CN204276884U - A kind of cinder ladle with diversion channel - Google Patents

A kind of cinder ladle with diversion channel Download PDF

Info

Publication number
CN204276884U
CN204276884U CN201420691468.5U CN201420691468U CN204276884U CN 204276884 U CN204276884 U CN 204276884U CN 201420691468 U CN201420691468 U CN 201420691468U CN 204276884 U CN204276884 U CN 204276884U
Authority
CN
China
Prior art keywords
cinder ladle
diversion channel
cinder
cooling water
ladle body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420691468.5U
Other languages
Chinese (zh)
Inventor
施毅红
陈伟
卢松林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Heng Wei Chen Equipment Manufacturing Co., Ltd.
Original Assignee
WUHAN HENGWEI HEAVY MACHINERY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN HENGWEI HEAVY MACHINERY CO Ltd filed Critical WUHAN HENGWEI HEAVY MACHINERY CO Ltd
Priority to CN201420691468.5U priority Critical patent/CN204276884U/en
Application granted granted Critical
Publication of CN204276884U publication Critical patent/CN204276884U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Furnace Details (AREA)

Abstract

The utility model discloses a kind of cinder ladle with diversion channel, it comprises the cinder ladle body of cup-shaped, it is characterized in that: the upper end of cinder ladle body is provided with diversion channel, make the cooling water be positioned at above cinder ladle smelting slag can flow into the water inlet of diversion channel, the delivery port of diversion channel is lower than this water inlet, the delivery port of diversion channel is arranged down along cinder ladle body outer wall, makes the cooling water of outflow can along cinder ladle outer wall to dirty.The utility model, by arranging diversion channel, effectively can accelerate cinder ladle cooling velocity on the one hand and conduct to the smelting slag in cinder ladle, cinder ladle entirety is played to the effect of accelerating cooling, reduces the turn around time of cinder ladle, reduce the amount of purchase of cinder ladle; After closedown cooling water water feeding switch, then reduce cinder ladle inner cooling water water level by the siphon principle in diversion channel, such cinder ladle car is in lifting and transport in the process of cinder ladle car, just can cooling water be avoided completely excessive.

Description

A kind of cinder ladle with diversion channel
Technical field
The utility model relates to a kind of copper smelting slag copper-clad, particularly a kind of cinder ladle with diversion channel.
Background technology
Along with the scarcity gradually of copper ore resource, for the strategy of respective country recycling economy, domestic nearly all copper smelting plant had all carried out slow cooling to copper weld pool slag and had solidified ore-dressing technique in recent years, be exactly no longer by smelting slag shrend, slow cooling, then fragmentation, ball milling, flotation but smelting slag splendid attire gets up by the cast steel cinder ladle of employing 12 cubic metres.Not only make use of limited resource fully, reduce the pressure of Copper making to environmental protection, smeltery also therefrom obtains rich profit simultaneously.
Slag ore-dressing technique key link is slag slow cooling, the accumulative crystallization of the copper ion in smelting slag is a complicated dressing process, higher to link temperature requirement, copper ion only under the liquid condition of smelting slag free gathering finally meet ore-dressing technique requirement, that is the smelting slag time that is in a liquid state longlyer more is conducive to ore-dressing technique, so require smelting slag long-term storage in cinder ladle, this just needs to purchase a large amount of cast steel cinder ladles of 12 cubic metres, in order to reduce the usage quantity of cinder ladle, reduce beneficiation cost.So slag retarded cooling process to require that smelting slag loads natural slow cooling after cinder ladle long as far as possible, copper ion fully complete free, assemble, require to cool rapidly after crystallization, accelerate the turnover of cinder ladle.Normally Water spray is carried out to the smelting slag solidified, accelerating cooling, due to copper ashes pack arrangement form limitation, adds that field management problem is considered emphatically in slow cooling field in construction project, cinder ladle 1 generally in 1-2 ° of inclinations angle, is beneficial to cooling water flow to corresponding gutter 2.Cooling water major part is directly let out after overflowing from the direction that cinder ladle bead is lower and has been fallen ground, cooling effect rapidly can only be played to cinder ladle upper part, divide impact little (as shown in Figure 1) on the bottom of cinder ladle and the higher direction of cinder ladle bead, be difficult to effect cinder ladle entirety being played to accelerating cooling, and the spot temperature that cooling water does not flow through is relatively high.In addition, cinder ladle car is when load mucks haulage bag, cinder ladle is leaving the moment on ground and is travelling in way at cinder ladle car, and by center of gravity, gravity and inertia effects, cinder ladle 1 can centered by cinder ladle gudgeon, sharply rock (as shown in Figure 2) in the prong of cinder ladle car 3, cooling water now in cinder ladle can be a large amount of spilling, trickle down on cinder ladle car, because cooling water contains higher sulfide, the hydraulic jack of meeting to cinder ladle car, the key positions such as tire cause more serious erosion and damage.
Utility model content
Technical problem to be solved in the utility model is that the deficiency existed for above-mentioned prior art provides a kind of cooling velocity can not only accelerating smelting slag in cinder ladle, can avoid again the cinder ladle with diversion channel of cinder ladle car generation of the excessive situation of cooling water in the process of lifting and transport.
The technical scheme that the utility model adopts is: a kind of cinder ladle with diversion channel, it comprises the cinder ladle body of cup-shaped, it is characterized in that: the upper end of cinder ladle body is provided with diversion channel, make the cooling water be positioned at above cinder ladle smelting slag can flow into the water inlet of diversion channel, the delivery port of diversion channel is lower than this water inlet, the delivery port of diversion channel is arranged down along cinder ladle body outer wall, makes the cooling water of outflow can along cinder ladle outer wall to dirty.
By technique scheme, described diversion channel and cinder ladle body cast entirety.
By technique scheme, the peak of described diversion channel is lower than the upper surface of cinder ladle body.
By technique scheme, be arranged at intervals with multiple diversion channel along the circumferential direction of cinder ladle body.
By technique scheme, described cinder ladle body is obliquely installed.
By technique scheme, the water inlet being positioned at the diversion channel of cinder ladle highest point is arranged on the position being positioned at smelting slag nominal load more than line 30mm, and the water inlet of the diversion channel of lowest part is arranged on more than smelting slag nominal load line.
By technique scheme, described diversion channel is that inverted U is arranged.
By technique scheme, left and right gudgeon is symmetrically arranged with in the outer wall upper end of cinder ladle body, periphery circumference along left and right gudgeon place is all arranged at intervals with reinforcement, in the outer wall upper end of cinder ladle body, the vertical place of left and right gudgeon is provided with left and right bearing, the bottom of cinder ladle body is provided with feet.
Beneficial effect acquired by the utility model is: the utility model is by arranging diversion channel, cooling water can be drained to the outer wall of cinder ladle on the one hand, the cooling water of outflow is trickled downwards along cinder ladle outer wall, take away heat, effectively can accelerate cinder ladle cooling velocity and conduct to the smelting slag in cinder ladle, cinder ladle entirety is played to the effect of accelerating cooling, reduce the turn around time of cinder ladle, reduce the amount of purchase of cinder ladle; After closedown cooling water water feeding switch, then reduce cinder ladle inner cooling water water level by the siphon principle in diversion channel, such cinder ladle car is in lifting and transport in the process of cinder ladle car, just can cooling water be avoided completely excessive, effectively avoid cooling water to the erosion of cinder ladle car and infringement, reduce the fault rate of cinder ladle car, improve its service life.
Accompanying drawing explanation
Fig. 1 is cinder ladle state of cooling schematic diagram of the prior art.
Fig. 2 is the view of cinder ladle car transport cinder ladle.
Fig. 3 is main sectional view of the present utility model.
Fig. 4 is the partial enlarged drawing of the I in Fig. 3.
Fig. 5 is the three-dimensional structure diagram of cinder ladle.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described in further detail.
As in Figure 3-5, a kind of cinder ladle with diversion channel that the present embodiment provides, it comprises the cinder ladle body 4 of cup-shaped, a left side is symmetrically arranged with in the outer wall upper end of cinder ladle body 4, auris dextra axle 5, along left, the periphery circumference at auris dextra axle 5 place is all arranged at intervals with reinforcement 7, in the outer wall upper end of cinder ladle body with left, the vertical place of auris dextra axle 5 is provided with a left side, right support abutment 6, the bottom of cinder ladle body is provided with feet 8, 4 diversion channel 10 are arranged at intervals with along the circumferential direction of cinder ladle body 1 below the bead of cinder ladle body, make the cooling water 14 be positioned at above cinder ladle smelting slag 9 can flow into the water inlet 11 of diversion channel 10, the top 12 of described diversion channel is lower than the upper surface of cinder ladle body.Wherein, the delivery port 13 of diversion channel 10 is lower than this water inlet 11, and the delivery port 13 of diversion channel is arranged down along cinder ladle body 4 outer wall, makes the cooling water of outflow can along cinder ladle outer wall to dirty.
In the present embodiment, described diversion channel is U-shaped, existing by after diversion channel 10 machine-shaping, when casting cinder ladle, casts entirety with cinder ladle body 4.
Described cinder ladle body is obliquely installed, angle of inclination a is 1-2 °, the water inlet being positioned at the diversion channel of cinder ladle highest point is arranged on the position being positioned at smelting slag nominal load line A place more than 30mm, and the water inlet of the diversion channel of lowest part is arranged on smelting slag nominal load line A place.
Diversion channel 10 is arranged to the form meeting siphonage generation by the utility model, when the cooling water water level in cinder ladle is higher than diversion channel top 12, water in diversion channel 10 from delivery port 13 along the mild downward trickling of cinder ladle outer wall, will play the effect of the overall accelerating cooling of cinder ladle.As long as confluent is greater than the summation of diversion channel 10 water outlet, cinder ladle inner cooling water water level still in the state be full of, can not affect the cooling velocity on cinder ladle top equally.Once water feeding switch is closed, will there is siphonage in the water in diversion channel 10, the water in cinder ladle can be extracted into lower water level, and cinder ladle car 3, in lifting with the process of transport cinder ladle, the excessive phenomenon of cooling water would not occur.

Claims (8)

1. one kind has the cinder ladle of diversion channel, it comprises the cinder ladle body of cup-shaped, it is characterized in that: the upper end of cinder ladle body is provided with diversion channel, make the cooling water be positioned at above cinder ladle smelting slag can flow into the water inlet of diversion channel, the delivery port of diversion channel is lower than this water inlet, the delivery port of diversion channel is arranged down along cinder ladle body outer wall, makes the cooling water of outflow can along cinder ladle outer wall to dirty.
2. a kind of cinder ladle with diversion channel according to claim 1, is characterized in that, described diversion channel and cinder ladle body cast entirety.
3. a kind of cinder ladle with diversion channel according to claim 1 and 2, is characterized in that, the peak of described diversion channel is lower than the upper surface of cinder ladle body.
4. a kind of cinder ladle with diversion channel according to claim 1 and 2, is characterized in that, is being arranged at intervals with multiple diversion channel along the circumferential direction of cinder ladle body.
5. a kind of cinder ladle with diversion channel according to claim 4, is characterized in that, described cinder ladle body is obliquely installed.
6. a kind of cinder ladle with diversion channel according to claim 5, it is characterized in that, the water inlet being positioned at the diversion channel of cinder ladle highest point is arranged on the position being positioned at smelting slag nominal load more than line 30mm, and the water inlet of the diversion channel of lowest part is arranged on more than smelting slag nominal load line.
7. a kind of cinder ladle with diversion channel according to claim 1 and 2, is characterized in that, described diversion channel is that inverted U is arranged.
8. a kind of cinder ladle with diversion channel according to claim 1 and 2, it is characterized in that, left and right gudgeon is symmetrically arranged with in the outer wall upper end of cinder ladle body, periphery circumference along left and right gudgeon place is all arranged at intervals with reinforcement, in the outer wall upper end of cinder ladle body, the vertical place of left and right gudgeon is provided with left and right bearing, the bottom of cinder ladle body is provided with feet.
CN201420691468.5U 2014-11-18 2014-11-18 A kind of cinder ladle with diversion channel Expired - Fee Related CN204276884U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420691468.5U CN204276884U (en) 2014-11-18 2014-11-18 A kind of cinder ladle with diversion channel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420691468.5U CN204276884U (en) 2014-11-18 2014-11-18 A kind of cinder ladle with diversion channel

Publications (1)

Publication Number Publication Date
CN204276884U true CN204276884U (en) 2015-04-22

Family

ID=52860080

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420691468.5U Expired - Fee Related CN204276884U (en) 2014-11-18 2014-11-18 A kind of cinder ladle with diversion channel

Country Status (1)

Country Link
CN (1) CN204276884U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104525927A (en) * 2014-11-18 2015-04-22 武汉恒威重机有限公司 Slag ladle with flow guide water channel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104525927A (en) * 2014-11-18 2015-04-22 武汉恒威重机有限公司 Slag ladle with flow guide water channel

Similar Documents

Publication Publication Date Title
CN203725753U (en) Steelmaking ladle structure
CN203197232U (en) Steel ladle bottom structure capable of effectively reducing amount of residual molten steel of steel ladle
CN204276884U (en) A kind of cinder ladle with diversion channel
CN103302280A (en) Construction method of steel ladle bottom for ultra-low carbon steel
CN104525927A (en) Slag ladle with flow guide water channel
CN203091697U (en) Large-section continuous casting machine connecting piece for replacing tundish rapidly
CN201720418U (en) Molten iron diversion device
CN103302278B (en) Automatic cover adding and taking device of torpedo tank car
CN203371032U (en) Automatic capping and uncapping device of torpedo car
CN203778726U (en) 12-strand conticaster tundish with reasonable flow-dividing function
CN201271738Y (en) Structure of continuous casting machine tundish dam
CN208577751U (en) A kind of blast furnace ironmaking long-life swing runner
CN202610246U (en) Furnace shutdown remaining iron discharge pit
CN209491337U (en) The tundish of resistance to melting loss
CN205676490U (en) A kind of big brake shoe of main trough of blast furnace
CN201693162U (en) Pulvis ferri groove brick
CN206153522U (en) Continuous casting ware current drive system
CN202090007U (en) Prefabricated member for dam of iron tap channel of blast furnace
CN204818026U (en) Package blows argon barricade in middle of modified
CN204311072U (en) Shell of blast furnace cooling drainage device
CN201755637U (en) Slag wall inside tundish
CN206244418U (en) A kind of modified silicon liquid transferring device for silicon melting
CN205085347U (en) Modular self -interacting ferroalloy casting machine
CN201198483Y (en) Tap cinder water-cooling spout
CN204159857U (en) Tundish

Legal Events

Date Code Title Description
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190108

Address after: 430000 No. 52 Liufang Avenue, Donghu New Technology Development Zone, Wuhan, Hubei Province

Patentee after: Wuhan Heng Wei Chen Equipment Manufacturing Co., Ltd.

Address before: Room 601-602, Building 2, 6 Floors, No. 1 International Enterprise Center, No. 2, Guanshan Second Road, Donghu High-tech Park, Wuhan City, Hubei Province, 430074

Patentee before: Wuhan Hengwei Heavy Machinery Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150422

Termination date: 20191118