CN204436418U - Lid digs top board structure that is prefabricated in subway station and cast-in-place combination - Google Patents

Lid digs top board structure that is prefabricated in subway station and cast-in-place combination Download PDF

Info

Publication number
CN204436418U
CN204436418U CN201520113094.3U CN201520113094U CN204436418U CN 204436418 U CN204436418 U CN 204436418U CN 201520113094 U CN201520113094 U CN 201520113094U CN 204436418 U CN204436418 U CN 204436418U
Authority
CN
China
Prior art keywords
prefabricated
superimposed sheet
top board
cast
prefabricated superimposed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520113094.3U
Other languages
Chinese (zh)
Inventor
王国富
路林海
曹正龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Rail Transit Group Co Ltd
Original Assignee
Jinan Rail Transit Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Rail Transit Group Co Ltd filed Critical Jinan Rail Transit Group Co Ltd
Priority to CN201520113094.3U priority Critical patent/CN204436418U/en
Application granted granted Critical
Publication of CN204436418U publication Critical patent/CN204436418U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a kind of lid and dig top board structure that is prefabricated in subway station and cast-in-place combination, comprise horizontal shore, the left and right sides of described horizontal shore is equipped with the collar tie beam that bears down on one, and described horizontal shore is added is provided with prefabricated superimposed sheet, and described prefabricated superimposed sheet is provided with casting top slab.Described prefabricated superimposed sheet bears down on one between collar tie beam two.Described horizontal shore, prefabricated superimposed sheet and the height that casting top slab combines with bear down on one that to enclose depth of beam identical.Top board of the present utility model adopts prefabricated superimposed sheet to do template, and without the need to removing, save formwork striking time, saved mould material, prefabricated superimposed sheet becomes a part for structure roof, increases the globality of station top board.

Description

Lid digs top board structure that is prefabricated in subway station and cast-in-place combination
Technical field
The utility model relates to a kind of lid and digs in subway station the station top board structure utilizing prefabricated units to do template to build.
Background technology
At present, bustling Metro Excavation station, location, city is that after adopting cap excavation method to be faced down be excavated to the top board degree of depth by ground, by top seal, recover temporary road, remaining bottom engineering is constructed under the top cover closed; But existing lid digs station top board and all adopts cast-in-place structural, formwork form removal required time is longer, and construction is complicated, and have a strong impact on the backfill time, long-term blocked road has increased the weight of traffic jam issue.
Chinese patent CN 102926403 A discloses a kind of top board of digging method construction, and its top board adopts first matting layer then formwork supporting plate cast-in-place concrete structure, and need stripping and bed course after concrete curing completes, the required duration is oversize.
Utility model content
The purpose of this utility model is for overcoming above-mentioned the deficiencies in the prior art, and provide a kind of prefabricated units that utilize to do the cast-in-place station top board structure of template, top board adopts prefabricated superimposed sheet to do template, without the need to removing, saving formwork striking time, having saved mould material; Prefabricated superimposed sheet becomes a part for structure roof, and the double secondary beam doing top board bears upper load.
For achieving the above object, the utility model adopts following technical proposals:
A kind of lid digs top board structure that is prefabricated in subway station and cast-in-place combination, comprise horizontal shore, the left and right sides of described horizontal shore is equipped with the collar tie beam that bears down on one, and described horizontal shore is added is provided with prefabricated superimposed sheet, and described prefabricated superimposed sheet is provided with casting top slab.
Described prefabricated superimposed sheet bears down on one between collar tie beam two.
Described horizontal shore, prefabricated superimposed sheet and the height that casting top slab combines with bear down on one that to enclose depth of beam identical.
The vertical sectional shape of described prefabricated superimposed sheet is that multiple convex shape connects to form.
Longitudinally reinforcing bar is provided with in described prefabricated superimposed sheet.
The high spot reserved joint bar of described prefabricated superimposed sheet, described reserved joint bar top is provided with crotch, can hold the main muscle in the cast-in-place structural of top, together with the reinforcing bar binding in the cast-in-place structural of top, increases the fastness of cast-in-place structural and prefabricated superimposed sheet.
The beneficial effects of the utility model are:
Bear down on one in the utility model collar tie beam and top board beam is built simultaneously, and stability is better, and genus is rigidly connected, and the pressure of the top backfill soil body passes to stake by top board, can add the anti-floating ability at station.
Top board of the present utility model adopts prefabricated superimposed sheet to do template, without the need to removing, saves formwork striking time, greatly reduces the off-period of top road.Save mould material, prefabricated superimposed sheet becomes a part for structure roof simultaneously, and the double secondary beam doing top board bears upper load, increases the globality of station top board.
Accompanying drawing explanation
Fig. 1 is that the utility model lid digs top board structure schematic diagram that is prefabricated in subway station and cast-in-place combination;
Fig. 2 is that the utility model lid digs top board structure top view that is prefabricated in subway station and cast-in-place combination;
Fig. 3 is that the utility model top board structure is covering the application schematic diagram dug in subway station;
Fig. 4 is the sectional view of the prefabricated superimposed sheet of the utility model top board structure;
Fig. 5 is the top view of the prefabricated superimposed sheet of the utility model top board structure;
In figure, 1 is fender post; 3 is stand column pile; 4 is prefabricated superimposed sheet; 5 is reinforcing bar; 6 is reserved joint bar; 7 is casting top slab; 8 is horizontal shore; 9 is water-stop curtain; 10 is the collar tie beam that bears down on one, and 11 is backfill.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is further illustrated.
As Figure 1-Figure 2, lid digs top board structure that is prefabricated in subway station and cast-in-place combination, comprise horizontal shore 8, the left and right sides of horizontal shore 8 is equipped with the collar tie beam 10 that bears down on one, on horizontal shore 8, two erections of bearing down on one between collar tie beam 10 have prefabricated superimposed sheet 4, and prefabricated superimposed sheet 4 is provided with casting top slab 7.Horizontal shore 8, prefabricated superimposed sheet 4 are identical with the height of the collar tie beam 10 that bears down on one with the height that casting top slab 7 combines.
As shown in Figure 3, utilize the utility model top board structure lid to dig the application of subway station, comprise the following steps:
Step 1. utilizes pile press that prefabricated fender post 1, stand column pile 3 are pressed into the position designed on construction ground;
A) combine near vehicle flowrate rule, at night closure construction section road between 9 to morning 7 next day, and carry out road Warning Mark;
B) utilize pile press that prefabricated fender post 1 is pressed into design attitude, injected hole grouting and reinforcing stake end stratum in the middle of utilizing;
C) outside fender post 1, set a circle cement mixing method as water-stop curtain 9, coordinate dewatering measure to ensure that foundation pit dewatering does not cause the problems such as the sedimentation of surrounding building with measure of recharging;
D) utilize pile press that prefabricated stand column stake 3 is pressed into design attitude.
Step 2. excavation pit, builds the collar tie beam 10 that bears down on one, horizontal support 8, lays prefabricated superimposed sheet 4, pouring structure top board 7;
A) full-time blocked road, carries out enclosing and road Warning Mark;
B) little slope excavation pit to fender post of putting exposes position, stake top;
C) excavation pit side shotcrete with steel bar nets, prevents side slope slump, optionally adopts plate brad supporting;
D) bear down on one in the colligation of fender post top the reinforcing bar of collar tie beam 10, and the reinforcing bar of colligation horizontal shore 8, horizontal shore 8 frame stands in the tip position of stand column pile 3;
E) install bear down on one collar tie beam 10 and horizontal shore 8 template, build bear down on one collar tie beam 10 and horizontal shore 8;
F) on horizontal shore 8, lay prefabricated superimposed sheet 4, the two end supports of plate is double on horizontal shore 8 does top board secondary beam, the double girder doing top board of horizontal shore 8;
G) colligation roof steel bar on prefabricated superimposed sheet 4, the reserved joint bar 6 of roof steel bar and prefabricated superimposed sheet links together, and then builds top board 7, reserves soil outlet and charging aperture in both sides, road;
H) curing concrete is to design strength, laying water-proof coiled material.
Step 3. backfills the top earthwork, road traffic directly over recovery;
A) carry out the protection of soil outlet and charging aperture, backfill tabia above top board and compacting;
B) construction subgrade, laying road, resumes traffic.
As shown in fig. 4-5, the vertical sectional shape of prefabricated superimposed sheet 4 is that multiple convex shape connects to form.With convex shape plate base plate for plane, the length direction of convex shape plate bossing is longitudinally, is longitudinally provided with reinforcing bar 5 in prefabricated superimposed sheet 4.The high spot reserved joint bar 6 of prefabricated superimposed sheet 4.
By reference to the accompanying drawings detailed description of the invention of the present utility model is described although above-mentioned; but the restriction not to the utility model protection domain; one of ordinary skill in the art should be understood that; on the basis of the technical solution of the utility model, those skilled in the art do not need to pay various amendment or distortion that creative work can make still within protection domain of the present utility model.

Claims (6)

1. a lid digs top board structure that is prefabricated in subway station and cast-in-place combination, it is characterized in that, comprise horizontal shore, the left and right sides of described horizontal shore is equipped with the collar tie beam that bears down on one, described horizontal shore is added is provided with prefabricated superimposed sheet, and described prefabricated superimposed sheet is provided with casting top slab.
2. lid as claimed in claim 1 digs top board structure that is prefabricated in subway station and cast-in-place combination, and it is characterized in that, described prefabricated superimposed sheet is bearing down on one between collar tie beam.
3. lid as claimed in claim 1 digs top board structure that is prefabricated in subway station and cast-in-place combination, it is characterized in that, described horizontal shore, prefabricated superimposed sheet and the height that casting top slab combines with bear down on one that to enclose depth of beam identical.
4. lid as claimed in claim 1 digs top board structure that is prefabricated in subway station and cast-in-place combination, and it is characterized in that, the vertical sectional shape of described prefabricated superimposed sheet is that multiple convex shape connects to form.
5. lid as claimed in claim 1 digs top board structure that is prefabricated in subway station and cast-in-place combination, it is characterized in that, the high spot reserved joint bar of described prefabricated superimposed sheet.
6. lid as claimed in claim 5 digs top board structure that is prefabricated in subway station and cast-in-place combination, and it is characterized in that, described reserved joint bar top is provided with crotch.
CN201520113094.3U 2015-02-16 2015-02-16 Lid digs top board structure that is prefabricated in subway station and cast-in-place combination Active CN204436418U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520113094.3U CN204436418U (en) 2015-02-16 2015-02-16 Lid digs top board structure that is prefabricated in subway station and cast-in-place combination

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520113094.3U CN204436418U (en) 2015-02-16 2015-02-16 Lid digs top board structure that is prefabricated in subway station and cast-in-place combination

Publications (1)

Publication Number Publication Date
CN204436418U true CN204436418U (en) 2015-07-01

Family

ID=53604296

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520113094.3U Active CN204436418U (en) 2015-02-16 2015-02-16 Lid digs top board structure that is prefabricated in subway station and cast-in-place combination

Country Status (1)

Country Link
CN (1) CN204436418U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482147A (en) * 2021-06-28 2021-10-08 五冶集团上海有限公司 Construction method of '0' -layer frame structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482147A (en) * 2021-06-28 2021-10-08 五冶集团上海有限公司 Construction method of '0' -layer frame structure

Similar Documents

Publication Publication Date Title
CN105041349B (en) A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel
CN101914925B (en) Basement by using optimized composite prefabricated arch wall as external wall
CN104674846B (en) A kind of construction method utilizing precast construction lid to dig subway station
CN105064397B (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN105003272B (en) Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways
CN206800412U (en) The foundation pit enclosure structure that a kind of steel-pipe pile is combined with Larsen steel sheet pile fore shaft
CN108868778A (en) A kind of Large Underground Structure no-dig technique construction method
CN101418569B (en) Optimization complex arch wall combining prefabricated arch leaf, support and major structure
CN104452809A (en) Ultra-shallow buried tunnel cover-excavation construction method
CN105201516B (en) A kind of main structure of subway station and its tetrad arch PBA excavating construction methods
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN105178327A (en) Composite retaining structure of foundation pit project and construction method thereof
CN205875209U (en) Temporary road surface system supports with concrete and closes subway station half range bedding structure of establishing
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN202247575U (en) Structure for strengthening roadbed in high-speed railway station turnout area with highly developed karst
CN204959762U (en) Barricade formula portal crane track girder construction
CN206752667U (en) A kind of basement barrier wall structure
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN204940298U (en) A kind of Composite Enclosure Structure of base pit engineering
CN108487234B (en) Construction method of cast-in-situ pile plate type platform wall
CN204753261U (en) Light -duty road bed of a doublestage shelves structure
CN108374663B (en) Twice-molding construction method for sandy gravel geological tunnel
CN203113335U (en) Counterfort type U-type groove retaining structure
CN204436418U (en) Lid digs top board structure that is prefabricated in subway station and cast-in-place combination
CN205036388U (en) Block of four encircles knot hunch construction structures that PBA secretly dug subway station

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant