CN204456862U - The fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor - Google Patents

The fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor Download PDF

Info

Publication number
CN204456862U
CN204456862U CN201520112954.1U CN201520112954U CN204456862U CN 204456862 U CN204456862 U CN 204456862U CN 201520112954 U CN201520112954 U CN 201520112954U CN 204456862 U CN204456862 U CN 204456862U
Authority
CN
China
Prior art keywords
vertical
embedded pipe
pipe
cast
guard member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520112954.1U
Other languages
Chinese (zh)
Inventor
王敬媛
张迅
吴余
胡劲岩
杨长征
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Fourth Construction & Engineering Co Ltd
Original Assignee
Beijing Fourth Construction & Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Fourth Construction & Engineering Co Ltd filed Critical Beijing Fourth Construction & Engineering Co Ltd
Priority to CN201520112954.1U priority Critical patent/CN204456862U/en
Application granted granted Critical
Publication of CN204456862U publication Critical patent/CN204456862U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model relates to the fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor; it is the half-set be welded by cross bar and vertical rod vertical symmetry; vertical rod is parallel to vertical duct and integral with vertical duct colligation, and cross bar is vertical with horizontal tube and colligation is fixed on the end muscle of structural slab in both sides.The utility model structure is simple, easy to make, and construction leftover pieces can be adopted to facilitate welding production, economic and practical; Can be applicable in the mouth of pipe protection of pre-embedded pipe when the protection of the vertical part of pre-embedded pipe in fixing, concreting process when spool lays, form removable and material are had bad luck; effectively can strengthen the stability of pre-embedded pipe; avoid being shifted; ensure the verticality of pre-embedded pipe vertical duct; and when operation is had bad luck in form removable and material; the vertical duct that concrete slab is stretched out in protection makes it avoid being damaged, and effectively avoids the secondary caused because exposing pre-embedded pipe to damage to pick cutter, repairing situation occurs.

Description

The fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor
Technical field
The utility model relates to the construction field of pre-embedded pipe in cast-in-situ floor, particularly the fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor.
Background technology
At present, the construction of pre-embedded pipe mainly faces following problem:
(1) in cast-in-place concrete structure main body construction process, there is a large amount of spool burying work beforehands, due to the vertical duct that there is horizontal tube and be bent to form by the end of horizontal segment spool, work progress needs fixing separately, and process is more loaded down with trivial details; In the reinforcing bar binding stage, carpenter, bar bender, water power work and other relate to the work post of set aside pre-embedded work, construct in the scope of operation simultaneously, the stacking of material in the scope of operation in addition, the spool laid is very easily damaged;
(2) when concrete pouring construction operation, because pre-embedded pipe vertical duct is because lacking fixation, in the process of vibrating, this position spool displacement is easily caused;
(3) when returning spool under in concrete slab, because needs are through template, under there is no safeguard measure situation, in dismounting structure backplanes support template procedure, easily cause the damage of this position vertical duct, section is drawn long if vertical, the words that verticality is inadequate, form removable work can be affected simultaneously, cause damaged template, reduce operating efficiency, and at vertical structure body of wall, pillar shuttering, in stripping construction operation process, especially during large-scale integral steel template construction, tower crane is utilized uprightly to transport, template base is nearer apart from ground, also the damage returning the vertical section of extraction of spool in structural slab is very easily caused,
(4) in secondary building construction process, because on-the-spot lot of materials needs to have bad luck, also the damage returning the vertical section of extraction of spool in structural slab can be caused in various degree, if this is vertically drawn section short tube and damages, when there is damage to the terminal, bending situation, need treat that civil engineering structure has been checked and accepted, and after reaching criterion of acceptability, before starting the operation of secondary masonry construction, cutter is picked to structural slab, expose intralamellar part cable manifiold, adjunction head reconnects, and therefore causes extra recruitment, reduces work efficiency, if pick cutter position shutoff not reach requirement, structural slab intensity and compactness can be affected; And board memory is at joint, add unnecessary hidden danger.
Therefore; current needs are a kind of can the structure of available protecting and fixing pre-embedded pipe, can be applied in the mouth of pipe protection of pre-embedded pipe when the protection of the vertical part of pre-embedded pipe in fixing, concreting process when spool lays and form removable and material are had bad luck simultaneously.
Utility model content
The purpose of this utility model is to provide the fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor, solves the mouth of pipe protection problem of pre-embedded pipe when the protection problem of the vertical part of pre-embedded pipe in fixation problem when spool lays in prior art, concreting process and form removable and material are had bad luck.
For solving the problems of the technologies described above, the utility model takes following technical scheme:
The fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor; described pre-embedded pipe comprises the horizontal tube be layered on template and the vertical duct be bent to form by the end of horizontal segment spool; described fixture is fixedly connected with pre-embedded pipe; it is characterized in that: described fixture is the half-set be welded by cross bar and vertical rod vertical symmetry; described vertical rod is parallel to vertical duct and integral with vertical duct colligation, and described cross bar is vertical with horizontal tube and colligation is fixed on the end muscle of structural slab in both sides.
Wherein, described vertical duct is the vertical extraction section that the end of horizontal tube is upwards bent to form, and described half-set is that cross bar is arranged at upper inverted T-shaped.Described vertical duct also can be that the end of horizontal tube bends downwards and the vertical extraction section formed after passing template, described half-set be cross bar under T-shaped arrange, vertical rod is fixed through template and vertical duct colligation.
Preferably, described vertical rod is than vertical pipe range 20 ~ 40mm.
Further, described half-set is the support be made with reinforcing bar, angle steel or steel pipe leftover pieces.
Further, the length of described cross bar is 250 ~ 400mm, and the length of vertical rod is 150 ~ 400mm.
Further, described pre-embedded pipe is coating steel pipe, SC welded steel pipe, JDG/KBG thin-walled coating steel pipe or PVC material pipe.
Compared with prior art, technical advantage of the present utility model is:
1, when during this device can be applied to when spool lays fixing, concreting process simultaneously, the protection of the vertical part of pre-embedded pipe and form removable and material are had bad luck pre-embedded pipe mouth of pipe protection in, the stability of the pre-buried vertical part of spool in cast-in-situ concrete can be strengthened, ensure its verticality, concrete slab place short tube can be gone out to it again and play a very good protection;
2, structure is simple, and work progress is convenient and practical, spool can be avoided to damage the later stage of causing and pick the extra work generations such as cutter, adapter, therefore can save artificial generally, improve efficiency of construction, reduce costs.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 be the utility model embodiment 1 vertical duct 51 upwards time the using state schematic diagram of fixing guard member;
Fig. 3 be the utility model embodiment 2 vertical duct 51 downwards time the using state schematic diagram of fixing guard member.
Reference numeral: at the bottom of 1-cast-in-situ floor, 2-T font support, 21-cross bar, 22-vertical rod, 3-, muscle, 4-tie up silk, 5-pre-embedded pipe, 51-horizontal tube, 52-vertical duct, 6-template.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
As Fig. 1; the utility model relates to the fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor; described pre-embedded pipe 5 comprises the horizontal tube 51 be layered on template and the vertical duct 52 be bent to form by the end of horizontal segment spool; described fixture is fixedly connected with pre-embedded pipe 5; it is characterized in that: described fixture is the half-set 2 be welded by cross bar 21 and vertical rod 22 vertical symmetry; described vertical rod 22 is parallel to vertical duct 52 and integral with vertical duct 52 colligation, and described cross bar 21 is vertical with horizontal tube 51 and colligation is fixed on the end muscle 3 of structural slab in both sides.
Wherein, as Fig. 2, described vertical duct 52 is can the vertical extraction section that is upwards bent to form of the end of horizontal tube 51, and described half-set 2 is that cross bar 21 is arranged at upper inverted T-shaped.Fig. 2 be the utility model embodiment 1 vertical duct upwards time the using state schematic diagram of fixing guard member; Pre-embedded pipe 5 vertically upwards routs up floor, and the vertical rod 22 of described half-set 2 and the vertical part colligation of pre-embedded pipe 5, direction is perpendicular to plate face.The horizontal tube 51 of described half-set 2 cross bar and pre-embedded pipe 5 is arranged vertically, and cross bar is placed in the top of muscle 3 at the bottom of lower floor, firm with tying up silk 4 colligation with end muscle 3, makes vertical duct 52 as a whole with described half-set 2 one-tenth.
As Fig. 3, described vertical duct 52 also can be that the end of horizontal tube 51 bends downwards and passes the vertical extraction section formed after template 6, described half-set 2 be cross bar 21 under T-shaped arrange, vertical rod 22 is fixed through template 6 and vertical duct 52 colligation.Described vertical rod 22 20 ~ 40mm longer than vertical duct 52.Fig. 3 be the utility model embodiment 2 vertical duct downward time the using state schematic diagram of fixing guard member; return out template 6 under pre-embedded pipe 5 vertical portion is divided into, the vertical part of described pre-embedded pipe 5 and the vertical rod colligation of described half-set 2 firmly pass template downwards.Half-set 2 and pre-embedded pipe 5 wear template 6, and time should punch according to the reinforcing bar size of the caliber of pre-embedded pipe 5 and half-set 2, to avoid impacting concreting work.
Described half-set 2 can use reinforcing bar, angle steel or steel pipe leftover pieces to make, and the length of cross bar 21 is 250 ~ 400mm, and the length of vertical rod 22 is 150 ~ 400mm.Described pre-embedded pipe 5 can be coating steel pipe, SC welded steel pipe, JDG/KBG thin-walled coating steel pipe or PVC material pipe.Half-set 2 described in embodiment is made by 12 reinforcing bar leftover pieces in structure construction, in practice of construction, can according to field condition and concrete needs, select reinforcing bar size, the cross bar of half-set 2 described in embodiment length is 300mm, in practice of construction, can be according to specific needs, bracket cross bar length is adjusted, vertical rod length is 400mm/150mm, in practice of construction, and can be according to specific needs, bracket vertical rod length is adjusted, but vertical pole need be longer than the spool vertically section of extraction 20 ~ 40mm.
The mouth of pipe shutoff of spool exit, construction method shutoff routinely, is not included within the utility model research range.
The above; it is only preferred embodiment of the present utility model; not the utility model is imposed any restrictions; every above embodiment is done according to the utility model technical spirit any simple modification, change and equivalent structure change, all still belong in the protection domain of technical solutions of the utility model.

Claims (7)

1. the fixing guard member of pre-embedded pipe in a cast-in-situ floor, described pre-embedded pipe (5) comprises the horizontal tube (51) be layered on template and the vertical duct (52) be bent to form by the end of horizontal segment spool, described fixture is fixedly connected with pre-embedded pipe (5), it is characterized in that: described fixture is the half-set (2) be welded by cross bar (21) and vertical rod (22) vertical symmetry, described vertical rod (22) is parallel to vertical duct (52), and it is integral with vertical duct (52) colligation, described cross bar (21) is vertical with horizontal tube (51), and colligation is fixed on the end muscle (3) of structural slab in both sides.
2. the fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor according to claim 1; it is characterized in that: the vertical extraction section that the end that described vertical duct (52) is horizontal tube (51) is upwards bent to form, described half-set (2) is arranged at upper inverted T-shaped for cross bar (21).
3. the fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor according to claim 1; it is characterized in that: described vertical duct (52) is that the end of horizontal tube (51) bends downwards and passes the vertical extraction section that template (6) formed afterwards; described half-set (2) for cross bar (21) under T-shaped arrange, vertical rod (22) is fixed through template (6) and vertical duct (52) colligation.
4. the fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor according to claim 1, is characterized in that: described vertical rod (21) 20 ~ 40mm longer than vertical duct (52).
5. the fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor according to claim 1, is characterized in that: described half-set (2) is the support be made with reinforcing bar, angle steel or steel pipe leftover pieces.
6. pre-embedded pipe fixture in a kind of cast-in-situ floor according to claim 1, is characterized in that: the length of described cross bar (21) is 250 ~ 400mm, and the length of vertical rod (22) is 150 ~ 400mm.
7. the fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor according to claim 1, is characterized in that: described pre-embedded pipe (5) is coating steel pipe, SC welded steel pipe, JDG/KBG thin-walled coating steel pipe or PVC material pipe.
CN201520112954.1U 2015-02-16 2015-02-16 The fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor Expired - Fee Related CN204456862U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520112954.1U CN204456862U (en) 2015-02-16 2015-02-16 The fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520112954.1U CN204456862U (en) 2015-02-16 2015-02-16 The fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor

Publications (1)

Publication Number Publication Date
CN204456862U true CN204456862U (en) 2015-07-08

Family

ID=53663769

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520112954.1U Expired - Fee Related CN204456862U (en) 2015-02-16 2015-02-16 The fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor

Country Status (1)

Country Link
CN (1) CN204456862U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797871A (en) * 2018-06-22 2018-11-13 中国二冶集团有限公司 The protective cradle of pre-embedded pipe
CN109914800A (en) * 2019-03-15 2019-06-21 中国五冶集团有限公司 A kind of civil buildings townhouse wire box accurately pre-installs structure and construction method
CN113482374A (en) * 2021-06-16 2021-10-08 五冶集团上海有限公司 Construction method for protecting PVC pipe head by using waste steel bars

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797871A (en) * 2018-06-22 2018-11-13 中国二冶集团有限公司 The protective cradle of pre-embedded pipe
CN109914800A (en) * 2019-03-15 2019-06-21 中国五冶集团有限公司 A kind of civil buildings townhouse wire box accurately pre-installs structure and construction method
CN109914800B (en) * 2019-03-15 2021-02-26 中国五冶集团有限公司 Accurate pre-installation structure and construction method for civil building line-connecting and line-arranging pipes
CN113482374A (en) * 2021-06-16 2021-10-08 五冶集团上海有限公司 Construction method for protecting PVC pipe head by using waste steel bars

Similar Documents

Publication Publication Date Title
CN204299185U (en) Build pipeline reinforcing steel bar buffering structure
CN204456862U (en) The fixing guard member of pre-embedded pipe in a kind of cast-in-situ floor
CN210658968U (en) Auxiliary fixing framework of frame column node core stirrup cage
CN102589973B (en) Pullout test auxiliary device for hook anchor rod and test method
CN103758348A (en) Profile steel framework structure concrete floor slab suspension mould pouring construction method
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN204982673U (en) Continuous steel of high mound of hollow thin wall structure 0# section binds and pre -compaction support in 100 -meter dash
CN204626453U (en) The supporting device of pipeline in Urban Underground pipe gallery
CN203097253U (en) Elevator shaft triangular support type formwork platform
CN103967332A (en) Construction method of building site barrier
CN204080793U (en) Hoisting device for reinforcement cage
CN215760524U (en) Main structure floor thickness control block
CN202031309U (en) Suspending operation platform for structural concrete constructions
CN201809974U (en) Glass steel cylindrical formwork device
CN101514551B (en) Artificial excavating pile reinforcing cage vertical colligation and installation method
CN106193578B (en) It is a kind of that modular system and construction technology are matched somebody with somebody based on groove type quarter bend
CN112227814B (en) Method for dismantling straight-barrel type concrete tower body
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
CN104153374A (en) Combined foundation pit supporting structure with inclined strut and pull anchor
CN209670395U (en) A kind of ruggedized construction suitable for building hoist basement roof
CN202273345U (en) Positioning and anti-floating device for BDF thin-walled cement hollow pipes
CN203145017U (en) Large-sized chute device for pouring mass concrete into deep foundation pit
CN219951909U (en) Pile foundation steel reinforcement cage positioner
CN206233117U (en) A kind of continuous beam catenary mast construction formwork auxiliary implement
CN203531249U (en) Control device of reinforcement cover of reinforcement concrete column

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150708