CN204738524U - Safe quick construction scaffold constructional device - Google Patents

Safe quick construction scaffold constructional device Download PDF

Info

Publication number
CN204738524U
CN204738524U CN201520371081.6U CN201520371081U CN204738524U CN 204738524 U CN204738524 U CN 204738524U CN 201520371081 U CN201520371081 U CN 201520371081U CN 204738524 U CN204738524 U CN 204738524U
Authority
CN
China
Prior art keywords
horizon bar
sleeve
vertical rod
main body
fast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520371081.6U
Other languages
Chinese (zh)
Inventor
刘新明
刘恺
江磊
陈阳
景云萍
董梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CREEC Kunming Survey Design and Research Co Ltd
Original Assignee
CREEC Kunming Survey Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CREEC Kunming Survey Design and Research Co Ltd filed Critical CREEC Kunming Survey Design and Research Co Ltd
Priority to CN201520371081.6U priority Critical patent/CN204738524U/en
Application granted granted Critical
Publication of CN204738524U publication Critical patent/CN204738524U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model discloses a safe quick construction scaffold constructional device, including main pole setting, horizontal connection rod, the socket component, the horizon bar connecting piece, the rotating member, the connecting device main part, the bolt, the sleeve, the socket joint pole setting, triangle strengthening rib and main part strengthening rib, the welding of connecting device main part is in main pole setting, be provided with four horizon bar connecting pieces in the connecting device main part, a horizontal connection rod is connected to every horizon bar connecting piece, still be provided with a rotating member on every horizon bar connecting piece, the rotating member is fixed on the sleeve, the sleeve weld is in main pole setting, be provided with a gliding bolt from top to bottom on the sleeve, the bolt connection rotating member, the socket joint pole setting is connected through the socket component in main pole setting top, be provided with triangle strengthening rib and main part strengthening rib in the connecting device main part, can standardize production and wide application and be under construction in building engineering, install fast and safety.

Description

Building operations scaffolding structure device safely and fast
Technical field
The utility model relates to architectural engineering construction technique field, especially one building operations scaffolding structure device safely and fast.
Background technology
The means for fastening scaffolding that current building operations adopts is fastener type, bowl fastening type, disc type and spigot-and-socket substantially.
Existing means for fastening scaffolding because the weight of too much consideration rod member and syndeton too simple, although also reach the requirement of Fast Installation in work progress, but when construction transport and use, link is easily impaired, or due to artificial factor, can not accurately put in place after installation, produce the indivedual discrepancy of scaffold, and cause overall collapse, and so there is installation accurately not put in place, the defect of poor stability.201320448951.6) and patent existing patent: means for fastening scaffolding (application number:: scaffold connecting joint structure (application number: 201410467556.1), although solve disconnection and overall collapse problem, device overall structure is scattered, still there is operating procedure more, device feature is many, the problem that operation efficiency is low.
Utility model content
The purpose of this utility model is for above-mentioned the deficiencies in the prior art, provides a kind of building operations scaffolding structure device safely and fast.
For achieving the above object, the utility model adopts following technical scheme to be achieved: one is building operations scaffolding structure device safely and fast, comprise main vertical rod 1, horizontal brace rod 2, socket component 3, horizon bar connector 4, revolving part 5, linkage main body 6, latch 7, sleeve 8, socket joint vertical rod 9, triangle reinforcing rib 10 and main body reinforcing rib 11, linkage main body 6 is weldingly fixed in main vertical rod 1, linkage main body 6 is provided with four horizon bar connectors 4, each horizon bar connector 4 connects a horizontal brace rod 2, the fast clamp type that linkage main body 6 accepts four horizontal brace rods 4 is installed, not only stable but also high efficiency, each horizon bar connector 4 is also provided with a revolving part 5, revolving part 5 is fixed on sleeve 8, sleeve 8 is welded in main vertical rod 1, sleeve 8 is provided with a latch that can slide up and down 7, latch 7 connects on any one revolving part 5, namely 5 can be fixed fast, a step can complete the locking of horizontal direction again, socket joint vertical rod 9 is connected by socket component 3 above main vertical rod 1, linkage main body 6 is provided with triangle reinforcing rib 10 and main body reinforcing rib 11.
Described revolving part 5 can present 45 degree of left rotation and right rotation, namely can fix the vertical displacement of four horizontal brace rods 4 simultaneously, strengthen coupling stiffness again.
Described main vertical rod 1 adopts steel pipe manufacturing, and length is 1500-1700 millimeter.
Described socket component 3 socket joint length is not less than 50 millimeters.
Described horizon bar 2 adopts steel pipe manufacturing, and length is 1500-1700 millimeter.
In the technical solution of the utility model, coordinated with revolving part 5, the effective of latch 7 by linkage main body 6, operationally safe, efficient, convenient, 3 parts can be used, connection that 2 actions just can complete main vertical rod 1 and four horizontal brace rods 4.
Accompanying drawing explanation
Fig. 1 is plan view of the present utility model;
Fig. 2 is structure chart of the present utility model;
In figure: the main vertical rod of 1-, 2-horizontal brace rod, 3-socket component, 4-horizon bar connector, 5-revolving part, 6-linkage main body, 7-latch, 8-sleeve, the vertical rod of 9-socket joint, 10-triangle reinforcing rib, 11-main body reinforcing rib.
Detailed description of the invention
Below in conjunction with accompanying drawing 1-2 and specific embodiment, the utility model is described further.
As shown in Figure 1-2, one is building operations scaffolding structure device safely and fast, comprise main vertical rod 1, horizontal brace rod 2, socket component 3, horizon bar connector 4, revolving part 5, linkage main body 6, latch 7, sleeve 8, socket joint vertical rod 9, triangle reinforcing rib 10 and main body reinforcing rib 11, main vertical rod 1 adopts steel pipe manufacturing, length is 1500-1700 millimeter, linkage main body 6 is weldingly fixed in main vertical rod 1, linkage main body 6 is provided with four horizon bar connectors 4, each horizon bar connector 4 connects a horizontal brace rod 2, horizon bar 2 also adopts steel pipe manufacturing, length is 1500-1700 millimeter, caliber is identical with main vertical rod 1, the fast clamp type that linkage main body 6 accepts four horizontal brace rods 4 is installed, not only stable but also high efficiency, each horizon bar connector 4 is also provided with a revolving part 5, revolving part 5 is fixed on sleeve 8, described revolving part 5 can present 45 degree of left rotation and right rotation, both can fix the vertical displacement of four horizontal brace rods 4 simultaneously, and can coupling stiffness have been strengthened again, sleeve 8 is welded in main vertical rod 1, sleeve 8 is also provided with a latch that can slide up and down 7, latch 7 is connected on one of them revolving part 5,5 can either be fixed fast, a step can complete the locking of horizontal direction again, connect socket joint vertical rod 9 by socket component 3 above main vertical rod 1, described socket component 3 socket joint length is not less than 50 millimeters, triangle reinforcing rib 10 and main body reinforcing rib 11 adopt steel plate to make, and weld with linkage main body 6, sleeve 8, revolving part 5, linkage main body 6, latch 7, socket component 3, horizon bar connector 4 all adopt the mode of machining to obtain.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (5)

1. a building operations scaffolding structure device safely and fast, it is characterized in that, comprise main vertical rod (1), horizontal brace rod (2), socket component (3), horizon bar connector (4), revolving part (5), linkage main body (6), latch (7), sleeve (8), socket joint vertical rod (9), triangle reinforcing rib (10) and main body reinforcing rib (11), linkage main body (6) is weldingly fixed in main vertical rod (1), linkage main body (6) is provided with four horizon bar connectors (4), each horizon bar connector (4) connects a horizontal brace rod (2), each horizon bar connector (4) is also provided with a revolving part (5), revolving part (5) is fixed on sleeve (8), sleeve (8) is welded in main vertical rod (1), sleeve (8) is provided with a latch that can slide up and down (7), latch (7) connects revolving part (5), main vertical rod (1) top connects socket joint vertical rod (9) by socket component (3), linkage main body (6) is provided with triangle reinforcing rib (10) and main body reinforcing rib (11).
2. one according to claim 1 building operations scaffolding structure device safely and fast, is characterized in that, the anglec of rotation of described revolving part (5) is 45 degree.
3. one according to claim 1 building operations scaffolding structure device safely and fast, is characterized in that, described main vertical rod (1) adopts steel pipe manufacturing, and length is 1500-1700 millimeter.
4. one according to claim 1 building operations scaffolding structure device safely and fast, is characterized in that, described socket component (3) socket joint length is not less than 50 millimeters.
5. one according to claim 1 building operations scaffolding structure device safely and fast, is characterized in that, described horizon bar (2) adopts steel pipe manufacturing, and length is 1500-1700 millimeter.
CN201520371081.6U 2015-06-02 2015-06-02 Safe quick construction scaffold constructional device Expired - Fee Related CN204738524U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520371081.6U CN204738524U (en) 2015-06-02 2015-06-02 Safe quick construction scaffold constructional device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520371081.6U CN204738524U (en) 2015-06-02 2015-06-02 Safe quick construction scaffold constructional device

Publications (1)

Publication Number Publication Date
CN204738524U true CN204738524U (en) 2015-11-04

Family

ID=54420267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520371081.6U Expired - Fee Related CN204738524U (en) 2015-06-02 2015-06-02 Safe quick construction scaffold constructional device

Country Status (1)

Country Link
CN (1) CN204738524U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485713A (en) * 2020-04-13 2020-08-04 宁波铭奥科技发展有限公司 Roller bearing type joint with changeable horizontal angle of steel pipe bearing frame for building construction tool

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111485713A (en) * 2020-04-13 2020-08-04 宁波铭奥科技发展有限公司 Roller bearing type joint with changeable horizontal angle of steel pipe bearing frame for building construction tool

Similar Documents

Publication Publication Date Title
CN204738524U (en) Safe quick construction scaffold constructional device
CN211499678U (en) Construction fastener formula steel pipe template strutting arrangement
CN208347296U (en) A kind of belt lacing rod piece
CN104372928A (en) Cantilever type scaffold assembly
CN201809880U (en) Curtain wall upright post hanging connecting structure
CN201991229U (en) Combined fixture of beam
CN205206267U (en) Safe multi -functional scaffold
CN207633226U (en) Easy-to-mount high stability supporting bridge fixed frame
CN102367701A (en) Quick connecting piece for scaffolds
CN205276854U (en) A fastener for connecting steel pipe
CN204983719U (en) Assembly type structure faces flat protection of edge water and chooses net
CN207878469U (en) The steel support structure that foundation pit type is connected with X-shaped connector
CN203834686U (en) Corrugated web H-shaped steel beam and column connecting structure
CN209369185U (en) Multidirectional reinforcing steel bar connecting device
CN102777703A (en) Assembly type light pipeline hanger
CN203452356U (en) Combined frame type scaffold
CN209942342U (en) Steel constructs tower support connecting piece
CN201714048U (en) Chrysanthemum clip connection type scaffold
CN204552069U (en) A kind of novel combination type scaffold
CN204823744U (en) Crane end beam end plate welded structure
CN204152192U (en) A kind of scaffold fastenings
CN205296397U (en) Huge node field weld construction platform of box steel truss polylinker
CN204163365U (en) A kind of overhanging scaffold assembly
CN214117248U (en) Reinforcing bar and sleeve auxiliary device that counterpoints
CN205063350U (en) Portable assembled horizontal channel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151104

Termination date: 20200602

CF01 Termination of patent right due to non-payment of annual fee