CN204225486U - The plugging structure of pre-buried pipeline in a kind of concrete floor - Google Patents

The plugging structure of pre-buried pipeline in a kind of concrete floor Download PDF

Info

Publication number
CN204225486U
CN204225486U CN201420709640.5U CN201420709640U CN204225486U CN 204225486 U CN204225486 U CN 204225486U CN 201420709640 U CN201420709640 U CN 201420709640U CN 204225486 U CN204225486 U CN 204225486U
Authority
CN
China
Prior art keywords
sleeve pipe
pipeline
concrete
concrete floor
plugging structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420709640.5U
Other languages
Chinese (zh)
Inventor
范凯
李亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DANDONG POWER SURVEY AND DESIGN INSTITUTE
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Original Assignee
DANDONG POWER SURVEY AND DESIGN INSTITUTE
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DANDONG POWER SURVEY AND DESIGN INSTITUTE, State Grid Corp of China SGCC, State Grid Liaoning Electric Power Co Ltd filed Critical DANDONG POWER SURVEY AND DESIGN INSTITUTE
Priority to CN201420709640.5U priority Critical patent/CN204225486U/en
Application granted granted Critical
Publication of CN204225486U publication Critical patent/CN204225486U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rigid Pipes And Flexible Pipes (AREA)

Abstract

The utility model relates to a kind of plugging structure, particularly relates to the plugging structure of pre-buried pipeline in a kind of concrete floor.A plugging structure for pre-buried pipeline in concrete floor, it is by following Structure composing: be vertically embedded in the sleeve pipe in concrete floor, longitudinally through pipeline in its sleeve pipe; Between this pipeline and sleeve pipe, one deck concrete mix layer is at least filled in space; Sleeve pipe leans out slab surfaces at least 20mm, and the outer ring that sleeve pipe leans out part is provided with sealing ring; And sealing ring and slab surfaces close contact.The utility model is simple and reasonable for structure, is easy to constructing operation, and with low cost, and for each transformer station, power transformation box is anti-blocking can save nearly 100,000 yuan of fund every year, has good economic benefit and social benefit.

Description

The plugging structure of pre-buried pipeline in a kind of concrete floor
Technical field
The utility model relates to a kind of plugging structure, especially relates to the plugging structure of pre-buried pipeline in a kind of concrete floor.
Background technology
At present, the 10kV of newly-built and reorganization and expansion and following transformer station, power transformation box are a lot, because high and low pressure cable incoming-outgoing transformer station, case need wear protective casing, often cause transformer station, power transformation box is inner causes into water problem because waterproof measure is not in place in construction.Pump sump and artificial drainage can only be adopted after leaking to enter in network of underground, and workload is very large, wasting manpower and material resources.In addition, because the waterproof pipe plug construction quality of pipeline is not high, during annual rainy season set, rainwater often enters transformer station, power transformation box inside forms ponding, threatens, be unfavorable for transformer station, power transformation box safe operation to security of operation.
Summary of the invention
The utility model is exactly to solve the problems of the technologies described above, and a kind of waterproof quality difference formation ponding avoiding transformer station, power transformation box interior conduit provided, improve transformer station, power transformation box reliable, and the plugging structure of service sleeve in a kind of concrete floor with low cost.
The technical scheme that the utility model solves the problems of the technologies described above is:
A plugging structure for pre-buried pipeline in concrete floor, it is by following Structure composing: be vertically embedded in the sleeve pipe in concrete floor, longitudinally through pipeline in its sleeve pipe; Between this pipeline and sleeve pipe, one deck concrete mix layer is at least filled in space; Sleeve pipe leans out slab surfaces at least 20mm, and the outer ring that sleeve pipe leans out part is provided with sealing ring; And sealing ring and slab surfaces close contact.
Described concrete mix layer is made up of pea gravel concreten layer and 12%USA expansion oxidant layer.
Described pea gravel concreten layer is the pea gravel concreten layer formed than floorslab concrete label high one-level concrete.
Owing to adopting technique scheme, the utility model is made compared with prior art to have following beneficial effect:
The utility model solves transformer station, power transformation box water leakage inside and ponding problem, the waterproof quality difference avoided and eliminate because of transformer station, power transformation box water leakage inside and pipeline forms ponding and damages transformer station, power transformation box basis, thus causes the generation of security incident.Improve the operational reliability of transformer station, power transformation box, the utility model is simple and reasonable for structure, is easy to constructing operation, and with low cost, and for each transformer station, power transformation box is anti-blocking can save nearly 100,000 yuan of fund every year, has good economic benefit and social benefit.
Accompanying drawing explanation
Fig. 1 is the structural representation for a kind of embodiment of the utility model.
In figure: sleeve pipe 1, concrete mix layer 2, pipeline 3, floor 4, water-proof wing-ring 5.
Detailed description of the invention
Below in conjunction with specific embodiment, the utility model is described in further detail; but protection domain of the present utility model not limited by specific embodiment; be as the criterion with claims; in addition; with without prejudice under the prerequisite of technical solutions of the utility model, any change that the those of ordinary skill in the art made the utility model easily realize or change can fall within right of the present utility model.
Embodiment 1
The plugging structure of pre-buried pipeline in a kind of concrete floor of the utility model as shown in Figure 1, it is by following Structure composing, is vertically embedded in the sleeve pipe 1 in concrete floor 4, longitudinally through pipeline 3 in its sleeve pipe 1; Fill gaps three layer concrete batch mixing layer 2 between this pipeline 3 and sleeve pipe 1; Concrete mix layer 2 is made up of pea gravel concreten layer and 12%USA expansion oxidant layer, and described pea gravel concreten layer is the pea gravel concreten layer formed than floorslab concrete label high one-level concrete.Sleeve pipe 1 leans out floor 4 surface at least 20mm, and the outer ring that sleeve pipe 1 leans out part is provided with sealing ring 5; And sealing ring 5 and floor 4 intimate surface contact.
Embodiment 2
The plugging structure of pre-buried pipeline in a kind of concrete floor of the utility model as shown in Figure 1, it is by following Structure composing, is vertically embedded in the sleeve pipe 1 in concrete floor 4, longitudinally through pipeline 3 in its sleeve pipe 1; Fill gaps two layer concrete batch mixing layer 2 between this pipeline 3 and sleeve pipe 1; Concrete mix layer 2 is made up of pea gravel concreten layer and 12%USA expansion oxidant layer, and described pea gravel concreten layer is the pea gravel concreten layer formed than floorslab concrete label high one-level concrete.Sleeve pipe 1 leans out floor 4 surface at least 20mm, and the outer ring that sleeve pipe 1 leans out part is provided with sealing ring 5; And sealing ring 5 and floor 4 intimate surface contact.
The utility model is simple and reasonable for structure, practical, effective, is beneficial to and applies.

Claims (3)

1. the plugging structure of pre-buried pipeline in concrete floor, it is characterized in that by following Structure composing: be vertically embedded in the sleeve pipe (1) in concrete floor (4), longitudinally through pipeline (3) in its sleeve pipe (1); Between this pipeline (3) and sleeve pipe (1), one deck concrete mix layer (2) is at least filled in space; Sleeve pipe (1) leans out floor (4) surface at least 20mm, and the outer ring that sleeve pipe (1) leans out part is provided with sealing ring (5); And sealing ring (5) and floor (4) intimate surface contact.
2. the plugging structure of pre-buried pipeline in a kind of concrete floor according to claim 1, is characterized in that described concrete mix layer (2) is made up of pea gravel concreten layer and 12%USA expansion oxidant layer.
3. the plugging structure of pre-buried pipeline in a kind of concrete floor according to claim 2, is characterized in that described pea gravel concreten layer is the pea gravel concreten layer formed than floorslab concrete label high one-level concrete.
CN201420709640.5U 2014-11-24 2014-11-24 The plugging structure of pre-buried pipeline in a kind of concrete floor Active CN204225486U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420709640.5U CN204225486U (en) 2014-11-24 2014-11-24 The plugging structure of pre-buried pipeline in a kind of concrete floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420709640.5U CN204225486U (en) 2014-11-24 2014-11-24 The plugging structure of pre-buried pipeline in a kind of concrete floor

Publications (1)

Publication Number Publication Date
CN204225486U true CN204225486U (en) 2015-03-25

Family

ID=52923599

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420709640.5U Active CN204225486U (en) 2014-11-24 2014-11-24 The plugging structure of pre-buried pipeline in a kind of concrete floor

Country Status (1)

Country Link
CN (1) CN204225486U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104033167A (en) * 2013-03-08 2014-09-10 国家电网公司 Cable tunnel outlet water resisting device and method
CN107905527A (en) * 2017-11-30 2018-04-13 上海宝冶集团有限公司 Assemble box floor slab preformed hole mouth and hang molding blocking method
CN109252662A (en) * 2018-09-22 2019-01-22 陕西建工第十建设集团有限公司 Vertical shaft gantry wears cast-in-place concrete floor one-pass molding construction method
CN109723153A (en) * 2017-10-27 2019-05-07 五冶集团上海有限公司 A kind of Kitchen in High Rise Apartment flue root Antiseep method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104033167A (en) * 2013-03-08 2014-09-10 国家电网公司 Cable tunnel outlet water resisting device and method
CN104033167B (en) * 2013-03-08 2016-02-24 国家电网公司 The water-tight device of cable tunnel outlet and waterproof method
CN109723153A (en) * 2017-10-27 2019-05-07 五冶集团上海有限公司 A kind of Kitchen in High Rise Apartment flue root Antiseep method
CN107905527A (en) * 2017-11-30 2018-04-13 上海宝冶集团有限公司 Assemble box floor slab preformed hole mouth and hang molding blocking method
CN109252662A (en) * 2018-09-22 2019-01-22 陕西建工第十建设集团有限公司 Vertical shaft gantry wears cast-in-place concrete floor one-pass molding construction method

Similar Documents

Publication Publication Date Title
CN204225486U (en) The plugging structure of pre-buried pipeline in a kind of concrete floor
CN204552818U (en) The drainage system of ditch, side, anti-tunnel bottom leaky
CN204004816U (en) A kind of Direct-Buried Heating Pipeline water-tight device through walls
CN205716049U (en) Fixed wall pipe waterproof construction
CN204739329U (en) A pipeline waterproof construction for concrete wall
CN201731178U (en) Rigid waterproof sleeve
CN204300520U (en) A kind of cable penetration sleeve structure
CN103741695A (en) Embedded grouting pipe installed on waterstop and grouting method
CN105697886B (en) The plugging structure of pre-buried cable tube in a kind of concrete walls body
CN103822027A (en) Cable hole plugging device
CN204267894U (en) The plugging structure of pre-buried cable trunk in a kind of concrete wall
CN204828964U (en) First structure of waterproof receipts that floor was worn to hot -water heating riser between residential sanitation
CN204662506U (en) A kind of cable communication well
CN104019324B (en) The quick maintenance device of Underwater Two-layer oil transport pipeline
CN103924694B (en) Leakage repairing treatment method for waterproof concrete expansion joint
CN202424089U (en) Pipe plugging device
CN205244643U (en) Municipal administration is with having drainage pipe who prevents corrosive effects
CN204919787U (en) Drainage pipe device for municipal works
CN204437508U (en) A kind of prefabricated direct-buried thermal insulation pipe with waterproof construction
CN203907037U (en) Waterproof device for floor-through pipeline
CN203488854U (en) Penetrating pipe leakage-proof structure of building floors
CN102536268A (en) Buried high-pressure water channel or tunnel anti-seepage lining structure
CN202483590U (en) Buried high-pressure water channel or tunnel anti-seepage lining structure
CN102808630B (en) Method for plugging power cable tunnel duct piece bolt hole
CN206570959U (en) A kind of building transformation joint is combined trapping structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant