CN204826701U - Precast beam construction and installation's protection canopy arrangement structure - Google Patents

Precast beam construction and installation's protection canopy arrangement structure Download PDF

Info

Publication number
CN204826701U
CN204826701U CN201520508233.2U CN201520508233U CN204826701U CN 204826701 U CN204826701 U CN 204826701U CN 201520508233 U CN201520508233 U CN 201520508233U CN 204826701 U CN204826701 U CN 204826701U
Authority
CN
China
Prior art keywords
precast beam
web
protection
protection canopy
braced structures
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520508233.2U
Other languages
Chinese (zh)
Inventor
孙晓伟
潘焕辉
张勇
王鑫
刘奖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201520508233.2U priority Critical patent/CN204826701U/en
Application granted granted Critical
Publication of CN204826701U publication Critical patent/CN204826701U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a bridge construction practice field, concretely relates to precast beam construction and installation's protection canopy arrangement structure and the method of arranging. Including protecting the canopy and arranging the precast beam between two rows of piers, the precast beam includes the roof that is located the precast beam top and is located the web of precast beam both sides, arranges to form clearance between the roof beam between the precast beam roof between two rows of piers, the protection canopy sets up between the relative web of adjacent precast beam, is located clearance below between the roof beam, the protection canopy is fixed in the web lower part. Set up the protection platform as load -carrying members through the bearing structure attached to on the precast beam body, provide reliable protection to the construction region below, eliminated complicated management that land construction brought and safe risk, the protection platform forming speed of having accelerated simultaneously.

Description

The protection canopy arrangement of precast beam install construction
Technical field
The utility model relates to technical field of bridge construction, is specifically related to the protection canopy arrangement of a kind of precast beam install construction.
Background technology
In bridge construction field, engineering superstructure often adopts precast beam structure, after precast beam lifting puts in place, generally needs the construction carrying out seam between Liang Yuliang.When agent structure crosses over the region of the totally-enclosed covered protection of the needs such as existing line or existing building, between precast beam, seam construction needs to transfer in working face to set up protection canopy, plays the protective effect to lower zone.Traditional protection canopy adopts the form of structure of " steel pipe support+steel ceiling ", needs to take construction area for a long time setting up in process, affects greatly, and there is larger potential safety hazard to social environment (as be open to traffic, pedestrian etc.).
Utility model content
For solving the problems of the technologies described above, it is reliable that the utility model provides a kind of protection, sets up the protection canopy arrangement of precast beam install construction easily.
Technical solutions of the utility model are: comprise protection canopy and be arranged in the precast beam between two row's bridge piers, described precast beam comprises the top board being positioned at precast beam top and the web being positioned at precast beam both sides, gap between beam is formed between the described precast beam top board be arranged between two row's bridge piers, described protection canopy is arranged between the relative web of precast beam, be positioned between beam below gap, described protection canopy is fixed on web bottom.
Further, the braced structures that described protection canopy comprises protection face board and evenly arranges along precast beam length direction, described braced structures is fixedly connected with the web plate face of both sides, and described protection face board is arranged in braced structures, and protection face board upper surface is corresponding with gap between beam.
Further, described braced structures comprises left and right braced structures monomer, and described braced structures monomer comprises embedded sleeve barrel, angle steel and standing screw, and described embedded sleeve barrel is arranged in web, and described angle steel side is threaded with embedded sleeve barrel by standing screw.
Further, described braced structures monomer also comprises correcting wedge, described correcting wedge clamping is arranged between angle steel and web, and the lozenges of described correcting wedge is corresponding with web, and described standing screw is threaded with embedded sleeve barrel through angle steel, correcting wedge.
Further, described protection face board comprises the wooden a tree, used in making timber for boats be installed in braced structures and the plank be installed on wooden a tree, used in making timber for boats.
Further, described plank upper surface is equipped with fireprotection layer.
The beneficial effects of the utility model: the utility model sets up protective platform by the braced structures be attached on precast beam body as load-carrying members, to providing reliable protection below construction area, eliminating complex management and security risk that land construction brings simultaneously, accelerating protective platform and form speed.To set up defences on plank upper berth fire bed, can prevent electric welding Mars in work progress from directly dropping on plank and cause fire.
Accompanying drawing explanation
Fig. 1 is the utility model front view;
Fig. 2 is Fig. 1 longitudinal sectional view;
Fig. 3 is Fig. 1 partial enlarged drawing;
In figure: 1-precast beam, 2-top board, 3-web, gap between 4-beam, 5-protection canopy, 6-angle steel, 7-embedded sleeve barrel, 8-correcting wedge, 9-standing screw, 10-wooden a tree, used in making timber for boats, 11-plank, 12-fireprotection layer.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail:
As Figure 1-3, the utility model comprises protection canopy 5 and is arranged in the precast beam 1 between two row's bridge piers, precast beam 1 comprises the top board 2 being positioned at precast beam top and the web 3 being positioned at precast beam both sides, forms gap 4 between beam between the top board 2 being arranged in the precast beam 1 between two row's bridge piers.Protection canopy 5 is arranged between the relative web of precast beam 1, to be positioned between beam below gap 4.
The braced structures that protection canopy 5 comprises protection face board and evenly arranges along precast beam length direction.Braced structures comprises left and right braced structures monomer, and braced structures monomer comprises embedded sleeve barrel 7, angle steel 6, correcting wedge 8 and standing screw 9.Protection face board comprises wooden a tree, used in making timber for boats 10, plank 11 and fireprotection layer 12.Embedded sleeve barrel 7 is arranged in web 3, and angle steel 6 is the steel bar that 90 ° of angles extend along bridge length direction, comprises side and end face, and its side is threaded with embedded sleeve barrel 7 by standing screw 9.Correcting wedge 8 is fixed between the side of angle steel 6 and web 3 plate face by standing screw 9, and its lozenges is corresponding with web 3 plate face, for adjusting the gap between angle steel 6 to web 3 plate face.Wood a tree, used in making timber for boats 10 and plank 11 are fixed on the upper surface of angle steel 6 successively, and fireprotection layer 12 is laid on the upper surface of plank 11.Wherein, fireprotection layer 12 is fire-proof asbestos, causes fire for preventing electric welding Mars in work progress from directly dropping on plank.
The arrangement of this protection canopy arrangement is as follows:
(1) precast beam 1 is when precasting yard is produced, the pre-buried embedded sleeve barrel 7 in relevant position bottom web 3 plate face;
(2) precast beam 1 is in place;
(3) angle steel 6 is arranged on bottom web 3 plate face, correcting wedge 8 is set between angle steel 6 side and web, make the lozenges of correcting wedge 8 corresponding with web 3 plate face, by standing screw 9, angle steel 6 and correcting wedge 8 are fixed on embedded sleeve barrel 7, adjust the gap between angle steel 6 and web 3 by correcting wedge 8, make angle steel fixation;
(4), after angle steel 6 fixes, angle steel 6 is installed wooden a tree, used in making timber for boats 10;
(5) after wooden a tree, used in making timber for boats 10 installs, timber boarding 11 on wooden a tree, used in making timber for boats 10;
(6), after plank 11 installs, fire-proof asbestos is established on plank 11 upper berth.
The above; be only detailed description of the invention of the present utility model, it should be pointed out that any those of ordinary skill in the art are in the technical scope disclosed by the utility model; the change that can expect easily or replacement, all should be encompassed within protection domain of the present utility model.

Claims (6)

1. the protection canopy arrangement of a precast beam install construction, comprise protection canopy (5) and be arranged in the precast beam (1) between two row's bridge piers, described precast beam (1) comprises the top board (2) being positioned at precast beam (1) top and the web (3) being positioned at precast beam both sides, gap between beam (4) is formed between precast beam (1) top board (2) between described two row's bridge piers, it is characterized in that: described protection canopy (5) is arranged between the relative web (3) of precast beam (1), be positioned at below, gap between beam (4), described protection canopy (5) is fixed on web (3) bottom.
2. the protection canopy arrangement of precast beam install construction as claimed in claim 1, it is characterized in that: the braced structures that described protection canopy (5) comprises protection face board and evenly arranges along precast beam length direction, described braced structures is fixedly connected with web (3) the plate face of both sides, described protection face board is arranged in braced structures, and protection face board upper surface is corresponding with gap between beam (4).
3. the protection canopy arrangement of precast beam install construction as claimed in claim 2, it is characterized in that: described braced structures comprises left and right braced structures monomer, described braced structures monomer comprises embedded sleeve barrel (7), angle steel (6) and standing screw (9), described embedded sleeve barrel (7) is arranged in web (3), and described angle steel (6) side is threaded with embedded sleeve barrel (7) by standing screw (9).
4. the protection canopy arrangement of precast beam install construction as claimed in claim 3, it is characterized in that: described braced structures monomer also comprises correcting wedge (8), described correcting wedge (8) clamping is arranged between angle steel (6) and web (3), the lozenges of described correcting wedge (8) is corresponding with web (3), and described standing screw (9) is threaded with embedded sleeve barrel (7) through angle steel (6), correcting wedge (8).
5. the protection canopy arrangement of precast beam install construction as claimed in claim 2, is characterized in that: described protection face board comprises the wooden a tree, used in making timber for boats (10) be installed in braced structures and the plank (11) be installed on wooden a tree, used in making timber for boats (10).
6. the protection canopy arrangement of precast beam install construction as claimed in claim 5, is characterized in that: described plank (11) upper surface is equipped with fireprotection layer (12).
CN201520508233.2U 2015-07-14 2015-07-14 Precast beam construction and installation's protection canopy arrangement structure Active CN204826701U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520508233.2U CN204826701U (en) 2015-07-14 2015-07-14 Precast beam construction and installation's protection canopy arrangement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520508233.2U CN204826701U (en) 2015-07-14 2015-07-14 Precast beam construction and installation's protection canopy arrangement structure

Publications (1)

Publication Number Publication Date
CN204826701U true CN204826701U (en) 2015-12-02

Family

ID=54684316

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520508233.2U Active CN204826701U (en) 2015-07-14 2015-07-14 Precast beam construction and installation's protection canopy arrangement structure

Country Status (1)

Country Link
CN (1) CN204826701U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989117A (en) * 2015-07-14 2015-10-21 中交第二航务工程局有限公司 Layout structure and method of protective sheds for precast beam installation and construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989117A (en) * 2015-07-14 2015-10-21 中交第二航务工程局有限公司 Layout structure and method of protective sheds for precast beam installation and construction

Similar Documents

Publication Publication Date Title
CN102108676B (en) Arch bridge construction method for combined beam-steel arch combined system
CN205024907U (en) Vary joint construction of wide flange I -beam roof beam of prestressing force hollow floor and edge of a wing
CN104695337B (en) Self-lifting sliding and turnover construction system and construction method
CN106522997B (en) A kind of construction trolley and construction method of tunnels and underground engineering middle arch rack
CN105064511A (en) Connecting structure of prestress hollow floor slab and H-shaped steel beam and construction method thereof
CN205775674U (en) A kind of across railway prefabricated assembled protecting canopy frame
CN204401997U (en) A kind of suspension type ceiling construction scaffold
CN105544396A (en) Steel arc distributive girder structure of rod type bracket for cast-in-place arch bridge and construction method
CN106567548B (en) Rectangular raw coal bucket is segmented installation method
CN204826701U (en) Precast beam construction and installation's protection canopy arrangement structure
CN104500117B (en) Without repeatedly supporting continuous supporting advanced hydraulic support
CN207194014U (en) Piping lane construction supporting device
CN104989117A (en) Layout structure and method of protective sheds for precast beam installation and construction
CN205000252U (en) External strength nature skeleton of high mound reinforcement
CN205954482U (en) Construction structures of " people " style of calligraphy cable tower entablature support
CN108505539A (en) A kind of beam outrigger platform and its erection method
CN204023422U (en) A kind of assembling Coping Construction operating platform
CN102251477B (en) Traversing construction method for tie bar arch
CN203755178U (en) Novel ultra-wide large-span specially-shaped steel arch bridge construction device
CN205443962U (en) Self -supporting protective structure suitable for simply supported girder bridge construction
CN205205680U (en) Cast -in -place arched bridge member formula support steel arc distribution beam construction
CN110792276A (en) Unit type shaped horizontal protective shed with super high-rise structure and construction method thereof
CN206693035U (en) Fully-mechanized mining working equipment car section belt feeder circulating type safe pedestrian bridge
CN206486811U (en) Template expanding unit for bridge concrete guardrail slding form operation
CN205874988U (en) Case back board prestressing tendons positioner

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant