CN204370315U - A kind of steel box-girder thrusting slip falls beam servicing unit - Google Patents

A kind of steel box-girder thrusting slip falls beam servicing unit Download PDF

Info

Publication number
CN204370315U
CN204370315U CN201420819679.2U CN201420819679U CN204370315U CN 204370315 U CN204370315 U CN 204370315U CN 201420819679 U CN201420819679 U CN 201420819679U CN 204370315 U CN204370315 U CN 204370315U
Authority
CN
China
Prior art keywords
oil cylinder
falls
bracket
girder
steel box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420819679.2U
Other languages
Chinese (zh)
Inventor
张述明
张才伦
黄修生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YINGDU BRIDGE STEEL STRUCTURE ENGINEERING Co Ltd
Original Assignee
YINGDU BRIDGE STEEL STRUCTURE ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YINGDU BRIDGE STEEL STRUCTURE ENGINEERING Co Ltd filed Critical YINGDU BRIDGE STEEL STRUCTURE ENGINEERING Co Ltd
Priority to CN201420819679.2U priority Critical patent/CN204370315U/en
Application granted granted Critical
Publication of CN204370315U publication Critical patent/CN204370315U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model belongs to field of bridge construction, be specifically related to a kind of steel box-girder thrusting slip to fall beam servicing unit, this beam servicing unit that falls be installed on last across beam and rear across beam junction, comprise be fixed on last across beam fall beam oil cylinder and after being fixed on one across the bracket of beam, described fall beam oil cylinder be positioned at the downside of bracket lateral extensions, described bracket is connected with the beam oil cylinder that falls, and can abut the beam oil cylinder that falls on the downside of described bracket lateral extensions.The utility model has the beneficial effects such as construction is simple and convenient, efficiency is high, make steel box girder construction installation accurate.

Description

A kind of steel box-girder thrusting slip falls beam servicing unit
Technical field
The utility model belongs to field of bridge construction, is specifically related to a kind of steel box-girder thrusting slip and falls beam servicing unit.
Background technology
The traffic form of modern society's viaduct and overpass bridge is the important means of dredging urban congestion traffic, between bridge pier, the construction and installation of beam are the important stages of pontic construction, in prior art, between pier, beam construction existence rear easily produces error with last across beam junction across beam when the beam that falls is installed, and installation is technical problem not accurately.
For solving the problems of the technologies described above, the applicant provides a kind of steel box-girder thrusting slip to fall beam servicing unit, and this case produces thus.
Utility model content
The purpose of this utility model is to provide a kind of steel box-girder thrusting slip to fall beam servicing unit, to solve the problems of the technologies described above, concrete technical scheme of the present utility model is: a kind of steel box-girder thrusting slip falls beam servicing unit, this beam servicing unit that falls be installed on last across beam and rear across beam junction, comprise be fixed on last across beam fall beam oil cylinder and after being fixed on one across the bracket of beam, described fall beam oil cylinder be positioned at the downside of bracket lateral extensions, described bracket is connected with the beam oil cylinder that falls, and can abut the beam oil cylinder that falls on the downside of described bracket lateral extensions.
The beneficial effects of the utility model: when the lower side compression of bracket lateral extensions falls beam oil cylinder, rear one accurately installs across beam relative to last across beam, construct simple and convenient, efficiency is high, make steel box girder construction install the beneficial effects such as accurate.
Accompanying drawing explanation
Fig. 1 is the utility model steel box-girder thrusting slip construction schematic diagram;
Fig. 2 is the beam assistant apparatus structure schematic diagram that falls.
Detailed description of the invention
A kind of steel box-girder thrusting slip construction method, comprises the steps: 1), block mark mark; 2), benchmark sections is installed; 3), sections front pre-correction in place; 4), surplus cutting; 5), sections accurate adjustment; 6), pad at the bottom of beam; 7), install beam servicing unit; 8) beam that, falls is located; 9), fall Liang Chengqiao.
Above step is specifically unfolded as follows:
Described step 1) is specially: after steel box-girder has been assembled on platform for lining, measure camber, horizontal wall inscription, appearance and size inspection declaration, simultaneously, with total powerstation determination sections axis before lower tire, and top board indulge axis of pitch two ends carry out sample punching point mark, and paint to make and mark clearly, to fall beam datum mark in place as sections.
Described step 2) be specially: by bridge south 35# little pile No. end, install 35-37# successively across interior steel box-girder, the positioning datum of complete steel box-girder as next joint case beam-ends mouth has been located in prostatitis.
Described step 3) is specially: when steel box-girder first pushing tow sections is far away close to theoretical position 3 meters, starts tracking measurement and tentatively rectifies a deviation; Survey station is located on 35# pier, utilizes the axis off normal situation of total station survey pushing tow sections; Because track width is greater than pushing tow piston shoes width, therefore there will be the overall horizontal off normal of sections, if can tentatively finely tune by monolateral pushing tow when lateral deviation is excessive; If when still cannot rectify a deviation smoothly, special razor-edge liner frock can be adopted, wedge shape frock is encased inside track side and fixes with rail beam, more progressively pushing tow is rectified a deviation, rectify a deviation to axis lateral deviation within 1cm by this method; All the other sections are equally according to said method rectified a deviation.
Described step 4) is specially: portion segment port has surplus, surplus need measure cutting according to actual conditions before in place: sections pushing tow is extremely apart from last joint beam section 10cm place, the cutting quantity of steel ruler measurement port surplus is coordinated with total powerstation, measure sections panel length, port gap length, and the distance at below holder base plate and bridge pier pinner center, calculate port cutting quantity, then line is cut surplus and is opened groove processed; Do Special hanging basket protective tooling and be suspended at the bottom of beam during the cutting of base plate surplus, prevent spark from dropping, properly protect in case during the cutting of panel surplus in order to avoid under spark splashes to case beam.
Described step 5) is specially: it is involutory to prosthomere port with the complete 10cm of little running that sections keeps correct attitude to continue, stay seam 6-8mm, again measure axis off normal situation, check collar extension Chu Ge road web misalignment situation simultaneously, the dead in line of sections before and after emphasis ensures, if have partially, adopt gaily decorated basket screw rod to carry out sections laterally fine setting, make that port is involutory meets required precision, deviation controls as far as possible within 5mm; So far, the case back section of pushing away has arrived design plane position, but elevation is still higher than design altitude, needs to reduce beam section height, 4 group oil cylinders synchronously land, stop when being down to the above 10cm of design altitude, now again measure the absolute altitude of sections corner measuring point, utilize 4 groups of jacking cylinders to finely tune, the corner discrepancy in elevation is met the requirements, ensure beam section transverse horizontal, longitudinally coincide with design grade, before beam of guaranteeing to fall, attitude is correct.
Described step 6) is specially: carry out rapidly pad at the bottom of beam after accurate adjustment, pad is arranged on both sides before and after piston shoes, 16 pads are set bottom single-unit beam section, pad must pad and be adjacent to base plate, prevent from piston shoes oil cylinder from removing back rest section to loosen, press said process incremental launching positioning successively across interior 2nd, 3 section, and be welded as entirety, beam to be fallen.
Described step 7) is specially: the beam oil cylinder that falls of single span sections large pile No. end is arranged on the permanent pier of bridge, and each Dun Ding arranges two oil cylinders, is distributed in bearing pad stone both sides; Other end bridge pier is pushed down across beam section by last, beam section directly rides on prosthomere port, and at the bottom of beam between track and base plate insufficient height cannot put into beam oil cylinder, therefore, fall before beam and arrange bracket in top plate port, bracket is arranged on beam section panel and web correspondence position and carries out strengthening measure in case, and bracket is arranged on more than sections panel, laterally corresponding with web position, under bracket, install beam oil cylinder.
Bracket structure designs: the beam bracket that falls is barb type, and be arranged in single span girder segment to be fallen without permanent buttress one end, bracket root and steel box-girder top board are weldingly connected, and arrange 8 altogether along direction across bridge, and bracket web position is corresponding with box girder web.Bracket lower tank web both sides arrange reinforcement gusset, and gusset vertical with bracket is corresponding respectively to strengthen gusset.
Near front end dropping place sections top plate port, arrange beam oil cylinder, laterally 8 difference are corresponding above each web, because bridge floor has 2% horizontal wall inscription, adopt razor-edge liner levelling bottom oil cylinder.Below oil cylinder, web both sides arrange reinforcement gusset, middle one channel beam base plate.
Bracket height 840mm, length 1220mm, width 400mm are i shaped cross section structure.The thick 30mm of web, arc tips shrouding thickness 20mm, frange plate and gusset are 20mm, material Q345B.Bracket web and arc shrouding weld with beam section end face penetration, and all the other gussets weld with twin fillet wolt, welding and assembling height 10mm.Steel box-girder reinforcing rib plate thickness 16mm.
Described step 8) is specially: after installing beam oil cylinder, and the first synchronization of jacking up 5cm of each jacking cylinder, checks hydraulic test operating condition, lay down pad at the bottom of beam, more slowly synchronous decline, and the beam that falls is in place; At the bottom of beam, again add pad after beam section is in place prevents oil cylinder off-load from causing port misalignment, and pad is arranged in support capital position, and collar extension fixed by horse plate rapidly, carries out girth welding; Remove bracket, shed beam servicing unit.
As shown in Figure 1, 2, for a kind of steel box-girder thrusting slip falls beam servicing unit, this beam servicing unit that falls be installed on last across beam 1 and rear across beam 2 junction, comprise be fixed on last across beam 1 fall beam oil cylinder 4 and after being fixed on one across the bracket 3 of beam 2, described fall beam oil cylinder 4 be positioned at the downside of bracket 3 lateral extensions 31, described bracket 3 is connected with the beam oil cylinder 4 that falls, and can abut the beam oil cylinder 4 that falls on the downside of described bracket 3 lateral extensions 31.
The use principle of this beam servicing unit that falls: first install beam oil cylinder 4 and fixedly mount bracket 3 across on beam 2 rear last across on beam 1, wherein said fall beam oil cylinder 4 be positioned at the downside of bracket 3 lateral extensions 31, when after laying one across beam 2 time, rear one falls across beam 2, the downside of bracket 3 lateral extensions 31 abuts beam oil cylinder 4, the beam oil cylinder 4 that falls also synchronously declines, and when the beam oil cylinder 4 that falls touches the end, namely, one also accurately installs across beam 2.
The present embodiment is for explaining that utility model of the present utility model is conceived, but not the restriction to the utility model protection domain, allly does any unsubstantiality to above-described embodiment and changes, and all belongs to protection domain of the present utility model.

Claims (1)

1. a steel box-girder thrusting slip falls beam servicing unit, this beam servicing unit that falls be installed on last across beam and rear across beam junction, it is characterized in that: comprise be fixed on last across beam fall beam oil cylinder and after being fixed on one across the bracket of beam, described fall beam oil cylinder be positioned at the downside of bracket lateral extensions, described bracket is connected with the beam oil cylinder that falls, and can abut the beam oil cylinder that falls on the downside of described bracket lateral extensions.
CN201420819679.2U 2014-12-22 2014-12-22 A kind of steel box-girder thrusting slip falls beam servicing unit Active CN204370315U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420819679.2U CN204370315U (en) 2014-12-22 2014-12-22 A kind of steel box-girder thrusting slip falls beam servicing unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420819679.2U CN204370315U (en) 2014-12-22 2014-12-22 A kind of steel box-girder thrusting slip falls beam servicing unit

Publications (1)

Publication Number Publication Date
CN204370315U true CN204370315U (en) 2015-06-03

Family

ID=53326547

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420819679.2U Active CN204370315U (en) 2014-12-22 2014-12-22 A kind of steel box-girder thrusting slip falls beam servicing unit

Country Status (1)

Country Link
CN (1) CN204370315U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104562940A (en) * 2014-12-22 2015-04-29 盈都桥梁钢构工程有限公司 Steel box beam jacking pushing and slide moving construction method and beam falling auxiliary device
CN111455851A (en) * 2020-04-01 2020-07-28 冉光全 Temporary prestressing device for segmental prefabricated assembled beam
CN112146575A (en) * 2020-09-15 2020-12-29 中铁第五勘察设计院集团有限公司 System and method for monitoring beam falling deviation of bridge girder erection machine
CN113152306A (en) * 2021-03-17 2021-07-23 中铁八局集团有限公司 Small-radius large-gradient prefabricated T beam frame construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104562940A (en) * 2014-12-22 2015-04-29 盈都桥梁钢构工程有限公司 Steel box beam jacking pushing and slide moving construction method and beam falling auxiliary device
CN111455851A (en) * 2020-04-01 2020-07-28 冉光全 Temporary prestressing device for segmental prefabricated assembled beam
CN112146575A (en) * 2020-09-15 2020-12-29 中铁第五勘察设计院集团有限公司 System and method for monitoring beam falling deviation of bridge girder erection machine
CN112146575B (en) * 2020-09-15 2021-11-09 中铁第五勘察设计院集团有限公司 System and method for monitoring beam falling deviation of bridge girder erection machine
CN113152306A (en) * 2021-03-17 2021-07-23 中铁八局集团有限公司 Small-radius large-gradient prefabricated T beam frame construction method

Similar Documents

Publication Publication Date Title
CN104562940B (en) A kind of steel box-girder thrusting slip construction method and the beam auxiliary device that falls
CN204370315U (en) A kind of steel box-girder thrusting slip falls beam servicing unit
CN103266573B (en) Steel Box Girder of Self-Anchored Suspension beam unidirectional single-point three slideway synchronous push construction method
CN101684638B (en) Assembly method of section box girder
CN103470272B (en) A kind of chassis for the multiple section concrete construction of Mining Method and construction method thereof
CN101418535A (en) Construction method of monolithic road-bed in rail tunnel
CN103757993A (en) System and method for high-speed railway subgrade settlement restoration
CN105507155A (en) Construction process for installation of small-segment steel box girder
CN102619144A (en) Construction technology for prefabricated assembled steel spring floating slab track
CN102912693B (en) Floating track bed precast slab and construction method for precast slab assembled floating track bed
CN105507168A (en) Multi-span box girder integral ultrahigh alternate jacking construction system and method
CN105401520A (en) Integrated layer whole-width construction device for light truss type bridge and construction method of construction device
CN104018426A (en) Steel truss installation method
CN104329096A (en) Shield station-crossing launching translation construction process
CN107725066B (en) Prefabricated box culvert and layout method thereof
CN107386125B (en) A kind of construction method that Steel Box Girder of Self-Anchored Suspension beam closes up
CN203499697U (en) Trolley used for concrete construction of various cross sections through mining method
CN205973473U (en) Bridge crane base steel wiping line scale for support mounting
CN204877520U (en) Subway overlaps synchronous strutting arrangement in tunnel
CN203035204U (en) Large-section tunnel second lining grouping formwork trolley
JP2007205130A (en) Girder construction method by erection garter from side of bridge
CN203878479U (en) Bridge erection machine traversing support
CN203161252U (en) Mobile formwork used in tunnel ditch cable trough construction
CN105625462A (en) Precast beam pedestal construction process
CN205748584U (en) A kind of sleeper type frame-type entirety track scale

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant