CN105625462A - Precast beam pedestal construction process - Google Patents

Precast beam pedestal construction process Download PDF

Info

Publication number
CN105625462A
CN105625462A CN201410580391.9A CN201410580391A CN105625462A CN 105625462 A CN105625462 A CN 105625462A CN 201410580391 A CN201410580391 A CN 201410580391A CN 105625462 A CN105625462 A CN 105625462A
Authority
CN
China
Prior art keywords
pedestal
construction
steel
angle steel
precast beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410580391.9A
Other languages
Chinese (zh)
Inventor
祝建斌
张文坤
温玉群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 14th Bureau Group Co Ltd
Original Assignee
China Railway 14th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 14th Bureau Group Co Ltd filed Critical China Railway 14th Bureau Group Co Ltd
Priority to CN201410580391.9A priority Critical patent/CN105625462A/en
Publication of CN105625462A publication Critical patent/CN105625462A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

A precast beam pedestal construction technology comprises the steps of measuring and wire stringing; conducting basic excavation; performing foundation carrying capacity detection, basic cushion concrete pouring and basic steel bar colligation; then performing basic concrete pouring, pedestal steel bar binding, pedestal template installation, pedestal concrete pouring and pedestal steel plate laying; and finally welding channel steels at two sides. The problem that the precast beam construction production is influenced due to landform condition restriction and small beam land area is solved; beam land construction time and precast beam construction period are shortened; bean land construction cost is reduced; construction cost is greatly reduced; the normal construction of the precast beam lays a solid foundation for the normal development of subsequent engineering like floor erection and bridge floor construction, and guarantees the smooth construction of the project engineering.

Description

Precast beam Precasting Pedestal Construction technique
Technical field
The present invention relates to a kind of beam Precasting Pedestal Construction technique, specifically precast beam Precasting Pedestal Construction technique.
Background technology
Original precast beam Precasting Pedestal Construction needs relatively place, crossbeam field, and construction speed is slow, and construction quality is low, and construction cost is high, and Liang Chang takes over the land for use and smooth expense, precast pedestal construction cost height.
Summary of the invention
For solving the problems referred to above, it is an object of the invention to provide a kind of precast beam Precasting Pedestal Construction technique.
The present invention is for achieving the above object, it is achieved through the following technical solutions: precast beam Precasting Pedestal Construction technique, first carry out surveying setting-out, carry out foundation excavation again, then foundation bearing capacity detection, blinding layer concrete placings and reinforcement foundation colligation are carried out, it is sequentially carried out that foundation concrete is built, pedestal reinforcing bar binding, pedestal model sheetinstallat, pedestal concrete placings and pedestal steel plate are laid, and finally carry out both sides channel-section steel welding again.
For realizing the purpose of the present invention further, it is also possible to by the following technical solutions: pre-embedded steel slab installation site adjustment �� seam crossing polishing at the bottom of preparation of construction �� dismounting 30m pedestal side channel-section steel �� widened section angle steel welding, the welding of reinforcing �� channel-section steel, reinforcing �� beam. Before 30m beam making bench changes the construction of 40m beam making bench, first have to the preparation before carrying out the construction such as material purchase, machinery allotment, personnel placement, buy sufficient angle steel (10 �� 10cm), channel-section steel (5#), �� 22 reinforcing bar, expansion bolt (�� 12), welding rod (502), horizon rule etc. according to pedestal quantity, select the skilled industrial worker that solder technology is really up to the mark. Weld 10 �� 10cm angle steel, angle steel side and base steel plate end face level in former 30m beam making bench side, opposite side and concrete base side are close to, and angle steel docks with steel plate closely, and apical side height is consistent, firm welding, measure accurately with horizon rule before welding; After angle steel has welded, bottom angle steel, each rice slate pencil makes marks, and cuts the semicircle of a diameter 3cm with gas cutting, punches at this place and installs expansion bolt, screw support angle steel, it is ensured that angle steel is stable.
It is an advantage of the current invention that: the invention solves because orographic condition limits, Liang Chang place is less, affect the problem that precast beam construction produces, decrease beam fabricating yard construction time and precast beam construction period, reduce the expenses such as beam fabricating yard construction, largely reduce construction cost, the normal construction of precast beam, established solid foundation for normally carrying out of successive projects such as beam slab erection, bridge deck constructions, for project construction be smoothed out provide sound assurance.
Accompanying drawing explanation
Fig. 1 is present configuration schematic diagram.
Detailed description of the invention
Precast beam Precasting Pedestal Construction technique, first carry out surveying setting-out, carry out foundation excavation again, then foundation bearing capacity detection, blinding layer concrete placings and reinforcement foundation colligation are carried out, it is sequentially carried out that foundation concrete is built, pedestal reinforcing bar binding, pedestal model sheetinstallat, pedestal concrete placings and pedestal steel plate are laid, and finally carry out both sides channel-section steel welding again.
Pre-embedded steel slab installation site adjustment �� seam crossing polishing at the bottom of preparation of construction �� dismounting 30m pedestal side channel-section steel �� widened section angle steel welding, the welding of reinforcing �� channel-section steel, reinforcing �� beam.
Before 30m beam making bench changes the construction of 40m beam making bench, first have to the preparation before carrying out the construction such as material purchase, machinery allotment, personnel placement, buy sufficient angle steel (10 �� 10cm), channel-section steel (5#), �� 22 reinforcing bar, expansion bolt (�� 12), welding rod (502), horizon rule etc. according to pedestal quantity, select the skilled industrial worker that solder technology is really up to the mark.
Weld 10 �� 10cm angle steel, angle steel side and base steel plate end face level in former 30m beam making bench side, opposite side and concrete base side are close to, and angle steel docks with steel plate closely, and apical side height is consistent, firm welding, measure accurately with horizon rule before welding; After angle steel has welded, bottom angle steel, each rice slate pencil makes marks, and cuts the semicircle of a diameter 3cm with gas cutting, punches at this place and installs expansion bolt, screw support angle steel, it is ensured that angle steel is stable.
After angle steel has been constructed, weld channel-section steel (5#) in angle steel bottom surface, channel-section steel opening outwardly, outside and angle steel justified margin, firm welding, for ensureing that channel-section steel is reinforced stable, it is supported every two �� 22 reinforcing bars of one meter of use bottom channel-section steel, reinforcing bar one end and channel-section steel bottom welding, the other end is supported on pedestal basis and pedestal abutment body, firm welding, supporting & stablizing, it is ensured that channel-section steel is reinforced stable.
With pre-embedded steel slab reserved location at the bottom of the beam of epoxy resin mortar filling-in former 30m beam making bench end, and installed base steel plate, steel plate is installed and dock with both sides steel plate, it is ensured that docking and smooth out, firm welding, seam crossing powder of lacquer putty for use on is clogged, it is ensured that tight.
Checking whether angle steel and channel-section steel welding be firm, it has been found that the timely repair welding of problem is reinforced, with abrasive cutoff saw butt welding contact and there is the position of faulting of slab ends and polish, it is floating that the place powder of lacquer putty for use on that seam is bigger carries out filling, it is ensured that seam is tight, not spillage.
Technical scheme is not restricted in the scope of embodiment of the present invention. The technology contents of the not detailed description of the present invention is known technology.

Claims (4)

1. precast beam Precasting Pedestal Construction technique, it is characterized in that: first carry out surveying setting-out, carry out foundation excavation again, then foundation bearing capacity detection, blinding layer concrete placings and reinforcement foundation colligation are carried out, it is sequentially carried out that foundation concrete is built, pedestal reinforcing bar binding, pedestal model sheetinstallat, pedestal concrete placings and pedestal steel plate are laid, and finally carry out both sides channel-section steel welding again.
2. precast beam Precasting Pedestal Construction technique according to claim 1, it is characterised in that: pre-embedded steel slab installation site adjustment �� seam crossing polishing at the bottom of preparation of construction �� dismounting 30m pedestal side channel-section steel �� widened section angle steel welding, the welding of reinforcing �� channel-section steel, reinforcing �� beam.
3. precast beam Precasting Pedestal Construction technique according to claim 1, it is characterized in that: before 30m beam making bench changes the construction of 40m beam making bench, first have to the preparation before carrying out the construction such as material purchase, machinery allotment, personnel placement, buy sufficient angle steel (10 �� 10cm), channel-section steel (5#), �� 22 reinforcing bar, expansion bolt (�� 12), welding rod (502), horizon rule etc. according to pedestal quantity, select the skilled industrial worker that solder technology is really up to the mark.
4. precast beam Precasting Pedestal Construction technique according to claim 1, it is characterized in that: weld 10 �� 10cm angle steel in former 30m beam making bench side, angle steel side and base steel plate end face level, opposite side and concrete base side are close to, angle steel docks with steel plate closely, apical side height is consistent, firm welding, measures accurately with horizon rule before welding; After angle steel has welded, bottom angle steel, each rice slate pencil makes marks, and cuts the semicircle of a diameter 3cm with gas cutting, punches at this place and installs expansion bolt, screw support angle steel, it is ensured that angle steel is stable.
CN201410580391.9A 2014-10-27 2014-10-27 Precast beam pedestal construction process Pending CN105625462A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410580391.9A CN105625462A (en) 2014-10-27 2014-10-27 Precast beam pedestal construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410580391.9A CN105625462A (en) 2014-10-27 2014-10-27 Precast beam pedestal construction process

Publications (1)

Publication Number Publication Date
CN105625462A true CN105625462A (en) 2016-06-01

Family

ID=56040772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410580391.9A Pending CN105625462A (en) 2014-10-27 2014-10-27 Precast beam pedestal construction process

Country Status (1)

Country Link
CN (1) CN105625462A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110788984A (en) * 2019-10-28 2020-02-14 中建三局基础设施建设投资有限公司 Precast beam making pedestal side width device and implementation method thereof
CN113944110A (en) * 2021-11-23 2022-01-18 中国二十冶集团有限公司 Precast beam slab pedestal construction method
CN115091607A (en) * 2022-07-14 2022-09-23 华能铜川照金煤电有限公司 Construction method for accurately positioning pre-camber of precast beam pedestal

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110788984A (en) * 2019-10-28 2020-02-14 中建三局基础设施建设投资有限公司 Precast beam making pedestal side width device and implementation method thereof
CN113944110A (en) * 2021-11-23 2022-01-18 中国二十冶集团有限公司 Precast beam slab pedestal construction method
CN115091607A (en) * 2022-07-14 2022-09-23 华能铜川照金煤电有限公司 Construction method for accurately positioning pre-camber of precast beam pedestal
CN115091607B (en) * 2022-07-14 2024-01-16 华能铜川照金煤电有限公司 Construction method for accurately positioning pre-camber of precast beam pedestal

Similar Documents

Publication Publication Date Title
CN204054323U (en) Steel construction assembled beam making bench
CN106120561B (en) A kind of cast-in-situ box girder template construct installation method
CN101781879B (en) Construction method of single-pylon cable-stayed bridge without dorsal cables
CN204431472U (en) Make precast beam pedestal
CN105350654B (en) A kind of construction method for adjusting pre-embedded steel slab and reaching design and construction precision
CN108330835A (en) The construction method of setting bracket
CN106225707A (en) A kind of method for the deformation of fast monitored high CFRD extrusion side wall
CN203891058U (en) Built-in foundation bolt positioning tool for fixed type tower crane foundation
CN106498853A (en) A kind of construction method of high ferro across existing railway large-span steel bent cap
CN106641446B (en) Anti-settling pipe carrier of large-diameter pipeline and construction method thereof
CN1978838A (en) Construction method for combined V-shape steel pipe concrete pile
CN103485539A (en) Construction control method for large direct-buried steel anchor fluke embedded part
CN102121233A (en) Construction method of bridge cast-in-place box beam
CN104562940A (en) Steel box beam jacking pushing and slide moving construction method and beam falling auxiliary device
CN105625462A (en) Precast beam pedestal construction process
CN108487630A (en) Coagulation earth steps platform prefabrication and assembly construction construction method
CN108253193A (en) Wall pipe built-in construction method
CN105089184A (en) Multi-curved concrete hollow modelling wall construction method and rhombic hollow structure formwork
CN204370315U (en) A kind of steel box-girder thrusting slip falls beam servicing unit
CN104563525B (en) A kind of box steel arch beam Integral horizontal type group is to method
CN109736616A (en) The open caisson construction method of stereo garage
CN203863275U (en) Railway box girder embedded bolt welding mold frame
CN102995570A (en) Stiffening steel truss lower node location die
CN205604192U (en) Overflow surface concrete turns over mould construction system
CN205171700U (en) Prevent that peripheral building carrier plate of steel column from leaking structure of starching

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160601