Prior art keywords
bridge
bailey
bailey beam
bridge pier
make
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710364044.6A
Other languages
Chinese (zh)
Other versions
CN106978777B (en
Inventor
罗九林
程慧林
王治斌
杨永强
梁志新
罗红春
郭亚娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Fifth Survey and Design Institute Group Co Ltd
Original Assignee
China Railway Fifth Survey and Design Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Fifth Survey and Design Institute Group Co Ltd filed Critical China Railway Fifth Survey and Design Institute Group Co Ltd
Priority to CN201710364044.6A priority Critical patent/CN106978777B/en
Publication of CN106978777A publication Critical patent/CN106978777A/en
Application granted granted Critical
Publication of CN106978777B publication Critical patent/CN106978777B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • E01D15/133Portable or sectional bridges built-up from readily separable standardised sections or elements, e.g. Bailey bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/005Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of make-shift bridge device, Simple bridge for temporary erection, include the Bailey beam (8) across space under bridge of multiple vertical longitudinally spaced arrangements of runway, Bailey beam (8) lays the road surface distribution beam (9) of I-steel above, cast-in-place concrete floorings (11) on bamboo slab rubber (10), bamboo slab rubber (10) are laid in road surface distribution beam (9) and constitute road surface;The interior embedded U-shaped bolt (16) of concrete slab (11) is connected with Bailey beam (8);Each Bailey beam (8) two ends are provided with end bridge pier, and centre is provided with middle bridge pier, end bridge pier and middle bridge pier support Bailey beam (8).Whole track is arranged in above river course, and more traditional girder is reasonable to arrangement form along bridge, takes full advantage of space on river course, it is to avoid a large amount of expropriations of land, and effectively protection two sides are afforested.The quantity reduced in korneforos pile foundation of Yokogawa road arrangement, reduces difficulty of construction simultaneously, can effectively reduce current obstruction area simultaneously.

Description

A kind of make-shift bridge device
Technical field
The present invention relates to mechanical structure and traffic engineering technical field, more particularly to a kind of make-shift bridge device.
Background technology
Make-shift bridge is the Simple bridge of temporary erection.The bridge constructed and set up for convenience, can for construction machinery It is smoothly convenient current, major trunk roads driving is changed its course, it is necessary to relieve traffic congestion sometimes for heavy construction such as subway station etc. is built.Especially It is in city may no sufficient space build interim sidewalk, dredge friendship using make-shift bridge structure is built on river course Logical, general construction requirement is tight.Major urban arterial highway track is more, and vehicle flow is big.How to accomplish economy, safety and easy construction, be One major issue of required consideration when designing make-shift bridge.
Traditional temporary construction steel suspension bridge is also wide with regard to 4~8m, does not use beams of concrete substantially come as make-shift bridge.In addition Traditional steel suspension bridge is longitudinally arranged using Bailey beam, i.e., Bailey beam is identical with road arrangement direction.In Urban Metro Construction, especially Subway station is built under major trunk roads, the wide left and right of the general 30m of engineering make-shift bridge is discongested.Urban Bridge volume of traffic is big, right simultaneously Noise pollution requirement is strict, especially through school, hospital, resident living area.Traditional steel suspension bridge arrangement form, which is difficult to meet, to be wanted Ask, influence the actual cross-section of river in river course, next to that noise is inevitable.According to permanent concrete bridge structure, it is invested Cost is high, speed of application is slow, removal cost is higher.And can not possibly reuse.
Bailey beam combines frame structure by Bailey bracket and horizontal-associate frame by Bei Leixiao, and Bailey bracket and shellfish thunder pin are standards Commodity fittings, can with it splice be assembled into many components, equipment.As shown in figure 1, being Bailey bracket structure, such as Fig. 2 and Fig. 3 For shellfish thunder latch structure.
Bailey bridge is also referred to as " assembly type steel bridge on highway ", and original name is " 321 " highway steel bridge.It is the combat readiness highway steel of China Bridge.Bailey bridge is to be widely used in the world, a kind of the most popular bridge, and it has simple in construction, convenient transportation, sets up fast Speed, the characteristics of decomposing easy.Large carrying capacity is provided simultaneously with, structural rigidity is strong, the advantages of fatigue life is long.It can be according to reality The different across footpaths composition all kinds and the temporary bridge of various uses needed, meet an urgent need bridge and fixed bridge, weight few with component Gently, the characteristics of cost is low.
The content of the invention
It is an object of the invention to provide a kind of make-shift bridge device, reasonable in design, easy construction, can effectively reduce construction throw Enter, shorten the activity duration, and the interim construction suspension bridge in river course space can be made full use of.
The purpose of the present invention is achieved through the following technical solutions:
A kind of make-shift bridge device, for the Simple bridge of temporary erection, including multiple longitudinally spaced cloth of vertical runway The Bailey beam 8 across space under bridge put, described Bailey beam 8 is laterally including multigroup sub- beam connected by shellfish thunder pin 17 mutually Frame, every sub- roof beam structure is constituted by three Bailey brackets are arranged in parallel, is connected between three Bailey brackets by horizontal-associate frame 20;
Bailey beam 8 is laid lay bamboo slab rubber 10, bamboo slab rubber 10 in the road surface distribution beam 9 of I-steel, road surface distribution beam 9 above Upper cast-in-place concrete floorings 11 constitute road surface;Embedded U-shaped bolt 16 is connected with Bailey beam 8 in concrete slab 11 Connect;
Each two ends of Bailey beam 8 are provided with end bridge pier, and centre is provided with middle bridge pier, and end bridge pier supports Bailey beam 8 with middle bridge pier.
The top mark height of described middle bridge pier is high higher than the top mark of end bridge pier, and the middle part of Bailey beam 8 of support is higher than two ends, the gradient 1%.
Described end bridge pier includes end bored concrete pile 1 and the Guan Liang 2 located at the end upper end of bored concrete pile 1, the support Bailey beam 8 of Guan Liang 2 End.
Described middle bridge pier includes middle bored concrete pile 3, casing 4, cover plate 5, ribbed stiffener 6 and shaped steel distribution beam 7;Casing 4 is placed in The middle top of bored concrete pile 3, pours and welds shaped steel distribution beam 7 after middle bored concrete pile 3 on the top welded cover plate 5 of casing 4, cover plate 5, and set Ribbed stiffener 6.
The road surface side of described suspension bridge device pontic sets anticollision barrier 12, and opposite side is mated formation pavement 15, pavement 15 inner sides set kerbstone 14, and outside sets people's row railing 13.
Described suspension bridge device end of the bridge gateway road surface one end provided with top cap 22, parados 23, ear wall 24 and attachment strap 25;
Top cap 22 is installed on above the bridge pier of end, and parados 23 is installed in top cap 22 with ear wall 24, and attachment strap 25 is located at ear wall 24 On, paving 26 of mating formation on attachment strap 25.
The described spacer of concrete slab 11 sets multiple transverse expansion joints, the two ends concrete slab at expansion joint Set in 11 and strengthen channel-section steel 18 and U-shaped reinforcing bar 19;The U-shaped reinforcing bar 19 is welded with strengthening channel-section steel 18, is embedded in concrete bridge deck In plate 11.Transverse expansion joint is set at spacing intervals
As seen from the above technical solution provided by the invention, a kind of make-shift bridge dress provided in an embodiment of the present invention Put, reasonable in design, easy construction, can effectively reduce construction input, shorten the activity duration, and river course space can be made full use of It is interim to build suspension bridge.Avoid a large amount of expropriations of land, and effectively protection two sides greening.
Brief description of the drawings
In order to illustrate the technical solution of the embodiments of the present invention more clearly, being used required in being described below to embodiment Accompanying drawing be briefly described, it should be apparent that, drawings in the following description are only some embodiments of the present invention, for this For the those of ordinary skill in field, on the premise of not paying creative work, other can also be obtained according to these accompanying drawings Accompanying drawing.
Fig. 1 is Bailey bracket structural representation;
Fig. 2 is shellfish thunder latch structure schematic diagram;
Fig. 3 is the structural representation of section at the pontic of make-shift bridge device provided in an embodiment of the present invention;
Fig. 4 is the structural representation of section at the end of the bridge gateway of make-shift bridge device provided in an embodiment of the present invention;
Fig. 5 is the vertical structure schematic diagram of make-shift bridge device provided in an embodiment of the present invention.
Embodiment
With reference to the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Ground is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.Based on this The embodiment of invention, the every other implementation that those of ordinary skill in the art are obtained under the premise of creative work is not made Example, belongs to protection scope of the present invention.
The embodiment of the present invention is described in further detail below in conjunction with accompanying drawing.
Embodiment one
As shown in Fig. 3, Fig. 4 and Fig. 5, a kind of make-shift bridge device for the Simple bridge of temporary erection, including multiple hangs down The Bailey beam 8 across space under bridge of the longitudinally spaced arrangement of Through Lane, space under bridge is probably road or river, described shellfish Thunder beam 8 is laterally including multigroup sub- roof beam structure connected by shellfish thunder pin 17 mutually, as shown in figure 5, every sub- roof beam structure is by three shellfish thunders Frame is arranged in parallel to be constituted, and is connected between three Bailey brackets by horizontal-associate frame 20;Upper and lower chord member is connected by shellfish thunder pin 17 between Bailey beam 8 Connect, specifically using Bailey bracket, three one group, spacing 2X45cm, arrangement spacing is 90cm between longitudinal each group.Bailey beam vertical row Track arranges that runway is arranged along river course.Bailey beam top laying I-steel distribution beam, floorings are cast-in-place concrete floorings. Bamboo slab rubber is arranged between floorings and distribution beam, the template of casting concrete is used as.Embedded U-shaped bolt and shellfish in cast-in-place floorings Thunder beam top boom is connected.
Bailey beam 8 is laid lay bamboo slab rubber 10, bamboo slab rubber 10 in the road surface distribution beam 9 of I-steel, road surface distribution beam 9 above As the template of casting concrete, cast-in-place concrete floorings 11 constitute road surface on bamboo slab rubber 10;Concrete slab 11 Interior embedded U-shaped bolt 16 is connected with Bailey beam 8;U-bolt is specifically connected with Bailey beam top boom, i.e. top boom shellfish thunder Rod member below rod member above beam, i.e. corresponding lower boom Bailey beam;The described spacer of concrete slab 11 is set Multiple transverse expansion joints are put, specifically sets in transverse expansion joint, the two ends floorings 11 at expansion joint and sets at spacing intervals Strengthen channel-section steel 18 and U-shaped reinforcing bar 19.The U-shaped reinforcing bar 19 is welded with strengthening channel-section steel 18, is embedded in floorings 11.
The two ends of Bailey beam 8 are provided with end bridge pier, and centre is provided with middle bridge pier, and end bridge pier supports Bailey beam 8, and end bridge with middle bridge pier Stake supports Bailey beam 8 with setting laminated rubber bearing 21 on middle bridge pier.Top of the top mark height higher than end bridge pier of described middle bridge pier Absolute altitude, the middle part of Bailey beam 8 of support is higher than two ends, the gradient 1% or so.Specific method is the corresponding Bailey beam of bridge pier in releasing The shellfish thunder pin 17 of 8 top boom junction.By raising jackshaft stake top absolute altitude, while the lower edge of jackshaft pile top position Bailey beam 8 Bar junction is connected with shellfish thunder pin 17, and top boom junction does not install shellfish thunder pin 17, is being raised jackshaft stake top absolute altitude, is being made both sides shellfish Thunder beam 8 can freely be rotated around korneforos bridge pier top, form the 1% transverse drainage gradient.
Described end bridge pier includes end bored concrete pile 1 and the Guan Liang 2 located at the end upper end of bored concrete pile 1, the support Bailey beam 8 of Guan Liang 2 End.Described middle bridge pier includes middle bored concrete pile 3, casing 4, cover plate 5, ribbed stiffener 6 and shaped steel distribution beam 7;Casing 4 is placed in middle filling The top of stake 3 is noted, pours and welds shaped steel distribution beam 7 after middle bored concrete pile 3 on the top welded cover plate 5 of casing 4, cover plate 5, and setting is put more energy into Rib 6.
As shown in figure 1, the road surface side of described suspension bridge device pontic sets anticollision barrier 12, opposite side is mated formation pavement 15, the inner side of pavement 15 sets kerbstone 14, and outside sets people's row railing 13.
As shown in Fig. 2 described suspension bridge device end of the bridge gateway road surface one end be provided with top cap 22, parados 23, ear wall 24 With attachment strap 25;Top cap 22 is installed on above the bridge pier of end, and parados 23 is installed in top cap 22 with ear wall 24, and attachment strap 25 is located at ear wall 24 On, paving 26 of mating formation on attachment strap 25.
The present invention is due to using the lateral arrangement of Bailey beam 8, and horizontal span can reach 15m or more large span.27m's Make-shift bridge is built along river course on river, three campsheds need to be only set, wherein korneforos sets a campshed base, and two sides respectively set a row in addition Stake.Korneforos pier arrangement of pile foundation quantity is substantially reduced, current obstruction area is effectively reduced.Traditional Bailey beam indulges bridge to arrangement, During bridge floor wider (reaching 30m), direction across bridge pile foundation is arranged by 5m spacing, stake diameter 1m, at least 7 campsheds, and 5 rank in korneforos, block water Area is 5 times of Bailey beam lateral arrangement.
Cross fall is set using korneforos pier top absolute altitude mode is raised to arrangement using Bailey beam horizontal stroke 8 in addition, it is to avoid use Traditional increase in-situ layer thickness sets cross fall, can effectively reduce in-situ layer concrete works amount, so as to reduce Dead load.
Simultaneously using the Bailey beam bridge lateral arrangement, vehicle discrepancy bridge section abutment connection and reasonable arrangement, to the stress of Bailey beam 8 more To be favourable.
The foregoing is only a preferred embodiment of the present invention, but protection scope of the present invention be not limited thereto, Any one skilled in the art is in the technical scope of present disclosure, the change or replacement that can be readily occurred in, It should all be included within the scope of the present invention.Therefore, protection scope of the present invention should be with the protection model of claims Enclose and be defined.

Claims (7)

1. a kind of make-shift bridge device, the Simple bridge for temporary erection, it is characterised in that vertical including multiple vertical runways To the spaced apart Bailey beam (8) across space under bridge, described Bailey beam (8) laterally passes through Bei Leixiao mutually including multigroup (17) the sub- roof beam structure of connection, every sub- roof beam structure is constituted by three Bailey brackets are arranged in parallel, and horizontal-associate frame is passed through between three Bailey brackets (20) connect;
Bailey beam (8) is laid above lays bamboo slab rubber (10), bamboo glue in the road surface distribution beam (9) of I-steel, road surface distribution beam (9) Cast-in-place concrete floorings (11) constitute road surface on plate (10);The interior embedded U-shaped bolt (16) of concrete slab (11) with Bailey beam (8) is connected;
Each Bailey beam (8) two ends are provided with end bridge pier, and centre is provided with middle bridge pier, end bridge pier and middle bridge pier support Bailey beam (8).
2. make-shift bridge device according to claim 1, it is characterised in that the top mark height of described middle bridge pier is higher than end bridge The top mark of stake is high, and two ends, the gradient 1% are higher than in the middle part of the Bailey beam (8) of support.
3. make-shift bridge device according to claim 1 or 2, it is characterised in that described end bridge pier includes end bored concrete pile (1) with the Guan Liang (2) located at end bored concrete pile (1) upper end, Guan Liang (2) support Bailey beam (8) end.
4. make-shift bridge device according to claim 1 or 2, it is characterised in that described middle bridge pier includes middle bored concrete pile (3), casing (4), cover plate (5), ribbed stiffener (6) and shaped steel distribution beam (7);Casing (4) is placed at the top of middle bored concrete pile (3), is poured Shaped steel distribution beam (7) is welded on middle bored concrete pile (3), rear casing (4) top welded cover plate (5), cover plate (5), and ribbed stiffener is set (6)。
5. make-shift bridge device according to claim 1 or 2, it is characterised in that the road surface of described suspension bridge device pontic Side sets anticollision barrier (12), and opposite side is mated formation pavement (15), and kerbstone (14) is set on the inside of pavement (15), and outside is set People's row railing (13).
6. make-shift bridge device according to claim 1 or 2, it is characterised in that described suspension bridge device end of the bridge gateway Road surface one end provided with top cap (22), parados (23), ear wall (24) and attachment strap (25);
Top cap (22) is installed on above the bridge pier of end, and parados (23) is installed in top cap (22) with ear wall (24), and attachment strap (25) is located at On ear wall (24), paving (26) of mating formation on attachment strap (25).
7. make-shift bridge device according to claim 1 or 2, it is characterised in that between described concrete slab (11) Strengthen channel-section steel (18) and U-shaped reinforcing bar every setting to set in many outer transverse expansion joints, the concrete slab (11) at expansion joint two ends (19);The U-shaped reinforcing bar (19) is welded with strengthening channel-section steel (18), is embedded in concrete slab (11).
CN201710364044.6A 2017-05-22 2017-05-22 A kind of make-shift bridge device Active CN106978777B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710364044.6A CN106978777B (en) 2017-05-22 2017-05-22 A kind of make-shift bridge device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710364044.6A CN106978777B (en) 2017-05-22 2017-05-22 A kind of make-shift bridge device

Publications (2)

Publication Number Publication Date
CN106978777A true CN106978777A (en) 2017-07-25
CN106978777B CN106978777B (en) 2018-09-14

Family

ID=59342597

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710364044.6A Active CN106978777B (en) 2017-05-22 2017-05-22 A kind of make-shift bridge device

Country Status (1)

Country Link
CN (1) CN106978777B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700337A (en) * 2017-11-28 2018-02-16 北京中铁隧建筑有限公司 It is a kind of quickly to pacify the light section suspension bridge torn open
CN109555004A (en) * 2018-11-08 2019-04-02 广东省第建筑工程有限公司 A kind of method of construction of temporary traffic suspension bridge
CN110872807A (en) * 2018-09-04 2020-03-10 宏润建设集团股份有限公司 A kind of construction method of steel stool bridge and steel stool bridge
CN111305038A (en) * 2020-04-09 2020-06-19 江苏鹏创电力设计有限公司 A river crossing device for rapid disassembly and assembly of high-voltage transmission line engineering
CN113737631A (en) * 2021-09-23 2021-12-03 中交二公局第三工程有限公司 Transverse turning connection structure of Bailey steel trestle
CN114525726A (en) * 2022-03-21 2022-05-24 中铁大桥局第七工程有限公司 Bailey beam construction trestle expansion joint system and construction method
CN115652772A (en) * 2022-12-28 2023-01-31 中冶建筑研究总院有限公司 Quick connecting system and method for bridge deck of steel temporary bridge

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100936824B1 (en) * 2007-06-07 2010-01-14 서옥석 Truss structure of a hypothetical bridge
KR101126083B1 (en) * 2011-10-10 2012-03-29 주식회사 케이에스씨건설 A lining board support structure of truss temporary bridge
CN202530367U (en) * 2012-03-14 2012-11-14 中铁二十二局集团第一工程有限公司 Deepwater complex geology foundation construction system
CN103410084A (en) * 2013-08-15 2013-11-27 中交二航局第三工程有限公司 Assembly-type steel trestle
CN203684059U (en) * 2013-09-29 2014-07-02 中铁四局集团第四工程有限公司 Large-span deck Bailey beam steel trestle structure
CN204039922U (en) * 2014-07-10 2014-12-24 中交二航局第四工程有限公司 A kind of temporary steel trestle
CN204151662U (en) * 2014-09-26 2015-02-11 中建交通建设集团有限公司 A kind of one across the temporary trestle bridge crossing over river valley
CN204753354U (en) * 2015-06-11 2015-11-11 辽宁紫竹桩基础工程股份有限公司 Cover worker's board landing stage

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100936824B1 (en) * 2007-06-07 2010-01-14 서옥석 Truss structure of a hypothetical bridge
KR101126083B1 (en) * 2011-10-10 2012-03-29 주식회사 케이에스씨건설 A lining board support structure of truss temporary bridge
CN202530367U (en) * 2012-03-14 2012-11-14 中铁二十二局集团第一工程有限公司 Deepwater complex geology foundation construction system
CN103410084A (en) * 2013-08-15 2013-11-27 中交二航局第三工程有限公司 Assembly-type steel trestle
CN203684059U (en) * 2013-09-29 2014-07-02 中铁四局集团第四工程有限公司 Large-span deck Bailey beam steel trestle structure
CN204039922U (en) * 2014-07-10 2014-12-24 中交二航局第四工程有限公司 A kind of temporary steel trestle
CN204151662U (en) * 2014-09-26 2015-02-11 中建交通建设集团有限公司 A kind of one across the temporary trestle bridge crossing over river valley
CN204753354U (en) * 2015-06-11 2015-11-11 辽宁紫竹桩基础工程股份有限公司 Cover worker's board landing stage

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700337A (en) * 2017-11-28 2018-02-16 北京中铁隧建筑有限公司 It is a kind of quickly to pacify the light section suspension bridge torn open
CN110872807A (en) * 2018-09-04 2020-03-10 宏润建设集团股份有限公司 A kind of construction method of steel stool bridge and steel stool bridge
CN109555004A (en) * 2018-11-08 2019-04-02 广东省第建筑工程有限公司 A kind of method of construction of temporary traffic suspension bridge
CN111305038A (en) * 2020-04-09 2020-06-19 江苏鹏创电力设计有限公司 A river crossing device for rapid disassembly and assembly of high-voltage transmission line engineering
CN113737631A (en) * 2021-09-23 2021-12-03 中交二公局第三工程有限公司 Transverse turning connection structure of Bailey steel trestle
CN114525726A (en) * 2022-03-21 2022-05-24 中铁大桥局第七工程有限公司 Bailey beam construction trestle expansion joint system and construction method
CN114525726B (en) * 2022-03-21 2024-01-30 中铁大桥局第七工程有限公司 Beehive beam construction trestle bridge expansion joint system and construction method
CN115652772A (en) * 2022-12-28 2023-01-31 中冶建筑研究总院有限公司 Quick connecting system and method for bridge deck of steel temporary bridge

Also Published As

Publication number Publication date
CN106978777B (en) 2018-09-14

Similar Documents

Publication Publication Date Title
CN106978777B (en) A kind of make-shift bridge device
CN205205635U (en) Stride footpath bailey frame steel suspension bridge structure greatly
CN110184950B (en) Construction method for rebuilding and expanding new bridge at original site of bridge under condition of ensuring communication
CN202899015U (en) Modular highway steel truss bridge
CN108374319A (en) A kind of through tied arch bridge structural unit and arch bridge structure and its construction method
CN106480818B (en) Composite connecting plate structure of simply supported girder bridge and its construction method
CN108505405A (en) A kind of suspension type monorail and highway bridge build structure jointly
CN106049289A (en) Construction method for transforming Bailey beam temporary bridge into reinforced concrete combined permanent bridge
CN206538672U (en) Novel fabricated truss steel trestle
CN104775368B (en) Prefabricated jacking box culvert provided with steel blade corners
CN208136705U (en) A kind of make-shift bridge device
CN107905084B (en) RPC steel truss combined bridge deck and continuous beam bridge
CN202081383U (en) Temporary support used in construction striding over existing line bridge
CN108708290A (en) The case crane span structure hollow structure and cast-in-situ construction method of minor radius railway curve unit
CN110184903B (en) A truss-type prefabricated pipe column assembled bridge pier
CN208472473U (en) A kind of suspension type monorail and highway bridge build structure jointly
CN207110599U (en) A kind of under(-)chassis of up-down cross sliding type multi-storied garage
CN215857324U (en) A road culvert reinforcement system
CN102677563A (en) Modularized direct-moving fast channel system for crossroads of urban main road and construction method
CN204370284U (en) A kind of automobile and light rail are with the intermediate deck arch bridge of layer
CN210737255U (en) Box frame and reinforced concrete box frame road bed for road bed
CN214005282U (en) A waterproof and anti-settling highway subgrade structure
CN110184929B (en) Comprehensive construction method for main and auxiliary lines of public rail co-constructed bridge
CN208072458U (en) A kind of pier sheet-pile engaging portion structure
CN206667292U (en) It is a kind of to justify pile foundation counterfort wall station road structure close to bridge pier

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant