CN204343154U - Assembled continuous rigid frame bridge steel tie beam - Google Patents
Assembled continuous rigid frame bridge steel tie beam Download PDFInfo
- Publication number
- CN204343154U CN204343154U CN201420810170.1U CN201420810170U CN204343154U CN 204343154 U CN204343154 U CN 204343154U CN 201420810170 U CN201420810170 U CN 201420810170U CN 204343154 U CN204343154 U CN 204343154U
- Authority
- CN
- China
- Prior art keywords
- bolt
- bridge
- crab
- steel
- junction plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 35
- 239000010959 steel Substances 0.000 title claims abstract description 35
- 239000011230 binding agent Substances 0.000 claims description 20
- 238000010276 construction Methods 0.000 abstract description 8
- 239000004567 concrete Substances 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002372 labelling Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000011513 prestressed concrete Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a continuous rigid frame bridge steel tie beam of assembled. The bridge pier comprises anchor bolts (2) which are embedded in the inner sides of two bridge piers (1) and symmetrically arranged, and the anchor bolts are connected with a bearing steel plate (4) through a connecting plate (3). Adopt the technical scheme of the utility model, tie beam and pier junction can not ftracture, have improved the durability of bridge. Additionally, the technical scheme of the utility model also can regard as the interim support in the pier construction, wait that the bridge construction finishes the back and demolish.
Description
Technical field
the utility model relates to a kind of assembling continuous rigid frame bridge steel binder, belongs to bridge construction and technical field of construction.
Background technology
prestressed concrete continuous rigid-framed bridge is one of current more common a kind of bridge pattern, the bridge pier of this kind of bridge generally adopts two board-like solid pier of limb or twin legged thin wall hollow pier, for the bridge pier that these are higher, generally steel concrete binder is set between two limbs.
existing binder cross section is generally board-like or case structure.In the process of actual motion, very easily produce crack at steel concrete binder and bridge pier junction, the appearance in crack can reduce the durability of bridge construction.
in addition, in the practice of construction of continuous rigid frame bridge bridge pier, for the bridge pier that some are not very high, binder is not set in design, but for increasing the interim rigidity of bridge pier and support, provisional lateral ties structure need be set between two limb bridge pier, after bridge builds up, then by these interim lateral ties structural demolitions.
Utility model content
the purpose of this utility model is, provides a kind of assembling continuous rigid frame bridge steel binder, to solve the technical problem that existing structure easily produces crack, solves the technical problem arranging interim lateral ties between two limb bridge pier simultaneously.
the technical solution of the utility model:
a kind of assembling continuous rigid frame bridge steel binder, comprise and be embedded in symmetrically arranged crab-bolt inside two bridge piers, crab-bolt is connected with carrying steel plate through junction plate.
in aforementioned steel binder, described crab-bolt is L shape, and one end, long limit of L shape is provided with screw thread, and the minor face of L shape and one section of long limit are embedded in bridge pier, and long limit establishes threaded end to expose bridge pier side to be connected with junction plate through nut.
in aforementioned steel binder, be provided with the crab-bolt of the equidistant horizontal distribution of two rows inside described bridge pier, two row's crab-bolts are symmetrical arranged.
in aforementioned steel binder, described junction plate is steel angle structure, and the two sides of angle steel are equipped with the through hole corresponding with crab-bolt spacing, and the through hole of junction plate side is enclosed within crab-bolt and establishes threaded one end, fixes through nut and bridge pier; Junction plate in two row's crab-bolts is symmetrical fixing back-to-back.
in aforementioned steel binder, described carrying steel plate is rectangle, and the both sides that rectangle is relative are clipped between junction plate fixing on two bridge piers, are fixedly connected with through bolt.
compared with prior art, the utility model provides a kind of standardized continuous rigid frame bridge bridge pier binder structure, and adopt the technical solution of the utility model, can not ftracture in binder and bridge pier junction, improve the durability of bridge.In addition, the technical solution of the utility model also can be used as the temporary support in Bridge Pier Construction, removes after treating bridge construction.
Accompanying drawing explanation
fig. 1 is structural representation of the present invention.
being labeled as in accompanying drawing: 1-bridge pier, 2-crab-bolt, 3-junction plate, 4-carry steel plate, 5-nut, 6-bolt.
Detailed description of the invention
below in conjunction with drawings and Examples, the utility model is described in further detail, but not as to any restriction of the present utility model.
a kind of assembling continuous rigid frame bridge steel binder, as shown in Figure 1, comprise and be embedded in symmetrically arranged crab-bolt 2 inside two bridge piers 1, crab-bolt 2 is connected with carrying steel plate 4 through junction plate 3.Crab-bolt 2 is L shape, and one end, long limit of L shape is provided with screw thread, and the minor face of L shape and one section of long limit are embedded in bridge pier 1, and long limit establishes threaded end to expose bridge pier 1 side to be connected with junction plate 3 through nut 5.Crab-bolt 2, the two row crab-bolt 2 being provided with the equidistant horizontal distribution of two rows inside bridge pier 1 is symmetrical arranged.Junction plate 3 is steel angle structure, and the two sides of angle steel are equipped with the through hole corresponding with crab-bolt 2 spacing, and the through hole of junction plate 3 side is enclosed within crab-bolt 2 and establishes threaded one end, fixes through nut 5 and bridge pier; Junction plate 3 in two row's crab-bolts 2 is symmetrical fixing back-to-back.Carrying steel plate 4 is rectangle, and the both sides that rectangle is relative are clipped between junction plate 3 fixing on two bridge piers 1, are fixedly connected with through bolt 6.
Embodiment
during concrete enforcement, first the tension and compressive resistance that need between continuous rigid frame bridge bridge pier two limb is calculated, the thickness and the width that carry steel plate 4 and junction plate 3 is determined according to result of calculation, and the quantity of cast-in fixing bolt 2 and arrangement, and determine quantity and the arrangement of bolt 5.Then assembled by shown in Fig. 1.
fig. 2 is the application site schematic diagram of the utility model on continuous rigid frame bridge, and in figure, circle labeling position is application site of the present utility model.
be more than embody rule example of the present utility model, do not form any restriction of the present utility model, if one piece carries the bearing capacity that steel plate 4 does not reach designing requirement, multiple carrying steel plate 4 can be set by said structure.All employings are equal to the technical scheme of replacement or equivalent transformation formation, all belong to protection domain of the present utility model.
Claims (5)
1. an assembling continuous rigid frame bridge steel binder, is characterized in that: comprise and be embedded in two bridge piers (1) the symmetrically arranged crab-bolt in inner side (2), crab-bolt (2) is connected with carrying steel plate (4) through junction plate (3).
2. steel binder according to claim 1, it is characterized in that: described crab-bolt (2) is L shape, one end, long limit of L shape is provided with screw thread, the minor face of L shape and one section of long limit are embedded in bridge pier (1), and long limit establishes threaded end to expose bridge pier (1) side to be connected with junction plate (3) through nut (5).
3. steel binder according to claim 2, is characterized in that: described bridge pier (1) inner side is provided with the crab-bolt (2) of the equidistant horizontal distribution of two rows, and two rows' crab-bolt (2) are symmetrical arranged.
4. steel binder according to claim 1, it is characterized in that: described junction plate (3) is steel angle structure, the two sides of angle steel are equipped with the through hole corresponding with crab-bolt (2) spacing, the through hole of junction plate (3) side is enclosed within crab-bolt (2) and establishes threaded one end, fixes through nut (5) and bridge pier; Junction plate (3) on two rows' crab-bolt (2) is symmetrical fixing back-to-back.
5. steel binder according to claim 3, is characterized in that: described carrying steel plate (4) is rectangle, and the both sides that rectangle is relative are clipped between the upper fixing junction plate (3) of two bridge piers (1), are fixedly connected with through bolt (6).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420810170.1U CN204343154U (en) | 2014-12-20 | 2014-12-20 | Assembled continuous rigid frame bridge steel tie beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420810170.1U CN204343154U (en) | 2014-12-20 | 2014-12-20 | Assembled continuous rigid frame bridge steel tie beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204343154U true CN204343154U (en) | 2015-05-20 |
Family
ID=53226432
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420810170.1U Active CN204343154U (en) | 2014-12-20 | 2014-12-20 | Assembled continuous rigid frame bridge steel tie beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204343154U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700105A (en) * | 2019-10-21 | 2020-01-17 | 中交一公局第七工程有限公司 | Synchronous construction method for high pier column and tie beam and template used in same |
-
2014
- 2014-12-20 CN CN201420810170.1U patent/CN204343154U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700105A (en) * | 2019-10-21 | 2020-01-17 | 中交一公局第七工程有限公司 | Synchronous construction method for high pier column and tie beam and template used in same |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203145194U (en) | Internal diaphragm joint of variable flange steel I-beam and square concrete filled steel tubular column | |
CN103993753B (en) | Tradition stone-made house angle hoop drawknot hardened system and construction technology | |
CN104831627A (en) | Bridge deck slab longitudinal unequal strength steel-concrete composite structure bridge and construction method thereof | |
CN204081079U (en) | A kind of structure of open pore steel plate shear force | |
CN203559354U (en) | Stay cable anchoring structure applied to prestressed concrete partially cable-stayed bridge | |
CN205242238U (en) | Be applied to self anchored suspension bridge's main girder structure | |
CN204343154U (en) | Assembled continuous rigid frame bridge steel tie beam | |
CN205296966U (en) | Transmission line iron tower | |
CN103510521A (en) | Connecting component | |
CN104265005B (en) | The back ruggedized construction that a kind of steel plate combines with reinforcing bar | |
CN203514323U (en) | Connection component | |
CN202689585U (en) | Ground fitting up assembly mould of large steel truss | |
CN204000562U (en) | The compound rigid frame bridge of a kind of vertical prestressing steel-concrete | |
CN204238095U (en) | A kind of interlace mode that adopts is arranged on dowel bar assembly on airport rigid pavement plate | |
CN204401829U (en) | RPC compound shear wall is filled out in a kind of encased steel plate | |
CN104818800A (en) | Fabricated steel-concrete composite coupling beam | |
CN202416701U (en) | Combined pre-stressed concrete beam with binder and no binder | |
CN203462572U (en) | Composite floor large cantilever edge beam joint | |
CN201850655U (en) | T-shaped connector for new and old buildings | |
CN202000266U (en) | Supporting structure of bridge coping template | |
CN204022286U (en) | Transfer crane is without corbel type door frame | |
CN205557828U (en) | Big space garret structure | |
CN105095585A (en) | Method for integral collaborative design of anti-floating anchor rod type basement | |
CN204646265U (en) | A kind of tunnel lining trolley truss type formwork stiffener assembly | |
CN104532743A (en) | Tower girder fixed-connection mechanism, corresponding cable-stayed bridge and building method of cable-stayed bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |