CN204282860U - Interim board house bracing means - Google Patents

Interim board house bracing means Download PDF

Info

Publication number
CN204282860U
CN204282860U CN201420698245.1U CN201420698245U CN204282860U CN 204282860 U CN204282860 U CN 204282860U CN 201420698245 U CN201420698245 U CN 201420698245U CN 204282860 U CN204282860 U CN 204282860U
Authority
CN
China
Prior art keywords
steel pipe
wire rope
board house
bracing means
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420698245.1U
Other languages
Chinese (zh)
Inventor
洪辉
税远明
王冬冬
陈浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201420698245.1U priority Critical patent/CN204282860U/en
Application granted granted Critical
Publication of CN204282860U publication Critical patent/CN204282860U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model interim board house bracing means relates to a kind of device for the reinforcing to board house interim under coastal typhoon environment.Its objective is to provide a kind of interim board house bracing means effectively can resisting typhoon.This device comprises steel pipe rack, reinforce steel pipe and drawknot wire rope, reinforcing steel pipe is four, be separately positioned on interim board house all around on four direction, the bottom that every root reinforces steel pipe is fixed on concrete surface by the first anchor device, the upper end of every root steel pipe is provided with anti-skidding projection, drawknot wire rope is four, its setting position and each reinforce the position one_to_one corresponding of steel pipe, angle between drawknot wire rope and ground is acute angle, one end of every bar drawknot wire rope is fixed on concrete surface by the second anchor device, the other end of every bar drawknot wire rope is on the reinforcing steel pipe corresponding to it and be positioned at the upper end of anti-skidding projection, steelpipe net frame is arranged on roof, one end of steel pipe rack is fixedly connected with the top reinforcing steel pipe.

Description

Interim board house bracing means
Technical field
The utility model relates to a kind of bracing means of interim board house, particularly relates to a kind of device for the reinforcing to board house interim under coastal typhoon environment.
Background technology
Interim board house is built usually used as general shanty, have unification handsome in appearance, easy construction, speed of application fast, be easy to dismounting, the advantage such as can reuse, also there is good anti-seismic performance simultaneously, be widely used in engineering construction and rescue and relief work, cost performance is higher, not only economy but also environmental protection.And compared to permanent house, movable plank house wind resistance is poor, though movable plank house basis is concrete foundation, its column shearing resistance, bending resistance are less, are difficult to keep out high-grade, the violent typhoon that take place frequently.Particularly taking place frequently at coastal area typhoon, if do not considered the impact of violent typhoon on movable plank house, often can occur to be thrown in board house roof, building structure is impaired the situation such as even to topple over.
Utility model content
The technical problems to be solved in the utility model is to provide a kind of interim board house bracing means effectively can resisting typhoon.
The interim board house bracing means of the utility model, comprise steel pipe rack, reinforce steel pipe and drawknot wire rope, described reinforcing steel pipe is four, be separately positioned on interim board house all around on four direction, the bottom that every root reinforces steel pipe is fixed on concrete surface by the first anchor device, the upper end of every root steel pipe is provided with anti-skidding projection, described drawknot wire rope is four, its setting position and each reinforce the position one_to_one corresponding of steel pipe, angle between described drawknot wire rope and ground is acute angle, one end of every bar drawknot wire rope is fixed on concrete surface by the second anchor device, the other end of every bar drawknot wire rope is on the reinforcing steel pipe corresponding to it and be positioned at the upper end of described anti-skidding projection, described steelpipe net frame is arranged on roof, one end of steel pipe rack is fixedly connected with the top of described reinforcing steel pipe.
The interim board house bracing means of the utility model, wherein said first anchor device comprises the first steel plate and expansion bolt, four bight perforates of described first steel plate, and be fixed on hardening of concrete ground by expansion bolt, described reinforcing steel pipe is connected with described first Interal fixation.
The interim board house bracing means of the utility model, wherein said first anchor device also comprise be arranged on reinforce steel pipe with the angle steel of described first steel plate junction.
The interim board house bracing means of the utility model, wherein said second anchor device comprises the second steel plate, expansion bolt and flower basket bolt, four bight perforates of described second steel plate, and be fixed on hardening of concrete ground by expansion bolt, described second steel plate is fixedly installed latch closure, one end of described flower basket bolt is buckled on described latch closure, and the other end of described flower basket bolt connects one end of described drawknot wire rope.
The interim board house bracing means of the utility model, wherein said steel pipe rack comprises the horizontal steel pipe and longitudinal steel pipe that are fixedly connected with, and horizontal steel pipe is arranged at eaves place and ridge, and longitudinal steel pipe is fixed on horizontal steel pipe equally spacedly.
The utility model interim board house bracing means difference from prior art is that the interim board house bracing means of the utility model adopts two kinds of reinforcing modes of steel pipe support and wire rope drawknot, anti-typhoon capacity is stronger, and wire cable strengthening can pack up suspension under environment at ordinary times, can not occupied ground, only when larger typhoon, itself and ground rollering junction are fixed.Convenient disassembly, can to reuse.
Below in conjunction with accompanying drawing, interim board house bracing means of the present utility model is described further.
Accompanying drawing explanation
Fig. 1 is the front view of the interim board house bracing means of the utility model;
Fig. 2 is the top view of the first steel plate in the interim board house bracing means of the utility model;
Fig. 3 is the amplification view at A place in the interim board house bracing means of the utility model;
Fig. 4 is the top view of the second steel plate in the interim board house bracing means of the utility model;
Fig. 5 is the amplification view at B place in the interim board house bracing means of the utility model.
Detailed description of the invention
As Fig. 1, shown in Fig. 2 and Fig. 3, the interim board house bracing means of the utility model, comprise steel pipe rack 1, reinforce steel pipe 2 and drawknot wire rope 3, reinforcing steel pipe 2 is four, be separately positioned on interim board house all around on four direction, the bottom that every root reinforces steel pipe 2 is fixed on concrete surface 6 by the first anchor device 4, the upper end of every root steel pipe is provided with anti-skidding projection, anti-skidding projection be with reinforce the circular steel ring that is welded and fixed of steel pipe 2 or with the integrated square projection of reinforcing steel pipe 2, first anchor device 4 comprises the first steel plate 41 and expansion bolt, four bight perforates of the first steel plate 41, and be fixed on hardening of concrete ground by expansion bolt, between expansion bolt 43 and ground, pad 44 is also installed, tighten fixing by nut 45, reinforcing steel pipe 2 and the first steel plate 41 are welded and fixed, for ensureing that reinforcing steel pipe 2 is connected with the first the reliable of steel plate 41, angle steel 42 is also provided with in the reinforcing lower end of steel pipe 2 and the junction of the first steel plate 41.
As shown in Figure 4 and Figure 5, drawknot wire rope 3 is four, its setting position and each reinforce the position one_to_one corresponding of steel pipe 2, angle between drawknot wire rope 3 and ground is 45 ° of acute angles, one end of drawknot wire rope 3 is fixed on concrete surface 6 by the second anchor device 5, the other end of drawknot wire rope 3 is on the reinforcing steel pipe 2 corresponding to it and be positioned at the upper end of anti-skidding projection, second anchor device 5 comprises the second steel plate 51, expansion bolt 43 and flower basket bolt 52, four bight perforates of the second steel plate 51, and be fixed on hardening of concrete ground by expansion bolt 43, between expansion bolt 43 and ground, pad 44 is also installed, tighten fixing by nut 45, second steel plate 51 is fixedly installed latch closure 53, one end of flower basket bolt 52 is buckled on latch closure 53, the other end of flower basket bolt 52 connects one end of drawknot wire rope 3.
Steel pipe rack 1 is arranged on roof, and one end of steel pipe rack 1 is fixedly connected with the top reinforcing steel pipe.Steel pipe rack 1 comprises the horizontal steel pipe and longitudinal steel pipe that are welded to connect, and horizontal steel pipe is arranged at eaves place and ridge, and longitudinal steel pipe is fixed on horizontal steel pipe equally spacedly.
The use procedure of this device is, first auger shell keyhole on concrete surface 6, the size in hole and the degree of depth meet the specification requirement of expansion bolt 43, the first steel plate 41 holding hole successfully is placed on level ground, and hole on the first steel plate 41 is alignd with ground bolt hole, then expansion bolt 43 is screwed in bolt hole, be inserted in pad, and fastening nut, then reinforcing steel pipe 2 is positioned over the center of the first steel plate 41, be welded and fixed, and weld angle steel 42 in the lower end reinforcing steel pipe 2 with the junction of the first steel plate 41, thus realize the fixing of the bottom reinforcing steel pipe 2.
In like manner, when installing drawknot wire rope 3, first according to above step, the second steel plate 51 is fixed on concrete surface 6, then one end of flower basket bolt 52 is buckled on latch closure 53, the other end connects one end of drawknot wire rope 3, and by the other end of wire rope around on reinforcing steel pipe 2, the drawknot realizing wire rope is fixed.
Above-described embodiment is only be described preferred embodiment of the present utility model; not scope of the present utility model is limited; under the prerequisite not departing from the utility model design spirit; the various distortion that those of ordinary skill in the art make the technical solution of the utility model and improvement, all should fall in protection domain that the utility model claims determine.

Claims (5)

1. an interim board house bracing means, it is characterized in that: comprise steel pipe rack (1), reinforce steel pipe (2) and drawknot wire rope (3), described reinforcing steel pipe (2) is four, be separately positioned on interim board house all around on four direction, the bottom that every root reinforces steel pipe (2) is fixed on concrete surface (6) by the first anchor device (4), the upper end of every root steel pipe is provided with anti-skidding projection, described drawknot wire rope (3) is four, its setting position and each reinforce the position one_to_one corresponding of steel pipe (2), angle between described drawknot wire rope (3) and ground is acute angle, one end of every bar drawknot wire rope (3) is fixed on concrete surface (6) by the second anchor device (5), the other end of every bar drawknot wire rope (3) is gone up around the reinforcing steel pipe (2) corresponding to it and is positioned at the upper end of described anti-skidding projection, described steel pipe rack (1) is arranged on roof, one end of steel pipe rack (1) is fixedly connected with the top of described reinforcing steel pipe (2).
2. interim board house bracing means according to claim 1, it is characterized in that: described first anchor device (4) comprises the first steel plate (41) and expansion bolt (43), four bight perforates of described first steel plate (41), and be fixed on hardening of concrete ground by expansion bolt (43), described reinforcing steel pipe (2) is fixedly connected with described first steel plate (41).
3. interim board house bracing means according to claim 2, is characterized in that: described first anchor device (4) also comprises the angle steel (42) being arranged on and reinforcing steel pipe (2) and described first steel plate (41) junction.
4. interim board house bracing means according to claim 1, it is characterized in that: described second anchor device (5) comprises the second steel plate (51), expansion bolt (43) and flower basket bolt (52), four bight perforates of described second steel plate (51), and be fixed on hardening of concrete ground by expansion bolt (43), described second steel plate (51) is fixedly installed latch closure (53), one end of described flower basket bolt (52) is buckled on described latch closure (53), the other end of described flower basket bolt (52) connects one end of described drawknot wire rope (3).
5. according to the arbitrary described interim board house bracing means of claim 1-4, it is characterized in that: described steel pipe rack (1) comprises the horizontal steel pipe and longitudinal steel pipe that are fixedly connected with, horizontal steel pipe is arranged at eaves place and ridge, and longitudinal steel pipe is fixed on horizontal steel pipe equally spacedly.
CN201420698245.1U 2014-11-19 2014-11-19 Interim board house bracing means Expired - Fee Related CN204282860U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420698245.1U CN204282860U (en) 2014-11-19 2014-11-19 Interim board house bracing means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420698245.1U CN204282860U (en) 2014-11-19 2014-11-19 Interim board house bracing means

Publications (1)

Publication Number Publication Date
CN204282860U true CN204282860U (en) 2015-04-22

Family

ID=52866037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420698245.1U Expired - Fee Related CN204282860U (en) 2014-11-19 2014-11-19 Interim board house bracing means

Country Status (1)

Country Link
CN (1) CN204282860U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201223A (en) * 2015-10-20 2015-12-30 浙江乔兴建设集团有限公司 Windproof reinforcing structure used for temporary board houses on soil
CN105804401A (en) * 2016-05-16 2016-07-27 中国建筑第二工程局有限公司 Construction steel jig frame and method for constructing daylighting roof steel structure by utilizing the same
CN106836931A (en) * 2017-03-13 2017-06-13 中国十七冶集团有限公司 The coastal big facility typhoon protection that faces of engineering reinforces locking means

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201223A (en) * 2015-10-20 2015-12-30 浙江乔兴建设集团有限公司 Windproof reinforcing structure used for temporary board houses on soil
CN105804401A (en) * 2016-05-16 2016-07-27 中国建筑第二工程局有限公司 Construction steel jig frame and method for constructing daylighting roof steel structure by utilizing the same
CN106836931A (en) * 2017-03-13 2017-06-13 中国十七冶集团有限公司 The coastal big facility typhoon protection that faces of engineering reinforces locking means

Similar Documents

Publication Publication Date Title
US9428877B2 (en) Modular monopole tower foundation
CN204282860U (en) Interim board house bracing means
CN108625481A (en) A kind of movable plank house typhoon protection device
CN202530816U (en) A hurricane-shielding reinforcing device of a prefabricated house
CN105201223B (en) A kind of windproof ruggedized construction for the interim board house in soil ground
CN205116461U (en) Device that whole anti -seismic performance in timber structure bearing house was gone along with sb. to guard him to reinforcing adobe wall
CN204850052U (en) Outer skeleton is prevent wind to activity board house
CN204126290U (en) Elevator shaft horizontal protective device
CN204662926U (en) A kind of operating platform for steel pipe column top construction operation
CN203821929U (en) Wind resistant building structure
CN104164998B (en) Wind resistance road closure plate for road construction
CN204386138U (en) Wall construction is connected between building scaffold platform
CN204385762U (en) A kind of Rock Bolt Foundation structure
CN204059415U (en) A kind of fall arrest inspection shaft
CN202990395U (en) Rotating horizontal protection tool for climbing scaffold
CN203878563U (en) Suspended single-row scaffold
CN207974506U (en) A kind of regularization hard protection device for elevator
CN204959794U (en) Field word roof beam pile cap and flat slab floor structure system
CN202117303U (en) Adjustable clamping frame
CN206289997U (en) Construction protection safety net
CN203947455U (en) A kind of Deep Water Steel structure bridging constructional device
CN204174903U (en) Scaffold
CN204326658U (en) LNG storage tank reinforced mesh wind-resistant column bracing means
CN205804999U (en) The attachment structure of prefabrication tower crane
CN204531467U (en) A kind of superposed beam, plate support bar tripod

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150422

Termination date: 20191119

CF01 Termination of patent right due to non-payment of annual fee