CN204527557U - A kind of modularization drilling ship - Google Patents
A kind of modularization drilling ship Download PDFInfo
- Publication number
- CN204527557U CN204527557U CN201520004619.XU CN201520004619U CN204527557U CN 204527557 U CN204527557 U CN 204527557U CN 201520004619 U CN201520004619 U CN 201520004619U CN 204527557 U CN204527557 U CN 204527557U
- Authority
- CN
- China
- Prior art keywords
- module
- hull part
- platform
- drilling ship
- hull
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Earth Drilling (AREA)
Abstract
A kind of modularization drilling ship, the longitudinal front upper of hull part (1) installs life building module and helicopter platform (2), handling module (3) and memory module (4) are installed above hull part (1) longitudinal middle part, hull part (1) longitudinal rear upper installing drill platform shaft and basis (5), and extra large work module (6) is installed in hull part (1) rear end.By correct model structural design; make drilling ship construction scale greatly little; debug processization is long for short; construction is simplified; modules is built and can be carried out simultaneously; thus realize the same work in strange land, complete more how higher-quality engineering with the minimum time, also make the mass of module and product be built into reality simultaneously.Production cycle shortens greatly, cost declines, engineering efficiency significantly promotes.
Description
Technical field
The utility model relates to the structural development technology of offshore engineering equipment device, especially a kind of modularization drilling ship.
Background technology
The modular concept of ship building starts from a large amount of shipbuildings of US during World War II, and at that time, the U.S. once had 1,650,000 shipbuilding workers, had built military boats and ships 1768.The construction of a large amount of standard ship facilitates the development of welding technique and sectional construction technology.Modularization one word derives from production field the earliest, Starr mentions a completely new concept-modularized production (Modular Production) in nineteen sixty-five in Harvard Business Review, is widely applied in field of software development very soon afterwards.Current modular technology is extensively present in every field.
6th generation ultra deepwater drilling ship compared for the 5th generation and forth generation drilling ship can resist the dual lifting having had quality and quantity in environment, probing ability and automation etc., the complexity of its inside is well imagined.Close up according to segment design original in the past, construction, installation, that the method for overall japanning obviously works is heavy trifling, complicated and changeable, whole production cycle is seriously elongated, and cost increase takes time and effort.
Modular shipbuilding is different from the regional shipbuilding mode in modern age, is more different from original Tinkertoy approach shipbuilding again, the widespread use that its various advantages is inevitable after determining it.And specifically how to carry out Module Division, sport technique segment wherein crucial just.
Utility model content
The purpose of this utility model is to provide a kind of modularization drilling ship, with the Module Division organization plan of economical rationality, has not only been convenient to specialty and has manufactured but also constructability management.
The purpose of this utility model will be realized by following technical measures: comprise hull part, life building module and helicopter platform, drilling platform and basis, extra large work module, handling module and memory module; The longitudinal front upper of hull part installs life building module and helicopter platform, installs handling and memory module above hull part longitudinal middle part, the longitudinal rear upper installing drill platform shaft of hull part and basis, and hull portion rear end installs extra large work module.
Especially, drilling platform and basis comprise derrick, top is driven, compensator, tensioner, anchor rack and winch, high-pressure slurry manifold etc.
Especially, life building module and helicopter platform are arranged on the top, bow deck of hull part, and hull part postmedian comprises the independent sector that two are positioned at two sides, have longitudinally vertical and posteriorly open courtyard between this two part, and this two parts rear upper has connection structure.
Especially, each module comprises agent structure, platform support, a/c system, pipeline system, electric wiring, fitting-out, mechanical device and instrument and equipment respectively.
Especially, hull part comprises cabin module, propeller module and treatment of mud module by dividing elements.
Especially, life building module and helicopter platform comprise operator's compartment, emergency power generation room, residence, office, restaurant kitchen, laundry and gymnasium etc.
Especially, each module comprises hull structure module, turbine module and electrical module by specialty; If each specialty can be subdivided into individual submodule again again, wherein, turbine module comprises again piping module, HVAC module, turbine module and drilling module etc.
Advantage of the present utility model and effect: by correct model structural design; make drilling ship construction scale greatly little; debug processization is long for short; construction is simplified; modules is built and can be carried out simultaneously; thus realize the same work in strange land, complete more how higher-quality engineering with the minimum time, also make the mass of module and product be built into reality simultaneously.Production cycle shortens greatly, cost declines, engineering efficiency significantly promotes.
Accompanying drawing explanation
Fig. 1 is the utility model embodiment 1 structural representation.
Fig. 2 is hull section separation structure schematic diagram in the utility model embodiment 1.
Reference numeral comprises: hull part 1, life building module and helicopter platform 2, drilling platform and basis 5, extra large work module 6, handling module 3, memory module 4.
Detailed description of the invention
The utility model principle is, module (MODULE) can be defined as have certain or several functions, a unit of band independence or group system, connect the more complicated system of formation each other between module, little module is combined into large module, and large block combiner becomes product.
The utility model comprises: hull part 1, life building module and helicopter platform 2, drilling platform and basis 5, extra large work module 6, handling module 3 and memory module 4.
Below in conjunction with drawings and Examples, the utility model is described in further detail.
Embodiment 1: as shown in Figure 1, the longitudinal front upper of hull part 1 installs life building module and helicopter platform 2, above hull part 1 longitudinal middle part, handling and memory module 3 & 4 are installed, hull part 1 longitudinal rear upper installing drill platform shaft and basis 5, and extra large work module 6 is installed in hull part 1 rear end.
In aforementioned, drilling platform and basis 5 comprise derrick, top is driven, compensator, tensioner, anchor rack and winch, high-pressure slurry manifold etc.
In aforementioned, extra large work module 6 provides produced on-site operation support for drilling ship.
In aforementioned, as shown in Figure 2, life building module and helicopter platform 2 are arranged on the top, bow deck of hull part 1, hull part 1 postmedian comprises the independent sector that two are positioned at two sides, longitudinally vertical and posteriorly open courtyard is had between this two part, and this two parts rear upper has connection structure.
In aforementioned, each module comprises agent structure, platform support, a/c system, pipeline system, electric wiring, fitting-out, mechanical device and instrument and equipment respectively.
In aforementioned, hull part 1 comprises cabin module, propeller module and slurry processing module by dividing elements.
In aforementioned, life building module and helicopter platform 2 comprise operator's compartment, emergency power generation room, residence, office, restaurant kitchen, laundry and gymnasium etc.Life building module and helicopter platform 2 hold 180 people's daily life.
In aforementioned, each module comprises hull structure module, turbine module and electrical module by specialty; If each specialty can be subdivided into individual submodule again again, wherein, turbine module comprises again piping module, HVAC module, turbine module and drilling module etc.
In the utility model, drilling platform and basis 5 are nucleus modules of drilling ship, and its structure is most complicated, and many equipment on drilling platform and basis 5 all needs hydraulic-driven; Therefore its operating characteristic, construction, buying and follow-up maintenance is taken into full account when design of Hydraulic System, set up the welding design standard of a hydraulic efficiency pressure system complete set, and this is set up software library as standard, be laying the first stone smoothly of model, the design of rig floor module is more precisely run efficiently.
In the utility model, drilling ship hull is divided into some modules, then design and the construction of each module is carried out, serial production model is substituted with parallel production pattern, finally modules is carried out integral installation, the same work in strange land, multiple module is carried out simultaneously, the time that namely saves also allow the whole process of project and flow process all clear; Thus realize that production cycle shortens greatly, cost declines, engineering efficiency significantly promotes.
During utility model works, the advantage being its structure design for cooperation the technical solution of the utility model obtains best performance, the theory that extension die blocking is built in construction management should be continued, specify from tentative programme PPS, detail design submit to a higher level for approval or revision, move back careful, Production design is fully under way, build and go into operation, pre outfitting, be brought together into the main each link of engineering process such as debugging, each step can be segmented again several modules again and carry out, and the contraposition simultaneously taking into account intermodule connects accurate.Modular obtains abundant application on drilling ship, each module selects different construction site according to its size with complexity etc., realize each incorporated business to work according to his ability, strange land is with the parallel construction effect of work, again three is closed up into a composite module after completing, once the overall delivery of row is to place of delivery, thus greatly shortens construction and haul-cycle time, also achieves the Appropriate application to transport resource.
The standard of the utility model modular division is equally also applicable in multiple drilling ship and drilling platform, as semi-submersible drilling unit, jack-up drilling unit etc.
Claims (7)
1. a modularization drilling ship, comprises hull part (1), life building module and helicopter platform (2), drilling platform and basis (5), extra large work module (6), handling module (3) and memory module (4); It is characterized in that, the longitudinal front upper of hull part (1) installs life building module and helicopter platform (2), handling module (3) and memory module (4) are installed above hull part (1) longitudinal middle part, hull part (1) longitudinal rear upper installing drill platform shaft and basis (5), and extra large work module (6) is installed in hull part (1) rear end.
2. a kind of modularization drilling ship as claimed in claim 1, is characterized in that, drilling platform and basis (5) comprise derrick, top drive, compensator, tensioner, anchor rack and winch, high-pressure slurry manifold.
3. a kind of modularization drilling ship as claimed in claim 1, it is characterized in that, life building module and helicopter platform (2) are arranged on the top, bow deck of hull part (1), hull part (1) postmedian comprises the independent sector that two are positioned at two sides, longitudinally vertical and posteriorly open courtyard is had between this two part, and this two parts rear upper has connection structure.
4. a kind of modularization drilling ship as claimed in claim 1, it is characterized in that, each module comprises agent structure, platform support, a/c system, electric wiring, fitting-out, mechanical device and instrument and equipment respectively.
5. a kind of modularization drilling ship as claimed in claim 1, is characterized in that, sea work module, hull part (1) rear end (6) comprises cabin module, propeller module and treatment of mud module by dividing elements.
6. a kind of modularization drilling ship as claimed in claim 1, is characterized in that, life building module and helicopter platform (2) comprise operator's compartment, emergency power generation room, residence, office, restaurant kitchen, laundry and gymnasium.
7. a kind of modularization drilling ship as claimed in claim 1, is characterized in that, each module comprises hull structure module, turbine module and electrical module by specialty; If each specialty can be subdivided into individual submodule again again, wherein, turbine module comprises again piping module, HVAC module, turbine module and drilling module.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520004619.XU CN204527557U (en) | 2015-01-04 | 2015-01-04 | A kind of modularization drilling ship |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520004619.XU CN204527557U (en) | 2015-01-04 | 2015-01-04 | A kind of modularization drilling ship |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204527557U true CN204527557U (en) | 2015-08-05 |
Family
ID=53741590
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520004619.XU Active CN204527557U (en) | 2015-01-04 | 2015-01-04 | A kind of modularization drilling ship |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204527557U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108082409A (en) * | 2017-11-30 | 2018-05-29 | 中海油能源发展股份有限公司 | A kind of dynamic positioning type floating production and storage facilities for having both well workover function |
WO2019047355A1 (en) * | 2017-09-11 | 2019-03-14 | 青岛武船麦克德莫特海洋工程有限公司 | Integrated construction and installation method for upper part processing module of floating production facility |
US10941561B2 (en) | 2017-07-27 | 2021-03-09 | Rad Urban, Llc | Prefabricated modular buildings |
CN114313123A (en) * | 2021-11-25 | 2022-04-12 | 太重(天津)滨海重型机械有限公司 | Multifunctional offshore construction ship adopting functional modules |
-
2015
- 2015-01-04 CN CN201520004619.XU patent/CN204527557U/en active Active
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10941561B2 (en) | 2017-07-27 | 2021-03-09 | Rad Urban, Llc | Prefabricated modular buildings |
US10947720B2 (en) | 2017-07-27 | 2021-03-16 | Rad Urban, Llc | Block construction of prefabricated buildings |
WO2019047355A1 (en) * | 2017-09-11 | 2019-03-14 | 青岛武船麦克德莫特海洋工程有限公司 | Integrated construction and installation method for upper part processing module of floating production facility |
RU2707205C2 (en) * | 2017-09-11 | 2019-11-25 | ЦИНДАО МакДЕРМОТТ УЧУАНЬ ОФФШОР ИНДЖИНИРИНГ КО., ЛТД | Method for integrated construction and installation of equipment for floating structure upper technological unit |
CN108082409A (en) * | 2017-11-30 | 2018-05-29 | 中海油能源发展股份有限公司 | A kind of dynamic positioning type floating production and storage facilities for having both well workover function |
CN108082409B (en) * | 2017-11-30 | 2023-09-19 | 中海油能源发展股份有限公司 | Dynamic positioning type floating production and oil storage facility with well repairing function |
CN114313123A (en) * | 2021-11-25 | 2022-04-12 | 太重(天津)滨海重型机械有限公司 | Multifunctional offshore construction ship adopting functional modules |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204527557U (en) | A kind of modularization drilling ship | |
CN102582784B (en) | Process for sectionally putting up ship berths or docks | |
CN102518397B (en) | Tension mooring type underwater drilling system and mounting method for same | |
CN104527940A (en) | Ocean platform block offshore double-boat integral migration method | |
CN105480380B (en) | Tension leg platform (TLP) upper module and the closure workmanship of lower float structure | |
CN102234999A (en) | Underwater drilling platform | |
CN105003232B (en) | A kind of ultra-deep sea marine oil and gas dry type production system and its installation evacuation method | |
CN101817393A (en) | Shipbuilding method by utilizing floating dock | |
CN104029789B (en) | A kind of construction implementation of ocean platform | |
CN105151242A (en) | Application of modular shipbuilding in semi-submersible platform building | |
CN102632965A (en) | Combined type module ship and module connecting way thereof | |
CN207737468U (en) | A kind of dynamic positioning type floating production and storage facilities having both well workover function | |
CN108082409B (en) | Dynamic positioning type floating production and oil storage facility with well repairing function | |
CN106593363B (en) | Modularization production of hydrocarbons platform and its working method in water | |
Hwang et al. | Detailed design and construction of the hull of a floating, production, storage and off-loading (FPSO) unit | |
CN103921905B (en) | Semi-submersible module for combining into large-scale floating body on the water and assembling method thereof | |
CN113715986A (en) | Basin fitting-out unit installation method | |
CN204000813U (en) | A kind of standardization that adopts floating holder method to install can be moved formula wellhead platform | |
CN104802945A (en) | Power cable system of oceanographic engineering and arrangement method of system | |
CN105216975A (en) | Carry the workover platform of thrust power position fixing system | |
CN206012922U (en) | A kind of marine oil and gas increase production the propulsion system of ship | |
Smogeli et al. | DynCap—Full Scale Validation of a Vessel’s Station-Keeping Capability Analysis | |
CN206847905U (en) | A kind of experiment be hinged simulation of floating body and test device | |
Feller | WIN WIN-wind-powered water injection | |
CN203977395U (en) | Split self-elevating drilling platform and module connected mode thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |