CN204691825U - Based on the coal illegal mining monitoring system of coal mine output and energy consumption monitoring - Google Patents

Based on the coal illegal mining monitoring system of coal mine output and energy consumption monitoring Download PDF

Info

Publication number
CN204691825U
CN204691825U CN201520285359.8U CN201520285359U CN204691825U CN 204691825 U CN204691825 U CN 204691825U CN 201520285359 U CN201520285359 U CN 201520285359U CN 204691825 U CN204691825 U CN 204691825U
Authority
CN
China
Prior art keywords
coal
energy consumption
monitoring
equipment
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520285359.8U
Other languages
Chinese (zh)
Inventor
孙继平
刘毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology Beijing CUMTB
Original Assignee
China University of Mining and Technology Beijing CUMTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology Beijing CUMTB filed Critical China University of Mining and Technology Beijing CUMTB
Priority to CN201520285359.8U priority Critical patent/CN204691825U/en
Application granted granted Critical
Publication of CN204691825U publication Critical patent/CN204691825U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Arrangements For Transmission Of Measured Signals (AREA)

Abstract

The utility model discloses a kind of coal illegal mining monitoring system based on coal mine output and energy consumption monitoring, native system Real-Time Monitoring mine coal carbon yield and all getting working face coal productions in this mine resource circle, system comprises transport measuring equipment, haulage device energy consumption measure equipment, main shaft substation, monitor server and monitoring host computer etc.; Monitor server monitoring coal production and haulage device energy consumption data, when the exception or energy consumption data finding yield data is abnormal, send coal illegal mining alarm signal and output metering error alarm signal to monitoring host computer.Native system more adequately can find that coal illegal mining and some colliery are conceal the doubtful situations that actual production takes deliberately to turn down or heighten equipment variable; avoid the various human factors of artificial supervision; further strengthening illegal mining supervision, containment illegal mining event occurs, and protects national coal resource.

Description

Based on the coal illegal mining monitoring system of coal mine output and energy consumption monitoring
Technical field
The utility model relates to a kind of coal illegal mining monitoring system based on coal mine output and energy consumption monitoring, and this system relates to sensing data process and the field such as to communicate.
Background technology
Coal is China's main energy sources, accounts for primary energy 70%.Coal industry is high risk industries, and the accidents such as gas, floods, fire, top board, coal dust annoying Safety of Coal Mine Production.In addition, accident investigation shows, in coal production super layer cross the border illegal mining cause death by accident, in coal mining accident, occupy larger ratio.
Coal illegal mining has the features such as disguise is strong, discovery is difficult, supervision difficulty.For Timeliness coverage and supervision, some local administrative departments accredit ore deposit personnel to private small coal mines, exercise supervision inspection.But bribe because ore deposit is main, the reason such as the personnel of supervision and check in ore deposit professional ability and sense of responsibility difference, not having can Timeliness coverage and contain illegal mining and then play death by accident together with leading to.Therefore, be badly in need of the Automatic Measurement Technique that research prevents coal illegal mining, avoid the various human factors of artificial supervision, further strengthening illegal mining supervision, containment illegal mining event occurs, and protects national coal resource, prevents the casualty accident caused by illegal mining.
Summary of the invention
The utility model proposes a kind of coal illegal mining monitoring system based on coal mine output and energy consumption monitoring, system mainly comprises transport measuring equipment, haulage device energy consumption measure equipment, main shaft substation, getting working face substation, down-hole switch, the network switch, the communication server, monitor server and monitoring host computer.Transport measuring equipment is responsible for gathering coal production amount data; Haulage device energy consumption measure equipment is responsible for the energy consumption data gathering haulage device, comprises power consumption, power or electric current; Main shaft substation is responsible for communicate access and the exchanges data of transport measuring equipment and haulage device energy consumption measure equipment in main shaft; Getting working face substation is responsible for communicate access and the exchanges data of getting working face transport measuring equipment and haulage device energy consumption measure equipment; Down-hole switch is responsible for access and the exchanges data of substation; The network switch is responsible for management and the exchanges data of the equipment accessed network; The communication server is responsible for receiving transport measuring equipment and the data uploaded of haulage device energy consumption measure equipment, and is uploaded to monitor server to data packing; Monitor server is responsible for gathering output and equipment energy consumption data, store and monitoring, and sends coal illegal mining alarm signal and output metering error alarm signal, and provide inquiry to transfer service for monitoring host computer user according to monitoring result to monitoring host computer; Monitoring host computer has sound and light of alarm, can check that monitor server provides warning message and historical data.
1. this system comprises further: installation and transportation measuring equipment on coal main shaft travelling belt and on getting working face travelling belt, comprises elevator weighing-appliance, belted electronic balance, controlled nucleon operated belt conveyor scale or laser scale.
2. this system comprises further: on coal main shaft travelling belt He on getting working face travelling belt, install energy consumption measure equipment, comprise energy meter, power meter or ammeter.
3. this system comprises further: transport measuring equipment and equipment energy consumption measuring equipment are according to passing through on-scene communication bus transfer to substation.
4. this system comprises further: substation is connected by mining ethernet ring network with down-hole switch.
5. this system comprises further: the communication server is connected by internet or coal network with monitor server.
Accompanying drawing explanation
Fig. 1 is based on the coal illegal mining monitoring system schematic diagram of coal mine output and energy consumption monitoring.
Fig. 2 is based on the course of work schematic diagram of the coal illegal mining monitoring system of coal mine output and energy consumption monitoring.
Detailed description of the invention
Coal illegal mining monitoring system based on coal mine output and energy consumption monitoring forms as shown in Figure 1, mainly comprises:
1. the communication server (101), the communication server is responsible for receiving and is stored transport measuring equipment and the data uploaded of haulage device energy consumption measure equipment, and is uploaded to monitor server to data packing.
2. monitoring host computer (102); Have sound and light of alarm, production supervision administrative staff check each coal production situation in area under one's jurisdiction by monitoring host computer, check that monitor server (203) provides warning message, and can transfer historical data from monitor server.
3. monitor server (103); Be responsible for gathering output and equipment energy consumption data, store and monitoring, send coal illegal mining alarm signal and output metering error alarm signal according to monitoring result to monitoring host computer (202), and provide inquiry to transfer service for monitoring host computer (202) user.
4. the network switch (104); Be responsible for management and the exchanges data of the equipment accessed network.
5. down-hole switch (105); Be responsible for access and the exchanges data of substation, there is flameproof enclosure, meet underground coal mine requirement of explosion proof.
6. getting working face substation (106); Be responsible for communication access and the exchanges data of getting working face front end data acquisition equipment, there is flameproof enclosure, meet underground coal mine requirement of explosion proof.
7. main shaft substation (107); Be responsible for communication access and the exchanges data of main shaft Inner Front End data acquisition equipment, there is flameproof enclosure, meet underground coal mine requirement of explosion proof.
8. transport measuring equipment (108); Comprise elevator weighing-appliance, belted electronic balance, controlled nucleon operated belt conveyor scale or laser scale.
9. haulage device energy consumption measure equipment (109); Comprise energy meter, power meter or ammeter.
Based on the coal illegal mining monitoring system of coal mine output and energy consumption monitoring the course of work as shown in Figure 2:
1. the coal production data of (201) transport measuring equipment collection and the energy consumption data of haulage device energy consumption measure equipment collection are by communication line to substation, and communication line adopts on-scene communication bus.
2. (202) substation transmits data to down-hole switch by network communication circuit, and network communication circuit medium can adopt twisted-pair feeder, coaxial cable or optical fiber.
3. data are transferred to the aboveground network switch by mining ethernet ring network by (203) down-hole switch, data are issued the communication server by the network switch, the communication server receives data, data are stored, data is packed by internet or the long-range monitor server being sent to higher level supervision department of coal network simultaneously.
4. (204) monitor server analyzes mine coal total output data and all coal face coal production data, when monitor the ratio of all coal face coal production sums in the mine coal carbon yield data and this mine resource circle uploaded or difference meet impose a condition time, send coal illegal mining alarm signal.Should be equal to foundation with total output and each coal face output sum, whether this colliery of Timeliness coverage exists the doubtful situations of illegal mining.
5. the energy consumption data of (205) monitor server monitoring coal master haulage device and the output metering device data on this equipment, when monitor the actual Energy in use of haulage device much larger than the consumption needed for coal production and meet impose a condition time, send output metering error alarm signal.With the energy consumption data of main haulage device for foundation finds this colliery total output measuring equipment Problems existing, some colliery of Timeliness coverage is conceal the doubtful situations that actual production takes deliberately to turn down equipment variable.
6. (206) monitor server Real-Time Monitoring colliery is all is provided with the energy consumption data of each getting working face haulage device of measuring equipment and the measuring equipment data on this equipment, when monitoring the actual Energy in use of haulage device much smaller than consumption needed for coal production, send output metering error alarm signal.With the energy consumption data of haulage device for according to finding getting working face transport measuring equipment Problems existing, the doubtful situations of equipment variable is taked deliberately to heighten for meeting the monitoring condition of (204) in some colliery of Timeliness coverage.
7. (207) monitoring host computer shows the data cases such as output in real time, when receiving the data-signal meeting alert if, then and automatic sound-light alarm; Produce supervisor and can check Realtime Alerts situation and equipment in detail, transfer historical data, take measures on customs clearance.

Claims (6)

1. based on a coal illegal mining monitoring system for coal mine output and energy consumption monitoring, it is characterized in that: system mainly comprises: transport measuring equipment, haulage device energy consumption measure equipment, main shaft substation, getting working face substation, down-hole switch, the network switch, the communication server, monitor server and monitoring host computer; Transport measuring equipment is responsible for gathering coal production amount data; Haulage device energy consumption measure equipment is responsible for the energy consumption data gathering haulage device, comprises power consumption, power or electric current; Main shaft substation is responsible for communicate access and the exchanges data of transport measuring equipment and haulage device energy consumption measure equipment in main shaft; Getting working face substation is responsible for communicate access and the exchanges data of getting working face transport measuring equipment and haulage device energy consumption measure equipment; Down-hole switch is responsible for access and the exchanges data of substation; The network switch is responsible for management and the exchanges data of the equipment accessed network; The communication server is responsible for receiving transport measuring equipment and the data uploaded of haulage device energy consumption measure equipment, and is uploaded to monitor server to data packing; Monitor server is responsible for gathering output and equipment energy consumption data, store and monitoring, and sends coal illegal mining alarm signal and output metering error alarm signal, and provide inquiry to transfer service for monitoring host computer user according to monitoring result to monitoring host computer; Monitoring host computer has sound and light of alarm, can check that monitor server provides warning message and historical data.
2. coal illegal mining monitoring system as claimed in claim 1, is characterized in that: installation and transportation measuring equipment on coal main shaft travelling belt and on getting working face travelling belt, comprises elevator weighing-appliance, belted electronic balance, controlled nucleon operated belt conveyor scale or laser scale.
3. coal illegal mining monitoring system as claimed in claim 1, is characterized in that: on coal main shaft travelling belt He on getting working face travelling belt, install energy consumption measure equipment, comprise energy meter, power meter or ammeter.
4. coal illegal mining monitoring system as claimed in claim 1, is characterized in that: transport measuring equipment and equipment energy consumption measuring equipment are according to passing through on-scene communication bus transfer to substation.
5. coal illegal mining monitoring system as claimed in claim 1, is characterized in that: substation is connected by mining ethernet ring network with down-hole switch.
6. coal illegal mining monitoring system as claimed in claim 1, is characterized in that: the communication server is connected by internet or coal network with monitor server.
CN201520285359.8U 2015-05-06 2015-05-06 Based on the coal illegal mining monitoring system of coal mine output and energy consumption monitoring Expired - Fee Related CN204691825U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520285359.8U CN204691825U (en) 2015-05-06 2015-05-06 Based on the coal illegal mining monitoring system of coal mine output and energy consumption monitoring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520285359.8U CN204691825U (en) 2015-05-06 2015-05-06 Based on the coal illegal mining monitoring system of coal mine output and energy consumption monitoring

Publications (1)

Publication Number Publication Date
CN204691825U true CN204691825U (en) 2015-10-07

Family

ID=54232128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520285359.8U Expired - Fee Related CN204691825U (en) 2015-05-06 2015-05-06 Based on the coal illegal mining monitoring system of coal mine output and energy consumption monitoring

Country Status (1)

Country Link
CN (1) CN204691825U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104806294A (en) * 2015-05-06 2015-07-29 中国矿业大学(北京) Method for monitoring coal illegal mining based on coal output and energy consumption monitoring
CN108446998A (en) * 2018-03-29 2018-08-24 成都精灵云科技有限公司 Coal mine output based on cloud platform and mass monitoring system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104806294A (en) * 2015-05-06 2015-07-29 中国矿业大学(北京) Method for monitoring coal illegal mining based on coal output and energy consumption monitoring
CN108446998A (en) * 2018-03-29 2018-08-24 成都精灵云科技有限公司 Coal mine output based on cloud platform and mass monitoring system

Similar Documents

Publication Publication Date Title
CN203070069U (en) Integrated monitoring system for power cable tunnel
CN203283810U (en) Underground belt conveyor detecting system based on image processing technique
CN202001063U (en) System for pre-warning water disaster of mine bottom plate
CN104806286B (en) Underground LED lighting escaping system based on power carrier communication
CN103899356A (en) Integrated information system for monitoring, early warning, management and control of mine water disasters
CN207813654U (en) Based on ranging and the coal working face calamity forecast system to test the speed
CN203809051U (en) Fiber bragg grating based safety monitoring system for mine tunnel
CN203035263U (en) Underground ventilation monitoring system
CN103942635A (en) Coal-mine gas safety intelligent patrol system
CN106597213A (en) Distributed power transmission and distribution line maintenance operation safety protection digital monitoring system
CN104806294A (en) Method for monitoring coal illegal mining based on coal output and energy consumption monitoring
CN205264004U (en) Nearly electric early warning device of high -voltage line
CN209070698U (en) A kind of coal mine gas monitoring and positioning device and system based on BIM
CN202024755U (en) High-voltage cable construction safety monitoring system based on magnetic field sensor
CN204691825U (en) Based on the coal illegal mining monitoring system of coal mine output and energy consumption monitoring
CN204591347U (en) Based on the coal illegal mining monitoring system of personnel positioning
CN205638554U (en) Colliery floods alarm system based on image and hydrologic data monitoring
CN101968538A (en) Positioning management system for underground personnel
CN106290743A (en) A kind of coal mine gas concentration detection and safety early warning device
CN101956566B (en) Dynamic disaster monitoring substation of coal rock
CN102705012A (en) Monitoring system of coal roadway roof separation based on M-BUS
LU500830B1 (en) Coal Mine Safety Monitoring and Early Warning System
CN102721406B (en) Construction beam gesture monitoring system
CN204357488U (en) Based on the driving face in coal mine bump warning system of image
CN204299615U (en) A kind of down-hole LED illumination escape system based on power line carrier, PLC

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151007

Termination date: 20200506