CN204530433U - Steel pipe pile foundation combination steel trestle - Google Patents
Steel pipe pile foundation combination steel trestle Download PDFInfo
- Publication number
- CN204530433U CN204530433U CN201520064322.2U CN201520064322U CN204530433U CN 204530433 U CN204530433 U CN 204530433U CN 201520064322 U CN201520064322 U CN 201520064322U CN 204530433 U CN204530433 U CN 204530433U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- steel
- trestle
- pipe piles
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 82
- 239000010959 steel Substances 0.000 title claims abstract description 82
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical group [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims abstract description 12
- 230000001681 protective effect Effects 0.000 claims abstract description 7
- 239000002689 soil Substances 0.000 claims abstract description 4
- 239000002131 composite material Substances 0.000 claims description 6
- 229910052742 iron Inorganic materials 0.000 claims description 5
- 238000003466 welding Methods 0.000 claims description 4
- 238000010276 construction Methods 0.000 abstract description 16
- 238000009434 installation Methods 0.000 abstract description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 4
- 238000000034 method Methods 0.000 abstract description 3
- 239000000463 material Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本实用新型属于水中桥梁便道施工技术领域,为解决传统结构形式栈桥施工速度慢、安装复杂、稳定性差的技术问题,提供了一种钢管桩基础组合钢栈桥,包括钢管桩、横梁、贝雷梁和桥面钢板,钢管桩沿栈桥长度方向纵向等间距布置若干排,每排横向等间距布置若干根钢管桩,所述钢管桩的下部均打入水下泥土中,横向布置的相邻两钢管桩的中上部通过水平连接杆和剪刀撑固定,横向布置的钢管桩的顶部架设横梁,贝雷梁纵向垂直搭设在钢管桩上部横梁上,贝雷梁与横梁通过U型铁件连接,贝雷梁上部铺设桥面钢板,桥面钢板两侧沿栈桥长度方向设置防护栏杆。本实用新型安装简单,稳定性好,提高了栈桥施工速度,降低了施工成本,保证了后期使用过程的安全。
The utility model belongs to the technical field of bridge access construction in water. In order to solve the technical problems of slow construction speed, complicated installation and poor stability of traditional trestle bridges, the utility model provides a steel pipe pile foundation combined steel trestle, which includes steel pipe piles, beams, shells Thunder beams and deck steel plates, steel pipe piles are arranged in several rows at equal intervals longitudinally along the length of the trestle, and several steel pipe piles are arranged at equal intervals in each row horizontally. The lower parts of the steel pipe piles are driven into the underwater soil, and the horizontal The middle and upper parts of two adjacent steel pipe piles are fixed by horizontal connecting rods and scissor braces. The top of the horizontally arranged steel pipe piles is erected with a beam. The Bailey beam is vertically erected on the upper beam of the steel pipe pile. The Bailey beam and the beam pass through The U-shaped iron parts are connected, the bridge deck steel plate is laid on the upper part of the Bailey beam, and the protective railings are set on both sides of the bridge deck steel plate along the length of the trestle. The utility model has simple installation and good stability, improves the construction speed of the trestle bridge, reduces the construction cost, and ensures the safety of the later use process.
Description
技术领域 technical field
本实用新型属于水中桥梁便道施工技术领域,具体涉及一种钢管桩基础组合钢栈桥。 The utility model belongs to the technical field of bridge access construction in water, and in particular relates to a combined steel trestle bridge with steel pipe pile foundations.
背景技术 Background technique
在桥梁建设中,栈桥作为运输材料、设备、人员而修建的临时桥梁设施,是水上主桥梁施工物资供应及交通出入的唯一通道,也是整个大桥施工的基础性工程和控制性工程,特别是跨江、跨海大桥,往往栈桥修建的比较长,投入的人力、物力比较多,随着高速公路和高速铁路的迅速发展,水中桥梁在公路和铁路中被广泛应用,怎样快速建设施工便桥,是保证桥梁建设工期的关键问题,因此选择合理的栈桥结构形式和施工方法,成为水中桥梁便桥施工急需解决的问题。传统结构形式栈桥施工时横梁与贝雷梁直接焊接,施工速度慢、安装复杂、稳定性差,严重影响桥梁建设工期。 In bridge construction, the trestle bridge is a temporary bridge facility built to transport materials, equipment and personnel. For river and sea-crossing bridges, the construction of trestle bridges is often relatively long, and the input of manpower and material resources is relatively large. With the rapid development of expressways and high-speed railways, bridges in water are widely used in highways and railways. How to quickly build convenient bridges is the key The key issue is to ensure the construction period of the bridge. Therefore, choosing a reasonable trestle structure and construction method has become an urgent problem to be solved in the construction of the bridge in the water. In the construction of traditional trestle bridges, the beams and Bailey beams are directly welded. The construction speed is slow, the installation is complicated, and the stability is poor, which seriously affects the construction period of the bridge.
发明内容 Contents of the invention
本实用新型为解决传统结构形式栈桥施工速度慢、安装复杂、稳定性差的技术问题,提供了一种钢管桩基础组合钢栈桥。 The utility model provides a steel pipe pile foundation combined steel trestle bridge for solving the technical problems of slow construction speed, complicated installation and poor stability of the traditional trestle bridge.
本实用新型采用的技术方案如下: The technical scheme that the utility model adopts is as follows:
一种钢管桩基础组合钢栈桥,包括多根钢管桩、多根横梁、多根贝雷梁和桥面钢板,钢管桩沿栈桥长度方向纵向等间距布置若干排,每排横向等间距布置若干根钢管桩,所述钢管桩的下部均打入水下泥土中,横向布置的相邻两钢管桩的中上部通过水平连接杆和剪刀撑固定,横向布置的钢管桩的顶部架设横梁,贝雷梁纵向垂直搭设在钢管桩上部横梁上,贝雷梁与横梁通过U型铁件连接,贝雷梁上部铺设桥面钢板,桥面钢板两侧沿栈桥长度方向设置防护栏杆。 A composite steel trestle bridge with steel pipe pile foundations, including multiple steel pipe piles, multiple beams, multiple Bailey beams and bridge deck steel plates, the steel pipe piles are arranged in several rows at equal intervals longitudinally along the length of the trestle, and each row is equally spaced horizontally Arrange several steel pipe piles, the lower parts of the steel pipe piles are all driven into the underwater soil, the middle and upper parts of two adjacent steel pipe piles arranged horizontally are fixed by horizontal connecting rods and scissor braces, and the steel pipe piles arranged horizontally The beam is erected on the top, and the Bailey beam is vertically erected on the upper beam of the steel pipe pile. The Bailey beam and the beam are connected by U-shaped iron pieces. railing.
每个钢管桩的桩顶焊接有一钢盖板,横梁与钢盖板焊接在一起。 The top of each steel pipe pile is welded with a steel cover plate, and the beam and the steel cover plate are welded together.
所述横梁采用工字钢对焊而成。 The beam is formed by butt welding of I-beams.
本实用新型的有益效果:本实用新型的贝雷梁与横梁通过U型铁件连接,安装简单,稳定性好,提高了栈桥施工速度,降低了施工成本,保证了后期使用过程的安全。 Beneficial effects of the utility model: the Bailey beam and the cross beam of the utility model are connected by U-shaped iron parts, which is easy to install and has good stability, improves the construction speed of the trestle bridge, reduces the construction cost, and ensures the safety of the later use process.
附图说明 Description of drawings
图1为本实用新型的主视图; Fig. 1 is the front view of the utility model;
图2为本实用新型的侧视图; Fig. 2 is a side view of the utility model;
图中:1-钢管桩,2-水平连接杆,3-剪刀撑,4-横梁,5-贝雷梁,6-U型铁件,7-桥面钢板,8-防护栏杆,9-浆砌片石。 In the figure: 1-steel pipe pile, 2-horizontal connecting rod, 3-scissors brace, 4-beam, 5-Berry beam, 6-U-shaped iron piece, 7-deck steel plate, 8-protective railing, 9- Mortar rubble.
具体实施方式 Detailed ways
如图1、2所示,一种钢管桩基础组合钢栈桥,包括多根钢管桩1、多根横梁4、多根贝雷梁5和桥面钢板7,钢管桩1沿栈桥长度方向纵向等间距布置若干排,每排横向等间距布置若干根钢管桩1,所述钢管桩1的下部均打入水下泥土中,横向布置的相邻两钢管桩1的中上部通过水平连接杆2和剪刀撑3固定,横向布置的钢管桩1的顶部架设横梁4,所述横梁4采用工字钢对焊而成。贝雷梁5纵向垂直搭设在钢管桩1上部横梁4上,贝雷梁5与横梁4通过U型铁件6连接,贝雷梁5上部铺设桥面钢板7,桥面钢板7两侧沿栈桥长度方向设置防护栏杆8。 As shown in Figures 1 and 2, a steel pipe pile foundation composite steel trestle bridge includes multiple steel pipe piles 1, multiple beams 4, multiple Bailey beams 5 and deck steel plates 7, and the steel pipe piles 1 are along the length of the trestle. Several rows are arranged at equal intervals in the vertical direction, and several steel pipe piles 1 are arranged at equal intervals in each row. Fixed by the horizontal connecting rod 2 and the scissor brace 3, the top of the horizontally arranged steel pipe pile 1 is erected with a crossbeam 4, and the crossbeam 4 is formed by I-beam butt welding. The Bailey beam 5 is vertically erected on the upper beam 4 of the steel pipe pile 1. The Bailey beam 5 and the beam 4 are connected by U-shaped iron pieces 6. The bridge deck steel plate 7 is laid on the upper part of the Bailey beam 5. Protective railings 8 are arranged in the length direction of the trestle bridge.
为了保证横梁与钢管桩焊接的牢固性,每个钢管桩1的桩顶焊接有一钢盖板,横梁4与钢盖板焊接在一起。 In order to ensure the firmness of the welding between the beam and the steel pipe pile, a steel cover plate is welded on the pile top of each steel pipe pile 1, and the beam 4 and the steel cover plate are welded together.
实施例1 Example 1
一种钢管桩基础组合钢栈桥,单跨长9m,桥面宽6m。如图1、2所示, A composite steel trestle bridge based on steel pipe piles, with a single span length of 9m and a deck width of 6m. As shown in Figure 1 and 2,
下部结构: 采用φ630mm×8mm钢管桩1打入土中,入土深度大于16m,钢管桩1沿栈桥长度方向纵向等间距布置若干排,每排横向布置3根钢管桩1,横向布置的3根钢管桩1间距为2.35m,桩间用水平连接杆2和剪刀撑3牢固焊接;钢管桩1的顶部焊接有650×650cm、δ=10mm的钢盖板,钢盖板与钢管桩1顶部周边满焊;横向布置的钢管桩1桩顶布置2根长6m 的I45工字钢双拼横梁4,横梁4与钢盖板焊接在一起。 Substructure: φ630mm×8mm steel pipe piles 1 are used to drive into the soil, and the depth of penetration is greater than 16m. The steel pipe piles 1 are arranged in several rows at equal intervals longitudinally along the length of the trestle, and three steel pipe piles 1 are arranged horizontally in each row. The distance between the three steel pipe piles 1 is 2.35m, and the horizontal connecting rods 2 and scissor braces 3 are firmly welded between the piles; the top of the steel pipe piles 1 is welded with a steel cover plate of 650×650cm and δ=10mm, and the steel cover plate and steel The periphery of the top of the pipe pile 1 is fully welded; the top of the horizontally arranged steel pipe pile 1 is arranged with two 6m-long I45 I-steel double beams 4, and the beams 4 are welded together with the steel cover plate.
上部结构:9米跨纵梁布置单层6片3组贝雷片(规格为150cm×300cm),横向布置形式见图1,贝雷片纵向用贝雷销连接,横向用90型定型支撑片连接以保证其整体稳定性,贝雷片与工字钢横梁4间用U型铁件6连接以防滑动。 Superstructure: a single layer of 6 pieces and 3 groups of Bailey sheets (specification: 150cm×300cm) arranged in a 9-meter-span longitudinal beam. See Figure 1 for the horizontal layout. Connect to ensure its overall stability, and the U-shaped iron pieces 6 are used to connect the Bailey sheet and the I-beam beam 4 to prevent sliding.
栈桥桥面结构:桥面净宽6m,采用装配式钢面板,单块面板长6m,宽1.5m,面板采用5.5mm厚印花钢板,底横肋采用I25cm工字钢,底横肋纵向间距50cm设置在贝雷梁上,底横肋上铺设印花钢板。 Deck structure of the trestle bridge: the net width of the bridge deck is 6m, using assembled steel panels, a single panel is 6m long and 1.5m wide, the panels are made of 5.5mm thick printed steel plates, the bottom transverse ribs are made of I25cm I-beam, and the longitudinal spacing of the bottom transverse ribs is 50cm It is set on the Bailey beam, and the printed steel plate is laid on the bottom transverse rib.
防护栏杆:防护栏杆8采用直径为4.8cm的小钢管做成,防护栏杆8高度为1.2米,防护栏杆8沿栈桥长度方向3米设置1根立柱、相邻两立柱之间等间距设置三道横杆。 Protective railings: protective railings 8 are made of small steel pipes with a diameter of 4.8cm. The height of the protective railings 8 is 1.2 meters. The protective railings 8 are provided with one column at 3 meters along the length of the trestle, and three columns are arranged at equal intervals between adjacent two columns. crossbar.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520064322.2U CN204530433U (en) | 2015-01-30 | 2015-01-30 | Steel pipe pile foundation combination steel trestle |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520064322.2U CN204530433U (en) | 2015-01-30 | 2015-01-30 | Steel pipe pile foundation combination steel trestle |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204530433U true CN204530433U (en) | 2015-08-05 |
Family
ID=53744455
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520064322.2U Expired - Fee Related CN204530433U (en) | 2015-01-30 | 2015-01-30 | Steel pipe pile foundation combination steel trestle |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204530433U (en) |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107119569A (en) * | 2017-05-19 | 2017-09-01 | 中铁十六局集团第五工程有限公司 | A kind of construction method of the oblique rock geology construction make-shift bridge of deep water shallow overburden |
CN107313355A (en) * | 2017-08-18 | 2017-11-03 | 中国十七冶集团有限公司 | A kind of steel trestle construction method waterborne |
CN107700337A (en) * | 2017-11-28 | 2018-02-16 | 北京中铁隧建筑有限公司 | It is a kind of quickly to pacify the light section suspension bridge torn open |
CN108103922A (en) * | 2017-12-22 | 2018-06-01 | 中铁十七局集团第二工程有限公司 | It is a kind of to cross water suspension bridge construction method for the big amount of increase river of high flow rate |
CN108193587A (en) * | 2017-12-30 | 2018-06-22 | 贵阳铝镁设计研究院有限公司 | A kind of device of aluminium alloy assembled trestle and preparation method thereof |
CN108660909A (en) * | 2018-07-24 | 2018-10-16 | 东北大学 | A kind of prefabricated steel and concrete combination beam trestle and construction method |
CN109653101A (en) * | 2019-02-25 | 2019-04-19 | 中交第三航务工程局有限公司 | A kind of erection method of the trestle for bridge construction |
CN109989412A (en) * | 2019-04-11 | 2019-07-09 | 江西省交通设计研究院有限责任公司 | Mountain area plank road landscape platform composite base structure |
CN110016868A (en) * | 2019-04-16 | 2019-07-16 | 中国铁建大桥工程局集团有限公司 | A kind of steel trestle platform damping and de-noising method |
CN110055895A (en) * | 2019-03-20 | 2019-07-26 | 广州市第二市政工程有限公司 | A kind of economical and practical steel trestle construction method |
CN112411466A (en) * | 2020-11-06 | 2021-02-26 | 中国港湾工程有限责任公司 | Construction platform based on old pile foundation transformation and construction method thereof |
CN112681135A (en) * | 2020-12-14 | 2021-04-20 | 中铁二十局集团第三工程有限公司 | Construction method of n-shaped sea-crossing temporary steel trestle |
CN113047155A (en) * | 2021-03-24 | 2021-06-29 | 中铁十六局集团有限公司 | Bridge engineering construction method |
CN113356065A (en) * | 2021-06-11 | 2021-09-07 | 中铁二十局集团第三工程有限公司 | Construction method for main trestle in deep water area |
CN113529581A (en) * | 2021-07-27 | 2021-10-22 | 中铁十二局集团有限公司 | Construction method of unsupported temporary steel-framed bridge |
-
2015
- 2015-01-30 CN CN201520064322.2U patent/CN204530433U/en not_active Expired - Fee Related
Cited By (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107119569A (en) * | 2017-05-19 | 2017-09-01 | 中铁十六局集团第五工程有限公司 | A kind of construction method of the oblique rock geology construction make-shift bridge of deep water shallow overburden |
CN107313355A (en) * | 2017-08-18 | 2017-11-03 | 中国十七冶集团有限公司 | A kind of steel trestle construction method waterborne |
CN107313355B (en) * | 2017-08-18 | 2019-03-12 | 中国十七冶集团有限公司 | A kind of steel trestle construction method waterborne |
CN107700337A (en) * | 2017-11-28 | 2018-02-16 | 北京中铁隧建筑有限公司 | It is a kind of quickly to pacify the light section suspension bridge torn open |
CN108103922A (en) * | 2017-12-22 | 2018-06-01 | 中铁十七局集团第二工程有限公司 | It is a kind of to cross water suspension bridge construction method for the big amount of increase river of high flow rate |
CN108193587A (en) * | 2017-12-30 | 2018-06-22 | 贵阳铝镁设计研究院有限公司 | A kind of device of aluminium alloy assembled trestle and preparation method thereof |
CN108193587B (en) * | 2017-12-30 | 2023-10-03 | 贵阳铝镁设计研究院有限公司 | Device of aluminum alloy assembled trestle and manufacturing method thereof |
CN108660909A (en) * | 2018-07-24 | 2018-10-16 | 东北大学 | A kind of prefabricated steel and concrete combination beam trestle and construction method |
CN109653101A (en) * | 2019-02-25 | 2019-04-19 | 中交第三航务工程局有限公司 | A kind of erection method of the trestle for bridge construction |
CN110055895A (en) * | 2019-03-20 | 2019-07-26 | 广州市第二市政工程有限公司 | A kind of economical and practical steel trestle construction method |
CN110055895B (en) * | 2019-03-20 | 2020-08-18 | 广州市第二市政工程有限公司 | Economical and practical steel trestle construction method |
CN109989412A (en) * | 2019-04-11 | 2019-07-09 | 江西省交通设计研究院有限责任公司 | Mountain area plank road landscape platform composite base structure |
CN110016868A (en) * | 2019-04-16 | 2019-07-16 | 中国铁建大桥工程局集团有限公司 | A kind of steel trestle platform damping and de-noising method |
CN112411466A (en) * | 2020-11-06 | 2021-02-26 | 中国港湾工程有限责任公司 | Construction platform based on old pile foundation transformation and construction method thereof |
CN112411466B (en) * | 2020-11-06 | 2021-12-24 | 中国港湾工程有限责任公司 | Construction platform based on old pile foundation transformation and construction method thereof |
CN112681135A (en) * | 2020-12-14 | 2021-04-20 | 中铁二十局集团第三工程有限公司 | Construction method of n-shaped sea-crossing temporary steel trestle |
CN112681135B (en) * | 2020-12-14 | 2022-10-11 | 中铁二十局集团第三工程有限公司 | Construction method of n-shaped sea-crossing temporary steel trestle |
CN113047155A (en) * | 2021-03-24 | 2021-06-29 | 中铁十六局集团有限公司 | Bridge engineering construction method |
CN113356065A (en) * | 2021-06-11 | 2021-09-07 | 中铁二十局集团第三工程有限公司 | Construction method for main trestle in deep water area |
CN113529581A (en) * | 2021-07-27 | 2021-10-22 | 中铁十二局集团有限公司 | Construction method of unsupported temporary steel-framed bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204530433U (en) | Steel pipe pile foundation combination steel trestle | |
CN101935986B (en) | Overwater large-span steel tube pile cast-in-situ trestle and building method thereof | |
CN104404861A (en) | Steel trestle provided with steel anchor pile and construction method of steel trestle | |
CN203229874U (en) | Repeatedly used cast-in-place support system for simply-supported beam | |
CN102839678B (en) | Structure for improving rigidity and stability of foundation pit steel support | |
CN205024600U (en) | A work platform that is used for bridge aquatic pile foundation to be under construction | |
CN204662444U (en) | Large diameter steel pipe sunk pile fixed guide | |
CN203904971U (en) | Reinforcement cage protective device capable of controlling necking, bar leakage and mud inclusion of underground diaphragm wall | |
CN203487487U (en) | Anti-collision guardrail structure | |
CN202755370U (en) | Structure for improving rigidity and stability of foundation pit steel support | |
CN102733307A (en) | Method for constructing cast-in-place beam falsework | |
CN203834487U (en) | Section steel inner brace and Lassen pile support for excavation of dumbbell-shaped deep and large foundation pit | |
CN211446616U (en) | Deepwater river pier construction operation platform | |
CN202745057U (en) | Integrated structural steel guide frame device used for vibrating and sinking steel pile | |
CN203795305U (en) | New bridge and old bridge connecting and reinforcing structure for bridge widening | |
CN203846512U (en) | Supporting device for long edges of strip-shaped and rectangular foundation pit | |
CN203846505U (en) | Supporting structure used for long edges of strip-shaped and rectangular foundation pit | |
CN202577162U (en) | Combined-type steel pipe bracket | |
CN206468030U (en) | Independent beam combined type limb protective railing | |
CN110924312A (en) | Construction method of steel trestle | |
CN209025051U (en) | An anti-seismic dam body hydraulic structure | |
CN210066524U (en) | Inclined beam column type supporting system for bridge cast-in-place section | |
CN104652837B (en) | A kind of method and structure for increasing steel pipe frame newly on former concrete pipe support | |
CN203755165U (en) | Bracket structure for steel pipe pile | |
CN103397638A (en) | Tie bar for supporting system in high-rigidity integral prestressed fabricated foundation pit support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150805 |
|
CF01 | Termination of patent right due to non-payment of annual fee |