CN204457795U - Integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel - Google Patents
Integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel Download PDFInfo
- Publication number
- CN204457795U CN204457795U CN201520103342.6U CN201520103342U CN204457795U CN 204457795 U CN204457795 U CN 204457795U CN 201520103342 U CN201520103342 U CN 201520103342U CN 204457795 U CN204457795 U CN 204457795U
- Authority
- CN
- China
- Prior art keywords
- protection structure
- surrounding rock
- supporting
- anchor cable
- shaped steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of mine coal column base plate breaking surrounding rock tunnel and close integrated carrying supporting and protection structure, comprise U-shaped steel bracket, wall rock grouting back-up coat, stabilizing surrounding rock layer, prestressing force band beam anchor cable and roadway floor supporting and protection structure, U-shaped steel bracket as basic supporting along tunnel axial equidistant placement, prestressing force band beam anchor cable is arranged along tunnel circumference perpendicular to roadway surrounding rock surface between U-shaped steel bracket as strengthening supporting, single U-shaped steel bracket is connected into an entirety by one end of prestressing force band beam anchor cable, its other end is fixed in stabilizing surrounding rock layer, roadway floor supporting and protection structure is by concrete, steel mesh reinforcement, channel-section steel, anchor pole and anchor cable composition.Stabilizing surrounding rock layer, wall rock grouting back-up coat and U-shaped steel bracket can also couple together by the prestressing force band beam anchor cable in the utility model, and form closed integrated carrying supporting and protection structure with roadway floor supporting and protection structure.The utility model can eliminate the weak part in tunnel, ensures homogeneous deformation and the long-term stability thereof of roadway surrounding rock.
Description
Technical field
The utility model relates to a kind of colliery tunnel support structure, especially relates to a kind of mine coal column base plate breaking surrounding rock tunnel and closes integrated carrying supporting and protection structure.
Background technology
The a lot of mining area of China is when roadway layout; for improve tunnel its maintenance situation, prevent spontaneous combustion of coal seam from getting angry, improve tunnel transport capacity, ensure safe and efficient production; to be gone down the hill in longer for service time main large lane, exploiting field and set of segments inter-road is all arranged in the more stable floor strata of country rock, stay the protection coal pillar establishing one fixed width be such base plate tunnel mainly protect lane mode.But by the impact of on-the-spot actual mining conditions; not only stay the protection coal pillar established usually not play the effect of protection base plate tunnel; tunnel is made to be subject to the impact of high bearing pressure on coal column and strong deformation on the contrary; especially the joint fissure breaking surrounding rock tunnel of very growing is under high stress; roadway support structure often owing to adopting is improper, and is absorbed in the vicious circle of " repairing after front pick ".
Roadway support structure common is at present open supporting and protection structure, and this supporting and protection structure only carries out emphasis reinforcing and supporting to roadway's sides and roof rock, and seldom takes effective reinforcement measure to floor rocks.When tunnel buried depth is more shallow, because vertical stress value is little, even if roadway floor does not take reinforcement measure, also can guarantee that it is stablized, thus be unlikely to produce larger pucking amount.But for coal column base plate breaking surrounding rock tunnel, situation then will be different greatly.Due to the effect by high bearing pressure on coal column, the vertical stress in coal column base plate tunnel country rock is very high, under its effect, does not take the base plate of reinforcement measure then to become the most weak part in tunnel.The release of roadway surrounding rock stress and the dilatation distortion of rock mass will concentrate on base plate, thus cause strongly bloating of floor rocks, and bloating of floor rocks has obvious continuation, and be difficult to from line stabilization, and by have a strong impact on side, topmast protection structure stable, the deformation instability of globality destroys finally to cause tunnel to occur.
Utility model content
The purpose of this utility model is the weak point overcome in prior art, and simply, easily integrated carrying supporting and protection structure is closed in construction, effective mine coal column base plate breaking surrounding rock tunnel to provide a kind of method.
For achieving the above object, the technical solution adopted in the utility model is: integrated carrying supporting and protection structure is closed in a kind of mine coal column base plate breaking surrounding rock tunnel, comprise U-shaped steel bracket, wall rock grouting back-up coat, stabilizing surrounding rock layer, prestressing force band beam anchor cable and roadway floor supporting and protection structure, described U-shaped steel bracket as basic supporting along tunnel axial equidistant placement, prestressing force band beam anchor cable is arranged along tunnel circumference perpendicular to roadway surrounding rock surface between U-shaped steel bracket as strengthening supporting, single U-shaped steel bracket is connected into an entirety by one end of prestressing force band beam anchor cable, its other end is fixed in stabilizing surrounding rock layer, described roadway floor supporting and protection structure is by concrete, steel mesh reinforcement, channel-section steel, anchor pole and anchor cable composition, described prestressing force band beam anchor cable is by stabilizing surrounding rock layer, wall rock grouting back-up coat and U-shaped steel bracket couple together, and form closed integrated carrying supporting and protection structure with roadway floor supporting and protection structure.
The material of described U-shaped steel bracket is 36U shaped steel, and U-shaped steel bracket array pitch D is 500mm, and U-shaped steel bracket lap length L1 is 500 ~ 550mm, and card cable nut pre-fastening moment is 300 ~ 400Nm.
Described wall rock grouting back-up coat (2) thickness is 4000mm, and slip casting strengthening material is cement grout.
Described prestressing force band beam anchor cable and baseboard anchor cable are 1860 steel strand of Φ 17.8mm, resin the extensible bolting in stabilizing surrounding rock layer, anchor cable pretightning force 120 ~ 150kN.
The joist of described prestressing force with beam anchor cable adopts U-shaped steel to process, and length L2 is 1671mm; Base angle prestressing force with beam anchor cable is 200 ~ 300mm apart from roadway floor distance h.
Concrete thickness d in described roadway floor supporting and protection structure is 200mm, and intensity is C30.
Channel-section steel in described roadway floor supporting and protection structure adopts the processing of 18# channel-section steel.
Anchor pole in described roadway floor supporting and protection structure adopts the left-handed nothing of Φ 22 × 3000mm to indulge muscle twisted steel anchor rod, and yield strength is not less than 400MPa; Along vertical working axial direction, adopt channel-section steel that anchor pole, anchor cable are linked to be entirety.
The beneficial effects of the utility model: the weak part that tunnel can be eliminated, farthest play the supporting capacity of various support pattern, and reach collaborative integer support effect, avoid occurring simple combination, by the supporting effect of defeating in detail, thus ensure that homogeneous deformation and the long-term stability thereof of roadway surrounding rock.
Accompanying drawing explanation
Fig. 1 is the utility model structural representation.
Fig. 2 is A-A cross sectional side view in Fig. 1.
In figure: 1-U shape steel bracket, 2-wall rock grouting back-up coat, 3-stabilizing surrounding rock layer, 4-prestressing force band beam anchor cable, 5-concrete, 6-steel mesh reinforcement, 7-channel-section steel, 8-anchor pole, 9-anchor cable, 10-card cable, 11-joist, L1-support lap length, L2-joist length, h-base angle prestressing force band beam anchor cable distance roadway floor distance, d-concrete thickness, D-U shape steel bracket array pitch.
Detailed description of the invention
Below in conjunction with accompanying drawing, an embodiment of the present utility model is further described:
As shown in Figure 1 and Figure 2, integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel of the present utility model, comprises U-shaped steel bracket 1, wall rock grouting back-up coat 2, stabilizing surrounding rock layer 3, prestressing force band beam anchor cable 4 and roadway floor supporting and protection structure.Described U-shaped steel bracket 1 is as basic supporting along tunnel axis equidistant placement, and the material of U-shaped steel bracket 1 is 36U shaped steel, and U-shaped steel bracket 1 array pitch D is 500mm, and U-shaped steel bracket 1 lap length L1 is 500 ~ 550mm, and card cable 10 nut pre-fastening moment is 300 ~ 400Nm.Described wall rock grouting back-up coat 2 thickness is 4000mm, and slip casting strengthening material is cement grout.Described prestressing force band beam anchor cable 4 is arranged along tunnel circumference perpendicular to roadway surrounding rock surface between U-shaped steel bracket 1 as strengthening supporting, single U-shaped steel bracket 1 is connected into an entirety by one end of prestressing force band beam anchor cable 4, and its other end is fixed in stabilizing surrounding rock layer 3.Described roadway floor supporting and protection structure is made up of concrete 5, steel mesh reinforcement 6, channel-section steel 7, anchor pole 8 and anchor cable 9.Prestressing force band beam anchor cable 4 and baseboard anchor cable 9 are 1860 steel strand of Φ 17.8mm, resin the extensible bolting in stabilizing surrounding rock layer 3, anchor cable pretightning force 120 ~ 150kN; The joist 11 of prestressing force with beam anchor cable 4 adopts U-shaped steel to process, and length L2 is 1671mm; Base angle prestressing force with beam anchor cable 4 is 200 ~ 300mm apart from roadway floor distance h; Concrete 5 thickness d is 200mm, and intensity is C30; Channel-section steel 7 adopts 18# channel-section steel to process; Anchor pole 8 adopts the left-handed nothing of Φ 22 × 3000mm to indulge muscle twisted steel anchor rod, and yield strength is not less than 400MPa; Along vertical working axial direction, adopt channel-section steel 7 that anchor pole 8, anchor cable 9 are linked to be entirety.Stabilizing surrounding rock layer 3, wall rock grouting back-up coat 2 and U-shaped steel bracket 1 couple together by described prestressing force band beam anchor cable 4, and form closed integrated carrying supporting and protection structure with roadway floor supporting and protection structure.
Application process: after tunnel excavates, adopts U-shaped steel bracket 1 pair of roadway's sides and roof rock to carry out supporting in time; Lagging support work plane certain distance sprayed mortar mortar enclosing tunnel surface country rock; After, cranny development relatively stable until deformation of the surrounding rock in tunnel is abundant, carries out tunneling boring roadway surrounding rock grouting and reinforcing, form certain thickness wall rock grouting back-up coat 2; After grout cures, arrangement prestress band beam anchor cable 4 between U-shaped steel bracket 1; Finally, concrete+bolt-mesh-anchor support is carried out to roadway floor, thus form closed integrated carrying supporting and protection structure, and realize the supporting to tunnel.
Claims (8)
1. integrated carrying supporting and protection structure is closed in a mine coal column base plate breaking surrounding rock tunnel, comprise U-shaped steel bracket (1), wall rock grouting back-up coat (2), stabilizing surrounding rock layer (3), prestressing force band beam anchor cable (4) and roadway floor supporting and protection structure, it is characterized in that: described U-shaped steel bracket (1) as basic supporting along tunnel axial equidistant placement, prestressing force band beam anchor cable (4) is arranged along tunnel circumference perpendicular to roadway surrounding rock surface between U-shaped steel bracket (1) as strengthening supporting, single U-shaped steel bracket (1) is connected into an entirety by one end of prestressing force band beam anchor cable (4), its other end is fixed in stabilizing surrounding rock layer (3), described roadway floor supporting and protection structure is by concrete (5), steel mesh reinforcement (6), channel-section steel (7), anchor pole (8) and anchor cable (9) composition, described prestressing force band beam anchor cable (4) is by stabilizing surrounding rock layer (3), wall rock grouting back-up coat (2) and U-shaped steel bracket (1) couple together, and form closed integrated carrying supporting and protection structure with roadway floor supporting and protection structure.
2. integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel according to claim 1, it is characterized in that: the material of described U-shaped steel bracket (1) is 36U shaped steel, U-shaped steel bracket (1) array pitch D is 500mm, U-shaped steel bracket (1) lap length L1 is 500 ~ 550mm, and card cable (10) nut pre-fastening moment is 300 ~ 400Nm.
3. integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel according to claim 1, it is characterized in that: described wall rock grouting back-up coat (2) thickness is 4000mm, and slip casting strengthening material is cement grout.
4. integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel according to claim 1, it is characterized in that: 1860 steel strand that described prestressing force band beam anchor cable (4) and baseboard anchor cable (9) are Φ 17.8mm, resin the extensible bolting in stabilizing surrounding rock layer (3), anchor cable pretightning force 120 ~ 150kN.
5. integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel according to claim 1, it is characterized in that: the joist (11) of described prestressing force with beam anchor cable (4) adopts U-shaped steel to process, and length L2 is 1671mm; Base angle prestressing force with beam anchor cable (4) is 200 ~ 300mm apart from roadway floor distance h.
6. integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel according to claim 1, it is characterized in that: concrete (5) thickness d in described roadway floor supporting and protection structure is 200mm, and intensity is C30.
7. integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel according to claim 1, it is characterized in that: the channel-section steel (7) in described roadway floor supporting and protection structure adopts the processing of 18# channel-section steel.
8. integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel according to claim 1, it is characterized in that: the anchor pole (8) in described roadway floor supporting and protection structure adopts the left-handed nothing of Φ 22 × 3000mm to indulge muscle twisted steel anchor rod, and yield strength is not less than 400MPa; Along vertical working axial direction, adopt channel-section steel (7) that anchor pole (8), anchor cable (9) are linked to be entirety.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520103342.6U CN204457795U (en) | 2015-02-12 | 2015-02-12 | Integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520103342.6U CN204457795U (en) | 2015-02-12 | 2015-02-12 | Integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204457795U true CN204457795U (en) | 2015-07-08 |
Family
ID=53664697
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520103342.6U Expired - Fee Related CN204457795U (en) | 2015-02-12 | 2015-02-12 | Integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204457795U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104675412A (en) * | 2015-02-12 | 2015-06-03 | 湖南省煤炭地质勘查院 | Closed integral bearing supporting structure for coal-mine coal-pillar bottom plate crushed surrounding rock roadway |
CN105201526A (en) * | 2015-11-03 | 2015-12-30 | 陈冬冬 | Anchor cable and metal support uniting complementing support device and method |
CN114294016A (en) * | 2021-12-29 | 2022-04-08 | 国网北京市电力公司 | Reinforcing device for cable tunnel, manufacturing method and cable tunnel assembly |
-
2015
- 2015-02-12 CN CN201520103342.6U patent/CN204457795U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104675412A (en) * | 2015-02-12 | 2015-06-03 | 湖南省煤炭地质勘查院 | Closed integral bearing supporting structure for coal-mine coal-pillar bottom plate crushed surrounding rock roadway |
CN105201526A (en) * | 2015-11-03 | 2015-12-30 | 陈冬冬 | Anchor cable and metal support uniting complementing support device and method |
CN114294016A (en) * | 2021-12-29 | 2022-04-08 | 国网北京市电力公司 | Reinforcing device for cable tunnel, manufacturing method and cable tunnel assembly |
CN114294016B (en) * | 2021-12-29 | 2024-03-15 | 国网北京市电力公司 | Reinforcing device for cable tunnel, manufacturing method and cable tunnel assembly |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104675412A (en) | Closed integral bearing supporting structure for coal-mine coal-pillar bottom plate crushed surrounding rock roadway | |
CN100577986C (en) | Goaf surrounding rock around gob-side supporting method under three soft geological condition | |
CN104533482B (en) | A kind of reinforcement means improving gob side entry driving fender stability | |
CN104763434B (en) | A kind of without coal column double lanes driving method | |
CN103628911B (en) | Work plane segmented gob-side entry retaining method is adopted/put to a kind of combining | |
CN103603675A (en) | Supporting method of permeable soft broken rock stratum roadway | |
CN102322273A (en) | A kind of roadway floor anchor is annotated integrated reinforcement means | |
CN104594926A (en) | Rapid composite roof roadway support method for high-stress water guiding karst cave group | |
CN102230382A (en) | Progressive shielding booster-type grouting and reinforcing technology for baseboard | |
CN205297580U (en) | Soft rock bate distension control structure | |
CN101235719A (en) | Prevacuated decompressed soft rock laneway support technology | |
CN103306713A (en) | Networking reinforcement method for cross drilling holes of outburst coal seam | |
CN101509383A (en) | Tunnel footing anchor pouring reinforcement anti bottom expanding method and construction technique | |
CN108930543A (en) | A kind of big cross section gob side entry driving coupling supporting structure and construction method | |
CN204457795U (en) | Integrated carrying supporting and protection structure is closed in mine coal column base plate breaking surrounding rock tunnel | |
CN104533483A (en) | Roadway total-space prestress truss, anchor cable and anchor rod coordinated supporting method | |
CN105019924A (en) | Strong roof support pier column and method for protecting section coal pillar | |
CN106014443B (en) | A kind of method of the Floor Heave in Roadway for preventing gob side entry retaining and wall sliding | |
CN104863588A (en) | Advanced pier column pre-arranging gob-side entry retaining method | |
CN105089693A (en) | Goaf-side-roadway-retaining wall roof-contact improving method | |
CN101082281A (en) | Method for controlling deformation of surrounding rocks of gallery influenced by overhead mining | |
CN103573280B (en) | Method for supporting porous ooze invasion compound roof roadway | |
CN204591306U (en) | A kind of combined steel pipe concrete bow member for supporting | |
CN105649673A (en) | Roadside gangue mixture filling and gob-side entry retaining method for large-dip angle coal seams | |
CN105350993B (en) | A kind of roadway full-fracture-surfacanchoring-rod anchor cable beam spray Combined Support Technology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150708 Termination date: 20170212 |