CN204491912U - Curtain wall structure between architecture pipe - Google Patents

Curtain wall structure between architecture pipe Download PDF

Info

Publication number
CN204491912U
CN204491912U CN201520177456.5U CN201520177456U CN204491912U CN 204491912 U CN204491912 U CN 204491912U CN 201520177456 U CN201520177456 U CN 201520177456U CN 204491912 U CN204491912 U CN 204491912U
Authority
CN
China
Prior art keywords
grc
partition wall
steel
wall structure
curtain wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201520177456.5U
Other languages
Chinese (zh)
Inventor
王跃伟
沈成红
陈春波
钱峰
庄高
章鹏
方浩英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HANGZHOU TONGDA GROUP Co Ltd
Original Assignee
HANGZHOU TONGDA GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HANGZHOU TONGDA GROUP Co Ltd filed Critical HANGZHOU TONGDA GROUP Co Ltd
Priority to CN201520177456.5U priority Critical patent/CN204491912U/en
Application granted granted Critical
Publication of CN204491912U publication Critical patent/CN204491912U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

本实用新型公开了一种建筑物管道间的隔墙结构。为克服现有隔墙结构施工不便、施工工序复杂、周期长的缺陷,本实用新型采用的技术方案包括GRC条板、上钢卡组和下钢卡组;钢卡组包括两个钢卡板,钢卡板包括竖边和横边,每组钢卡组中的两竖边构成一用于卡置GRC条板的端部的卡槽;所述钢卡板的横边外凸于GRC条板的端面,与GRC条板的端面构成一空隙,该空隙内填充用于与楼板粘结的水泥砂浆粘结层;位于隔墙结构两端的隔墙单元中,GRC条板的外侧边形成凹槽,所述凹槽内填充用于与主墙体粘结的水泥砂浆粘结层;构成转角的两个隔墙单元的GRC条板之间也填充水泥砂浆粘结层。其优点是:便于施工,且能简化施工工序、缩短施工周期。

The utility model discloses a partition wall structure between building pipelines. In order to overcome the defects of inconvenient construction, complex construction process and long period of the existing partition wall structure, the technical scheme adopted by the utility model includes GRC slats, an upper steel clamp group and a lower steel clamp group; the steel clamp group includes two steel clamps , the steel clamping plate includes a vertical edge and a horizontal edge, and the two vertical edges in each steel clamping group form a card slot for clamping the end of the GRC strip; the horizontal edge of the steel clamping plate protrudes outward from the GRC strip The end face of the slab forms a gap with the end face of the GRC slab, and the gap is filled with a cement mortar bonding layer for bonding with the floor slab; in the partition wall units located at both ends of the partition wall structure, the outer side of the GRC slab forms The groove is filled with a cement mortar bonding layer for bonding with the main wall; the cement mortar bonding layer is also filled between the GRC strips of the two partition wall units forming the corner. The advantage is that it is convenient for construction, and can simplify the construction process and shorten the construction period.

Description

建筑物管道间的隔墙结构Partition wall structure between building pipes

技术领域 technical field

本实用新型涉及建筑施工领域,具体地说是一种建筑物管道间的隔墙结构。 The utility model relates to the field of building construction, in particular to a partition wall structure between building pipelines.

背景技术 Background technique

建筑工程中有较多的竖向管道需要集中安装,如基本的供水、供电、排水管道,这样在集中安装处就形成了管道井。管道井内水平设置多块楼板,在楼板上砌筑隔墙,使其与楼板、管道井主墙体共同构成封闭的管道间,隔墙的内侧必须粉刷平整。目前,管道间隔墙在施工时只能现场砌筑并粉刷,隔墙质量难以保证,而且需要在狭小的管道井空间内完成,存在施工不便、施工工序复杂、周期长的缺陷。 There are many vertical pipes in construction projects that need to be installed in a centralized manner, such as basic water supply, power supply, and drainage pipes, so that a pipe well is formed at the centralized installation place. A plurality of floor slabs are arranged horizontally in the pipeline well, and a partition wall is built on the floor slabs to form a closed pipeline room together with the floor slab and the main wall of the pipeline well. The inner side of the partition wall must be painted evenly. At present, the pipeline partition wall can only be built and painted on site during construction, the quality of the partition wall is difficult to guarantee, and it needs to be completed in a narrow pipeline well space, which has the disadvantages of inconvenient construction, complicated construction process and long period.

实用新型内容 Utility model content

本实用新型所要解决的技术问题是克服上述现有技术存在的缺陷,提供一种建筑物管道间的隔墙结构,便于施工,且能简化施工工序、缩短施工周期。 The technical problem to be solved by the utility model is to overcome the above-mentioned defects in the prior art, and provide a partition wall structure between building pipes, which is convenient for construction, and can simplify the construction process and shorten the construction period.

为此,本实用新型采用的技术方案如下:建筑物管道间的隔墙结构,其技术特征是,所述的隔墙结构由多个隔墙单元拼接而成; For this reason, the technical scheme that the utility model adopts is as follows: the partition wall structure between building pipes, its technical feature is that described partition wall structure is spliced by a plurality of partition wall units;

所述的隔墙单元包括GRC条板、至少一上钢卡组和至少一下钢卡组;所述的钢卡组包括两个钢卡板,所述的钢卡板呈“L”形,包括用于对GRC条板限位的竖边和用于与楼板连接的横边,每组钢卡组中的两竖边构成一用于卡置GRC条板的端部的卡槽; The partition wall unit includes GRC slats, at least one upper steel clamp and at least one lower steel clamp; the steel clamp includes two steel clamps, and the steel clamp is in an "L" shape, including The vertical edge used to limit the GRC slab and the horizontal edge used to connect with the floor. The two vertical edges in each set of steel clamps form a card slot for clamping the end of the GRC slab;

所述钢卡板的横边外凸于GRC条板的端面,与GRC条板的端面构成一空隙,该空隙内填充用于与楼板粘结的水泥砂浆粘结层; The transverse edge of the steel clamping plate protrudes outward from the end surface of the GRC slab, and forms a gap with the end surface of the GRC slat, and the cement mortar bonding layer used for bonding with the floor is filled in the gap;

位于隔墙结构两端的隔墙单元中,GRC条板的外侧边形成凹槽,所述凹槽内填充用于与主墙体粘结的水泥砂浆粘结层; In the partition wall units located at both ends of the partition wall structure, grooves are formed on the outer side of the GRC slats, and the grooves are filled with a cement mortar bonding layer for bonding with the main wall;

构成转角的两个隔墙单元的GRC条板之间也填充水泥砂浆粘结层。 The cement mortar bonding layer is also filled between the GRC slats of the two partition wall units forming the corner.

用GRC条板(轻质钢筋混凝土空心条板)代替原先需要在现场砌筑并粉刷的隔墙结构,利用GRC条板面层光滑、平整的特点,省去了粉刷的工序,避免了粉刷裂缝的产生,确保工程质量;而且,只需要将GRC条板成品运送到现场,完成安装即可,便于施工,简化了施工工序,缩短了施工周期。钢卡组的设置起到了对GRC条板的定位作用。水泥砂浆粘结层的设置使得隔墙单元与隔墙单元、主墙体、上下楼板之间的连接稳固。 GRC slats (lightweight reinforced concrete hollow slabs) are used to replace the original partition wall structure that needs to be built and painted on site, and the smooth and flat surface of the GRC slats is used to save the process of painting and avoid painting cracks The generation of the project ensures the quality of the project; moreover, it is only necessary to transport the finished GRC slats to the site and complete the installation, which is convenient for construction, simplifies the construction process, and shortens the construction period. The setting of the steel card group plays a role in positioning the GRC slats. The setting of the cement mortar bonding layer makes the connection between the partition wall unit and the partition wall unit, the main wall body, and the upper and lower floors stable.

作为改进,所述隔墙结构的转角的阴阳角处均设置玻纤带;所述与主墙体拼接的隔墙单元的阴角处设置玻纤带;相邻两个隔墙单元的GRC条板拼接后的板缝处设置玻纤带。这一设置,使得玻纤带对隔墙结构作拼缝处理,能够有效地防止开裂。 As an improvement, glass fiber tapes are provided at the male and female corners of the corners of the partition wall structure; glass fiber tapes are provided at the female corners of the partition wall units spliced with the main wall; the GRC strips of two adjacent partition wall units After the boards are spliced, glass fiber tapes are set at the seams of the boards. This setting enables the glass fiber tape to do seam processing on the partition wall structure, which can effectively prevent cracking.

作为改进,所述钢卡板的横边上穿设射钉。这一设置,使得钢卡板与楼板之间的连接结构简单、稳固,便于操作。 As an improvement, a nail is pierced on the lateral edge of the steel clamp. This setting makes the connection structure between the steel pallet and the floor slab simple, stable and easy to operate.

作为改进,所述的上钢卡组有两组,且对称设置在GRC条板的两侧;所述上钢卡组中的两个钢卡板的朝向相反。这一设置,使得上钢卡组对GRC条板的定位效果更好。 As an improvement, there are two sets of the upper steel clips, which are arranged symmetrically on both sides of the GRC slats; the two steel clips in the upper steel clips face opposite directions. This setting makes the positioning effect of Shanggang deck on the GRC slats better.

作为改进,所述的下钢卡组有两组,且对称设置在GRC条板的两侧;所述下钢卡组中的两个钢卡板的朝向一致。这一设置,使得下钢卡组对GRC条板的定位效果更好。 As an improvement, there are two groups of the lower steel clamps, which are arranged symmetrically on both sides of the GRC slats; the orientation of the two steel clamps in the lower steel clamps is the same. This setting makes the positioning effect of the lower steel deck on the GRC slats better.

作为改进,所述隔墙结构中的一隔墙单元上开设观察门。 As an improvement, an observation door is provided on a partition wall unit in the partition wall structure.

附图说明 Description of drawings

图1为本实用新型在使用时的结构示意图(去掉楼板)。 Fig. 1 is the structural representation of the utility model when in use (remove floor).

图2为本实用新型在使用时的侧面剖视图。 Fig. 2 is a side sectional view of the utility model in use.

图中所示:1、隔墙单元,2、GRC条板,21、凹槽,3、钢卡板,4、水泥砂浆粘结层,5、射钉,6、观察门,7、主墙体,8、楼板。 As shown in the figure: 1. Partition wall unit, 2. GRC slats, 21. Groove, 3. Steel clamping board, 4. Cement mortar bonding layer, 5. Nail shooting, 6. Observation door, 7. Main wall Body, 8, floor.

具体实施方式 Detailed ways

下面结合附图和具体实施方式对本实用新型作进一步说明。 Below in conjunction with accompanying drawing and specific embodiment, the utility model is further described.

如图1、图2所示的建筑物管道间的隔墙结构,由多个隔墙单元1拼接而成。 The partition wall structure between building pipelines as shown in FIG. 1 and FIG. 2 is formed by splicing a plurality of partition wall units 1 .

所述的隔墙单元1主要由GRC条板2、两个上钢卡组和两个下钢卡组组成。所述的钢卡组包括两个钢卡板3,所述的钢卡板3呈“L”形,包括用于对GRC条板2限位的竖边31和用于与楼板8连接的横边32,所述钢卡板3的横边32上穿设射钉5,通过射钉5与楼板8连接。每组钢卡组中的两竖边31构成一用于卡置GRC条板2的端部的卡槽。两组上钢卡组对称设置在GRC条板2的两侧,上钢卡组中的两个钢卡板3的朝向相反。两组下钢卡组对称设置在GRC条板2的两侧,下钢卡组中的两个钢卡板3的朝向一致(为了配合下楼板8的结构)。 The partition wall unit 1 is mainly composed of GRC slats 2, two upper steel decks and two lower steel decks. The steel clip set includes two steel clips 3, the steel clips 3 are in the shape of an "L" and include a vertical edge 31 for limiting the GRC strip 2 and a horizontal edge for connecting with the floor 8. Side 32 , the transverse side 32 of the steel clasp 3 is pierced with nails 5 , and is connected with the floor 8 through the nails 5 . The two vertical sides 31 in each group of steel clips form a clipping groove for clipping the end of the GRC slat 2 . The two sets of upper steel decks are arranged symmetrically on both sides of the GRC slats 2 , and the orientations of the two steel decks 3 in the upper steel decks are opposite. The two sets of lower steel decks are arranged symmetrically on both sides of the GRC slats 2 , and the orientation of the two steel decks 3 in the lower steel decks is consistent (in order to match the structure of the lower floor 8 ).

所述钢卡板3的横边32外凸于GRC条板2的端面,与GRC条板2的端面构成一空隙,该空隙内填充用于与楼板8粘结的水泥砂浆粘结层4。位于隔墙结构两端的隔墙单元1中,GRC条板2的外侧边形成凹槽21,所述凹槽21内填充用于与主墙体7粘结的水泥砂浆粘结层4。构成转角的两个隔墙单元1的GRC条板2之间也填充水泥砂浆粘结层4。 The transverse edge 32 of the steel clamping plate 3 protrudes outward from the end surface of the GRC slat 2 , forming a gap with the end surface of the GRC slat 2 , and the gap is filled with the cement mortar bonding layer 4 for bonding with the floor 8 . In the partition wall units 1 located at both ends of the partition wall structure, grooves 21 are formed on the outer sides of the GRC slats 2 , and the grooves 21 are filled with cement mortar bonding layers 4 for bonding with the main wall 7 . The cement mortar adhesive layer 4 is also filled between the GRC strips 2 of the two partition wall units 1 forming the corner.

所述隔墙结构的转角的阴阳角处均设置玻纤带;所述与主墙体7拼接的隔墙单元1的阴角处设置玻纤带;相邻两个隔墙单元1的GRC条板2拼接后的板缝处设置玻纤带。 Glass fiber tapes are arranged at the male and female corners of the corners of the partition wall structure; glass fiber tapes are arranged at the female corners of the partition wall unit 1 spliced with the main wall 7; the GRC strips of two adjacent partition wall units 1 The glass fiber tape is arranged at the seam of the board after the board 2 is spliced.

所述隔墙结构中的一隔墙单元1上开设观察门6。 A partition wall unit 1 in the partition wall structure is provided with an observation door 6 .

施工时,先将钢卡板3用射钉5固定于上、下楼板8,构成钢卡组,再将GRC条板放入钢卡组的卡槽内,并填充水泥砂浆粘结层4;在GRC条板2与主墙体7的连接阴角处粘结玻纤带;在GRC条板2转角拼接的阴阳角处粘结玻纤带。 During construction, first fix the steel pallet 3 to the upper and lower floors 8 with nails 5 to form a steel pallet group, then put the GRC slats into the grooves of the steel pallet group, and fill the cement mortar bonding layer 4; Bond glass fiber tapes at the inner and outer corners of the GRC slab 2 and the main wall 7;

以上仅就本实用新型较佳的实施例作了说明,但不能理解为是对权利要求的限制。本实用新型不仅局限于以上实施例,其具体结构允许有变化。凡在本实用新型独立权利要求的保护范围内所作的各种变化均在本实用新型的保护范围内。 The above is only a description of the preferred embodiments of the present utility model, but should not be construed as a limitation on the claims. The utility model is not limited to the above embodiments, and its specific structure allows changes. All the various changes made within the scope of protection of the independent claims of the utility model are within the scope of protection of the utility model.

Claims (6)

1. the curtain wall structure between architecture pipe, is characterized in that: described curtain wall structure is spliced by multiple partition wall unit (1);
Described partition wall unit (1) comprises GRC batten (2), at least one upper steel card group and at least one lower steel card group; Described steel card group comprises two steel clamps (3), described steel clamp (3) is L-shaped, comprise for the spacing vertical edge (31) of GRC batten (2) and the horizontal edge (32) for being connected with floor, two vertical edges (31) often organized in steel card group form one for the draw-in groove of the end of holding GRC batten (2);
Horizontal edge (32) evagination of described steel clamp (3), in the end face of GRC batten (2), forms a space with the end face of GRC batten (2), fills the cement mortar tack coat (4) being used for boning with floor in this space;
Be arranged in the partition wall unit (1) at curtain wall structure two ends, the outer side edges of GRC batten (2) forms groove (21), fills the cement mortar tack coat (4) being used for boning with main wall body in described groove (21);
Also filling concrete mortar bonding layer (4) between the GRC batten (2) forming two partition wall unit (1) of corner.
2. the curtain wall structure between architecture pipe according to claim 1, is characterized in that: the negative and positive angle place of the corner of described curtain wall structure all arranges glass fibre belt; The inner corner trim place of the described partition wall unit (1) spliced with main wall body arranges glass fibre belt; GRC batten (2) the spliced plate seam place of adjacent two partition wall unit (1) arranges glass fibre belt.
3. the curtain wall structure between architecture pipe according to claim 1, is characterized in that: the horizontal edge (32) of described steel clamp (3) wears nailing (5).
4. the curtain wall structure between architecture pipe according to claim 1, is characterized in that: described upper steel card group has two groups, and is symmetricly set on the both sides of GRC batten (2); Two steel clamps (3) in described upper steel card group towards the opposite.
5. the curtain wall structure between architecture pipe according to claim 1, is characterized in that: described lower steel card group has two groups, and is symmetricly set on the both sides of GRC batten (2); Two steel clamps (3) in described lower steel card group towards unanimously.
6. the curtain wall structure between architecture pipe according to claim 1, is characterized in that: the partition wall unit (1) in described curtain wall structure is offered and observes door (6).
CN201520177456.5U 2015-03-27 2015-03-27 Curtain wall structure between architecture pipe Expired - Lifetime CN204491912U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520177456.5U CN204491912U (en) 2015-03-27 2015-03-27 Curtain wall structure between architecture pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520177456.5U CN204491912U (en) 2015-03-27 2015-03-27 Curtain wall structure between architecture pipe

Publications (1)

Publication Number Publication Date
CN204491912U true CN204491912U (en) 2015-07-22

Family

ID=53571221

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520177456.5U Expired - Lifetime CN204491912U (en) 2015-03-27 2015-03-27 Curtain wall structure between architecture pipe

Country Status (1)

Country Link
CN (1) CN204491912U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109763628A (en) * 2018-12-21 2019-05-17 苏州美瑞德建筑装饰有限公司 A kind of bright dress natural gas line encapsulating structure in kitchen

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109763628A (en) * 2018-12-21 2019-05-17 苏州美瑞德建筑装饰有限公司 A kind of bright dress natural gas line encapsulating structure in kitchen
CN109763628B (en) * 2018-12-21 2023-11-28 苏州美瑞德建筑装饰有限公司 Kitchen open-installation natural gas pipeline packaging structure

Similar Documents

Publication Publication Date Title
CN103711236B (en) Assembled wall panel and its installation method
CN107605071B (en) Light composite batten system and construction method thereof
CN203795655U (en) Keel partition wall
CN103388367B (en) Construction method of waterproof structure of prefabricated wall or wallboard building block connecting joint
CN204252330U (en) A kind of light porous inner partition plate anti-cracking structure
CN207739431U (en) Modularization Timberwork wall
CN204662719U (en) A kind of indoor seamless spliced secondary light partition wall system
CN204491912U (en) Curtain wall structure between architecture pipe
CN105201118A (en) Crack resistant gypsum board suspended ceiling and back-to-back type mounting and splicing method
CN210421694U (en) Steel wire mesh connecting device of building element plastering layer
CN204282773U (en) Inside corner line structure between a kind of furred ceiling face and metope
CN103437562B (en) A kind of building method of hollow wall
CN204754055U (en) Light weight, high strength exempts from cement and spreads pin -connected panel wall ground decorative board that pastes
CN203296242U (en) STP compound block
CN210828154U (en) Wallboard connecting structure
CN104895244A (en) Light wallboard for building and flexible connection way thereof
CN208858174U (en) A kind of double-layer brick is laid bricks device
CN204510524U (en) A kind of steam pressure sand aerated concrete block combination masonry panel
CN105089246A (en) Installation structure and construction technology for decoration board
CN211923338U (en) A V-shaped assembly structure for wall panels
CN206070944U (en) A kind of new insert-type wooden decorative wallboard
CN208072817U (en) It is a kind of without damaged face linked network connector
CN205637437U (en) Wall wraps mounting structure who lays one's hand on skin firmly
CN205259443U (en) External wall board
CN205314466U (en) Take dampproofing ground plate brick of self -adhesive layer

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20150722