CN204848675U - Automatic glaze spraying line of china - Google Patents
Automatic glaze spraying line of china Download PDFInfo
- Publication number
- CN204848675U CN204848675U CN201520490421.7U CN201520490421U CN204848675U CN 204848675 U CN204848675 U CN 204848675U CN 201520490421 U CN201520490421 U CN 201520490421U CN 204848675 U CN204848675 U CN 204848675U
- Authority
- CN
- China
- Prior art keywords
- glaze spraying
- storehouse
- spray gun
- natural gas
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Spray Control Apparatus (AREA)
- Nozzles (AREA)
Abstract
The utility model discloses an automatic glaze spraying line of china installs loading attachment, body in proper order from a dextrad left side in the frame and preheats storehouse, glaze spraying storehouse, dry storehouse, cooling bin, and the body preheats and sets up many in the storehouse and preheat the bleeder, preheats bleeder and natural gas intake -tube connection, preheats and evenly sets up a plurality of ventholes on the bleeder, the upper and lower spray gun of installation axle in the glaze spraying storehouse, the epaxial even installation of upper and lower spray gun installation is many the spray gun, and the spray gun feeds through through glaze spraying pipe and glaze spraying bucket, set up natural gas bleeder in the dry storehouse, natural gas bleeder and natural gas intake pipe intercommunication set up a plurality of gas outlets on the natural gas bleeder, cooling bin top installation axial fan. The utility model discloses automatic glaze spraying line of china collects that automatic feeding, body preheat, glaze spraying, drying, cooling, washs in the full automatic glazing equipment of an organic whole, and degree of automation is high, and workman easy operation easily masters, and it is even, efficient to have a glaze spraying, economizes characteristics such as manual work, and gained product quality is good, simultaneously the cost is reduced.
Description
Technical field
The utility model belongs to china glaze spraying technical field, particularly relates to a kind of china automatic glaze spraying line.
Background technology
Current conventional bone porcelain glazing line comprises primary heater unit, glaze spraying device, drying installation, and workpiece, by manually placing, carries out glaze spraying after preheating, then drying is carried out, its Problems existing adopts manually to pick and place part, and labor strength is large, and cost is high and can not ensure the quality of glaze spraying product.
Utility model content
The technical problems to be solved in the utility model is to provide the china automatic glaze spraying line of a kind of automatic charging, cost-saving, good product quality.
For solving the problems of the technologies described above, the utility model adopts following technical scheme:
A kind of china automatic glaze spraying line, comprises frame, transmission rig, is characterized in that: in described frame, right-to-left installs materials device successively, base substrate pre-heating cabin, glaze spraying storehouse, dryness storehouse, cooling storehouse, bracket rinse bath is arranged on bottom frame, and the top of frame right-hand member is installed and dried blower fan, and transmission rig comprises motor, driving chain, motor and driving chain are in transmission connection, and the first-class intervals of driving chain installs multiple bracket, and feeding device comprises conveyor, support, horizontal mechanical arm, vertical mechanical arm, vacuum pad, conveyor is positioned at below support, and cradle top is installed left, right slide rail, the two ends of horizontal mechanical arm are arranged on a left side respectively, on right slide rail, cross motor is connected with horizontal mechanical arm by odontoid belt, the middle part of horizontal mechanical arm arranges chute, vertical mechanical arm is arranged in chute, vertical motor is connected with vertical mechanical arm by odontoid belt, sucker union lever is installed in the lower end of vertical mechanical arm, and sucker union lever evenly installs multiple vacuum pad, many preheating take-off pipes are set in base substrate pre-heating cabin, preheating take-off pipe is connected with Sweet natural gas inlet pipe, preheating take-off pipe evenly offers multiple production well, preheating take-off pipe is installed the first electronic lighter, the control signal output terminal of controller is connected with the control end of the first electronic lighter, install upper and lower spray gun installation shaft in glaze spraying storehouse, upper and lower spray gun installation shaft is evenly installed many spray gun, spray gun is communicated with glaze spraying bucket through glaze spraying pipe, Sweet natural gas take-off pipe is set in dryness storehouse, Sweet natural gas take-off pipe is communicated with Sweet natural gas inlet pipe, Sweet natural gas take-off pipe arranges multiple air outlet, Sweet natural gas take-off pipe is installed the second electronic lighter, the control signal output terminal of controller is connected with the control end of the second electronic lighter, cooling top, storehouse installation shaft flow fan, driving chain is through base substrate pre-heating cabin, glaze spraying storehouse, dryness storehouse, cooling storehouse, bracket rinse bath.
The utility model china automatic glaze spraying line, further, the inwall of described bracket rinse bath both sides installs hairbrush respectively.
The utility model china automatic glaze spraying line, further, described upper and lower spray gun installation shaft evenly installs multiple contiguous block, and install union lever bottom each contiguous block, described spray gun is arranged on union lever.
The utility model china automatic glaze spraying line, further, the spacing between described adjacent vacuum sucker is equal with the spacing between adjacent bracket.
The utility model china automatic glaze spraying line, preferably, in described upper and lower spray gun installation shaft, spray gun quantity is respectively 4-6 handle.
The utility model china automatic glaze spraying line integrates automatic charging, base substrate preheating, glaze spraying, drying, cooling, the full-automatic glazing equipment that cleans, level of automation is high, operative is simple and easy to grasp, there is glaze spraying even, efficiency is high, the features such as less manpower, reduce cost, and products obtained therefrom quality is good.
Below in conjunction with accompanying drawing, china automatic glaze spraying line of the present utility model is described further.
Accompanying drawing explanation
Fig. 1 is the front view of the utility model china automatic glaze spraying line;
Fig. 2 is A place enlarged view in Fig. 1;
Fig. 3 is B place enlarged view in Fig. 1;
Fig. 4 is the stereographic map of feeding device in the utility model china automatic glaze spraying line;
Fig. 5 is the structural representation of spraygun portion in the utility model china automatic glaze spraying line.
Embodiment
As shown in Figure 1-Figure 3, the utility model china automatic glaze spraying line comprises frame 1, transmission rig, in frame 1, right-to-left installs materials device 2, base substrate pre-heating cabin 3, glaze spraying storehouse 4, dryness storehouse 5, cooling storehouse 7 successively, bracket rinse bath 6 is arranged on bottom frame 1, the top of frame 1 right-hand member is installed and is dried blower fan 8, the effect of drying blower fan 8 is moisture rapid evaporation that drive wind-force makes on bracket 12, thus is dried by bracket.
Transmission rig comprises motor 13, driving chain 11, and motor 13 is arranged in frame 1, and motor and driving chain 11 are in transmission connection, and the first-class intervals of driving chain 11 installs multiple bracket 12.
Shown in composition graphs 4, feeding device 2 comprises conveyor 21, support 22, horizontal mechanical arm 23, vertical mechanical arm 24, vacuum pad 25, conveyor 21 is positioned at below support 22, support 22 top is installed left, right slide rail 26, 27, the two ends of horizontal mechanical arm 23 are arranged on a left side respectively, right slide rail 26, on 27, cross motor (not shown) is connected with horizontal mechanical arm 23 by odontoid belt, horizontal mechanical arm 23 can be driven along a left side, right slide rail 26, 27 carry out before, rear movement, the middle part of horizontal mechanical arm 23 arranges chute 28, vertical mechanical arm 24 is arranged in chute 28, vertical motor (not shown) is connected with vertical mechanical arm 24 by odontoid belt, vertical mechanical arm 24 can be driven along on chute, lower movement, sucker union lever 29 is installed in the lower end of vertical mechanical arm 24, sucker union lever 29 evenly installs multiple vacuum pad 25, spacing between adjacent vacuum sucker 25 is equal with the spacing between adjacent bracket 12.
Many preheating take-off pipes 31 are set in base substrate pre-heating cabin 3, preheating take-off pipe 31 is connected with Sweet natural gas inlet pipe 32, preheating take-off pipe 31 is evenly offered multiple production well 33, preheating take-off pipe 31 is installed the first electronic lighter (not shown), the control signal output terminal of controller is connected with the control end of the first electronic lighter.Sweet natural gas flows out from production well 33, and controller output signal to the first electronic lighter is struck sparks, thus heats workpiece.
In glaze spraying storehouse 4, upper and lower spray gun installation shaft 41,42 is installed, shown in composition graphs 5, upper and lower spray gun installation shaft 41,42 evenly installs multiple contiguous block 43, bottom each contiguous block 43, union lever 44 is installed, each union lever 44 is installed one spray gun 45.The setting angle of spray gun 45 is arranged as required.Spray gun 45 is communicated with glaze spraying bucket (not shown) through glaze spraying pipe 46.In upper and lower spray gun installation shaft 41,42, spray gun quantity is respectively 4-6 handle, is 4 shown in figure.
Arrange Sweet natural gas take-off pipe 51 in dryness storehouse 5, Sweet natural gas take-off pipe 51 is communicated with Sweet natural gas inlet pipe 32, and Sweet natural gas take-off pipe 51 being arranged shown in multiple air outlet 52, figure is 2.Sweet natural gas take-off pipe 51 is installed the second electronic lighter (not shown), the control signal output terminal of controller is connected with the control end of the second electronic lighter.Sweet natural gas flows out from air outlet 52, and controller output signal to the second electronic lighter is struck sparks, thus reaches the object of heat drying.
Cooling top, storehouse 7 installation shaft flow fan 71, aerofoil fan 71 drives air to lower the temperature to device.
The inwall of bracket rinse bath 6 both sides installs hairbrush 61 respectively, when completing cleaning under the flushing of bracket through bracket rinse bath and hairbrush friction and at water.
Driving chain 11 is through base substrate pre-heating cabin 3, glaze spraying storehouse 4, dryness storehouse 5, cooling storehouse 7, bracket rinse bath 6.
The working process of the utility model china automatic glaze spraying line is as follows:
By how folded workpiece is placed on the travelling belt 211 of conveyor 21, workpiece is delivered to specified location and vacuum pad 25 pickup position by travelling belt 211, cross motor drives horizontal mechanical arm 23 along a left side, right slide rail 26, 27 slide, the longitudinal mechanical arm 24 of longitudinal driven by motor slides along chute 28, the location of workpiece on vacuum pad 25 to travelling belt 211 is made to draw workpiece, then horizontal mechanical arm 23, longitudinal mechanical arm 24 moves again, workpiece is placed on bracket 12 by vacuum pad 25, first through base substrate pre-heating cabin 3, Sweet natural gas flows out from the production well 33 preheating take-off pipe 31, controller output signal to the first electronic lighter is struck sparks, preheating is carried out to workpiece, workpiece after preheating enters glaze spraying storehouse 4 glaze spraying, many spray gun 45 is carried out glaze spraying from different angles to workpiece, the inside and outside side surface of coating workpieces, sprayed the product introduction dryness storehouse 5 of glaze, Sweet natural gas flows out from the air outlet 52 Sweet natural gas take-off pipe 51, controller output signal to the second electronic lighter is struck sparks, heat drying is carried out to workpiece, then cooling storehouse 7 is entered, after aerofoil fan 71 pairs of workpiece are lowered the temperature, take off workpiece, empty bracket 12 enters bracket rinse bath 6 and cleans, then frame right-hand member is arrived, dried by oven dry blower fan 8, complete a circulation.
The utility model china automatic glaze spraying line integrates automatic charging, base substrate preheating, glaze spraying, drying, cooling, the full-automatic glazing equipment that cleans, level of automation is high, operative is simple and easy to grasp, there is glaze spraying even, efficiency is high, the features such as less manpower, products obtained therefrom quality is good, reduces cost simultaneously.
Above-described embodiment is only be described preferred implementation of the present utility model; not scope of the present utility model is limited; under the prerequisite not departing from the utility model design spirit; the various distortion that those of ordinary skill in the art make the technical solution of the utility model and improvement, all should fall in protection domain that the utility model claims determine.
Claims (5)
1. a china automatic glaze spraying line, comprises frame, transmission rig, is characterized in that: in described frame, right-to-left installs materials device successively, base substrate pre-heating cabin, glaze spraying storehouse, dryness storehouse, cooling storehouse, bracket rinse bath is arranged on bottom frame, and the top of frame right-hand member is installed and dried blower fan, and transmission rig comprises motor, driving chain, motor and driving chain are in transmission connection, and the first-class intervals of driving chain installs multiple bracket, and feeding device comprises conveyor, support, horizontal mechanical arm, vertical mechanical arm, vacuum pad, conveyor is positioned at below support, and cradle top is installed left, right slide rail, the two ends of horizontal mechanical arm are arranged on a left side respectively, on right slide rail, cross motor is connected with horizontal mechanical arm by odontoid belt, the middle part of horizontal mechanical arm arranges chute, vertical mechanical arm is arranged in chute, vertical motor is connected with vertical mechanical arm by odontoid belt, sucker union lever is installed in the lower end of vertical mechanical arm, and sucker union lever evenly installs multiple vacuum pad, many preheating take-off pipes are set in base substrate pre-heating cabin, preheating take-off pipe is connected with Sweet natural gas inlet pipe, preheating take-off pipe evenly offers multiple production well, preheating take-off pipe is installed the first electronic lighter, the control signal output terminal of controller is connected with the control end of the first electronic lighter, install upper and lower spray gun installation shaft in glaze spraying storehouse, upper and lower spray gun installation shaft is evenly installed many spray gun, spray gun is communicated with glaze spraying bucket through glaze spraying pipe, Sweet natural gas take-off pipe is set in dryness storehouse, Sweet natural gas take-off pipe is communicated with Sweet natural gas inlet pipe, Sweet natural gas take-off pipe arranges multiple air outlet, Sweet natural gas take-off pipe is installed the second electronic lighter, the control signal output terminal of controller is connected with the control end of the second electronic lighter, cooling top, storehouse installation shaft flow fan, driving chain is through base substrate pre-heating cabin, glaze spraying storehouse, dryness storehouse, cooling storehouse, bracket rinse bath.
2. china automatic glaze spraying line according to claim 1, is characterized in that: the inwall of described bracket rinse bath both sides installs hairbrush respectively.
3. china automatic glaze spraying line according to claim 1, is characterized in that: described upper and lower spray gun installation shaft evenly installs multiple contiguous block, and install union lever bottom each contiguous block, described spray gun is arranged on union lever.
4. china automatic glaze spraying line according to claim 3, is characterized in that: the spacing between described adjacent vacuum sucker is equal with the spacing between adjacent bracket.
5. china automatic glaze spraying line according to claim 4, is characterized in that: in described upper and lower spray gun installation shaft, spray gun quantity is respectively 4-6 handle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520490421.7U CN204848675U (en) | 2015-07-08 | 2015-07-08 | Automatic glaze spraying line of china |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520490421.7U CN204848675U (en) | 2015-07-08 | 2015-07-08 | Automatic glaze spraying line of china |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204848675U true CN204848675U (en) | 2015-12-09 |
Family
ID=54739247
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520490421.7U Active CN204848675U (en) | 2015-07-08 | 2015-07-08 | Automatic glaze spraying line of china |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204848675U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109129854A (en) * | 2018-09-13 | 2019-01-04 | 肇庆乐华陶瓷洁具有限公司 | A kind of ceramic tile glaze automatic filling system |
CN111792844A (en) * | 2020-08-11 | 2020-10-20 | 鲁山花瓷股份有限公司 | Gold glaze material and glazing method thereof |
-
2015
- 2015-07-08 CN CN201520490421.7U patent/CN204848675U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109129854A (en) * | 2018-09-13 | 2019-01-04 | 肇庆乐华陶瓷洁具有限公司 | A kind of ceramic tile glaze automatic filling system |
CN111792844A (en) * | 2020-08-11 | 2020-10-20 | 鲁山花瓷股份有限公司 | Gold glaze material and glazing method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109731724A (en) | A kind of work piece hoisting spray-painting production line | |
CN103658099A (en) | Fully-automatic water aqua ultrasonic cleaner | |
CN105289903A (en) | Automatic spraying production line for automobile lamp anti-fogging paint | |
CN204255026U (en) | A kind of novel tunnel drying line | |
CN204848675U (en) | Automatic glaze spraying line of china | |
CN112524931B (en) | Automatic aluminum profile production line with intelligent aluminum bar heating furnace | |
CN109403195A (en) | A kind of town road pen machine | |
CN208712352U (en) | A kind of driven type crawler belt cleaning device | |
CN203944539U (en) | A kind of shell surface film curing drying plant | |
CN208133221U (en) | A kind of cupulate bowl class double end automatic rolling forming drying production line | |
CN105080762A (en) | Automatic paint spraying and drying device | |
CN112705395A (en) | Sheet metal part spraying system | |
CN204404738U (en) | A kind of plating post-drying equipment | |
CN206082972U (en) | Bumper shock absorber central siphon automatic spraying device | |
CN101462101A (en) | Putty-painting machine special for artificial board | |
CN201893415U (en) | Cleaning machine for button cells | |
CN106733348A (en) | A kind of automobile door handle automatic application product line | |
CN106042631A (en) | Diode printing ink drying device | |
CN206794054U (en) | One kind spray three proofings production equipment | |
CN205522543U (en) | Can realize automatic 3D printing apparatus stone device that cleans | |
CN109550621A (en) | A kind of automatic flocking production line | |
CN202212665U (en) | Flux coating and inserting machine of inner fin of heat dissipation pipe | |
CN211613215U (en) | Plastic product surface spraying device | |
CN210772781U (en) | Hot melt adhesive powder heated air circulation heating system | |
CN203091209U (en) | Mortar rolling-coating integration device of vacuum heat insulation board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |