CN204825815U - Novel unit arrange factory building - Google Patents

Novel unit arrange factory building Download PDF

Info

Publication number
CN204825815U
CN204825815U CN201520451567.0U CN201520451567U CN204825815U CN 204825815 U CN204825815 U CN 204825815U CN 201520451567 U CN201520451567 U CN 201520451567U CN 204825815 U CN204825815 U CN 204825815U
Authority
CN
China
Prior art keywords
factory building
water
hydrogenerator
draft tube
hydraulic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520451567.0U
Other languages
Chinese (zh)
Inventor
韦国宝
闫毅志
余琳君
廖敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming University of Science and Technology
Original Assignee
Kunming University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming University of Science and Technology filed Critical Kunming University of Science and Technology
Priority to CN201520451567.0U priority Critical patent/CN204825815U/en
Application granted granted Critical
Publication of CN204825815U publication Critical patent/CN204825815U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Other Liquid Machine Or Engine Such As Wave Power Use (AREA)

Abstract

The utility model relates to a novel unit arrange factory building belongs to the hydraulic engineering field. The utility model discloses a water -stop dam, diversion pipeline under pressure, the hydraulic turbine, hydraulic generator, draft tube, pipeline under pressure, factory building, the hydraulic turbine, hydraulic generator, draft tube, pipeline under pressure are located the factory building, and pipeline under pressure is introduced with water to the water -stop dam, and pipeline under pressure's water passes through the hydraulic turbine, and the hydraulic turbine drives hydraulic generator, and the tail water between first platform hydraulic generator and last hydraulic generator passes through draft tube outflow back, and through next hydraulic generator of pipeline under pressure entering, last hydraulic generator's tail water passes through the draft tube and flows. The utility model provides an under complicated topography geological conditions plants layout's problem, have better practicality, not only can increase the generated energy, can also reduce engineering excavation volume, practice thrift the cost, increase the stability of factory building.

Description

A kind of novel unit arranges factory building
Technical field
The utility model relates to a kind of novel unit and arranges factory building, belongs to hydraulic engineering field.
Background technology
The hydropower technology of China is in world-class level, China's hydropower development is extremely rapid, all rank first place from world wide Lai Kan China's hydropower installed capacity and generated energy, but from the reserves of hydraulic power potentials, China Water establishes the country of Pingyuan County lower than hydraulic power potentials relative abundance in the world of flooding by cable.This just needs us to optimize energy development, proposes some new technology and develops hydraulic power potentials better.When factory building is arranged, we can run into some precipitous landform sometimes, are not suitable for unit to be arranged in same elevation, at this moment according to landform geological conditions, be arranged on different elevations, so both can increase generating, engineering excavation amount can also be reduced, cost-saving.Do not destroy rock mass and increase factory building stability, all unit tail water is used and can also reduces washing away riverbed.
Summary of the invention
The utility model provides a kind of novel unit and arranges factory building, solve factory building arrange run into can not the problem of Appropriate application topographic and geologic condition.
The technical solution of the utility model is: a kind of novel unit arranges factory building, comprises and blocks water dam 1, diversion penstock 2, the hydraulic turbine 3, hydrogenerator 4, draft tube 5, pressure pipeline 6, factory building 7;
The described hydraulic turbine 3, hydrogenerator 4, draft tube 5, pressure pipeline 6 are positioned at factory building 7, block water dam 1 and water is introduced pressure pipeline 2, the water of pressure pipeline 2 is by the hydraulic turbine 3, the hydraulic turbine 3 drives hydrogenerator 4, after tail water between First hydrogenerator 4 and last hydrogenerator 4 is flowed out by draft tube 5, enter next hydrogenerator 4 through pressure pipeline 6, the tail water of last hydrogenerator 4 is flowed out by draft tube 5.
The multiple stage hydrogenerator 4 arranged in described factory building 7 is separately positioned on different elevations.
Operating principle of the present utility model is:
Block water dam 1 and water is introduced diversion penstock 2, factory building 7 is entered through diversion penstock 2, multiple stage (as 2) hydrogenerator 4 is arranged in factory building 7,2 hydrogenerators 4 are on different elevations, diversion penstock 2 enters last hydrogenerator 4 after water is introduced factory building 7, generating is started after last hydrogenerator 4 is moved by water-band, the tail water that water flows into second hydrogenerator, 4, second hydrogenerator 4 by the draft tube 5 of last hydrogenerator 4 more directly flows out from draft tube 5.
The beneficial effects of the utility model are: solve the problem that factory building is arranged under complex topographical and geological condition condition, have better practicality, not only can increase generated energy, can also reduce engineering excavation amount, cost-saving, increase the stability of factory building.
Accompanying drawing explanation
Fig. 1 is whole factory building arrangement diagram of the present utility model;
Fig. 2 is factory building drawing in side sectional elevation of the present utility model;
Fig. 3 is turbine floor arrangement diagram of the present utility model;
In figure, each label: 1-blocks water dam, 2-diversion penstock, the 3-hydraulic turbine, 4-hydrogenerator, 5-draft tube, 6-pressure pipeline, 7-factory building.
Detailed description of the invention
Embodiment 1: as Figure 1-3, a kind of novel unit arranges factory building, comprises and blocks water dam 1, diversion penstock 2, the hydraulic turbine 3, hydrogenerator 4, draft tube 5, pressure pipeline 6, factory building 7;
The described hydraulic turbine 3, hydrogenerator 4, draft tube 5, pressure pipeline 6 are positioned at factory building 7, block water dam 1 and water is introduced pressure pipeline 2, the water of pressure pipeline 2 is by the hydraulic turbine 3, the hydraulic turbine 3 drives hydrogenerator 4, after tail water between First hydrogenerator 4 and last hydrogenerator 4 is flowed out by draft tube 5, enter next hydrogenerator 4 through pressure pipeline 6, the tail water of last hydrogenerator 4 is flowed out by draft tube 5.
The multiple stage hydrogenerator 4 arranged in described factory building 7 is separately positioned on different elevations.
Embodiment 2: as Figure 1-3, a kind of novel unit arranges factory building, comprises and blocks water dam 1, diversion penstock 2, the hydraulic turbine 3, hydrogenerator 4, draft tube 5, pressure pipeline 6, factory building 7;
The described hydraulic turbine 3, hydrogenerator 4, draft tube 5, pressure pipeline 6 are positioned at factory building 7, block water dam 1 and water is introduced pressure pipeline 2, the water of pressure pipeline 2 is by the hydraulic turbine 3, the hydraulic turbine 3 drives hydrogenerator 4, after tail water between First hydrogenerator 4 and last hydrogenerator 4 is flowed out by draft tube 5, enter next hydrogenerator 4 through pressure pipeline 6, the tail water of last hydrogenerator 4 is flowed out by draft tube 5.
By reference to the accompanying drawings detailed description of the invention of the present utility model is explained in detail above, but the utility model is not limited to above-mentioned embodiment, in the ken that those of ordinary skill in the art possess, various change can also be made under the prerequisite not departing from the utility model aim.

Claims (2)

1. novel unit arranges a factory building, it is characterized in that: comprise and block water dam (1), diversion penstock (2), the hydraulic turbine (3), hydrogenerator (4), draft tube (5), pressure pipeline (6), factory building (7);
The described hydraulic turbine (3), hydrogenerator (4), draft tube (5), pressure pipeline (6) is positioned at factory building (7), block water dam (1) and water is introduced pressure pipeline (2), the water of pressure pipeline (2) is by the hydraulic turbine (3), the hydraulic turbine (3) drives hydrogenerator (4), after tail water between First hydrogenerator (4) and last hydrogenerator (4) is flowed out by draft tube (5), next hydrogenerator (4) is entered through pressure pipeline (6), the tail water of last hydrogenerator (4) is flowed out by draft tube (5).
2. novel unit according to claim 1 arranges factory building, it is characterized in that: the multiple stage hydrogenerator (4) arranged in described factory building (7) is separately positioned on different elevations.
CN201520451567.0U 2015-06-29 2015-06-29 Novel unit arrange factory building Expired - Fee Related CN204825815U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520451567.0U CN204825815U (en) 2015-06-29 2015-06-29 Novel unit arrange factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520451567.0U CN204825815U (en) 2015-06-29 2015-06-29 Novel unit arrange factory building

Publications (1)

Publication Number Publication Date
CN204825815U true CN204825815U (en) 2015-12-02

Family

ID=54683431

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520451567.0U Expired - Fee Related CN204825815U (en) 2015-06-29 2015-06-29 Novel unit arrange factory building

Country Status (1)

Country Link
CN (1) CN204825815U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185010A (en) * 2019-05-17 2019-08-30 天津天发总厂机电设备有限公司 Complete power generation device for recycling tail water of power station
WO2021077330A1 (en) * 2019-10-21 2021-04-29 孙燕 Tidal energy power generation device for small sea areas

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185010A (en) * 2019-05-17 2019-08-30 天津天发总厂机电设备有限公司 Complete power generation device for recycling tail water of power station
CN110185010B (en) * 2019-05-17 2021-05-25 天津天发总厂机电设备有限公司 Complete power generation device for recycling tail water of power station
WO2021077330A1 (en) * 2019-10-21 2021-04-29 孙燕 Tidal energy power generation device for small sea areas

Similar Documents

Publication Publication Date Title
CN204626355U (en) Draining storage station
CN204825815U (en) Novel unit arrange factory building
CN108487176A (en) Manage water model
Xu et al. Developments and characteristics of pumped storage power station in China
CN205475065U (en) Tower import crowd combined layout structure of steep narrow many holes of river valley of side slope bank
CN203429610U (en) Arrangement structure capable of improving minimum pressure of inlet of draft tube and decreasing tailrace surge chamber
CN104612111A (en) Method for increasing and adjusting storage capacity and generating compensation benefit of high-dam leading reservoir
CN105736219A (en) Siphonic power generation system
CN208899441U (en) Power plant building arragement construction for hydro-electric power project
CN203113359U (en) Earth rock cofferdam structure
CN206957862U (en) A kind of paddle wheel formula hydroelectric installation
CN105002863A (en) Ecological flow guaranteeing method based on downstream reservoir scheduling
CN205444132U (en) Spillway tunnel structure
CN204608736U (en) Power generation plant arranged in karst cave
CN103982364A (en) Power generation device
CN207598414U (en) Tide and flow magnitude electricity generation system
CN204000796U (en) Power station in river channel's structure
CN203604103U (en) Pipe-laying type hydroelectric power facility
CN207092034U (en) A kind of Pumped Storage Power Stations
CN203768883U (en) Tunnel differential surge chamber system
CN203977383U (en) Isosceles triangle water inlet structure
RU2377436C1 (en) Well pumped-storage installation
CN205934874U (en) Diversion formula power house arrangement structure
CN103397977A (en) Pipeline-laying type hydroelectric generation method and electric generation facility thereof
CN108677895A (en) Power plant building arrangement for hydro-electric power project

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151202

Termination date: 20170629

CF01 Termination of patent right due to non-payment of annual fee