A kind of novel elevator pit shaft operating platform frame Download PDF

Info

Publication number
CN203924655U
CN203924655U CN201420327290.6U CN201420327290U CN203924655U CN 203924655 U CN203924655 U CN 203924655U CN 201420327290 U CN201420327290 U CN 201420327290U CN 203924655 U CN203924655 U CN 203924655U
Authority
CN
China
Prior art keywords
pit shaft
brace summer
operating platform
platform frame
support bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420327290.6U
Other languages
Chinese (zh)
Inventor
朱金勇
仲鑫
宋大虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
First Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
First Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd, First Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201420327290.6U priority Critical patent/CN203924655U/en
Application granted granted Critical
Publication of CN203924655U publication Critical patent/CN203924655U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of novel elevator pit shaft operating platform frame, comprise support body, support body is provided with chock, on chock, be covered with panel, support body is the double-deck support body of level, comprise the construction layer on top and the overcoat of bottom, described construction layer comprises the support frame on brace summer and beam longitudinally, overcoat comprises fence rail longitudinally, between brace summer and fence rail, by symmetrically arranged vertical suspension rod, be connected as a single entity, the two ends of brace summer are fixedly connected with pit shaft barrel by connector, described connector is support bar, one end of support bar fixes support bar by being fixedly connected in advance the limiting plate of brace summer downside, within the other end is plugged to the pre-buried sleeve pipe in the interior vertical interval of pit shaft barrel.The utility model is used is the conventional constructional materials in job site, and cost-saving, construction is set up easy, can directly assemble at the construction field (site), use safety factor higher, can be with construction floor Integral lifting, can be recycled, solved the dangerous larger difficult problem of elevator shaft border construction.

Description

A kind of novel elevator pit shaft operating platform frame
Technical field
The utility model belongs to the realm of building construction, relates to a kind of elevator shaft operating platform frame.
Background technology
At present, when the elevator shaft in building Tall Shear Wall Structures is constructed, need erection construction protector to carry out a series of working procedure.Traditional construction protection device generally adopts and between shear wall and elevator beam, sets up two spandrel girders, and on spandrel girder, weld vertical spacer bars, on spacer bars, insert steel pipe and set up operating platform, and on laying on platform, people's panel operates, pit shaft protection is difficult to set up, when workman constructs on this protector, dangerous coefficient is larger, and operating platform is set up inconvenience, reuses the technical problems such as inconvenience.
Utility model content
The purpose of this utility model is to provide a kind of novel elevator pit shaft operating platform frame, solve traditional dangerous coefficient of elevator shaft paralell larger, and putting up platform inconvenience, reuses the technical problems such as inconvenience.
For achieving the above object, the utility model adopts following technical scheme:
A kind of novel elevator pit shaft operating platform frame, be positioned among the pit shaft that shear wall and elevator beam surround, comprise support body, support body is provided with chock, is covered with panel on chock, the double-deck support body that described support body is level, comprise the construction layer on top and the overcoat of bottom, described construction layer comprises the support frame on brace summer and beam longitudinally, and described overcoat comprises fence rail longitudinally
Between described brace summer and fence rail, by symmetrically arranged vertical suspension rod, be connected as a single entity, the two ends of brace summer are fixedly connected with pit shaft barrel by connector, described connector is support bar, one end of support bar fixes support bar by being fixedly connected in advance the limiting plate of brace summer downside, within the other end is plugged to the pre-buried sleeve pipe in the interior vertical interval of pit shaft barrel.
Described suspension rod is to be formed by round steel bending, the top bending of suspension rod is inverted U suspension ring, construction layer stretches out for lifting in the arc portion of suspension ring, and the foot of suspension ring is soldered to the outside at the both ends of brace summer, and the bottom bending of suspension rod is for placing the also U-shaped draw-in groove of fixed protection beam end.
Described brace summer is two limbs channel-section steels down, limiting plate be vertical welding to groove and the steel plate of two right-angled triangles that are oppositely arranged, support bar is adjusted it by the hypotenuse of limiting plate and is fixed position.
Described fence rail is two limbs channel-section steels down, the outside of channel-section steel two limbs and the welding of the inner side of U-shaped draw-in groove.
Described support bar is high-strength bolt or reinforcing bar.
Described support frame comprises a plurality of horizontal parallel main joists and longitudinal edge sealing at main joist two ends, and described main joist and edge sealing are reinforcing bar.
Compared with prior art the utlity model has following characteristics and beneficial effect:
The utility model is compared traditional steel pipe operating platform frame, adopt double-decked platform frame to form, the construction layer on top can be gone up people's operation, the overcoat of bottom can also be placed building unit except can protecting workman, also can carry out upper people's operation if desired, peg graft by the pre-buried sleeve pipe in vertical interval in support bar and pit shaft barrel in the two ends of construction layer brace summer, for convenience detach, support bar fixes support bar by being fixedly connected in advance the limiting plate of brace summer downside, during lifting, only brace summer need be mentioned to the lifting that can complete paralell from support bar, set up easy mobility strong, double-decked platform frame connects as one by suspension rod, suspension rod multi-use, and top can be bent into suspension ring and conveniently support body be lifted, and bottom is bent into the fence rail that cell body is placed overcoat.
The utility model is used is the conventional constructional materials in job site, and cost-saving, construction is set up easy, can directly assemble at the construction field (site), use safety factor higher, can be with construction floor Integral lifting, can be recycled, solved the dangerous larger difficult problem of elevator shaft border construction.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the utility model is described in more detail.
Fig. 1 is the schematic top plan view of the utility model operating platform frame.
Fig. 2 is brace summer and the support framework structure schematic diagram of construction layer.
Fig. 3 is that construction layer is laid the structural representation of chock and panel on brace summer and support frame.
Fig. 4 is the facade structures schematic diagram of the utility model operating platform frame.
Fig. 5 is the node connecting structure schematic diagram of the utility model operating platform frame and shear wall.
Reference numeral: 1-shear wall, 2-elevator beam, 3-construction layer, 3.1-brace summer, 3.2-support frame, 3.21-main joist, 3.22-edge sealing, 4-overcoat, 5-chock, 6-panel, 7-suspension rod, 7.1-inverted U suspension ring, 7.2-U type draw-in groove, 8-connector, 9-limiting plate, 10-sleeve pipe.
The specific embodiment
Embodiment is shown in Figure 1, a kind of novel elevator pit shaft operating platform frame, be positioned among the pit shaft that shear wall 1 and elevator beam 2 surround, four pit shafts of having encircled a city in the present embodiment, in each pit shaft, be provided with a paralell, shown in Figure 4, each paralell comprises support body, participate in described in Fig. 3 and Fig. 4, support body is provided with chock 5, on chock, be covered with panel 6, described support body is the double-deck support body of level, comprise the construction layer 3 on top and the overcoat 4 of bottom, shown in Figure 2, described construction layer 3 comprises the support frame 3.2 on brace summer 3.1 and beam longitudinally, described overcoat 4 comprises fence rail longitudinally.
Shown in Fig. 1 and Fig. 4, between described brace summer 3.1 and fence rail, by symmetrically arranged vertical suspension rod 7, be connected as a single entity, shown in Figure 5, the two ends of brace summer 3.1 are fixedly connected with pit shaft barrel by connector 8, described connector 8 is support bar, one end of support bar fixes support bar by being fixedly connected in advance the limiting plate 9 of brace summer downside, within the other end is plugged to the pre-buried sleeve pipe 10 in the interior vertical interval of pit shaft barrel.
Shown in Figure 4, described suspension rod 7 is to be formed by round steel bending, the top bending of suspension rod 7 is inverted U suspension ring 7.1, construction layer 3 stretches out for lifting in the arc portion of suspension ring, the foot of suspension ring is soldered to the outside at the both ends of brace summer, and the bottom bending of suspension rod 7 is for placing the also U-shaped draw-in groove 7.2 of fixed protection beam end.
Described brace summer 3.1 is two limbs channel-section steels down, and limiting plate 9 is for vertical welding is to groove and the steel plate of two right-angled triangles that are oppositely arranged, and support bar is adjusted it by the hypotenuse of limiting plate 9 and fixed position.
Described fence rail is two limbs channel-section steels down, the outside of channel-section steel two limbs and the welding of the inner side of U-shaped draw-in groove 7.2.
Described support bar is high-strength bolt or reinforcing bar.
Shown in Figure 2, described support frame 3.2 comprises a plurality of horizontal parallel main joists 3.21 and longitudinal edge sealing 3.22 at main joist two ends, and described main joist and edge sealing are reinforcing bar.
In the utility model, brace summer 3.1 and fence rail all arrange two, by suspension rod, the end of upper and lower two-layer beam are connected as one, and suspension rod arranges four altogether, and the two ends of every beam arrange one.
In the present embodiment, suspension ring adopt the round steel that diameter is 20mm, and brace summer is No. 12 channel-section steels, and fence rail is No. 10 channel-section steels, main joist in support frame adopts the reinforcing bar that diameter is 28mm, be spaced apart 300mm, edge sealing adopts the reinforcing bar that diameter is 16mm, and the length that edge sealing reinforcing bar stretches out main joist is 100mm.

Claims (6)

1. a novel elevator pit shaft operating platform frame, be positioned among the pit shaft that shear wall (1) and elevator beam (2) surround, comprise support body, support body is provided with chock (5), is covered with panel (6) on chock, it is characterized in that: the double-deck support body that described support body is level, comprise the construction layer (3) on top and the overcoat of bottom, described construction layer (3) comprises the support frame (3.2) on brace summer (3.1) and beam longitudinally, and described overcoat (4) comprises fence rail longitudinally
Between described brace summer (3.1) and fence rail, by symmetrically arranged vertical suspension rod (7), be connected as a single entity, the two ends of brace summer (3.1) are fixedly connected with pit shaft barrel by connector (8), described connector (8) is support bar, one end of support bar fixes support bar by being fixedly connected in advance the limiting plate (9) of brace summer downside, within the other end is plugged to the pre-buried sleeve pipe (10) in the interior vertical interval of pit shaft barrel.
2. a kind of novel elevator pit shaft operating platform frame according to claim 1, it is characterized in that: described suspension rod (7) is to be formed by round steel bending, the top bending of suspension rod (7) is inverted U suspension ring (7.1), construction layer (3) stretches out for lifting in the arc portion of suspension ring, the foot of suspension ring is soldered to the outside at the both ends of brace summer, and the bottom bending of suspension rod (7) is for placing the also U-shaped draw-in groove (7.2) of fixed protection beam end.
3. a kind of novel elevator pit shaft operating platform frame according to claim 1, it is characterized in that: described brace summer (3.1) is two limbs channel-section steel down, limiting plate (9) is for vertical welding is to groove and the steel plate of two right-angled triangles that are oppositely arranged, and support bar is adjusted its fixing position by the hypotenuse of limiting plate (9).
4. a kind of novel elevator pit shaft operating platform frame according to claim 2, is characterized in that: described fence rail is two limbs channel-section steel down, the inner side welding of the outside of channel-section steel two limbs and U-shaped draw-in groove (7.2).
5. a kind of novel elevator pit shaft operating platform frame according to claim 1, is characterized in that: described support bar is high-strength bolt or reinforcing bar.
6. a kind of novel elevator pit shaft operating platform frame according to claim 1, it is characterized in that: described support frame (3.2) comprises a plurality of horizontal parallel main joists (3.21) and longitudinal edge sealing (3.22) at main joist two ends, and described main joist and edge sealing are reinforcing bar.
CN201420327290.6U 2014-06-19 2014-06-19 A kind of novel elevator pit shaft operating platform frame Expired - Fee Related CN203924655U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420327290.6U CN203924655U (en) 2014-06-19 2014-06-19 A kind of novel elevator pit shaft operating platform frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420327290.6U CN203924655U (en) 2014-06-19 2014-06-19 A kind of novel elevator pit shaft operating platform frame

Publications (1)

Publication Number Publication Date
CN203924655U true CN203924655U (en) 2014-11-05

Family

ID=51820505

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420327290.6U Expired - Fee Related CN203924655U (en) 2014-06-19 2014-06-19 A kind of novel elevator pit shaft operating platform frame

Country Status (1)

Country Link
CN (1) CN203924655U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403608A (en) * 2018-11-20 2019-03-01 广州景兴建筑科技有限公司 A kind of building elevator shaft mouth security protection platform
CN110821162A (en) * 2019-11-25 2020-02-21 上海宝冶集团有限公司 Elevator shaft top plate erecting device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403608A (en) * 2018-11-20 2019-03-01 广州景兴建筑科技有限公司 A kind of building elevator shaft mouth security protection platform
CN110821162A (en) * 2019-11-25 2020-02-21 上海宝冶集团有限公司 Elevator shaft top plate erecting device

Similar Documents

Publication Publication Date Title
CN104975566B (en) Apply the steel pipe support in cable-stayed bridge arch tower is constructed
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN102839678B (en) Structure for improving rigidity and stability of foundation pit steel support
CN107419893A (en) A kind of elevator steel platform and preparation method thereof
CN205775852U (en) A kind of active force conversion support for steel structure support moulding bed top
CN203924655U (en) A kind of novel elevator pit shaft operating platform frame
CN202755370U (en) Structure for improving rigidity and stability of foundation pit steel support
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN208363666U (en) It is a kind of for build face side construction safety protection frame
CN204040437U (en) Cantilever tripod and single protective frame system of encorbelmenting
CN109356190B (en) Lattice column type pier concrete tower crane foundation and construction method thereof
CN208934112U (en) A kind of steel column box bracket
CN206319597U (en) A kind of cantilever steel girder erecting device
CN202899639U (en) Concrete column structure
CN201915630U (en) Combined platform of fire control joint gallery form supporting steel beam
CN201614739U (en) Template bracket for roofing oblique beam
CN205116776U (en) Support access structure
CN203531348U (en) Self-stability elevator shaft construction operating frame
CN204435833U (en) Operation platform wall-attached supporting seat
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
CN204282816U (en) A kind of girder template
CN206846097U (en) A kind of Men Gangyu frameworks separately-loaded pipeline support structure
CN207277893U (en) A kind of section steel platform formwork erecting structure for high-altitude overhanging
CN207314793U (en) Operating platform between a kind of regularization precast stair
CN206034486U (en) It consolidates to draw formula to one side system for major structure subsides post -cast strip department

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141105

Termination date: 20150619