CN2048489U CN 89207646 CN89207646U CN2048489U CN 2048489 U CN2048489 U CN 2048489U CN 89207646 CN89207646 CN 89207646 CN 89207646 U CN89207646 U CN 89207646U CN 2048489 U CN2048489 U CN 2048489U
Authority
CN
China
Prior art keywords
cantilever
clamping plate
clamp
principal post
pincerlike
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN 89207646
Other languages
Chinese (zh)
Inventor
饶世德
蔡继祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 89207646 priority Critical patent/CN2048489U/en
Publication of CN2048489U publication Critical patent/CN2048489U/en
Withdrawn legal-status Critical Current

Links

Images

Abstract

The utility model relates to a cantilever scaffold fixed to a windowsill or a hole of a wall during construction. The cantilever scaffold is characterized in that the utility model is tightly fixed to the wall by forcipate clamping plates, and the outer side ends of the forcipate clamping plates are fixed with a cantilever; the front end of the cantilever is connected with a railing, and a spring plate is arranged on the cantilever. The upper forcipate clamping plate and the lower forcipate clamping plate are connected by a main column. The utility model changes the structure that a frame scaffold in the prior art is fixed to ground and adopts the structure of the cantilever and the frame hung in the air, a great deal of scaffold materials can be saved, the using period of the scaffold is shortened, ground is not occupied, the expenditure is saved, and the construction cost is reduced.

Description

Cantilever scaffold fixed on wall
The utility model is to belong to the scaffold that a kind of building operations is used, and more particularly relates to be fastened on the hanging scaffolding on body of wall windowsill or the hole.
The modern high-rise building construction generally all be unable to do without scaffold.No matter scaffold is mao bamboon or copper pipe, all be to adopt frame type to set up from ground, till binding to building together, need with a large amount of mao bamboons or steel always.Because scaffold begins frame and takes when building operations, after being completed to building again row remove, turnover period is longer, therefore, adopt frame construction from the built of ground last layer one deck to rising, not only expense is big, need to consume lot of materials, also to take building road on every side, influence pedestrian and traffic, but still not have a kind of scaffold that does not begin to set up at present from ground.
The purpose of this utility model provides a kind of cantilevered scaffold that is fixed on the body of wall, except that first floor is from the built of ground, begin to be installed on the windowsill or hole of body of wall from the second layer, along with building increases, the foot rest after the completion is removed, layer by layer upwards dismounting, can save lot of materials and expense, do not take up an area of face, do not influence pedestrian and traffic, accomplish civilized construction.
The utility model is realized by following technical scheme.
The utility model is made up of pincerlike clamping plate, cantilever, railing, springboard, principal post.The utility model feature is that pincerlike clamping plate are fastened on the windowsill or hole of body of wall, connects cantilever on one end of the pincerlike clamping plate outside.Cantilever is the shelf shape.Connect railing in the cantilever outer end, place springboard on the cantilever, between pincerlike clamping plate and pincerlike clamping plate, be connected principal post.
Pincerlike clamping plate are active clamp, and clamp is fastened on the body of wall, because body of wall is after maintenance, pincerlike clamping plate are fastened on the body of wall can bear certain power.Therefore, on the outside one end of pincerlike clamping plate cantilever is installed, the front end of cantilever connects railing.When first floor was constructed, railing lower end kiss the earth was installed springboard on the cantilever.Since tri-level construction, every interlayer adopts two fastening bodies of wall of pincerlike clamping plate up and down, is connected by principal post between two pincerlike clamping plate.Railing connects two cantilevers up and down, forms underslung framework, can hang safety guard net on the railing, lays springboard on the cantilever.
Pincerlike clamping plate shape such as channel-section steel, there is clamp at two ends, the left and right sides, and one is dead clamp, and one is the clamp of living.On the clamp alive screw rod is arranged, be furnished with adjusting nut on the screw rod.There is the cantilever patchhole in the outside of dead clamp, and pincerlike clamping plate plane central part has a garden connected in star, has three screws that connect principal post on the groove at least, and three inboards of pincerlike clamping plate are all fluted.
Principal post is hollow, and its lower end connects lower flange, and the principal post upper end joins with sleeve, and internal thread is arranged in the sleeve, and internal thread and screw rod match, and screw tip connects upper flange plate, on the principal post upper and lower side flange connecting dish screw that matches with the garden connected in star is arranged.
The utility model has the advantages that:
1, the utility model adopts the transverse arm suspended structure, and wheel turns over use, does not take to top of building from ground, saves scaffolding in a large number;
2, the frame of the utility model scaffold is taken, and adopts to tear open afterwards earlier and takes, or take, tear the method that develops simultaneously open, has shortened the scaffold use;
3, the utility model can take ground less, few expense that accounts for sidewalk or road surface of paying;
4, in sum, adopt hanging scaffolding, reduce construction cost with the frame type scaffold, cut down expenses, increase profit than former.
Fig. 1 is the utility model structural representation.
Fig. 2 is a pincerlike clamp region schematic diagram of the present utility model.
Fig. 3 is the vertical view of pincerlike clamping plate.
Fig. 4 is a principal post structural representation of the present utility model.
Number in the figure:
1, pincerlike clamping plate, 2, railing, 3, cantilever, 4, springboard, 5, principal post, 6, dead clamp, 7, the clamp of living, 8, the clamp screw rod of living, 9, the cantilever patchhole, 10, garden connected in star, 11, garden connected in star screw, 12, principal post lower end flange, 13, principal post sleeve, 14, screw rod, 15, adjusting nut, 16, principal post upper flanges dish, 17, screw, 18, pincerlike clamping plate groove.
By the following examples, in conjunction with the accompanying drawings, the utility model is further described.
Embodiment
Pincerlike clamping plate 1 vise on the windowsill lower plane of Stall body of wall, and rotation clamp plate alive screw rod 8 is fastened on the body of wall pincerlike clamping plate 1.Cantilever 3 is fixed on the pincerlike clamping plate 3 in the one end cantilever patchhole 9 of the outside.Railing 2 is packed in the hole of cantilever 3 front ends, railing is landed support on the ground.Screw is fixed on the cantilever 3 railing 2.Springboard 4 is placed on the cantilever 3, is screwed.This is that the scaffold of first floor Lower Half construction is by dress.After treating first floor first half construction maintenance, carry out the installation of first half scaffold, pincerlike clamping plate 1 promptly are installed on the plane of windowsill upper end, its pincers are tight.Link to each other by principal post 5 between two about in the of 1 at pincerlike clamping plate, promptly the flange 12,16 at principal post two ends about in the of 5 by bolton on pincerlike clamping plate 1.Cantilever 3 is fixed on the pincerlike clamping plate 1.Railing 2 penetrates in upper cantilever 3 front aperture from the ground pull-up.Lay springboard 4 on the cantilever 3.Can hang safety guard net 4 times in railing 2 outsides and springboard.The second layer, tri-level construction are installed scaffold by that analogy.

Claims (4)

1, a kind of hanging scaffolding that is used for building operations, it is characterized in that having pincerlike clamping plate 1 to be fastened on the windowsill of body of wall, one end connects cantilever 3 in the described pincerlike clamping plate outside, described cantilever is the shelf shape, connect railing 2 in the cantilever outer end, place springboard 4 on the cantilever, link to each other with principal post 5 between pincerlike clamping plate and pincerlike clamping plate.
2, scaffold according to claim 1, it is characterized in that pincerlike clamping plate shape such as channel-section steel, there is clamp at two ends, the left and right sides, one is that dead clamp 6, is the clamp 7 of living, and on the clamp of living screw rod 8 is arranged, is furnished with adjusting nut on the screw rod, there is cantilever patchhole 9 in the outside of dead clamp, and pincerlike folder plane central part has a garden connected in star 10, has three screws 11 that connect principal post on the groove at least.
3, scaffold according to claim 1 and 2, it is characterized in that principal post 5 is for hollow, its lower end connects lower flange 12, the principal post upper end joins with sleeve 13, internal thread is arranged in the sleeve, internal thread and screw rod 14 match, and the top of screw rod connects upper flange plate 16, on the principal post 5 upper and lower side flange connecting dishes screw 17 that matches with the garden connected in star is arranged.
4, scaffold according to claim 2 is characterized in that three inboards of pincerlike clamping plate are all fluted.
CN 89207646 1989-05-19 1989-05-19 Cantilever scaffold fixed on wall Withdrawn CN2048489U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 89207646 CN2048489U (en) 1989-05-19 1989-05-19 Cantilever scaffold fixed on wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 89207646 CN2048489U (en) 1989-05-19 1989-05-19 Cantilever scaffold fixed on wall

Publications (1)

Publication Number Publication Date
CN2048489U true CN2048489U (en) 1989-11-29

Family

ID=4864469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 89207646 Withdrawn CN2048489U (en) 1989-05-19 1989-05-19 Cantilever scaffold fixed on wall

Country Status (1)

Country Link
CN (1) CN2048489U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103266754A (en) * 2013-05-31 2013-08-28 中国海洋石油总公司 Scaffold suspension lap joint technology

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103266754A (en) * 2013-05-31 2013-08-28 中国海洋石油总公司 Scaffold suspension lap joint technology
CN103266754B (en) * 2013-05-31 2015-08-12 中国海洋石油总公司 Scaffold suspension lap joint technology

Similar Documents

Publication Publication Date Title
CN104532735B (en) A kind of assembled steel bridge and building method thereof
CN202017346U (en) Late poured band hanging formwork structure
CN202767488U (en) Steel pipe fastener hanging type handling frame
CN204455794U (en) A kind of assembled steel bridge
CN206949022U (en) A kind of urban road dimensional greening frame
CN201406844Y (en) Support of middle flange plate construction formwork of concrete-steel beam
CN2703074Y (en) Cantilever scaffold fixed on wall
CN2048489U (en) Cantilever scaffold fixed on wall
CN112065013A (en) Outer wall scaffold reinforcing mechanism for construction
CN2251595Y (en) Outside scaffold for building construction
CN209039985U (en) A kind of highway bridge construction Support bracket
CN108068206B (en) Spraying pipe network supporting device for concrete curing and automatic curing system thereof
CN206034676U (en) Shock attenuation antidetonation profiled steel structure
CN211571429U (en) U type bridge guardrail template
CN209443494U (en) A kind of piping lane aluminum dipping form support system
CN204370303U (en) Section connection structure is connect for wet between full prefabricated bridge
CN202925678U (en) A column foot connecting structure of a modern bamboo structure
CN207160563U (en) A kind of building engineering construction is with hanging die device
CN2161665Y (en) Adjuster for shuttering strut disassembling
CN214575505U (en) Scaffold reinforcing apparatus for building engineering
CN2238872Y (en) Extension electrical lift well die carrier
CN218619914U (en) Construction structure for installing bridge deck steel grating through self-made pulley balance car
CN2830032Y (en) U-shaped roofing match
CN220521117U (en) Climbing formwork hanging seat system for concave concrete structure
CN2263161Y (en) Self-lifting scaffold

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee