CN204327150U - A kind of tunnel airduct working vehicle - Google Patents

A kind of tunnel airduct working vehicle Download PDF

Info

Publication number
CN204327150U
CN204327150U CN201420666390.1U CN201420666390U CN204327150U CN 204327150 U CN204327150 U CN 204327150U CN 201420666390 U CN201420666390 U CN 201420666390U CN 204327150 U CN204327150 U CN 204327150U
Authority
CN
China
Prior art keywords
airduct
car body
bore
side shield
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420666390.1U
Other languages
Chinese (zh)
Inventor
介艳良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Kuoli Mechanical and Electrical Technology Co Ltd
Original Assignee
Xian Kuoli Mechanical and Electrical Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Kuoli Mechanical and Electrical Technology Co Ltd filed Critical Xian Kuoli Mechanical and Electrical Technology Co Ltd
Priority to CN201420666390.1U priority Critical patent/CN204327150U/en
Application granted granted Critical
Publication of CN204327150U publication Critical patent/CN204327150U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ventilation (AREA)

Abstract

The utility model discloses a kind of tunnel airduct working vehicle, comprise car body, be arranged on the walking mechanism of vehicle bottom, be arranged on side shield on the left of car body and two airduct guiding mechanisms be installed on the right side of car body top, side shield is that side shield is fixedly mounted on the left side wall of car body by former and later two caging bolts in the vertical rectangular flat to laying; Airduct guiding mechanism comprises former and later two airducts be installed on the right side of car body top to be fixed and bore governor motion, two airducts fix and the structure of bore governor motion identical; Adjust flexible duct and be clamped in side shield and two airducts are fixed and between bore governor motion; Two airducts are fixed and spacing between bore governor motion is 20 ~ 60cm.The utility model structure simple, reasonable in design and use easy and simple to handle, result of use good, while normal ventilation, can adjust airduct caliber size, can carry out easy adjustment again to the installation position of installation airduct.

Description

A kind of tunnel airduct working vehicle
Technical field
The utility model belongs to tunnel ventilation construction technical field, especially relates to a kind of tunnel airduct working vehicle.
Background technology
At present, the draft type that domestic and international construction ventilation of tunnel adopts pipeline forced mostly, outside hole, axial flow blower is set, fresh air is delivered to tunnel work face by coupled ventilating duct (i.e. flexible duct) by this axial flow blower, foul atmosphere in hole, under the squeezing action sending into fresh air in hole, drains into outside hole along the barrel excavated.When tunnel is longer, adopt multiple axial flow blower also, series connection mode to improve air quantity and air supplying distance.
But nowadays, when above-mentioned blower fan and ventilating duct are constructed, what the overwhelming majority all adopted is artificial construction's mode, for major long tunnel, site work amount is very large, needs first to install flexible duct and moves into place, again the airduct moved into place is fixed on piecemeal along on multiple airduct fixtures of longitudinal extension direction, tunnel laying, the required manpower and materials dropped into are many, take time and effort, had a strong impact on the efficiency of construction in tunnel.Thus, in practice of construction process, when existing tunnel construction flexible duct is installed, there is number of drawbacks and the deficiencies such as the manpower and materials of large, the required input of site work amount are more, efficiency of construction is low.In addition, in practice of construction process, flexible duct in tunnel is once after installation, and its position generally can not be moved easily, and flexible duct people is laid in the middle and upper part of side sidewall in tunnel usually, and the wind direction that such flexible duct is blown generally also immobilizes.
But during practice of construction, because explosion in hole is larger with the concentration of transporting blasting fume and the pernicious gas produced after explosion terminates, thus if adjust the mouth of pipe size of flexible duct, then can when air output be constant, the wind speed size of the flexible duct mouth of pipe is adjusted accordingly, thus the blasting fume near face and pernicious gas are discharged outside hole fast.Further, in practice of construction process, for meeting concrete ventilation requirement, the position of frequent needs to installation airduct adjusts temporarily, now needs to remove original airduct fixture, and reinstall airduct fixture on tunnel inside wall, waste time and energy, serious image constructing tunnel efficiency.Thus, nowadays a kind of structure is lacked simple, reasonable in design and use easy and simple to handle, that result of use is good tunnel airduct working vehicle, while normal ventilation, can adjust airduct caliber size, easy adjustment can be carried out to the installation position of installation airduct again.
Utility model content
Technical problem to be solved in the utility model is for above-mentioned deficiency of the prior art, a kind of tunnel airduct working vehicle is provided, its structure simple, reasonable in design and use easy and simple to handle, result of use good, while normal ventilation, can adjust airduct caliber size, easy adjustment can be carried out to the installation position of installation airduct again.
For solving the problems of the technologies described above, the technical solution adopted in the utility model is: a kind of tunnel airduct working vehicle, it is characterized in that: comprise car body, be arranged on the walking mechanism of vehicle bottom, to be arranged on the left of car body and can the side shield of oscilaltion and two to be installed on the right side of car body top and with side shield with the use of airduct guiding mechanism, described side shield is that described side shield is fixedly mounted on the left side wall of car body by former and later two caging bolts in the vertical rectangular flat to laying; Described side shield has two respectively for the first installing hole that two described caging bolts are installed, the left side wall of described car body being provided with front and back two arranges respectively for the second installing hole that two described caging bolts are installed, often arrange on described second installing hole and include multiple the second installing hole laid from top to bottom, described first installing hole and the second installing hole are circular hole; Described airduct guiding mechanism comprises former and later two airducts be installed on the right side of car body top to be fixed and bore governor motion, two described airducts fix and the structure of bore governor motion identical; Adjust flexible duct and be clamped in side shield and two described airducts are fixed and between bore governor motion; Two described airducts are fixed and spacing between bore governor motion is 20cm ~ 60cm;
Described airduct is fixed and bore governor motion comprises horizontal base, be arranged on the vertical pole on horizontal base, be arranged on the rotary support on vertical pole top, the arc be installed on the right side of adjusted flexible duct clamps frame, with be laid in arc and clamp arc pressuring plate inside frame, described arc clamps on frame and is provided with multiple inner thread sleeve laid in level, on described arc pressuring plate, corresponding being provided with multiplely is used in combination with multiple described inner thread sleeve respectively and can carries out the threaded rod that moves forward and backward in inner thread sleeve, multiple described inner thread sleeve is from top to bottom laid, and multiple described inner thread sleeve and multiple described threaded rod are all in parallel laying, the quantity of multiple described threaded rod is identical with the quantity of multiple described inner thread sleeve, and the installation position of multiple described threaded rod respectively with the installation position one_to_one corresponding of multiple described inner thread sleeve, be connected in hinged way between described rotary support with vertical pole.
Above-mentioned a kind of tunnel airduct working vehicle, is characterized in that: the length of described side shield is 30cm ~ 100cm.
Above-mentioned a kind of tunnel airduct working vehicle, is characterized in that: the quantity of described inner thread sleeve and threaded rod is two.
Above-mentioned a kind of tunnel airduct working vehicle, is characterized in that: the cross section of described vertical pole is rectangle, and the cross section of described horizontal base is concave shape, and is installed in horizontal base bottom described vertical pole.
Above-mentioned a kind of tunnel airduct working vehicle, is characterized in that: described horizontal base is channel-section steel.
Above-mentioned a kind of tunnel airduct working vehicle, is characterized in that: described walking mechanism comprises multiple universal wheel being installed in vehicle bottom.
The utility model compared with prior art has the following advantages:
1, structure is simple and reasonable in design, and input cost is low, and installation is laid easy.
2, use simple to operate and result of use good, can adjust airduct caliber size, easy adjustment can be carried out to the installation position of installation airduct again, and tunnel internal can not be affected normally ventilate.
In sum, the utility model structure simple, reasonable in design and use easy and simple to handle, result of use good, while normal ventilation, can adjust airduct caliber size, can carry out easy adjustment again to the installation position of installation airduct.
Below by drawings and Examples, the technical solution of the utility model is described in further detail.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the right view of Fig. 1.
Description of reference numerals:
1-car body; 2-side shield; 3-caging bolt;
4-horizontal base; 5-vertical pole; 6-arc clamps frame;
7-arc pressuring plate; 8-inner thread sleeve; 9-threaded rod;
10-rotary support; 11-universal wheel.
Detailed description of the invention
As shown in Figure 1 and Figure 2, the utility model comprises car body 1, be arranged on walking mechanism bottom car body 1, to be arranged on the left of car body 1 and can the side shield 2 of oscilaltion and two be installed in car body 1 top right side and with side shield 2 with the use of airduct guiding mechanism, described side shield 2 is that described side shield 2 is fixedly mounted on the left side wall of car body 1 by former and later two caging bolts 3 in the vertical rectangular flat to laying.Described side shield 2 has two respectively for the first installing hole that two described caging bolts 3 are installed, the left side wall of described car body 1 being provided with front and back two arranges respectively for the second installing hole that two described caging bolts 3 are installed, often arrange on described second installing hole and include multiple the second installing hole laid from top to bottom, described first installing hole and the second installing hole are circular hole; Described airduct guiding mechanism comprises former and later two airducts being installed in car body 1 top right side to be fixed and bore governor motion, two described airducts fix and the structure of bore governor motion identical.Adjust flexible duct and be clamped in side shield 2 and two described airducts are fixed and between bore governor motion.Two described airducts are fixed and spacing between bore governor motion is 20cm ~ 60cm.
Described airduct is fixed and bore governor motion comprises horizontal base 4, be arranged on the vertical pole 5 on horizontal base 4, be arranged on the rotary support 10 on vertical pole 5 top, the arc be installed on the right side of adjusted flexible duct clamps frame 6, with be laid in arc and clamp arc pressuring plate 7 inside frame 6, described arc clamps on frame 6 and is provided with multiple inner thread sleeve 8 laid in level, on described arc pressuring plate 7, corresponding being provided with multiplely is used in combination with multiple described inner thread sleeve 8 respectively and can carries out the threaded rod 9 that moves forward and backward in inner thread sleeve 8, multiple described inner thread sleeve 8 is from top to bottom laid, and multiple described inner thread sleeve 8 and multiple described threaded rod 9 are all in parallel laying.The quantity of multiple described threaded rod 9 is identical with the quantity of multiple described inner thread sleeve 8, and the installation position of multiple described threaded rod 9 respectively with the installation position one_to_one corresponding of multiple described inner thread sleeve 8.Be connected in hinged way between described rotary support 10 with vertical pole 5.
In the present embodiment, the length of described side shield 2 is 30cm ~ 100cm.
Actual when using, can according to specific needs, two described airducts to be fixed and the length of spacing between bore governor motion and described side shield 2 adjusts accordingly.
In the present embodiment, the quantity of described inner thread sleeve 8 and threaded rod 9 is two.
In the present embodiment, the cross section of described vertical pole 5 is rectangle, and the cross section of described horizontal base 4 is concave shape, and is installed in horizontal base 4 bottom described vertical pole 5.
Further, described horizontal base 4 is channel-section steel.
In the present embodiment, described walking mechanism comprises multiple universal wheel 11 be installed in bottom car body 1.
The above; it is only preferred embodiment of the present utility model; not the utility model is imposed any restrictions; every above embodiment is done according to the utility model technical spirit any simple modification, change and equivalent structure change, all still belong in the protection domain of technical solutions of the utility model.

Claims (6)

1. a tunnel airduct working vehicle, it is characterized in that: comprise car body (1), be arranged on the walking mechanism of car body (1) bottom, be arranged on car body (1) left side and can the side shield (2) of oscilaltion and two be installed in car body (1) top right side and with side shield (2) with the use of airduct guiding mechanism, described side shield (2) is that described side shield (2) is fixedly mounted on the left side wall of car body (1) by former and later two caging bolts (3) in the vertical rectangular flat to laying; Described side shield (2) has two the first installing holes supplying two described caging bolts (3) to install respectively, the left side wall of described car body (1) is provided with front and back two and arranges the second installing hole supplying two described caging bolts (3) to install respectively, often arrange on described second installing hole and include multiple the second installing hole laid from top to bottom, described first installing hole and the second installing hole are circular hole; Described airduct guiding mechanism comprises former and later two airducts being installed in car body (1) top right side to be fixed and bore governor motion, two described airducts fix and the structure of bore governor motion identical; Adjust flexible duct and be clamped in side shield (2) and two described airducts are fixed and between bore governor motion; Two described airducts are fixed and spacing between bore governor motion is 20cm ~ 60cm;
Described airduct is fixed and bore governor motion comprises horizontal base (4), be arranged on the vertical pole (5) on horizontal base (4), be arranged on the rotary support (10) on vertical pole (5) top, the arc be installed on the right side of adjusted flexible duct clamps frame (6), with be laid in arc clamp frame (6) inner side arc pressuring plate (7), described arc clamps on frame (6) and is provided with multiple inner thread sleeve (8) laid in level, the upper correspondence of described arc pressuring plate (7) is provided with and is multiplely used in combination with multiple described inner thread sleeve (8) respectively and can carries out the threaded rod (9) that moves forward and backward in inner thread sleeve (8), multiple described inner thread sleeve (8) is from top to bottom laid, and multiple described inner thread sleeve (8) and multiple described threaded rod (9) are all in parallel laying, the quantity of multiple described threaded rod (9) is identical with the quantity of multiple described inner thread sleeve (8), and the installation position of multiple described threaded rod (9) respectively with the installation position one_to_one corresponding of multiple described inner thread sleeve (8), be connected in hinged way between described rotary support (10) with vertical pole (5).
2. according to a kind of tunnel according to claim 1 airduct working vehicle, it is characterized in that: the length of described side shield (2) is 30cm ~ 100cm.
3., according to a kind of tunnel airduct working vehicle described in claim 1 or 2, it is characterized in that: the quantity of described inner thread sleeve (8) and threaded rod (9) is two.
4. according to a kind of tunnel airduct working vehicle described in claim 1 or 2, it is characterized in that: the cross section of described vertical pole (5) is rectangle, the cross section of described horizontal base (4) is concave shape, and described vertical pole (5) bottom is installed in horizontal base (4).
5., according to a kind of tunnel according to claim 4 airduct working vehicle, it is characterized in that: described horizontal base (4) is channel-section steel.
6. according to a kind of tunnel airduct working vehicle described in claim 1 or 2, it is characterized in that: described walking mechanism comprises multiple universal wheel (11) being installed in car body (1) bottom.
CN201420666390.1U 2014-11-10 2014-11-10 A kind of tunnel airduct working vehicle Expired - Fee Related CN204327150U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420666390.1U CN204327150U (en) 2014-11-10 2014-11-10 A kind of tunnel airduct working vehicle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420666390.1U CN204327150U (en) 2014-11-10 2014-11-10 A kind of tunnel airduct working vehicle

Publications (1)

Publication Number Publication Date
CN204327150U true CN204327150U (en) 2015-05-13

Family

ID=53163522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420666390.1U Expired - Fee Related CN204327150U (en) 2014-11-10 2014-11-10 A kind of tunnel airduct working vehicle

Country Status (1)

Country Link
CN (1) CN204327150U (en)

Similar Documents

Publication Publication Date Title
CN100595420C (en) Pressure regulating and distributing chamber ventilation construction method inside tunnel assist drift heading hole
CN205858397U (en) Inclined shaft and positive hole ventilating system in constructing tunnel
CN204327150U (en) A kind of tunnel airduct working vehicle
CN202090939U (en) Ventilating house
CN209212274U (en) A kind of ventilation of underground mine tunnelling and dust removal integrated plant
CN105569705A (en) Tunnel air duct construction operating vehicle
CN104627746A (en) Automatic flexible air duct winding and unwinding device based on hydraulic lifting support
CN204312113U (en) A kind of flexible duct wind speed and direction self-checking device
CN206678296U (en) A kind of injecting machine material tube Aeroassisted blanking device
CN204312115U (en) A kind of flexible duct wind direction comprehensive regulation system
CN204312110U (en) A kind of flexible duct Wind direction regulating mechanism
CN104405428A (en) Mobile ventilating device applied to tunnel pavement construction
CN102392675B (en) Method and device for collecting ventilation air methane on top of diffuser of main fan of coal mine
CN207289249U (en) A kind of numerical control cutting machine lathe longitudinal direction dust-removing device
CN203531946U (en) Pipe opening size automatic adjusting device of automatic moving type flexible air pipe for tunnel construction
CN204327193U (en) A kind of constructing tunnel ventilation state monitoring robot
CN204312114U (en) A kind of packaged type flexible duct mouth of pipe wind direction adjusting bracket
CN204327149U (en) Based on the online regulator control system in tunnel ventilation path of automatic adjustment rack
CN205578024U (en) A dust collector for tunnel
CN203798145U (en) Dehumidification waste gas exhaust system for tunnel kiln
CN214330669U (en) Hyperbolic pipeline air duct for tunnel engineering
CN205116382U (en) Prefabricated pump station of integration with deodorizing device
CN204342193U (en) A kind of tunnel ventilation Pipe installing chassis
CN218117823U (en) Ventilation device for long-distance double-side-wall pit guiding method of underground excavation section of subway
CN202618233U (en) Material-collecting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150513

Termination date: 20151110

EXPY Termination of patent right or utility model