CN204343154U CN201420810170.1U CN201420810170U CN204343154U CN 204343154 U CN204343154 U CN 204343154U CN 201420810170 U CN201420810170 U CN 201420810170U CN 204343154 U CN204343154 U CN 204343154U
Authority
CN
China
Prior art keywords
bolt
bridge
crab
steel
junction plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420810170.1U
Other languages
Chinese (zh)
Inventor
罗海燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201420810170.1U priority Critical patent/CN204343154U/en
Application granted granted Critical
Publication of CN204343154U publication Critical patent/CN204343154U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a continuous rigid frame bridge steel tie beam of assembled. The bridge pier comprises anchor bolts (2) which are embedded in the inner sides of two bridge piers (1) and symmetrically arranged, and the anchor bolts are connected with a bearing steel plate (4) through a connecting plate (3). Adopt the technical scheme of the utility model, tie beam and pier junction can not ftracture, have improved the durability of bridge. Additionally, the technical scheme of the utility model also can regard as the interim support in the pier construction, wait that the bridge construction finishes the back and demolish.

Description

A kind of assembling continuous rigid frame bridge steel binder
Technical field
the utility model relates to a kind of assembling continuous rigid frame bridge steel binder, belongs to bridge construction and technical field of construction.
Background technology
prestressed concrete continuous rigid-framed bridge is one of current more common a kind of bridge pattern, the bridge pier of this kind of bridge generally adopts two board-like solid pier of limb or twin legged thin wall hollow pier, for the bridge pier that these are higher, generally steel concrete binder is set between two limbs.
existing binder cross section is generally board-like or case structure.In the process of actual motion, very easily produce crack at steel concrete binder and bridge pier junction, the appearance in crack can reduce the durability of bridge construction.
in addition, in the practice of construction of continuous rigid frame bridge bridge pier, for the bridge pier that some are not very high, binder is not set in design, but for increasing the interim rigidity of bridge pier and support, provisional lateral ties structure need be set between two limb bridge pier, after bridge builds up, then by these interim lateral ties structural demolitions.
Utility model content
the purpose of this utility model is, provides a kind of assembling continuous rigid frame bridge steel binder, to solve the technical problem that existing structure easily produces crack, solves the technical problem arranging interim lateral ties between two limb bridge pier simultaneously.
the technical solution of the utility model:
a kind of assembling continuous rigid frame bridge steel binder, comprise and be embedded in symmetrically arranged crab-bolt inside two bridge piers, crab-bolt is connected with carrying steel plate through junction plate.
in aforementioned steel binder, described crab-bolt is L shape, and one end, long limit of L shape is provided with screw thread, and the minor face of L shape and one section of long limit are embedded in bridge pier, and long limit establishes threaded end to expose bridge pier side to be connected with junction plate through nut.
in aforementioned steel binder, be provided with the crab-bolt of the equidistant horizontal distribution of two rows inside described bridge pier, two row's crab-bolts are symmetrical arranged.
in aforementioned steel binder, described junction plate is steel angle structure, and the two sides of angle steel are equipped with the through hole corresponding with crab-bolt spacing, and the through hole of junction plate side is enclosed within crab-bolt and establishes threaded one end, fixes through nut and bridge pier; Junction plate in two row's crab-bolts is symmetrical fixing back-to-back.
in aforementioned steel binder, described carrying steel plate is rectangle, and the both sides that rectangle is relative are clipped between junction plate fixing on two bridge piers, are fixedly connected with through bolt.
compared with prior art, the utility model provides a kind of standardized continuous rigid frame bridge bridge pier binder structure, and adopt the technical solution of the utility model, can not ftracture in binder and bridge pier junction, improve the durability of bridge.In addition, the technical solution of the utility model also can be used as the temporary support in Bridge Pier Construction, removes after treating bridge construction.
Accompanying drawing explanation
fig. 1 is structural representation of the present invention.
being labeled as in accompanying drawing: 1-bridge pier, 2-crab-bolt, 3-junction plate, 4-carry steel plate, 5-nut, 6-bolt.
Detailed description of the invention
below in conjunction with drawings and Examples, the utility model is described in further detail, but not as to any restriction of the present utility model.
a kind of assembling continuous rigid frame bridge steel binder, as shown in Figure 1, comprise and be embedded in symmetrically arranged crab-bolt 2 inside two bridge piers 1, crab-bolt 2 is connected with carrying steel plate 4 through junction plate 3.Crab-bolt 2 is L shape, and one end, long limit of L shape is provided with screw thread, and the minor face of L shape and one section of long limit are embedded in bridge pier 1, and long limit establishes threaded end to expose bridge pier 1 side to be connected with junction plate 3 through nut 5.Crab-bolt 2, the two row crab-bolt 2 being provided with the equidistant horizontal distribution of two rows inside bridge pier 1 is symmetrical arranged.Junction plate 3 is steel angle structure, and the two sides of angle steel are equipped with the through hole corresponding with crab-bolt 2 spacing, and the through hole of junction plate 3 side is enclosed within crab-bolt 2 and establishes threaded one end, fixes through nut 5 and bridge pier; Junction plate 3 in two row's crab-bolts 2 is symmetrical fixing back-to-back.Carrying steel plate 4 is rectangle, and the both sides that rectangle is relative are clipped between junction plate 3 fixing on two bridge piers 1, are fixedly connected with through bolt 6.
Embodiment
during concrete enforcement, first the tension and compressive resistance that need between continuous rigid frame bridge bridge pier two limb is calculated, the thickness and the width that carry steel plate 4 and junction plate 3 is determined according to result of calculation, and the quantity of cast-in fixing bolt 2 and arrangement, and determine quantity and the arrangement of bolt 5.Then assembled by shown in Fig. 1.
fig. 2 is the application site schematic diagram of the utility model on continuous rigid frame bridge, and in figure, circle labeling position is application site of the present utility model.
be more than embody rule example of the present utility model, do not form any restriction of the present utility model, if one piece carries the bearing capacity that steel plate 4 does not reach designing requirement, multiple carrying steel plate 4 can be set by said structure.All employings are equal to the technical scheme of replacement or equivalent transformation formation, all belong to protection domain of the present utility model.

Claims (5)

1. an assembling continuous rigid frame bridge steel binder, is characterized in that: comprise and be embedded in two bridge piers (1) the symmetrically arranged crab-bolt in inner side (2), crab-bolt (2) is connected with carrying steel plate (4) through junction plate (3).
2. steel binder according to claim 1, it is characterized in that: described crab-bolt (2) is L shape, one end, long limit of L shape is provided with screw thread, the minor face of L shape and one section of long limit are embedded in bridge pier (1), and long limit establishes threaded end to expose bridge pier (1) side to be connected with junction plate (3) through nut (5).
3. steel binder according to claim 2, is characterized in that: described bridge pier (1) inner side is provided with the crab-bolt (2) of the equidistant horizontal distribution of two rows, and two rows' crab-bolt (2) are symmetrical arranged.
4. steel binder according to claim 1, it is characterized in that: described junction plate (3) is steel angle structure, the two sides of angle steel are equipped with the through hole corresponding with crab-bolt (2) spacing, the through hole of junction plate (3) side is enclosed within crab-bolt (2) and establishes threaded one end, fixes through nut (5) and bridge pier; Junction plate (3) on two rows' crab-bolt (2) is symmetrical fixing back-to-back.
5. steel binder according to claim 3, is characterized in that: described carrying steel plate (4) is rectangle, and the both sides that rectangle is relative are clipped between the upper fixing junction plate (3) of two bridge piers (1), are fixedly connected with through bolt (6).
CN201420810170.1U 2014-12-20 2014-12-20 Assembled continuous rigid frame bridge steel tie beam Active CN204343154U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420810170.1U CN204343154U (en) 2014-12-20 2014-12-20 Assembled continuous rigid frame bridge steel tie beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420810170.1U CN204343154U (en) 2014-12-20 2014-12-20 Assembled continuous rigid frame bridge steel tie beam

Publications (1)

Publication Number Publication Date
CN204343154U true CN204343154U (en) 2015-05-20

Family

ID=53226432

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420810170.1U Active CN204343154U (en) 2014-12-20 2014-12-20 Assembled continuous rigid frame bridge steel tie beam

Country Status (1)

Country Link
CN (1) CN204343154U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110700105A (en) * 2019-10-21 2020-01-17 中交一公局第七工程有限公司 Synchronous construction method for high pier column and tie beam and template used in same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110700105A (en) * 2019-10-21 2020-01-17 中交一公局第七工程有限公司 Synchronous construction method for high pier column and tie beam and template used in same

Similar Documents

Publication Publication Date Title
CN203145194U (en) Internal diaphragm joint of variable flange steel I-beam and square concrete filled steel tubular column
CN103993753B (en) Tradition stone-made house angle hoop drawknot hardened system and construction technology
CN104831627A (en) Bridge deck slab longitudinal unequal strength steel-concrete composite structure bridge and construction method thereof
CN204081079U (en) A kind of structure of open pore steel plate shear force
CN203559354U (en) Stay cable anchoring structure applied to prestressed concrete partially cable-stayed bridge
CN205242238U (en) Be applied to self anchored suspension bridge's main girder structure
CN204343154U (en) Assembled continuous rigid frame bridge steel tie beam
CN205296966U (en) Transmission line iron tower
CN103510521A (en) Connecting component
CN104265005B (en) The back ruggedized construction that a kind of steel plate combines with reinforcing bar
CN203514323U (en) Connection component
CN202689585U (en) Ground fitting up assembly mould of large steel truss
CN204000562U (en) The compound rigid frame bridge of a kind of vertical prestressing steel-concrete
CN204238095U (en) A kind of interlace mode that adopts is arranged on dowel bar assembly on airport rigid pavement plate
CN204401829U (en) RPC compound shear wall is filled out in a kind of encased steel plate
CN104818800A (en) Fabricated steel-concrete composite coupling beam
CN202416701U (en) Combined pre-stressed concrete beam with binder and no binder
CN203462572U (en) Composite floor large cantilever edge beam joint
CN201850655U (en) T-shaped connector for new and old buildings
CN202000266U (en) Supporting structure of bridge coping template
CN204022286U (en) Transfer crane is without corbel type door frame
CN205557828U (en) Big space garret structure
CN105095585A (en) Method for integral collaborative design of anti-floating anchor rod type basement
CN204646265U (en) A kind of tunnel lining trolley truss type formwork stiffener assembly
CN104532743A (en) Tower girder fixed-connection mechanism, corresponding cable-stayed bridge and building method of cable-stayed bridge