CN204370796U - Hoistway formwork platform - Google Patents

Hoistway formwork platform Download PDF

Info

Publication number
CN204370796U
CN204370796U CN201420862518.1U CN201420862518U CN204370796U CN 204370796 U CN204370796 U CN 204370796U CN 201420862518 U CN201420862518 U CN 201420862518U CN 204370796 U CN204370796 U CN 204370796U
Authority
CN
China
Prior art keywords
platform
self
operating desk
return ratchet
iron
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420862518.1U
Other languages
Chinese (zh)
Inventor
张剑
陈韶临
刘超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Broad Homes Industrial Group Co Ltd
Original Assignee
Changsha Broad Homes Industrial Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha Broad Homes Industrial Group Co Ltd filed Critical Changsha Broad Homes Industrial Group Co Ltd
Priority to CN201420862518.1U priority Critical patent/CN204370796U/en
Application granted granted Critical
Publication of CN204370796U publication Critical patent/CN204370796U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Types And Forms Of Lifts (AREA)

Abstract

A kind of hoistway formwork platform, comprise the upper mounting plate and lower platform that are connected by square tube, described upper mounting plate is connected and composed by upper operating desk, extensible canopy and self-return ratchet, and described lower platform is connected and composed by lower operating desk and bottom girder, and pre-buried cover fixed by elevator shaft cast-in-place shear wall interior wall.After elevator shaft first floor pouring concrete completes, four ratchets that automatically reset of template platform drop in pre-buried cover, during the firm overlap joint pouring concrete second layer, sling on template platform with tower crane, entirety is up carried, automatic aftertaste ratchet adduction, when reaching the pre-buried cover of the second layer, self-return ratchet its one end under the effect of balancing weight is dropped in pre-buried cover, make template platform firmly be overlapped on the second layer, at this moment workman is to lower operating desk, four pre-buried covers of first floor of dismantling, then pour into a mould third layer, construct so successively.The utility model cost of manufacture is low, simple to operate, material resources that time and manpower is saved, improves building operations efficiency, good reliability.

Description

Hoistway formwork platform
Technical field
The utility model belongs to construction engineering technical field, is specifically related to a kind of hoistway formwork platform.
Background technology
In building operations, elevator shaft class bobbin type cast-in-place shear wall template construction does not have pin point in bobbin inside, in work progress, traditional way scaffolds erecting in bobbin, and often cast one deck all will build easy template platform, steel pipe, fastener, plank etc. is more commonly adopted to overlap, consumptive material is many, builds cost high, time-consuming, affect building operations efficiency, and there is very large potential safety hazard in easy template platform.
Summary of the invention
Technical problem to be solved in the utility model is: solve above-mentioned prior art Problems existing, and a kind of hoistway formwork platform is provided, cost of manufacture is low, constructing operation is simply easy, and a template platform can complete the construction of whole high-rise bobbin type cast-in-place shear wall, but also can reuse, activity duration and manpower and materials are greatly saved, improve building operations efficiency, safety factor is high, good reliability.
The technical solution adopted in the utility model is:
A kind of hoistway formwork platform, comprise upper mounting plate and lower platform, upper mounting plate is connected by square tube with lower platform, described upper mounting plate is connected and composed by upper operating desk, extensible canopy and self-return ratchet, extensible canopy is arranged on below operating desk, self-return ratchet is arranged on extensible canopy end, and described lower platform is connected and composed by lower operating desk and bottom girder; Corresponding with self-return ratchet, on elevator shaft inner formword He on elevator shaft cast-in-place shear wall interior wall, fix pre-buried cover.
In technique scheme, described self-return ratchet comprises riser and is arranged on balancing weight and the roller at riser two ends respectively, is connected in the middle part of riser by Assembly of pin with the extensible canopy end of template platform.
In technique scheme, described self-return ratchet is four, lays respectively at two jiaos of the two ends of template platform.
In technique scheme, described balancing weight is provided with screwed hole, and adjusting bolt is arranged in the screwed hole of balancing weight; Described riser is provided with sole bottom roller one end; Described riser is made up of two block plates, is connected with stiffener between two block plates.
In technique scheme, described extensible canopy comprises clamped beam and regulates beam, described clamped beam is welded by channel-section steel and i iron, described adjustment beam is formed by connecting with Plate Welding between interval, two channel-section steels back-to-back by two channel-section steels, the i iron of clamped beam one end is sleeved between two channel-section steels of adjustment beam, lower lock block one is welded on and regulates bottom beam, upper holder block one is locked at bolt assembly and regulates back portion, upper holder block dual-purpose bolt assembly is locked at the i iron top of clamped beam, and lower lock block dual-purpose bolt assembly is locked at bottom the i iron of clamped beam; The i iron of described clamped beam is welded with deep floor.
Hoistway formwork Platform Designing of the present utility model is ingenious, structure is simple, cost of manufacture is low, easily easy for operation, and a template platform just can complete the construction of whole high rise elevator well class bobbin type cast-in-place shear wall, and can reuse, all to set up foot rest temporarily relative to traditional construction technique every layer, lay interim operating desk, greatly save manpower and materials, improve efficiency of construction, and reliable operation, safety factor is high.
Accompanying drawing explanation
Fig. 1 is the utility model schematic diagram;
Fig. 2 is that template platform promotes working state figure;
Fig. 3 is template platform overlap joint schematic diagram;
Fig. 4 is self-return ratchet and extensible canopy schematic perspective view;
Fig. 5 is the utility model upper mounting plate schematic perspective view.
Accompanying drawing mark illustrates:
The upper operating desk of 1-, 2-self-return ratchet, 3-connecting square pipes, operating desk under 4-, 5-bottom girder, 6-extensible canopy, 7-bobbin inner formword, the pre-buried cover of 8-, 9-suspension ring, 10-plank, 11-wooden H-beam, 12-elevator shaft cast-in-place shear wall body, 13-roller, 14-lifting rope, 15-balancing weight, 16-adjusting bolt, 17-clamped beam, 18-regulates beam, 19-upper holder block one, 20-lower lock block one, 21-upper holder block two, 22-presses down fast two, 23-channel-section steels, 24-i iron, 25-steel plate.
Detailed description of the invention
See accompanying drawing, hoistway formwork platform of the present utility model, comprise upper mounting plate and lower platform, upper mounting plate is connected by square tube with lower platform, and described upper mounting plate is connected and composed by upper operating desk, extensible canopy and self-return ratchet, and extensible canopy is arranged on below operating desk, self-return ratchet is arranged on extensible canopy end, described lower platform is connected and composed by lower operating desk and bottom girder, corresponding with self-return ratchet, on elevator shaft inner formword He on elevator shaft cast-in-place shear wall interior wall, fix pre-buried cover.
Above-mentioned self-return ratchet comprises riser and is arranged on balancing weight and the roller at riser two ends respectively, is connected in the middle part of riser by Assembly of pin with the extensible canopy end of template platform.
Above-mentioned self-return ratchet is four, lays respectively at two jiaos of the two ends of template platform.
Above-mentioned balancing weight is provided with screwed hole, and adjusting bolt is arranged in the screwed hole of balancing weight; Described riser is provided with sole bottom roller one end; Described riser is made up of two block plates, is connected with stiffener between two block plates.
Above-mentioned extensible canopy comprises clamped beam and regulates beam, described clamped beam is welded by channel-section steel and i iron, described adjustment beam is formed by connecting with Plate Welding between interval, two channel-section steels back-to-back by two channel-section steels, the i iron of clamped beam one end is sleeved between two channel-section steels of adjustment beam, lower lock block one is welded on and regulates bottom beam, upper holder block one is locked at bolt assembly and regulates back portion, upper holder block dual-purpose bolt assembly is locked at the i iron top of clamped beam, and lower lock block dual-purpose bolt assembly is locked at bottom the i iron of clamped beam; The i iron of described clamped beam is welded with deep floor.
A kind of construction method using the utility model hoistway formwork platform, when elevator shaft first floor cast-in-place shear wall props up inner formword, one group of four pre-buried cover is fixed on inner formword by thread, after first floor pouring concrete completes, releasing lever, take inner formword apart, pre-buried cover is stayed in first floor cast-in-place shear wall, then template platform is put in first floor elevator shaft cast-in-place shear wall bobbin, one end of four ratchets that automatically reset of template platform is dropped in pre-buried cover, make template platform firm be overlapped in first floor elevator shaft bobbin, inner formword is placed on the upper operating desk table top of template platform, other one group of four pre-buried cover is fixed the second layer on inner formword, pouring concrete second layer shear wall, after reaching form removal condition, inner formword is taken apart, then the suspension ring sling on template platform with tower crane, template platform entirety is up carried, on carry in process, automatic aftertaste ratchet is around the bearing pin adduction of template platform, the roller of self-return ratchet rolls along bobbin wall metope, when reaching the pre-buried cover of the second layer, self-return ratchet flare up under the effect of balancing weight is horizontal, self-return ratchet one end is dropped in pre-buried cover, template platform is made firmly to be overlapped in elevator shaft second layer bobbin, at this moment workman is by arriving lower operating desk under ladder, to dismantle four pre-buried covers of first floor, four pre-buried covers are retightened on internal mold, then third layer is poured into a mould, so construct successively from low layer to high level.

Claims (5)

1. a hoistway formwork platform, it is characterized in that, comprise upper mounting plate and lower platform, upper mounting plate is connected by square tube with lower platform, described upper mounting plate is connected and composed by upper operating desk, extensible canopy and self-return ratchet, extensible canopy is arranged on below operating desk, and self-return ratchet is arranged on extensible canopy end, and described lower platform is connected and composed by lower operating desk and bottom girder; Corresponding with self-return ratchet, on elevator shaft inner formword He on elevator shaft cast-in-place shear wall interior wall, fix pre-buried cover.
2. hoistway formwork platform according to claim 1, is characterized in that, described self-return ratchet comprises riser and is arranged on balancing weight and the roller at riser two ends respectively, is connected in the middle part of riser by Assembly of pin with the extensible canopy end of template platform.
3. hoistway formwork platform according to claim 1, is characterized in that, described self-return ratchet is four, lays respectively at two jiaos of the two ends of template platform.
4. hoistway formwork platform according to claim 2, is characterized in that, described balancing weight is provided with screwed hole, and adjusting bolt is arranged in the screwed hole of balancing weight; Described riser is provided with sole bottom roller one end; Described riser is made up of two block plates, is connected with stiffener between two block plates.
5. hoistway formwork platform according to claim 1, it is characterized in that, described extensible canopy comprises clamped beam and regulates beam, described clamped beam is welded by channel-section steel and i iron, described adjustment beam is by two channel-section steels interval back-to-back, be formed by connecting with Plate Welding between two channel-section steels, the i iron of clamped beam one end is sleeved between two channel-section steels of adjustment beam, lower lock block one is welded on and regulates bottom beam, upper holder block one is locked at bolt assembly and regulates back portion, upper holder block dual-purpose bolt assembly is locked at the i iron top of clamped beam, lower lock block dual-purpose bolt assembly is locked at bottom the i iron of clamped beam, the i iron of described clamped beam is welded with deep floor.
CN201420862518.1U 2014-12-31 2014-12-31 Hoistway formwork platform Withdrawn - After Issue CN204370796U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420862518.1U CN204370796U (en) 2014-12-31 2014-12-31 Hoistway formwork platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420862518.1U CN204370796U (en) 2014-12-31 2014-12-31 Hoistway formwork platform

Publications (1)

Publication Number Publication Date
CN204370796U true CN204370796U (en) 2015-06-03

Family

ID=53327027

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420862518.1U Withdrawn - After Issue CN204370796U (en) 2014-12-31 2014-12-31 Hoistway formwork platform

Country Status (1)

Country Link
CN (1) CN204370796U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499706A (en) * 2014-12-31 2015-04-08 长沙远大住宅工业集团有限公司 Elevator well template platform and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499706A (en) * 2014-12-31 2015-04-08 长沙远大住宅工业集团有限公司 Elevator well template platform and construction method thereof

Similar Documents

Publication Publication Date Title
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN102535845A (en) Construction method of bearing frame of corridor structure
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN105586833B (en) Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method
CN104499706B (en) Hoistway formwork platform and construction method thereof
CN203878965U (en) Device for construction of elevator shaft
CN107165281A (en) A kind of high-altitude long-span overhung steel platform mould bases construction
CN103510541A (en) Device and method for installing steel pipe column to interior of lifting frame hole
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN103114754A (en) Alternative hoisting method for conjoined coal bunker top truss girder pre-placing
CN202401769U (en) Detachable concrete cloth machine for self-elevating creeping formwork system
CN104818729B (en) Can be for the mutual foundation of big or small tower crane conversion
CN203795311U (en) Multi-leg high pier and slip form construction device
CN109869153A (en) The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN203034799U (en) Tower hoist standard knot bearing overhead support formwork steel platform structure
CN105347142A (en) Plate penetrating installing method for installing construction lifting machine on basement top plate
CN203285050U (en) Combined type Bailey frame multifunctional platform carried by sliding formwork to rise and fall
CN105952129B (en) A kind of elevator combined type entirety lifting operation platform and its construction method
CN204370796U (en) Hoistway formwork platform
CN203755173U (en) Formwork device used for hydraulic climbing of bridge high pier
CN104453235B (en) Current conversion station fire wall construction technology
CN203613464U (en) Slip form construction cargo transportation device
CN103669219B (en) Many limbs height pier is with sliding construction equipment
CN205314539U (en) Large -scale cantilever type combination steel form
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20150603

Effective date of abandoning: 20160824

C25 Abandonment of patent right or utility model to avoid double patenting