CN204753398U - Construction equipment of trompil template leaking stoppage - Google Patents
Construction equipment of trompil template leaking stoppage Download PDFInfo
- Publication number
- CN204753398U CN204753398U CN201520440667.3U CN201520440667U CN204753398U CN 204753398 U CN204753398 U CN 204753398U CN 201520440667 U CN201520440667 U CN 201520440667U CN 204753398 U CN204753398 U CN 204753398U
- Authority
- CN
- China
- Prior art keywords
- nut
- template
- perforate
- putty
- bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
Abstract
The utility model provides a construction equipment of trompil template leaking stoppage, this construction equipment includes trompil template, nut, bolt and putty, the trompil template includes nonworking face and working face, and the trompil template has the holing position who has good positioning, is provided with the trompil on holing position, the nut includes first end and second end, the holing position department of the nonworking face side that the second butt welding of nut connect in the trompil template, the bolt leaves certain clearance twist the nut from the first end of nut in between the wrong incoming end of bolt and the second of the nut end, trompil department in trompil template work face side is smeared to putty, putty for the face sand papering level and trompil template work face flushes. Using after the template construction drawing of patterns after this construction equipment leaking stoppage pier shaft and roof beam surface beautifully, not having boss and pit, outward appearance visual effect is good.
Description
Technical field
The utility model relates to building engineering field, particularly relates to the construction equipment of a kind of perforate template leak stopping.
Background technology
At present, the construction in domestic large bridge pier shaft and beam portion, adopts steel form mostly.But in use, Cast-in-place concrete has lateral pressure to template to steel form, can cause the distortion of template; For preventing template deformation, often in template, lacing wire is established in boring, and the template after boring, as reused, certainly exists perforate Lost circulation problems.At present, because existing blocking method is bad to perforate process, after utilizing the template after leak stopping to pour into the concrete construction demoulding, often there are boss or pit in bridge pier shaft and beam surface, and appearance effect is undesirable.
Summary of the invention
The object of embodiment of the present utility model is intended to the deficiency and the defect that overcome existing perforate template blocking method, the utility model provides the construction equipment of a kind of perforate template leak stopping, leak stopping is carried out to the template of boring, template after leak stopping can reuse, after the template perfusion concrete construction demoulding after leak stopping, bridge pier shaft, beam portion or other cast-in-situ concrete structure are surperficial without boss or pit, surface aesthetic.
For solving the problem, the utility model provides the construction equipment of a kind of perforate template leak stopping, comprises perforate template, nut, bolt and putty; Perforate template comprises non-working surface and work plane, and perforate template has the position of opening of having good positioning, and position of opening is provided with perforate; Nut comprises first end and the second end, and the second end of nut is welded on the position with pores of the non-working surface side of perforate template; Bolt is screwed in nut from nut first end, and being screwed between end and the second end of nut of bolt leaves certain gap; Putty is put on the tapping of side, perforate shuttering work face, and the sand papering of putty face is smooth to be flushed with perforate shuttering work face.
According to an aspect of the present utility model, when bolt is screwed in nut, being screwed between end with the second end of nut of bolt at least leaves the distance of 2 pitch.
According to another aspect of the present utility model, the position with pores of the second end weld all around in the non-working surface side of perforate template of nut.
According to another aspect of the present utility model, putty glue, water, hydrated lime face stir and form.
According to another aspect of the present utility model, the internal diameter of nut is greater than the diameter of perforate.
According to another aspect of the present utility model, after putty wipes, smooth with sand papering, putty external surface flushes with shuttering work face.
By using the construction equipment of perforate template of the present utility model leak stopping, splitting after casement plate carries out leak stopping, can reuse it, after utilizing the template after leak stopping to pour into the concrete construction demoulding, pier shaft and beam surface do not have boss or pit, flat-satin, meets people to the specification of outward appearance and requirement attractive in appearance.
Accompanying drawing explanation
Fig. 1 is the perforate template shutoff lateral view of the utility model embodiment;
Fig. 2 is the perforate template shutoff plan view of the utility model embodiment.
Description of reference numerals:
1, perforate template 2, nut 3, bolt 4, putty
Detailed description of the invention
For making the purpose of this utility model, technical scheme and advantage clearly understand, below in conjunction with detailed description of the invention also with reference to accompanying drawing, enter to be further described in detail to the utility model.Should be appreciated that, these describe just exemplary, and do not really want to limit scope of the present utility model.In addition, in the following description, the description to known features and technology is eliminated, to avoid unnecessarily obscuring concept of the present utility model.
Embodiment of the present utility model provides the construction equipment of a kind of perforate template leak stopping.Fig. 1 is the perforate template shutoff lateral view of the utility model embodiment; Fig. 2 is the perforate template shutoff plan view of the utility model embodiment.
As shown in Figure 1, 2, the utility model provides the construction equipment of a kind of perforate template leak stopping, comprises perforate template 1, nut 2, bolt 3 and putty 4; Perforate template 1 comprises non-working surface and work plane, and perforate template 1 has the position of opening of having good positioning, and position of opening is provided with perforate; Nut 2 comprises first end and the second end, and the second end of nut 2 is welded on the position with pores of the non-working surface side of perforate template 1; Bolt 3 is screwed in nut 2 from nut first end, and being screwed between end and the second end of nut 2 of bolt 3 leaves certain gap; Putty 4 is put on the tapping of perforate template 1 work plane side, and the sand papering of putty face is smooth to be flushed with perforate template 1 work plane.
Herein, bolt be screwed into end when referring to that bolt is screwed in nut, enter the one end in nut, accordingly, bolt also comprises the other end be in outside nut.
Preferably, when bolt 3 is screwed in nut 2, being screwed between end with the second end of nut 2 of bolt 3 at least leaves the distance of 2 pitch, neither twist neat by the end that is screwed into of bolt with the second end of nut, is screwed into also not by bolt the second end that end protrudes nut.
But, being screwed between end with the second end of nut of bolt leaves the distance of at least two pitch, in order to when the work plane of perforate template smears putty, a certain amount of smeared putty can be held into the face flushed with perforate shuttering work face after acquisition sand papering, the work plane of perforate template can not be protruded from, making the shuttering work face after shutoff smooth, when reusing, pit or boss can not be produced.
Further, the position with pores of the second end weld all around in the non-working surface side of perforate template of nut 2.Adopt the welding manner of weld all around, in the non-working surface contact portion of nut with apertured panel, around all weld, better, two parts are more firm for such welding effect.
In the present embodiment, putty 4 glue, water, hydrated lime face stir and form.Certainly, the configuration of putty is not limited to the combination of this cited several construction material, can carry out reasonably combined as required.
In the present embodiment, the internal diameter of nut 2 is greater than the diameter of perforate.The internal diameter of nut is greater than the diameter of perforate, effectively blocks perforate.
In the present embodiment, after putty wipes, smooth with sand papering, putty external surface flushes with shuttering work face.
The utility model also provides the construction method of a kind of perforate template leak stopping, for carrying out leak stopping to the perforate in template, comprises the steps:
1. perforate template comprises non-working surface and work plane, and nut comprises first end and the second end, after position of opening that perforate template is had good positioning, the second end of nut is welded on the position with pores of the non-working surface side of perforate template, in position with pores perforate;
2. be screwed in nut by bolt from nut first end, being screwed between end and the second end of nut of bolt leaves certain gap;
3. at the tapping of side, perforate shuttering work face, adopt putty to wipe one's face, adopt sand papering smooth after putty is dry, putty face is flushed with perforate shuttering work face;
4. by bolt be screwed into end be screwed to the second end of nut time, back down putty, bolt of back-outing, then can re-use the perforate of template.
Step 1. in, described perforate can perforate immediately after position with pores has good positioning position; Also can be position of opening of having good positioning, perforate again after welding top nut; Also can be the template that there is perforate.
Step 2. in, leave certain gap being screwed between end with the second end of nut of bolt, in order to be held into the face that a certain amount of putty flushes with shuttering work face afterwards to obtain polishing.
Step 3. in, putty face flushes with perforate shuttering work face, and the template after such leak stopping can reuse, and after the demoulding of pouring construction concrete, pier shaft and beam surface do not have boss or pit, flat-satin, specious.
In embodiment of the present utility model, when bolt is screwed in nut, being screwed between end with the second end of nut of bolt at least leaves the distance of 2 pitch, neither twist neat by the end that is screwed into of bolt with the second end of nut, is screwed into also not by bolt the second end that end protrudes nut.
But, being screwed between end with the second end of nut of bolt leaves the distance of at least two pitch, in order to when the work plane of perforate template smears putty, a certain amount of putty can be held into obtain the rear face flushed with perforate shuttering work face of polishing, the work plane of perforate template can not be protruded from, making the shuttering work face after shutoff smooth, when reusing, pit or boss can not be produced.
Preferably, the position with pores of the second end weld all around in the non-working surface side of perforate template of nut.Adopt the welding manner of weld all around, in the non-working surface contact portion of nut with apertured panel, around all weld, better, two parts are more firm for such welding effect.
In embodiment of the present utility model, putty glue, water, hydrated lime face stir and form.Certainly, putty is not limited to the combination of this several material, can arrange in pairs or groups as required.
In embodiment of the present utility model, the internal diameter of nut is greater than the diameter of perforate.The internal diameter of nut is greater than the diameter of perforate, can hold a certain amount of putty, forms the face effectively blocking perforate.
By construction equipment and the construction method of perforate template of the present utility model leak stopping, splitting after casement plate carries out leak stopping, can reuse it, after utilizing the template after leak stopping to pour into the concrete construction demoulding, pier shaft and beam surface do not have boss or pit, flat-satin, meets people to the specification of outward appearance and requirement attractive in appearance.
Last it is noted that above each embodiment is only in order to illustrate the technical solution of the utility model, be not intended to limit; Although be described in detail the utility model with reference to foregoing embodiments, those of ordinary skill in the art is to be understood that: it still can be modified to the technical scheme described in foregoing embodiments, or carries out equivalent replacement to wherein some or all of technical characteristic; And these amendments or replacement, do not make the essence of appropriate technical solution depart from the scope of each embodiment technical scheme of the utility model.
Claims (5)
1. a construction equipment for perforate template leak stopping, is characterized in that: comprise perforate template, nut, bolt and putty;
Perforate template comprises non-working surface and work plane, and perforate template has the position of opening of having good positioning, and position of opening is provided with perforate;
Nut comprises first end and the second end, and the second end of nut is welded on the position with pores of the non-working surface side of perforate template;
Bolt is screwed in nut from nut first end, and being screwed between end and the second end of nut of bolt leaves certain gap;
Putty is put on the tapping of side, perforate shuttering work face, and the sand papering of putty face is smooth to be flushed with perforate shuttering work face.
2. construction equipment according to claim 1, is characterized in that, when bolt is screwed in nut, being screwed between end with the second end of nut of bolt at least leaves the distance of 2 pitch.
3. construction equipment according to claim 1, is characterized in that, the position with pores of the second end weld all around in the non-working surface side of perforate template of nut.
4. construction equipment according to claim 1, is characterized in that, the internal diameter of nut is greater than the diameter of perforate.
5. construction equipment according to claim 1, is characterized in that, after putty wipes, smooth with sand papering, and putty external surface flushes with shuttering work face.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520440667.3U CN204753398U (en) | 2015-06-24 | 2015-06-24 | Construction equipment of trompil template leaking stoppage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520440667.3U CN204753398U (en) | 2015-06-24 | 2015-06-24 | Construction equipment of trompil template leaking stoppage |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204753398U true CN204753398U (en) | 2015-11-11 |
Family
ID=54468124
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520440667.3U Withdrawn - After Issue CN204753398U (en) | 2015-06-24 | 2015-06-24 | Construction equipment of trompil template leaking stoppage |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204753398U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104929050A (en) * | 2015-06-24 | 2015-09-23 | 北京铁五院工程机械有限公司 | Construction device and construction method for perforated formwork leakage stopping |
CN111705957A (en) * | 2020-06-28 | 2020-09-25 | 河南森宇建筑工程有限公司 | High-strength shear wall and high-verticality construction method |
-
2015
- 2015-06-24 CN CN201520440667.3U patent/CN204753398U/en not_active Withdrawn - After Issue
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104929050A (en) * | 2015-06-24 | 2015-09-23 | 北京铁五院工程机械有限公司 | Construction device and construction method for perforated formwork leakage stopping |
CN111705957A (en) * | 2020-06-28 | 2020-09-25 | 河南森宇建筑工程有限公司 | High-strength shear wall and high-verticality construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204983662U (en) | To drawing screw rod and steel pipe framed bent combination unilateral formwork device | |
CN204753398U (en) | Construction equipment of trompil template leaking stoppage | |
CN105064579A (en) | Construction method guaranteeing pouring formation of toilet water-stop ridge platform | |
CN102367735B (en) | Back-to-back waterstop installation equipment for tunnel construction joint | |
CN204492021U (en) | The windproof fixture of standing seam roof slabs | |
CN103276673A (en) | Reusable bridge rotation construction spherical hinge | |
CN202969967U (en) | Temporary protecting device for once formed floor reserved hole | |
CN106223209B (en) | A kind of buried anchor box and construction method of post-tensioned method prestressed concrete box beam construction | |
CN104929050A (en) | Construction device and construction method for perforated formwork leakage stopping | |
CN204800838U (en) | A built -up plate for parapet production | |
CN203583514U (en) | Pre-buried structure of ultra-deep foundation bolt | |
CN204645627U (en) | A kind of un-bonded prestressed steel strand Special hole mold | |
CN217420549U (en) | Reusable concrete stubble blocking tool | |
CN203403679U (en) | Inner fixing connector, not penetrating through beam bottom template, of pre-buried line pipe | |
CN105756341B (en) | A kind of installation steps of hoistway formwork | |
CN104846753A (en) | Bridge deck opening maintaining method | |
CN210067406U (en) | Scaffold wall connecting piece | |
CN111411774A (en) | Template structure for preventing construction joint dislocation and slurry leakage and construction method | |
CN217734830U (en) | Ancient city wall attaches wall pouring type imitative rammed soil mould | |
CN209924425U (en) | Easy-to-detach aluminum alloy top plate template | |
CN206110668U (en) | Clear water concrete outseam strip | |
CN205000468U (en) | Hole shutoff platform sling is reserved to pipeline | |
CN105544533A (en) | Slab-pile wall digging pile retaining wall flitch plate | |
CN204804322U (en) | Board construction equipment falls in instrument formula building | |
CN204876543U (en) | Template for building engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20151111 Effective date of abandoning: 20160706 |
|
C25 | Abandonment of patent right or utility model to avoid double patenting |