CN204258160U - Change transmission tower insulator instrument - Google Patents

Change transmission tower insulator instrument Download PDF

Info

Publication number
CN204258160U
CN204258160U CN201420823005.XU CN201420823005U CN204258160U CN 204258160 U CN204258160 U CN 204258160U CN 201420823005 U CN201420823005 U CN 201420823005U CN 204258160 U CN204258160 U CN 204258160U
Authority
CN
China
Prior art keywords
card
insulator
core
groove
screw mandrel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420823005.XU
Other languages
Chinese (zh)
Inventor
韦国益
廖远利
毕明超
郭庆生
谭华章
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liuzhou Power Supply Bureau of Guangxi Power Grid Co Ltd
Original Assignee
Liuzhou Power Supply Bureau of Guangxi Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liuzhou Power Supply Bureau of Guangxi Power Grid Co Ltd filed Critical Liuzhou Power Supply Bureau of Guangxi Power Grid Co Ltd
Priority to CN201420823005.XU priority Critical patent/CN204258160U/en
Application granted granted Critical
Publication of CN204258160U publication Critical patent/CN204258160U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model discloses a kind of replacing transmission tower insulator instrument, relate to the electric device service technique field of transmission line; Comprise rear card and screw mandrel, screw mandrel is provided with handle; Rear cartoon cross screw mandrel and before link and connect; Front card comprises base and is columniform the core of the card, and base is provided with the hole for installing the core of the card and is connected with the core of the card by hold-down screw; The core of the card is provided with groove, the wall of these groove both sides is respectively equipped with breach.Length consuming time when it can solve replacing 500 kilovolt tangent tower two string side of wire first insulator, instrument carrying go up a hill difficulty, the problem of Suspension Small Angle Towers wire first insulator cannot be changed.

Description

更换线塔绝缘子工具Tool for replacing pylon insulators

技术领域 technical field

本实用新型涉及输电线路的电器件检修技术领域;尤其是一种用于500千伏直线塔双串导线侧第一片绝缘子更换的更换线塔绝缘子工具。 The utility model relates to the technical field of electric device maintenance of power transmission lines, in particular to a line tower insulator replacement tool for replacing the first piece of insulator on the double-string conductor side of a 500 kV straight line tower.

背景技术 Background technique

绝缘子是用来支持导线,并使导线与大地、杆塔之间有足够安全距离和绝缘,具有一定电气绝缘强度和机械强度。在输电线路运行中,绝缘子暴露在野外,在长期强电场、拉力作用下工作,容易出现零值。由于玻璃绝缘子的特性,当出现零值时会自暴。根据绝缘子的电压分布特性,靠近导线侧第一片绝缘子受到的电压最高,最容易零值而自暴。在同一串绝缘子中出现零值后会影响整串绝缘子的电压分布,促进绝缘子劣化零值,当绝缘子串良好片数达不到安全规定时,威胁输电线路安全运行,所以必须定期更换线路自暴绝缘子。 The insulator is used to support the wire, and make the wire and the earth, the tower have a sufficient safety distance and insulation, and have a certain electrical insulation strength and mechanical strength. In the operation of transmission lines, insulators are exposed to the wild and work under long-term strong electric fields and tension, and zero values are prone to occur. Due to the characteristics of the glass insulator, it will explode when there is a zero value. According to the voltage distribution characteristics of the insulator, the first insulator near the wire side receives the highest voltage, and is most likely to be zero and self-destruct. The occurrence of zero values in the same string of insulators will affect the voltage distribution of the entire string of insulators, and promote the deterioration of the insulators. When the number of good insulator strings does not meet the safety regulations, it will threaten the safe operation of the transmission line. Therefore, it is necessary to replace the line self-destruct insulators regularly. .

   更换自暴绝缘子的检修工作,通常使用专用卡具进行更换。目前更换500kV直线塔双串导线第一片绝缘子没有专用卡具,一般使用链条葫芦和配套工具完成,存在如下问题: The maintenance work of replacing self-violent insulators is usually replaced with special fixtures. At present, there is no special fixture for the replacement of the first insulator of the double-string conductor of the 500kV straight tower. Generally, chain hoists and supporting tools are used to complete the replacement. The following problems exist:

1、使用链条葫芦和配套工具更换500kV直线塔双串绝缘子导线第一片时,配套工具多,安装工序复杂,塔头需要1名工作人员,导线要1名工作人员,双人配合完成,耗人力多,耗时长。 1. When using the chain hoist and supporting tools to replace the first piece of the 500kV straight tower double-string insulator wire, there are many supporting tools and the installation process is complicated. One worker is required for the tower head and one worker for the wire. Two people cooperate to complete it, which consumes manpower Many, time-consuming.

2、输电线路杆塔全部是在野外,大多位于半山腰或山顶,山高路远,链条葫芦和配套工具重,搬运工具上山困难,同时存在有摔伤风险。 2. The transmission line towers are all in the wild, mostly on the mountainside or on the top of the mountain. The mountains are high and the roads are far away. The chain hoist and supporting tools are heavy, and it is difficult to move the tools up the mountain. At the same time, there is a risk of falling.

3、使用链条葫芦配套工具更换绝缘子,需提升导线行程大。 3. To replace the insulator with the supporting tools of the chain hoist, it is necessary to lift the conductor with a large stroke.

4、在大档距情况更换绝缘子,与塔头连接钢丝绳头需要做保护处理,导线过重,塔头与工具存在有变形、损坏的风险。 4. Replace the insulator in the case of a large span, and the wire rope head connected to the tower head needs to be protected. The wire is too heavy, and there is a risk of deformation and damage to the tower head and tools.

5、对于有小转角的直线杆塔,绝缘子串有倾斜角度,链条葫芦配套工具,无法更换双串导线侧第一片绝缘子。 5. For straight pole towers with small corners, the insulator strings have an inclination angle, and the chain hoist supporting tools cannot replace the first insulator on the side of the double string wire.

发明内容 Contents of the invention

本实用新型的目的是提供一种更换线塔绝缘子工具,它可以解决更换500千伏线路直线塔双串导线侧第一片绝缘子时耗时长、工具搬运上山困难、无法更换直线小转角塔导线第一片绝缘子的问题。 The purpose of the utility model is to provide a tool for replacing the insulators of the line tower, which can solve the problem of long time-consuming replacement of the first insulator on the side of the double-string conductor of the 500 kV line straight tower, difficulty in carrying the tool up the mountain, and the inability to replace the first wire of the straight line small corner tower. A piece of insulator problem.

为了解决上述问题,本实用新型采用的技术方案是:这种更换线塔绝缘子工具,包括后卡和丝杆,所述丝杆上设置有转把;所述后卡通过所述丝杆与前卡连接;所述前卡包括底座和为圆柱形的卡芯,所述底座设置有用于安装所述卡芯的孔;所述卡芯上设置有槽,该槽两侧的壁上分别设有缺口。 In order to solve the above problems, the technical solution adopted by the utility model is: the tool for replacing the insulator of the line tower includes a rear card and a screw rod, and a handle is arranged on the screw rod; the rear card passes through the screw rod and the front card connection; the front card includes a base and a cylindrical card core, the base is provided with a hole for installing the card core; the card core is provided with a groove, and the walls on both sides of the groove are respectively provided with gap.

在上述技术方案中,更为具体的方案还可以是:所述槽为上宽下窄的形状,该槽的底部成倾斜状。 In the above technical solution, a more specific solution may also be: the groove is in the shape of a wide top and a narrow bottom, and the bottom of the groove is inclined.

更进一步的:所述底座为中间大、两头小的形状,该底座两端的侧面开有用于与所述丝杆连接的孔。 Further: the base is in the shape of a large center and small ends, and the sides of both ends of the base are provided with holes for connecting with the screw.

进一步:所述槽窄的地方为26毫米,宽的地方为46毫米,从顶部到底部最深处的深度为80毫米,其底部与水平线的倾斜角度为40度。 Further: the narrow part of the groove is 26 mm, the wide part is 46 mm, the deepest depth from the top to the bottom is 80 mm, and the inclination angle between the bottom and the horizontal line is 40 degrees.

由于采用了上述技术方案,本实用新型与现有技术相比,具有的有益效果是: Owing to adopting above-mentioned technical scheme, the beneficial effect that the utility model has compared with prior art is:

由于设置了前卡,在更换500千伏线路直线塔双串导线侧第一片绝缘子时,不需要链条葫芦,由一名工作人员上杆工作,运安装工具、拆旧绝缘子、装新绝缘子都是一个人单独完成,一个人只需30分钟便可完成拆、装绝缘子的工作,耗时缩短了,而且本实用新型重量轻,搬运上山十分方便。 Due to the setting of the front clamp, when replacing the first insulator on the side of the double-string conductors of the 500 kV line straight tower, the chain hoist is not needed, and a staff member works on the pole, transporting the installation tools, removing the old insulators, and installing new insulators. It is done by one person alone, and one person only needs 30 minutes to complete the work of dismantling and assembling the insulators, which shortens the time consumption, and the utility model is light in weight and very convenient to carry up the mountain.

附图说明 Description of drawings

图1是本实用新型的结构示意图。 Fig. 1 is the structural representation of the utility model.

图2是移除后卡和丝杆的俯视图。 Figure 2 is a top view with the card and screw removed.

图3是图1的A-A剖视图。 Fig. 3 is a sectional view along line A-A of Fig. 1 .

具体实施方式 Detailed ways

下面结合附图和实施例对本实用新型作进一步详述: Below in conjunction with accompanying drawing and embodiment the utility model is described in further detail:

图1、图2和图3所示的更换线塔绝缘子工具,包括后卡5和丝杆4,丝杆4上设置有转把7;后卡5通过丝杆4与前卡6连接;前卡6包括底座1和为圆柱形的卡芯3,底座1设置有用于安装卡芯3的孔并通过固定螺钉2与卡芯3连接;卡芯3上设置有槽,该槽两侧的壁上分别设有缺口。该槽为上宽下窄的形状,其底部成倾斜状。底座1为中间大、两头小的形状,该底座1两端的侧面开有用于与丝杆4连接的孔。 The tool for replacing the line tower insulator shown in Fig. 1, Fig. 2 and Fig. 3 includes a rear card 5 and a screw mandrel 4, and the screw mandrel 4 is provided with a handle 7; the rear card 5 is connected with the front card 6 through the screw mandrel 4; The card 6 includes a base 1 and a cylindrical card core 3, the base 1 is provided with a hole for installing the card core 3 and is connected with the card core 3 by a fixing screw 2; the card core 3 is provided with a groove, and the walls on both sides of the groove There are notches on them respectively. The groove is wide at the top and narrow at the bottom, and its bottom is inclined. The base 1 is in the shape of a large middle and small ends, and the sides of the two ends of the base 1 are provided with holes for connecting with the screw mandrel 4 .

导线侧第一片绝缘子连接方式为:绝缘子,碗头,三角板。前卡6、后卡5通过收紧丝杆4使绝缘子松弛,要保持与绝缘子串受力在同一条线上,前卡6受力点设计在碗头与三角板的螺栓处。因此前卡6设计为:卡芯3加底座1。经过测量连接金具的尺寸计算,卡芯3要固定三角板和边接螺栓,在圆柱形卡芯3中间开出26毫米宽度,其底部设有40度的倾斜度,从顶部到底部最深处的深度为80毫米的槽,与三角板的宽度、深度、倾斜度相符。在卡芯3的开口处的槽壁处加宽20毫米,使该槽形成上宽下窄的形状,使之与碗头的形状相符。 The connection method of the first piece of insulator on the wire side is: insulator, bowl head, and triangular plate. The front clamp 6 and the rear clamp 5 loosen the insulator by tightening the threaded mandrel 4, so as to keep the stress on the same line as the insulator string. Therefore front card 6 is designed as: card core 3 adds base 1. After measuring and calculating the size of the connecting fittings, the clamp 3 needs to fix the triangular plate and the edge bolts, and a width of 26 mm is opened in the middle of the cylindrical clamp 3, and the bottom is provided with a 40-degree inclination, and the depth from the top to the bottom is the deepest It is a groove of 80 mm, which is consistent with the width, depth and inclination of the triangular plate. Widen 20 millimeters at the groove wall place of the opening of card core 3, make this groove form the shape that is wide at the top and narrow at the bottom, makes it conform to the shape of the bowl head.

本实用新型只需单人操作,安装方便,更换绝缘子时,通过摇动转把7收紧丝杆,预紧后再收2厘米就可拆、装绝缘子,工具安装在绝缘子和三角板上,受力均衡且在同一条直线上,减小对工具、设备变形损坏的风险。同时解决了葫芦配套工具更换不了小转角直线塔导线第一片绝缘子的问题。本实用新型配套工具少,重量轻,便于登山搬运、安装,可以高效、安全的完成线路检修更换工作。 The utility model only needs to be operated by a single person, and the installation is convenient. When replacing the insulator, the screw rod can be tightened by shaking the handle 7, and the insulator can be disassembled and installed after being pre-tightened by 2 cm. Balanced and on the same straight line, reducing the risk of deformation and damage to tools and equipment. At the same time, it solves the problem that the gourd supporting tool cannot replace the first insulator of the small corner straight tower conductor. The utility model has few supporting tools, light weight, is convenient for mountaineering, transportation and installation, and can efficiently and safely complete line maintenance and replacement work.

Claims (4)

1. change a transmission tower insulator instrument, it is characterized in that: comprise rear card (5) and screw mandrel (4), described screw mandrel (4) is provided with handle (7); Described rear card (5) is connected with front card (6) by described screw mandrel (4); Described front card (6) comprises base (1) and is columniform the core of the card (3), and described base (1) is provided with the hole for installing described the core of the card (3); (3) are provided with groove to described the core of the card, and the wall of these groove both sides is respectively equipped with breach.
2. replacing transmission tower insulator instrument according to claim 1, is characterized in that: described groove is shape wide at the top and narrow at the bottom, and the bottom of this groove becomes skewed.
3. replacing transmission tower insulator instrument according to claim 1 and 2, is characterized in that: described base (1) is broad in the middle, that two is little shape, and the side opening at this base (1) two ends has the hole for being connected with described screw mandrel (4).
4. replacing transmission tower insulator instrument according to claim 1 and 2, it is characterized in that: the narrow place of described groove is 26 millimeters, wide place is 46 millimeters, and the innermost from the top to the bottom degree of depth is 80 millimeters, is 40 degree with horizontal angle of inclination bottom it.
CN201420823005.XU 2014-12-23 2014-12-23 Change transmission tower insulator instrument Expired - Fee Related CN204258160U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420823005.XU CN204258160U (en) 2014-12-23 2014-12-23 Change transmission tower insulator instrument

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420823005.XU CN204258160U (en) 2014-12-23 2014-12-23 Change transmission tower insulator instrument

Publications (1)

Publication Number Publication Date
CN204258160U true CN204258160U (en) 2015-04-08

Family

ID=52962428

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420823005.XU Expired - Fee Related CN204258160U (en) 2014-12-23 2014-12-23 Change transmission tower insulator instrument

Country Status (1)

Country Link
CN (1) CN204258160U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105655919A (en) * 2016-03-21 2016-06-08 中国南方电网有限责任公司超高压输电公司百色局 Overhead OPGW composite optical cable ground wire lifter
CN106451233A (en) * 2016-10-28 2017-02-22 国网江苏省电力公司南京供电公司 Detachable clamping apparatus for replacement of monolithic insulator and method for replacement of monolithic insulator
CN108565777A (en) * 2018-06-05 2018-09-21 广西电网有限责任公司柳州供电局 35 kilovolts to 500 kilovolts insulator General clampings

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105655919A (en) * 2016-03-21 2016-06-08 中国南方电网有限责任公司超高压输电公司百色局 Overhead OPGW composite optical cable ground wire lifter
CN106451233A (en) * 2016-10-28 2017-02-22 国网江苏省电力公司南京供电公司 Detachable clamping apparatus for replacement of monolithic insulator and method for replacement of monolithic insulator
CN108565777A (en) * 2018-06-05 2018-09-21 广西电网有限责任公司柳州供电局 35 kilovolts to 500 kilovolts insulator General clampings

Similar Documents

Publication Publication Date Title
CN204258160U (en) Change transmission tower insulator instrument
CN105514877B (en) Common-tower double-return steel pipe pole replacement insulation subjob cross-arm fixture
CN204103316U (en) For the charged insulation eagle's beak pliers action bars disconnected of isolated circuit breaker
CN204243690U (en) A fixed heavy hammer structure for high-voltage overhead transmission lines
CN108847612A (en) The specific purpose tool of charged for replacement 35kV strain insulator string
CN107979024A (en) A kind of powered combination tool for eliminating transmission line of electricity drainage plate heating defect of ground potential method
CN106033872B (en) Equipotential changes the instrument of the double soft bus strain insulators of simply connected
CN205565511U (en) Change insulators cross arm fixture for operation with two steel pipe poles that return of tower
CN103883117A (en) Split mounting type staircase used for scaffold
CN205141528U (en) Three angle steel mounts
CN205314654U (en) Reinforcement iron tower of power transmission sequence
CN106241681A (en) A kind of removable portable load dispatcher well well cover opening device
CN104882687B (en) A kind of coupling type individual safety wire hook head
CN204858403U (en) A temporary hanging point fixing device for live replacement of V-shaped insulators on transmission lines
CN204144800U (en) The special cross-arm card of a kind of ZML type tower
CN204609430U (en) Emergent repairing tower tractive hangs connection box
CN105790158B (en) Charged for replacement 35kV strain insulator string specific purpose tools
CN204290154U (en) A kind of replacing insulator under electrified specific purpose tool
CN204205413U (en) A kind of link rod of Electrified fastening screw
CN206099159U (en) Electrified fixture of changing two clusters of straight line or two cluster insulators of strain insulator
CN207542669U (en) It replaces tangent tower list and hangs the multipurpose instrument (tool) that the twin insulator period of the day from 11 p.m. to 1 a.m fixes three yoke plates
CN204098593U (en) A kind of old concrete wire pole bracing means
CN204947467U (en) Vertical two elevator
CN104078878A (en) Wire lifting device for replacing insulator in live mode
CN206489913U (en) High-voltage power transmission tower insulator bird-proof device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150408

CF01 Termination of patent right due to non-payment of annual fee