch.
The spacing of the 3rd pile for prestressed pipe described in the utility model is equal with the spacing of the second pile for prestressed pipe.
Anchor tube described in the utility model adopts resin anchor.
The degree of depth bottom the insertion foundation ditch of the 3rd pile for prestressed pipe lower end described in the utility model is 3 meters.
The utility model compared with prior art, adopt at the top of foundation ditch, the bottom of the lower end of side slope and foundation ditch all arranges row's pile for prestressed pipe, thus improve the intensity of the foundation pit supporting construction of high strength, avoid the potential safety hazard caused because rainwater weather causes supporting intensity not enough.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is described in further detail.
As shown in Figure 1, the foundation pit supporting construction of high strength of the present utility model, be included in and be embedded with one respectively in the top of foundation ditch 1 and the lower end of side slope 2 and ranked first pile for prestressed pipe 4, second pile for prestressed pipe 5, first pile for prestressed pipe 4 and the second pile for prestressed pipe 5 respectively one_to_one corresponding are arranged, and spacing is equal, side along foundation ditch 1 is equipped with anchor net 3 to the lower end of side slope 2, the top of anchor net 3 and the axis being parallel of the first pile for prestressed pipe 4, bottom is laid along side slope 2, the upper end of anchor net 3 adopts the mode of welding to be fixedly connected with the pad of the upper end of the first pile for prestressed pipe 4, the lower end of anchor net 3 adopts the mode of welding to be fixedly connected with the pad of the upper end of the second pile for prestressed pipe 5, the side and side slope 2 of foundation ditch 1 are equipped with anchor tube 6, in the side that foundation ditch 1 is inserted in the front end of anchor tube 6 and side slope 2, the rear end of anchor tube 6 is fixedly connected with anchor net 3.
Further, in order to strengthen the intensity of the foundation pit supporting construction of high strength, the side surface thereof of foundation ditch 1 is provided with one and ranked third pile for prestressed pipe 7,3rd pile for prestressed pipe 7 is all arranged with first, second pile for prestressed pipe one_to_one corresponding, and spacing is equal, the upper end of the 3rd pile for prestressed pipe 7 withstands on the side of foundation ditch 1, and the lower end of the 3rd pile for prestressed pipe 7 is inserted in the bottom of foundation ditch 1, and the 3rd pile for prestressed pipe 7 degree of depth inserted bottom foundation ditch 1 is 3 meters.
The spacing of described first pile for prestressed pipe 4, second pile for prestressed pipe 5 and the 3rd pile for prestressed pipe 7 is 3 meters.
The axis of the 3rd pile for prestressed pipe 7 and the domatic parallel of side slope 2.
The utility model has by arranging pile for prestressed pipe in foundation ditch, and strengthen the intensity of the foundation pit supporting construction of high strength, prevent the side of foundation ditch from caving in, it is more regional that this structure is applicable to southern china rainwater.

Claims (6)

1. the foundation pit supporting construction of a high strength, comprise be arranged on foundation ditch (1) side slope (2) on anchor net (3), it is characterized in that: be embedded with one respectively in the top of described foundation ditch (1) and the lower end of side slope (2) and ranked first pile for prestressed pipe (4), second pile for prestressed pipe (5), described anchor net (3) extends to the lower end of side slope (2) along the side of foundation ditch (1), the top of described anchor net (3) and the axis being parallel of the first pile for prestressed pipe (4), the upper end of described anchor net (3) is fixedly connected with the upper end of the first pile for prestressed pipe (4), the lower end of anchor net (3) is fixedly connected with the upper end of the second pile for prestressed pipe (5), the described side at foundation ditch (1) and side slope (2) are equipped with anchor tube (6), in the side of the insertion foundation ditch (1) of described anchor tube (6) front end and side slope (2), the rear end of anchor tube (6) is fixedly connected with anchor net (3).
2. the foundation pit supporting construction of high strength according to claim 1, is characterized in that: described first pile for prestressed pipe (4) is equal with the spacing of the second pile for prestressed pipe (5).
3. the foundation pit supporting construction of high strength according to claim 2, it is characterized in that: the side surface thereof of described foundation ditch (1) is provided with one and ranked third pile for prestressed pipe (7), the upper end of described 3rd pile for prestressed pipe (7) withstands on the side of foundation ditch (1), and the lower end of the 3rd pile for prestressed pipe (7) is inserted in the bottom of foundation ditch (1).
4. the foundation pit supporting construction of high strength according to claim 3, is characterized in that: the spacing of described 3rd pile for prestressed pipe (7) is equal with the spacing of the second pile for prestressed pipe (5).
5. the foundation pit supporting construction of high strength according to claim 4, is characterized in that: described anchor tube (6) adopts resin anchor.
6. the foundation pit supporting construction of high strength according to claim 5, is characterized in that: the degree of depth of insertion foundation ditch (1) bottom of described 3rd pile for prestressed pipe (7) lower end is 3 meters.
CN201520598580.9U 2015-08-10 2015-08-10 Underground structure of high strength Active CN204898683U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520598580.9U CN204898683U (en) 2015-08-10 2015-08-10 Underground structure of high strength

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520598580.9U CN204898683U (en) 2015-08-10 2015-08-10 Underground structure of high strength

Publications (1)

Publication Number Publication Date
CN204898683U true CN204898683U (en) 2015-12-23

Family

ID=54920872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520598580.9U Active CN204898683U (en) 2015-08-10 2015-08-10 Underground structure of high strength

Country Status (1)

Country Link
CN (1) CN204898683U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111155534A (en) * 2020-01-18 2020-05-15 赵利 Anchor-shotcreting support construction method in foundation pit construction
CN111236267A (en) * 2020-03-25 2020-06-05 武汉金涛岩土工程有限公司 Foundation pit slope supporting structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111155534A (en) * 2020-01-18 2020-05-15 赵利 Anchor-shotcreting support construction method in foundation pit construction
CN111155534B (en) * 2020-01-18 2021-08-20 西北电力建设第一工程有限公司 Anchor-shotcreting support construction method in foundation pit construction
CN111236267A (en) * 2020-03-25 2020-06-05 武汉金涛岩土工程有限公司 Foundation pit slope supporting structure

Similar Documents

Publication Publication Date Title
CN103075165B (en) Vertical beam of coal road combined type supporting method
CN204152521U (en) A kind of tunnel supporting and protection structure
CN207228145U (en) A kind of piling strtucture of electric pole
CN105155548B (en) A kind of drag-line double-row pile (wall) supporting construction
CN202936798U (en) Double-row pile structure with prestress vertical anchor cables
CN204898683U (en) Underground structure of high strength
CN206289641U (en) A kind of tunnel face talus slide protection device
CN102011408B (en) Wire pole base embedded in pit
CN204825919U (en) Strut foundation ditch and enclose purlin structure of shearing
CN202108055U (en) Reinforcement cantilever type retaining wall structure
CN202347528U (en) Steel tube inserted foundation
CN204349391U (en) Bright sky erection and the anti-ponding wire casing of pre-buried installation
CN204690774U (en) Transmission pole pile foundation
CN204435209U (en) A kind of semi-rigid joint Integral Abutment Bridge of concrete pile supporting
CN204040033U (en) Anchor jacked pile piling structure
CN203684258U (en) Prefabricated concrete rod sleeve foundation
CN203411930U (en) Fixed direct burial type guardrail
CN203188201U (en) Reducing enlarged toe pile foundation
CN201943071U (en) Implantable steel tube anchor rod with stabs
CN102155015A (en) Barbed implanted steel pipe anchor rod
CN201789262U (en) Roof lightning protection support lattice
CN205475220U (en) Prestressed anchorage hitch constructs
CN204040322U (en) A kind of wind resistance gear snow structure of metal Roof
CN204959531U (en) Reinforced structure of outstanding ground road road bed
CN205382465U (en) Board -like mud -rock flow of ge bin - stake structure of blocking

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 518000 three storehouse 302-03 3, Taoyuan Road, No. 231 Taoyuan Road, Luohu District Sungang street, Shenzhen, Guangdong

Patentee after: Shenzhen Keyuan Construction Group Co., Ltd.

Address before: 518031 twelve floor, Trade Union Mansion, Shang Bu Zhong Road, Futian District, Shenzhen, Guangdong.

Patentee before: Shenzhen Keyuan Construction Group Co., Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: Room 302-03, No. 3, No. 231 Taoyuan Road, Shoot Hill Street, Luohu District, Shenzhen City, Guangdong Province

Patentee after: Shenzhen Keyuan Construction Group Co., Ltd.

Address before: 518000 three storehouse 302-03 3, Taoyuan Road, No. 231 Taoyuan Road, Luohu District Sungang street, Shenzhen, Guangdong

Patentee before: Shenzhen Keyuan Construction Group Co., Ltd.