CN204311435U - One is revolved and is dug occlusion steel concrete impervious wall - Google Patents

One is revolved and is dug occlusion steel concrete impervious wall Download PDF

Info

Publication number
CN204311435U
CN204311435U CN201420391698.XU CN201420391698U CN204311435U CN 204311435 U CN204311435 U CN 204311435U CN 201420391698 U CN201420391698 U CN 201420391698U CN 204311435 U CN204311435 U CN 204311435U
Authority
CN
China
Prior art keywords
stake
grouting
cage
reinforcement
occlusion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420391698.XU
Other languages
Chinese (zh)
Inventor
周祖茂
黄华
李文武
朱晓波
李明
范元虎
王礼才
张山金
李伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Is Huge Can Construction Group Road And Bridge Engineering Co Ltd
Original Assignee
Chongqing Is Huge Can Construction Group Road And Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Is Huge Can Construction Group Road And Bridge Engineering Co Ltd filed Critical Chongqing Is Huge Can Construction Group Road And Bridge Engineering Co Ltd
Priority to CN201420391698.XU priority Critical patent/CN204311435U/en
Application granted granted Critical
Publication of CN204311435U publication Critical patent/CN204311435U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

One is revolved and is dug occlusion steel concrete impervious wall, comprises mud off Spiral digging machine porous apart from jumping hole pore-creating, conduit underwater concreting, interlocking pile cage of reinforcement retainer ring, pre-buried pair of grouting pipe grouting behind shaft or drift lining.First adopt Spiral digging machine mud off porous apart from the stake of jumping hole pore-creating φ 800mm ~ 1000mm, 100mm is engaged between stake, embed rock stratum and be not less than 3 times of stake footpaths, first adopt the stake of tremie method underwater grouting odd number, reach after 15Mpa until concrete strength and carry out even number stake (i.e. interlocking pile) construction again.Cage of reinforcement is increased during interlocking pile construction, fix the two welded tube of pre-buried grouting φ 50mm at cage of reinforcement, welded tube adopts retainer ring to fix, and Grouting Pipe bores extravasating hole every 500mm, reach until concrete strength the cement paste noting admixture permeability-reducing admixture after 20Mpa, to be two-tubely in the milk simultaneously.This impervious wall good rigidity, anti-seepage effect is good, and speed of application is fast, can save the engineering time, ensures construction speed.

Description

One is revolved and is dug occlusion steel concrete impervious wall
[technical field]
The utility model relates to one and revolves and dig occlusion steel concrete impervious wall.
[background technology]
Impervious wall be by special to dig, jet-bedding equipment, periphery along underground building presses preposition, slurry-supported excavation or drill is utilized to go out the groove of one fixed width and the degree of depth, and the cage of reinforcement with certain rigidity is set in groove, with special method joint subsection catheter perfusion underwater concrete, make it to be formed that integrally closed encloses descend reinforced concrete wall continuously, in building foundation pit, have that gear is native, the double effect etc. of bearing top-out load of percolation-proof.Drilling hole bored concrete pile technology is an important technical innovation of construction foundation working method, effectively solve the construction problem of underwater foundation, underwater operation is changed into and carries out on the water, its Technological Economy superiority is very outstanding, applied widely in the Foundation Design of the systems such as national urban construction, railway, highway, water conservancy, but it is more outstanding to seep water between stake, become wall vertical bury pipe precision not high, anti-seepage effect is undesirable; Also to have in water conservancy and hydropower project and increase curtain grouting, but construction costs is higher.
[summary of the invention]
The purpose of this utility model is to provide one can rapid construction impervious wall, solves the anti-seepage effect existed in prior art bad, the technical problems such as inefficiency, and reduces operating expenses, ensure that construction speed.
The utility model is characterised in that: comprise stake, cage of reinforcement, retainer ring, Grouting Pipe, Grouting Pipe is positioned at occlusion place; Stake adopts mud off pore-creating to be formed, and aperture is the stake of φ 800mm ~ 1000mm, occlusion distance 100mm, i.e. pile center's spacing 700 ~ 900mm, embeds rock stratum and is not less than 3 times of stake footpaths; Stake adopts Spiral digging machine porous to construct apart from jumping hole mode, subdrilling odd-numbered stake holes, the stake of tremie method underwater grouting odd-numbered, reach after 15Mpa until concrete strength and carry out even number stake (i.e. interlocking pile) construction again, cage of reinforcement is increased during this even-numbered pile driving construction, cage of reinforcement fixes the two Grouting Pipe of pre-buried φ 50mm with retainer ring, Grouting Pipe bores extravasating hole every 500mm, reach after 20Mpa until concrete strength, the cement paste that two Grouting Pipe notes admixture permeability-reducing admixture is simultaneously formed to revolve and digs occlusion steel concrete impervious wall.
The utility model comprises mud off Spiral digging machine porous apart from jumping hole pore-creating, conduit underwater concreting, interlocking pile cage of reinforcement retainer ring, pre-buried pair of grouting pipe grouting behind shaft or drift lining.First adopt Spiral digging machine to make stake holes according to design attitude mud off, stake footpath φ 800 ~ 1000mm, occlusion distance is 100mm, embeds rock stratum and is not less than 3 times of stake footpaths.Stake adopts porous to construct apart from jumping hole mode, subdrilling odd-numbered is 1., 5., 9. ... stake, bore odd-numbered more 3., 7. ... stake, tremie method underwater grouting, reach until concrete strength and after 15Mpa, to carry out even-numbered stake (i.e. interlocking pile) construction again.Cage of reinforcement is increased, interlocking pile stake footpath φ 800 ~ 1000mm, every side occlusion 100mm during interlocking pile construction, cage of reinforcement is arranged in occlusion place, and main muscle adopts φ 20 indented bars, and hoop muscle adopts φ 20 indented bars stiffening ring, spacing 1 meter, and every spacing 1 meter increases the cross hang of φ 20 indented bars.Skeleton stiffening ring coils with φ 8 annulus of circle weld diameter φ 60mm, and pre-buried φ 50mm Grouting Pipe is fixed through annulus.Grouting Pipe bores extravasating hole every 500mm, extravasating hole diameter 10mm, the cement paste noting admixture permeability-reducing admixture after 20Mpa is reached until concrete strength, be in the milk with the cement paste of water/binder ratio 0.6, each occlusal area is two-tube to be in the milk simultaneously, and grouting initial pressure 0.2 ~ 0.3mpa, terminates pressure 0.35 ~ 0.5mpa, voltage stabilizing 10min midge amount is unchanged, can terminate grouting.
Needed for Spiral digging machine pore-creating, place scope is little, and maneuverability does not limit by landform, and construction can rapid deployment.Interlocking pile increases cage of reinforcement, adds impervious wall integral rigidity, can effectively prevent leakage proof wall from ftractureing, because jumping hole mounting framework, cost-saving.Rotary drilling rig is digital control system keyhole vertical bury pipe, and can adjust correction in time according to instrument board display data at any time in boring procedure, pore-forming vertical bury pipe precision can reach within 3 ‰, can meet the technical requirements of interlocking pile occlusion thickness qualities completely; Changing interlocking pile utilizes the adjacent studs concrete initial set time difference to realize the traditional handicraft of occlusion, hard patterning method is adopted to construct, the thick hot-tempered face utilizing rotary drilling rig pore-forming formerly to pour into pile lining formation is engaged, without the need to relying on the requirement of traditional handicraft to the concrete extra retarded set time, avoid " piping " accident occurs.
In occlusion place pre-buried pair of Grouting Pipe, post jacking, ensure that the compactness of occlusion place, further enhancing impervious effect.
The utility model compared with the prior art, owing to adopting Spiral digging machine pore-creating, reduce the working strength of construction operation personnel, improve boring precision, save the engineering time, improve operating efficiency, built-in slip casting pipe slip casting improves anti-seepage effect, and the utility model can be widely used in the short bridge pile foundation cofferdam of construction period, riverine, river, lake, sea deep foundation ditch near water, the foundation pit construction that groundwater table is higher, water conservancy and hydropower material for diaphragm wall of Cofferdam is constructed.
[accompanying drawing explanation]
Fig. 1 originally revolves to dig occlusion steel concrete impervious wall construction artwork
Fig. 2 originally revolves to dig occlusion steel concrete impervious wall plane, generalized section
Fig. 3 originally revolves to dig occlusion steel concrete impervious wall retainer ring schematic diagram
Fig. 4 originally revolves to dig occlusion steel concrete impervious wall built-in slip casting pipe schematic diagram
I-revolves and digs odd-numbered 1., 5., 9. ... hole is also poured into plain concrete II-and revolved and dig odd-numbered hole 3., 7. ... hole is also poured into plain concrete III-and ensured that occlusion distance is revolved and dig even hole IV-and transfer the reinforcing cage that is fixed with grout pipe and concrete perfusion V-is in the milk
1-odd number stake 2-even number stake 3-Grouting Pipe 4-interlocking pile reinforcing cage 5-cage of reinforcement stiffening ring 6-retainer ring 7-extravasating hole
[detailed description of the invention]
Dig occlusion steel concrete impervious wall below in conjunction with accompanying drawing be described in further detail originally revolving.
As shown in Figure 1, originally revolve and dig occlusion steel concrete impervious wall and comprise five large steps, step I: revolve and dig very
Number numbering 1., 5., 9. ... stake and pour into plain concrete; Step II: revolve and dig odd-numbered hole 3., 7. ... plain concrete is also poured in hole; Step II I: ensure that occlusion distance is revolved and dig even hole; Step IV: transfer the reinforcing cage concrete perfusion that are fixed with grout pipe; Step V: grouting.Tell described in the utility model revolving in detail below in conjunction with Fig. 1, Fig. 2, Fig. 3, Fig. 4 and dig occlusion steel concrete impervious wall construction activities.
Step I: carry out smooth to place, adopts Spiral digging machine to make stake holes according to design attitude mud off, stake footpath φ 800 ~ 1000mm, embeds rock stratum and is not less than 3 times of stake footpaths.Stake adopts jumps hole mode and constructs, and subdrilling odd number stake numbering is 1., 5., 9. ... stake, stake footpath φ 800 ~ 1000mm, tremie method underwater grouting plain concrete.Step II: revolve dig odd number stake numbering 3., 7. ... stake, stake footpath φ 800 ~ 1000mm, tremie method underwater grouting plain concrete.Step II I: carry out even-numbered stake 2 again and construct after odd number stake 1 concrete strength reaches 15Mpa, stake footpath φ 800 ~ 1000mm, revolves when digging and guarantees that occlusion distance in every side is 100mm, suitably slow down the speed of digging of revolving, strict Survey control center line, prevent stake tiltedly biased.Step IV: the vertical main muscle of cage of reinforcement adopts φ 20 reinforcing bar, and arrange 10 altogether, hoop stiffening ring 5 adopts φ 20 rebar spacing 1 meter, and every spacing 1 meter increases the cross hang of φ 20 reinforcing bar; Located by the retainer ring 6 on cage of reinforcement stiffening ring 5 by φ 50 grout pipe 3, fix grout pipe further simultaneously by tied silk, Grouting Pipe bores extravasating hole 7 every 500mm, extravasating hole diameter 10mm; Note the position of grout pipe when transferring reinforcing cage, what grout pipe 3 was arranged in odd number stake 1 and even number stake 2 is engaged place; Placement of cage of reinforcing bar acceptance(check) rear tube method underwater grouting.Step V: the cement paste noting admixture permeability-reducing admixture after even number stake 2 concrete strength reaches 20Mpa, be the cement paste of 0.6 with water/binder ratio, grouting initial pressure 0.2 ~ 0.3mpa, terminates pressure 0.35 ~ 0.5mpa, voltage stabilizing 10min midge amount is unchanged, can terminate grouting.
Be understandable that, above embodiment is only used to illustrate and originally revolves the technological principle digging occlusion steel concrete impervious wall and the illustrative embodiments adopted, but the utility model is not limited thereto.For those skilled in the art, when not departing from spirit of the present utility model and essence, can make various modification and improvement, these modification and improvement are also considered as protection domain of the present utility model.

Claims (1)

1. revolve and dig an occlusion steel concrete impervious wall, it is characterized in that: comprise stake, cage of reinforcement, retainer ring, Grouting Pipe, Grouting Pipe is positioned at stake occlusion place; Stake adopts mud off pore-creating to be formed, and aperture is the stake of φ 800mm ~ 1000mm, and occlusion distance is 100mm, i.e. pile center's spacing 700 ~ 900mm, embeds rock stratum and is not less than 3 times of stake footpaths; Stake adopts Spiral digging machine porous to construct apart from jumping hole mode, subdrilling odd-numbered stake holes, the stake of tremie method underwater grouting odd-numbered, reach after 15Mpa until concrete strength and carry out even number pile driving construction again, increase cage of reinforcement during this even-numbered pile driving construction, cage of reinforcement fixes the two Grouting Pipe of pre-buried φ 50mm with retainer ring, and Grouting Pipe bores extravasating hole every 500mm, reach after 20Mpa until concrete strength, the cement paste that two Grouting Pipe notes admixture permeability-reducing admixture is simultaneously formed to revolve and digs occlusion steel concrete impervious wall.
CN201420391698.XU 2014-07-16 2014-07-16 One is revolved and is dug occlusion steel concrete impervious wall Active CN204311435U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420391698.XU CN204311435U (en) 2014-07-16 2014-07-16 One is revolved and is dug occlusion steel concrete impervious wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420391698.XU CN204311435U (en) 2014-07-16 2014-07-16 One is revolved and is dug occlusion steel concrete impervious wall

Publications (1)

Publication Number Publication Date
CN204311435U true CN204311435U (en) 2015-05-06

Family

ID=53133759

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420391698.XU Active CN204311435U (en) 2014-07-16 2014-07-16 One is revolved and is dug occlusion steel concrete impervious wall

Country Status (1)

Country Link
CN (1) CN204311435U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089062A (en) * 2015-08-17 2015-11-25 陕西桩鑫建设工程有限公司 Engaged retaining pile and construction method and application thereof
CN108035346A (en) * 2018-01-11 2018-05-15 国家电网公司 A kind of severely-weathered ground anchor basis in Tibet, which is jumped, breaks into hole system and method
CN110872842A (en) * 2019-11-27 2020-03-10 甘肃建投建设有限公司 Saturated sand rock stratum occlusive water-stop pile supporting system and construction method thereof
CN113026688A (en) * 2021-02-08 2021-06-25 中国水电基础局有限公司 System for expanding piles to form wall by using foundation rocks at bottom of concrete guide wall foundation
CN115434282A (en) * 2022-08-31 2022-12-06 东莞市水利勘测设计院有限公司 Composite type diaphragm wall for hydraulic engineering and construction method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089062A (en) * 2015-08-17 2015-11-25 陕西桩鑫建设工程有限公司 Engaged retaining pile and construction method and application thereof
CN105089062B (en) * 2015-08-17 2016-08-17 陕西桩鑫建设工程有限公司 It is engaged lagging pile and construction method thereof and application
CN108035346A (en) * 2018-01-11 2018-05-15 国家电网公司 A kind of severely-weathered ground anchor basis in Tibet, which is jumped, breaks into hole system and method
CN110872842A (en) * 2019-11-27 2020-03-10 甘肃建投建设有限公司 Saturated sand rock stratum occlusive water-stop pile supporting system and construction method thereof
CN113026688A (en) * 2021-02-08 2021-06-25 中国水电基础局有限公司 System for expanding piles to form wall by using foundation rocks at bottom of concrete guide wall foundation
CN113026688B (en) * 2021-02-08 2022-04-22 中国水电基础局有限公司 System for expanding piles to form wall by using foundation rocks at bottom of concrete guide wall foundation
CN115434282A (en) * 2022-08-31 2022-12-06 东莞市水利勘测设计院有限公司 Composite type diaphragm wall for hydraulic engineering and construction method thereof
CN115434282B (en) * 2022-08-31 2023-08-15 东莞市水利勘测设计院有限公司 Composite type impervious wall for hydraulic engineering and construction method thereof

Similar Documents

Publication Publication Date Title
CN204311435U (en) One is revolved and is dug occlusion steel concrete impervious wall
CN103981898B (en) A kind of inverse underground engineering construction method done of overall open cut node
CN204370431U (en) A kind of occlusion long-short pile space enclosing structure
CN103422501B (en) Anti-floating anchor rod structure in sand seam geology and construction method thereof
CN103726495B (en) Coastal waters deep foundation pit supporting structure and construction method thereof
CN107386285A (en) A kind of novel steel tube pile foundation rock borehole anchorage method
CN103422510B (en) Steel pipe frame type cofferdam structure and construction method
CN104612179B (en) Through the construction method of the diaphram wall of super thick silty sand ground
CN101205721A (en) Method for surrounding water by combination of steel cofferdam and heavy-pressure rotary-spraying pile in deep-water low-pile cap construction
CN103114609A (en) Connection device of new and old underground diaphragm walls and construction method
CN202194149U (en) Water-proof curtain
CN108677926A (en) Coercion underground continuous wall and its construction method
CN106869138A (en) A kind of load retaining wall Retaining Structure with Double-row Piles and its foundation ditch excavation method
CN106758759B (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN103485347A (en) Batter pile used for building foundation pit support and construction method thereof
CN104947697A (en) Construction method for rapidly enclosing weir by utilizing Larsen steel sheet piles
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN102635126B (en) Method for constructing casting well for aluminum alloy hot-rolled sheet ingots
CN108179759A (en) The underwater drill core slotting of driftway is without bottom sealing method
CN201459708U (en) Rotatable multi-shaft drill hole irrigation concrete occlusion guard post wall
CN206477240U (en) A kind of trestle pile foundation for deep water drift net riverbed
CN206928281U (en) Pretensioning prestressed concrete porous hollow ecology stake
CN203475453U (en) Deeply-buried type bearing platform curtain structure of bridge
CN201172826Y (en) Deep base pit enclosure wall earth-blocking reinforced structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant