CN204662916U - For the construction operation platform between the narrow and small superaltitude of double-deck exterior wall - Google Patents

For the construction operation platform between the narrow and small superaltitude of double-deck exterior wall Download PDF

Info

Publication number
CN204662916U
CN204662916U CN201520148378.6U CN201520148378U CN204662916U CN 204662916 U CN204662916 U CN 204662916U CN 201520148378 U CN201520148378 U CN 201520148378U CN 204662916 U CN204662916 U CN 204662916U
Authority
CN
China
Prior art keywords
operation platform
construction
double
column
construction operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520148378.6U
Other languages
Chinese (zh)
Inventor
郭超
南洋
赵伟
杨士杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201520148378.6U priority Critical patent/CN204662916U/en
Application granted granted Critical
Publication of CN204662916U publication Critical patent/CN204662916U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of for the construction operation platform between the narrow and small superaltitude of double-deck exterior wall, comprise: operation support body, comprise operating desk and prop up the column being located at four bights of described operating desk, the inner side of described column is connected with ruggedized construction, described ruggedized construction and described operating desk are connected and fixed, the described column being located at double-deck inner side of outer wall is provided with sleeve, and described sleeve is fixedly arranged on the outside of described column; And connector, have for plugging the inserted terminal and socket end that is relative with described inserted terminal, that Gong be fixedly connected with that connect described sleeve.The utility model construction operation platform when solve conventional steel tube clamps formula scaffold peace tear open inconvenience, consumption large, synchronously can not set up with agent structure, can pacify flexibly in narrow and small superaltitude and dismount and mount full operation, turnover use and then ensured operating personnel's safety and building engineering construction quality, save the building operations cycle simultaneously.

Description

For the construction operation platform between the narrow and small superaltitude of double-deck exterior wall
Technical field
The utility model relates to the realm of building construction, espespecially a kind of for the construction operation platform between the narrow and small superaltitude of double-deck exterior wall.
Background technology
In Structural Engineering work progress, general employing external scaffolding is as temporary operating platform, for construction provides safeguard, this external scaffolding is generally synchronously set up with structure construction, but for the narrow and small superelevation area of space of the double-deck exterior wall of LOFT layer, the structure of this double-deck exterior wall is establish one deck exterior wall again in the outside of the alien invasion of building body, defines small space between this exterior wall and alien invasion, and the height of this small space is at least the height of single floor.Conventional external scaffolding engineering is owing to being subject to the restriction of double-deck exterior wall small space form of structure, existence synchronously can not set up external scaffolding, the problem ensureing follow-up each stage, each position can not be arranged into comprehensively, therefore at the narrow and small superelevation area of space of the double-deck exterior wall of LOFT layer in work progress, need to arrange a kind of temporary platform to provide constructor safety work, ensure construction safety and the quality of later process.
Utility model content
The purpose of this utility model is the defect overcoming prior art, there is provided a kind of for the construction operation platform between the narrow and small superaltitude of double-deck exterior wall, solve the problem that the restriction being subject to form of structure in the narrow and small superelevation area of space of existing double-deck exterior wall synchronously can not set up external scaffolding.
The technical scheme realizing above-mentioned purpose is:
The utility model is a kind of for the construction operation platform between the narrow and small superaltitude of double-deck exterior wall, comprising:
Operation support body, comprises operating desk and props up the column being located at described operating desk; Described column is provided with ruggedized construction, and described ruggedized construction and described operating desk are connected and fixed; The described column being located at double-deck inner side of outer wall is provided with sleeve; And
Connector, has for plugging the inserted terminal and link that is relative with described inserted terminal, that Gong be fixedly connected with that connect described sleeve.
A kind of construction operation platform be applicable between narrow and small superaltitude is provided, in superelevation small space, effective utilization can not be synchronously set up at conventional steel design of coupler scaffold, in the ungratified situation of market tradition external scaffolding, operation support body is installed in small space, adopt connector that handling frame and structural beams are carried out mutual bolt to guarantee the safety of operating platform, ruggedized construction is set in addition on the column of operation support body, improve the steadiness of operation support body further.The utility model construction operation platform when solve conventional steel tube clamps formula scaffold peace tear open inconvenience, consumption large, synchronously can not set up with agent structure, can pacify flexibly in narrow and small superaltitude and dismount and mount full operation, turnover use and then ensured operating personnel's safety and building engineering construction quality, save the building operations cycle simultaneously.
The further improvement of the construction operation platform that the utility model is used between the narrow and small superaltitude of double-deck exterior wall is, described operating desk has four strong points, each strong point place installs described column, between two columns being wherein located at described double-deck inner side of outer wall, support and connection have two diagonal members, and two described diagonal members are that X-shaped is arranged.
The further improvement of the construction operation platform that the utility model is used between the narrow and small superaltitude of double-deck exterior wall is, being located at support and connection between two columns outside described double-deck exterior wall has two diagonal members, and two described diagonal members are that X-shaped is arranged.
The further improvement of the construction operation platform that the utility model is used between the narrow and small superaltitude of double-deck exterior wall is, also comprises being located under described operation support body and another identical with described handling frame body structure of structure operates support body.
The further improvement of the construction operation platform that the utility model is used between the narrow and small superaltitude of double-deck exterior wall is, described operating desk comprises framework and is layed in the stripe board on described framework.
The further improvement of the construction operation platform that the utility model is used between the narrow and small superaltitude of double-deck exterior wall is, described ruggedized construction comprises two cross bars and a montant, one end of described cross bar is vertically connected at described column, described montant is connected to the other end of described cross bar, and the bottom of described montant is curved bends to described column and be connected to described column.
The further improvement of the construction operation platform that the utility model is used between the narrow and small superaltitude of double-deck exterior wall is, in described ruggedized construction, superposed described cross bar is fixedly connected with described framework.
The further improvement of the construction operation platform that the utility model is used between the narrow and small superaltitude of double-deck exterior wall is, the surrounding of described operating desk is equipped with guard bar structure.
The further improvement of the construction operation platform that the utility model is used between the narrow and small superaltitude of double-deck exterior wall is, described connector is E type connector, comprise three vertical bars that horizontally set connecting rod and interval vertical are connected to described connecting rod, the both ends of described connecting rod are located at by wherein two described vertical bars.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model for a preferred embodiment of the construction operation platform between the narrow and small superaltitude of double-deck exterior wall;
Fig. 2 is the structural representation of the two-layer operation support body of the utility model construction operation platform;
Fig. 3 is the structural representation of one deck operation support body of the utility model construction operation platform; And
Fig. 4 is the syndeton schematic diagram of connector attended operation support body and structural beams in the utility model construction operation platform.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
The utility model provides a kind of for the construction operation platform between the narrow and small superaltitude of double-deck exterior wall, turnover can use, can play green energy conservation, and be supplied to the platform of constructor's safety work in the narrow and small superaltitude of double-deck exterior wall.The utility model is particularly useful for the constructing operation between the narrow and small superaltitude of double-deck exterior wall under green building LOFT layer design concept, within construction operation platform of the present utility model props up and is located between the narrow and small superaltitude of double-deck exterior wall, by operation support body, E type connector, guard bar structure assembles, operation support body splices assembling by column and operating desk, E type connector one end is bolted to the column of handling frame, the other end and the active bolt of structural beams, guard bar structure is bolted to the top of operation support body, the utility model construction operation platform tears inconvenience open in solution conventional steel tube clamps formula scaffold peace, consumption is large, when synchronously can not set up with agent structure, can pacify flexibly in narrow and small superspace and tear open, safety operation, turnover uses, and then ensure the operating platform of construction safety and quality.Be described below in conjunction with the structure of accompanying drawing to the utility model construction operation platform.
As shown in Figure 1 and Figure 4, the utility model is used for the construction operation platform between the narrow and small superaltitude of double-deck exterior wall, propping up is located in the narrow and small superaltitude of double-deck exterior wall, this construction operation platform comprises operation support body 11 and E type connector 12, this operation support body 11 comprises operating desk 111 and props up the column 112 being located at four bights of operating desk 111, the inner side of column 112 is connected with ruggedized construction 113, this ruggedized construction 113 is connected and fixed with operating desk 111, the column 112 being located at double-deck inner side of outer wall is provided with sleeve 114, and sleeve 114 is fixedly arranged on the outside of column 112.This E type connector 12 has for plugging the inserted terminal of branch sleeve 114 and the link that Gong be fixedly connected with relative to this inserted terminal, this inserted terminal is inserted in sleeve 114, for the column 112 of attended operation support body 11, link is for being fixed on attachment basis by this E type connector 12, preferably, the mode that this link adopts socket to connect, sheathedly be fixed in structural beams 20, operation support body 11 is fixedly connected with the building body of double-deck exterior wall, guarantee the firm safety of this operation support body 11, operating desk 111 on operation support body 11 provides job platform for constructor, this operating desk 111 comprises framework and is layed in the stripe board on framework.
Consult Fig. 1, show the structural representation of the utility model for a preferred embodiment of the construction operation platform between the narrow and small superaltitude of double-deck exterior wall.Below in conjunction with Fig. 1, structure the utility model being used for a preferred embodiment of the construction operation platform between the narrow and small superaltitude of double-deck exterior wall is described.
As shown in Figure 1, the utility model construction operation platform be used between the narrow and small superaltitude of double-deck exterior wall props up to be located in the narrow and small superaltitude of double-deck exterior wall, in the present embodiment, this construction operation platform comprises two-layer operation support body, namely support body 11 and operation support body 11 ' is operated, the structure of operation support body 11 ' is identical with the structure of operation support body 11, and operation support body 11 ' is located under operation support body 11, the operating desk 111 of operation support body 11 has four strong points, each strong point place has installed column 112, between two columns 112 being located at double-deck inner side of outer wall on operation support body 11, support and connection have two diagonal members 116, two diagonal members 116 are arranged in X-shaped, these two diagonal members are for strengthening the structural strength of operation support body 11.Have two diagonal members 116 being located between outside double-deck exterior wall two columns 112 also support and connection, these two diagonal members 116 are arranged in X-shaped.As shown in Figure 2, for the construction operation platform with two-layer operation support body, E type connector 12 is connected and fixed with the column 112 of the operation support body 11 ' being positioned at bottom, and two-layer operation support body is connected in the structural beams of building body by this E type connector 12, guarantees the use safety of this operation support body.
As shown in Figure 3 and Figure 4, operation support body 11 includes four columns 112, four bights of operating desk 111 are located at by these 112, four columns, by column 112, operating desk 111 is supported on supporting surface, the ruggedized construction 113 that the inner side of four columns 112 is arranged comprises two cross bars 1131 and a montant 1132, one end of two cross bars 1131 is vertically connected on column 112, montant 1132 is connected to the other end of cross bar 1131, the bottom of this montant 1132 is curved to be bent to column 112 and is connected and fixed with column 112, this ruggedized construction 113 is for strengthening the structural strength of column 112, for firmly providing safeguard of supporting frame.In ruggedized construction 113, superposed cross bar 1131 is fixedly connected with operating desk 111, improves the structural strength of operation support body 11 further.
E type connector 12 comprises three vertical bars 122 that the connecting rod 121 of horizontally set and interval vertical are connected to connecting rod 121, the both ends of connecting rod 121 are located at by wherein two vertical bars 122, the vertical bar 122 of another root is located between the both ends of connecting rod 121, the vertical bar 122 being positioned at connecting rod 121 1 end is inserted in the sleeve 114 on column 112, the space adapting to structural beams 20 is formed between vertical bar 122 in connecting rod 121 the other end and the vertical bar 122 between connecting rod 121 both ends, E type connector 12 is made to be sheathed in structural beams 20 by this space, and be connected and fixed with structural beams 20, achieve like this and by E type connector 12, drawknot between operation support body and structural beams 20 is fixed.
As shown in Figure 1, guard bar structure 115 is erected in operating desk 111 surrounding of operation support body 11, this guard bar structure 115 comprises four vertical rods 1151 and Duo Gen cross bar 1152, cross bar 1152 is laterally connected between two vertical rods 1151, vertical rod 1151 and 1152 encloses formation framework, and the bottom of vertical rod 1151 is connected and fixed with the operating desk 111 of operation support body 11.Constructor stand on operating desk 111 and constructs, and by guard bar structure, 115 couples of constructors play a protective role.
The making of the utility model construction operation platform and use procedure are:
Make operation support body 11, 11 ' and guard bar structure 115, guarantee to operate support body 11, 11 ' meets the width of small space superelevation and the requirement of height with the width of guard bar structure 115, when making operation support body 11, first a column and two diagonal members are connected to form support stand, support stand by a pair to be again oppositely arranged, being laid by operating desk is fixed on a pair support stand, the inner side of column is connected with ruggedized construction, in the outside of column welding steel sleeve, for connecting E type connector, the general safety meeting construction operation platform is stablized, E type connector one end and the sleeve bolt on operation support body 11 are fixed, the other end and the outer structural beams cutting ferrule within the walls of bilayer are connected and fixed, according to the construction operation platform of bilayer operation support body, bolt mode is then adopted by operation support body 11 to be fixed on operation support body 11 '.Adopt vertical rod and cross bar to enclose and be connected to form guard bar structure; guard bar structure is bolted on operation support body 11 along short transverse; define construction operation platform; constructor carries out construction operation on the operating desk 111 of operation support body 11; guard bar structure plays a protective role to constructor, and constructor can carry out safe construction operation in the narrow and small superaltitude of double-deck exterior wall.
The utility model is used for the beneficial effect of the construction operation platform between the narrow and small superaltitude of double-deck exterior wall:
A kind of construction operation platform be applicable between narrow and small superaltitude is provided, in superelevation small space, effective utilization can not be synchronously set up at conventional steel design of coupler scaffold, in the ungratified situation of market tradition external scaffolding, operation support body is installed in small space, adopt E type connector that handling frame and structural beams are carried out mutual bolt to guarantee the safety of operating platform, ruggedized construction is set in addition on the column of operation support body, improve the steadiness of operation support body further.The utility model construction operation platform when solve conventional steel tube clamps formula scaffold peace tear open inconvenience, consumption large, synchronously can not set up with agent structure, can pacify flexibly in narrow and small superaltitude and dismount and mount full operation, turnover use and then ensured operating personnel's safety and building engineering construction quality, save the building operations cycle simultaneously.
Below embodiment has been described in detail the utility model by reference to the accompanying drawings, and those skilled in the art can make many variations example to the utility model according to the above description.Thus, some details in embodiment should not formed restriction of the present utility model, the utility model by the scope that defines using appended claims as protection domain of the present utility model.

Claims (9)

1., for the construction operation platform between the narrow and small superaltitude of double-deck exterior wall, it is characterized in that, comprising:
Operation support body, comprises operating desk and the column installing described operating desk; Described column is provided with ruggedized construction, and described ruggedized construction and described operating desk are connected and fixed; The described column being located at double-deck inner side of outer wall is provided with sleeve; And
Connector, has for plugging the inserted terminal and link that is relative with described inserted terminal, that Gong be fixedly connected with that connect described sleeve.
2. construction operation platform as claimed in claim 1, it is characterized in that, described operating desk has four strong points, and each strong point place installs described column, between two columns being wherein located at described double-deck inner side of outer wall, support and connection have two diagonal members, and two described diagonal members are that X-shaped is arranged.
3. construction operation platform as claimed in claim 2, it is characterized in that, being located at support and connection between two columns outside described double-deck exterior wall has two diagonal members, and two described diagonal members are that X-shaped is arranged.
4. construction operation platform as claimed in claim 1, is characterized in that, also comprises being located under described operation support body and another identical with described handling frame body structure of structure operates support body.
5. construction operation platform as claimed in claim 1, is characterized in that, described operating desk comprises framework and is layed in the stripe board on described framework.
6. construction operation platform as claimed in claim 5, it is characterized in that, described ruggedized construction comprises two cross bars and a montant, one end of described cross bar is vertically connected at described column, described montant is connected to the other end of described cross bar, and the bottom of described montant is curved bends to described column and be connected to described column.
7. construction operation platform as claimed in claim 6, it is characterized in that, in described ruggedized construction, superposed described cross bar is fixedly connected with described framework.
8. construction operation platform as claimed in claim 1, it is characterized in that, the surrounding of described operating desk is equipped with guard bar structure.
9. construction operation platform as claimed in claim 1, it is characterized in that, described connector is E type connector, and comprise three vertical bars that horizontally set connecting rod and interval vertical are connected to described connecting rod, the both ends of described connecting rod are located at by wherein two described vertical bars.
CN201520148378.6U 2015-03-16 2015-03-16 For the construction operation platform between the narrow and small superaltitude of double-deck exterior wall Expired - Fee Related CN204662916U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520148378.6U CN204662916U (en) 2015-03-16 2015-03-16 For the construction operation platform between the narrow and small superaltitude of double-deck exterior wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520148378.6U CN204662916U (en) 2015-03-16 2015-03-16 For the construction operation platform between the narrow and small superaltitude of double-deck exterior wall

Publications (1)

Publication Number Publication Date
CN204662916U true CN204662916U (en) 2015-09-23

Family

ID=54133311

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520148378.6U Expired - Fee Related CN204662916U (en) 2015-03-16 2015-03-16 For the construction operation platform between the narrow and small superaltitude of double-deck exterior wall

Country Status (1)

Country Link
CN (1) CN204662916U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088563A (en) * 2016-08-30 2016-11-09 苏州银海机电科技有限公司 One takes ladder
CN106836766A (en) * 2017-03-20 2017-06-13 无锡市龙海杰机械制造有限公司 Double-deck scaffold in simple type room
CN106836778A (en) * 2017-03-20 2017-06-13 无锡市龙海杰机械制造有限公司 The double-deck inner scaffold of protection air cushion is installed
CN106869469A (en) * 2017-03-20 2017-06-20 无锡市龙海杰机械制造有限公司 The rotary agitator special scaffold of groove building trade is installed
CN114837389A (en) * 2022-05-20 2022-08-02 中国建筑第八工程局有限公司 Construction operation platform and construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088563A (en) * 2016-08-30 2016-11-09 苏州银海机电科技有限公司 One takes ladder
CN106836766A (en) * 2017-03-20 2017-06-13 无锡市龙海杰机械制造有限公司 Double-deck scaffold in simple type room
CN106836778A (en) * 2017-03-20 2017-06-13 无锡市龙海杰机械制造有限公司 The double-deck inner scaffold of protection air cushion is installed
CN106869469A (en) * 2017-03-20 2017-06-20 无锡市龙海杰机械制造有限公司 The rotary agitator special scaffold of groove building trade is installed
CN114837389A (en) * 2022-05-20 2022-08-02 中国建筑第八工程局有限公司 Construction operation platform and construction method

Similar Documents

Publication Publication Date Title
CN204662916U (en) For the construction operation platform between the narrow and small superaltitude of double-deck exterior wall
CN205205694U (en) No. 0 piece multipurpose triangle -shaped bracket construction equipment on continuous beam pier top
CN102168484B (en) External hanging scaffold and application method thereof
CN205775852U (en) A kind of active force conversion support for steel structure support moulding bed top
CN103993728A (en) Assembly-type section steel cantilever protective shed
CN203403664U (en) Novel plug-in type scaffold assembly
CN211257756U (en) Progressive overhanging structure aiming at complex outer vertical surface modeling
CN103669817B (en) Building structure overhanging scaffold external corner assembling type frame body device
CN204040437U (en) Cantilever tripod and single protective frame system of encorbelmenting
CN204691201U (en) A kind of Liftable hanging formula scaffold system
CN204059909U (en) With the horizontal truss of avoiding structure
CN203924655U (en) A kind of novel elevator pit shaft operating platform frame
CN206971735U (en) Basic platform for cantilevered structure formwork
CN207749859U (en) A kind of trestle support system for structure floor operation in Large-scale Hoisting equipment
CN203795824U (en) Suspension type fastener scaffold erecting device
CN102817464B (en) Construction device for painting anti-corrosion and fireproof paint of building
CN104314183A (en) Building frame structure
CN204781885U (en) Novel crown cornice shaped steel operation platform that encorbelments
CN215107235U (en) High-altitude cantilever structure formwork support platform
CN207003265U (en) New road bridge formwork support meanss
CN203640245U (en) Scaffold structure for building exterior wall construction
CN214658075U (en) Node device of truss curtain wall
CN205153508U (en) Elevartor shaft interior instrument formula construction security operating platform
CN203569870U (en) Protective frame system for disassembling and extending of ultrahigh atrium frame
CN104153559B (en) Attachment type raise scaffold

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150923